Letter Sequence Request |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement
|
MONTHYEARML0725500632007-08-30030 August 2007 NFPA 805 Transition Pilot Plant FAQ 06-0019, Revision 2 Project stage: Request ML0730605502007-09-0707 September 2007 NFPA 805 Transition Pilot Plant FAQ 07-0040 Project stage: Request ML0727402622007-09-20020 September 2007 NFPA-805 Transition Pilot Plant FAQ 07-0038 Project stage: Request ML0727402682007-09-20020 September 2007 NFPA-805 Transition Pilot Plant FAQ 07-0039 Project stage: Request ML0727402482007-09-20020 September 2007 NFPA-805 Transition Pilot Plant FAQ 06-0011, Revision 2 Project stage: Request ML0726104552007-09-24024 September 2007 NFPA 805 Observation Visit Trip Report Project stage: Request ML0727402552007-09-28028 September 2007 NFPA-805 Transition Pilot Plant FAQ 06-0019, Revision 3 Project stage: Request ML0735500232007-11-12012 November 2007 NFPA 805 Transition Pilot Plant FAQ 07-0033, Revision 1 Project stage: Request ML0735100822007-11-12012 November 2007 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 3 (Corrected Version) Project stage: Request ML0733200282007-11-26026 November 2007 NFPA 805 Transition Pilot Plant FAQ 06-0012, Revision 5, Determining Manual Actions That Require a Change Evaluation During Transition. Project stage: Request ML0733700252007-12-0303 December 2007 NFPA 805 Transition Pilot Plant FAQ 06-0008, Revision 8, Alternative Method for Fire Protection Engineering Analyses Project stage: Request ML0734001472007-12-0606 December 2007 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 3 Project stage: Request ML0735402622007-12-20020 December 2007 Afpb Staff Response to NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 0 Project stage: Request ML0735500252007-12-20020 December 2007 NFPA 805 Transition Pilot Plant FAQ 07-0036, Revision 1 Project stage: Request ML0807004112008-03-10010 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 1, Clarification of 10 CFR 50.48(c), 50.48(a), and GDC 3. Project stage: Request ML0809101362008-03-28028 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 1, Lessons Learned - NEI 04-02 B-2 and B-3 Tables Project stage: Request ML0813006972008-05-0909 May 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 2 Project stage: Request ML0814300412008-05-22022 May 2008 NFPA 805 Transition Pilot Plant FAQ 07-0040, Revision 2 Project stage: Request HNP-08-061, Request for License Amendment to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2008-05-29029 May 2008 Request for License Amendment to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Request ML0820410142008-05-30030 May 2008 Public Version of Enclosures 2 Through 6 of License Amendment Request to Adopt NFPA-805 Project stage: Request ML0816504752008-05-30030 May 2008 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition). License Amendment Request (LAR) No. 2008-01 Project stage: Request ML0816901212008-06-17017 June 2008 Forthcoming Closed Meeting with Progress Energy Carolinas, Inc., to Discuss the May 29, 2008, License Amendment Request (LAR) to Transition the Shearon Harris Nuclear Plant, Unit 1 (Harris) to National Fire Protection Association (Nfpa).. Project stage: Meeting ML0818901932008-06-30030 June 2008 Completion Schedule for Part 2 of License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001) Edition, License Amendment Request No. 2008-01 Project stage: Request ML0818406962008-07-0707 July 2008 Meeting with Progress Energy Carolinas, Inc. and Duke Energy Carolinas, LLC, to Discuss the 05/29&30/2008, License Amendment Requests to Transition Shearon Harris, Unit 1, and Oconee, Units 1, 2, & 3 to NFPA Standard 805 Project stage: Meeting ML0818905292008-07-11011 July 2008 Summary of Closed Meeting with Progress Energy Carolinas Regarding May 29, 2008, License Amendment Request to Transition the Shearon Harris Nuclear Plant Unit 1, to National Fire Protection Association Standard 805, Performance-Based.... Project stage: Meeting ML0820703912008-07-17017 July 2008 Meeting Handouts from 7/17/08 Public Meeting on the Harris and Oconee LARs to Transition to NFPA-805 Project stage: Meeting ML0820605362008-08-0707 August 2008 Summary of Mtg. with Progress Energy Carolinas, and Duke Energy Carolinas to Discuss the LARs to Transition the Shearon Harris and Oconee Nuclear Plants to National Fire Protection Association Standard NFPA-805 Project stage: Acceptance Review ML0827011582008-09-26026 September 2008 Acceptance Review Regarding the License Amendment Request to Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants. Project stage: Acceptance Review ML0828700162008-09-26026 September 2008 Nc Warn'S Response to Board Notification - Enclosure P-1 - Shearon Harris Nuclear Power Plant, Unit 1 - Acceptance Review NFPA-805 License Amendment Request, September 26, 2008 Project stage: Request ML0828804552008-09-30030 September 2008 Preliminary Oconee LAR Acceptance Review Matrix Project stage: Acceptance Review ML0828902592008-10-16016 October 2008 and 10/08/2008 - Summary of Conference Calls with Duke Energy Carolinas to Discuss the Acceptance Review of the May 30, 2008, License Amendment Request (LAR) to Adopt National Fire Protection Association (NFPA) 805 for Oconee Project stage: Acceptance Review ML0830900742008-11-12012 November 2008 Summary of Category 2 Public Meeting Held to Discuss National Fire Protection Association Standard 805 Pilot Plant Process: Current Lessons Learned from the Pilot License Amendment Request Reviews (TAC Nos. MD8807, MD8832, MD8833, & MD8834) Project stage: Meeting HNP-08-113, Supplement to Request for License Amendment, to Adopt NFPA 805 Performance-Based Standards for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2008-11-14014 November 2008 Supplement to Request for License Amendment, to Adopt NFPA 805 Performance-Based Standards for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Supplement ML0829601532008-11-17017 November 2008 Summary of Meeting with Progress Energy Carolinas, Inc., to Discuss Shearon Harris Unit 1 National Fire Protection Association Standard 805 License Amendment Request Project stage: Meeting HNP-08-121, Supplement 2 to Request for License Amendment to Adopt NFPA 805 Performance-based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2008-12-11011 December 2008 Supplement 2 to Request for License Amendment to Adopt NFPA 805 Performance-based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Supplement ML0903000302009-01-30030 January 2009 Acceptance Review Regarding Amendment to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Acceptance Review ML0903304962009-02-0202 February 2009 Acceptance Review of License Amendment Request to Adopt the National Fire Protection Association Standard No. 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants,.. Project stage: Acceptance Review ML0902903272009-03-10010 March 2009 Regulatory Audit in Support of the License Amendment Request to Implement a Risk-Informed, Performance-Based Fire Protection Program as Allowed by Title 10 of the Code of Federal Regulations, Paragraph 50.48(c) Fire Protection Project stage: Other ML0909900182009-04-10010 April 2009 04/21-22/2009, Notice of Meeting with Progress Energy Carolinas, Inc., and Duke Energy Carolinas, LLC, to Discuss Topics Involving the License Amendment Requests to Transition the Shearon, Unit 1 and the Oconee, Units 1, 2 and 3 Project stage: Meeting ML0916002812009-06-11011 June 2009 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing Project stage: Other ML0921707152009-08-0606 August 2009 Request for Additional Information Regarding Amendment to Adopt National Fire Protection Association Standard 805 (NFPA 805), Performance-Based Standard for Fire Protection for Light Water Reactor ... Project stage: RAI HNP-09-084, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Generating Plants.2009-08-13013 August 2009 Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Generating Plants. Project stage: Response to RAI HNP-09-086, Second Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Reactor...2009-08-28028 August 2009 Second Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Reactor... Project stage: Response to RAI HNP-09-094, Third Response to Request for Additional Information License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor....2009-10-0909 October 2009 Third Response to Request for Additional Information License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor.... Project stage: Response to RAI HNP-09-096, Additional Information Re License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants2009-12-16016 December 2009 Additional Information Re License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants Project stage: Request ML1001302542010-01-14014 January 2010 Second Request for Additional Information Regarding the License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plant Project stage: RAI HNP-10-008, Response to Second Request for Additional Information Regarding License Amendment Request to Anfp Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants.2010-02-0404 February 2010 Response to Second Request for Additional Information Regarding License Amendment Request to Anfp Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants. Project stage: Request ML1006009872010-03-0909 March 2010 Discussion of Clarification Questions Related to the License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance - Based Standard for Fire Protection for Light ... Project stage: Other HNP-10-040, Response to 3rd Round of RAI License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants.2010-04-0505 April 2010 Response to 3rd Round of RAI License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants. Project stage: Request HNP-10-064, Additional Items Related to License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants.2010-06-0909 June 2010 Additional Items Related to License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants. Project stage: Request 2008-06-17
[Table View] |
|
---|
Category:- No Document Type Applies
MONTHYEARML22314A0752022-11-10010 November 2022 2B - Exam Administrative Items - Normal Release ML22034A3992022-02-16016 February 2022 Enclosure 1 - IP 71130.03 Cy 2021 - IR 8 Baseline Inspection Completion ML22034A3952022-02-16016 February 2022 Enclosure 3 - IP 96001 CY2021 - IR 8 Baseline Inspection Completion ML22034A3972022-02-16016 February 2022 Enclosure 2 - IP 92707 CY2021 - IR 8 Baseline Inspection Completion ML18338A0882018-12-0404 December 2018 Attachment FormerFAQResponses_11302018 ML18180A2602018-06-29029 June 2018 NFPA 805 FAQ 10-0059 - NFPA 805 Monitoring ML18073A3582018-03-15015 March 2018 NRC Staff Comments FAQ 18-0015 ML17235B1482017-08-23023 August 2017 U.S. Nuclear Regulatory Commission - Tornado Missile Risk Evaluator (TMRE) Methodology Topics and Methodology Feedback ML16315A2892016-11-10010 November 2016 Attachment 5 EPRI RETRAN-3D Computer Code Manuals, NP-7450(A) RA-16-003, Attachment 5 EPRI RETRAN-3D Computer Code Manuals, NP-7450(A)2016-11-10010 November 2016 Attachment 5 EPRI RETRAN-3D Computer Code Manuals, NP-7450(A) ML18039A8562016-06-0202 June 2016 Fpra FAQ 16-0011 - Cable Tray Ignition - Draft ML14191B2622014-07-10010 July 2014 NFPA 805 Transition FAQ 14-0070, Revision 0 ML13170A3282013-06-13013 June 2013 Special Inspection Question & Answers ML1214300352012-05-21021 May 2012 NFPA 805 Transition FAQ 12-0062, Revision 1 ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML1204105892012-02-10010 February 2012 NFPA 805 Transition FAQ 10-0059, Revision 5 ML1204105852012-02-10010 February 2012 NRC Staff Response to NFPA 805 Transition FAQ 10-0059, Revision 4 ML1203201932012-02-0101 February 2012 NFPA 805 Transition FAQ 10-0059, Revision 4 ML1202603842012-01-13013 January 2012 FAQ Revision NFPA 805 Monitoring ML1201903132012-01-13013 January 2012 NFPA 805 Transition FAQ 10-0059, Rev 3 ML1202603722012-01-13013 January 2012 NFPA 805 Monitoring ML1202604252012-01-13013 January 2012 FAQ-1 - NFPA 805 Monitoring ML1202604402012-01-13013 January 2012 FAQ - NFPA 805 Monitoring ML1128600532011-09-30030 September 2011 NRC Staff Comments on FAQ 59R2 ML1127304102011-09-30030 September 2011 NRC Staff Response to NFPA 805 Transition FAQ 10-0059, Revision 2 RA-11-025, Enclosure 1, Attachment 2 - Duke Energy Corporation and Progress Energy, Inc. Organization Charts Post Merger2011-09-0202 September 2011 Enclosure 1, Attachment 2 - Duke Energy Corporation and Progress Energy, Inc. Organization Charts Post Merger ML1123401522011-08-19019 August 2011 NFPA 805 Transition FAQ 10-0059, Rev 2 ML1111804812011-04-21021 April 2011 NFPA 805 Transition FAQ 10-0059, Rev 1 ML1109105082011-03-31031 March 2011 NRC Staff Response to NFPA 805 Transition FAQ 10-0059, Revision 0 (Part 2) ML0933507512010-01-14014 January 2010 Temporary Instruction 2515/180, Managing Fatigue ML0916101892009-06-0303 June 2009 NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 2, Bus Duct Counting Guidance for High Energy Arcing Faults ML0909905112009-04-29029 April 2009 Enclosure 1: Shearon Harris Regulatory Audit Participants ML1020301612009-04-12012 April 2009 Tritium Concern Talking Points ML1019402162009-04-12012 April 2009 Offsite Notification to State/Local Agencies Regarding Tritium Release Onsite - EN 44951 ML0909305002009-04-0303 April 2009 Afpb Staff Response to NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 1 ML1020301722009-04-0101 April 2009 Tritium Questions and Answers ML0908500122009-03-26026 March 2009 NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 1, Bus Duct Counting Guidance for High Energy Arching Faults ML0902902182009-01-22022 January 2009 NFPA 805 Transition Pilot Plant FAQ 07-0030 ML1019402762008-12-0202 December 2008 Nuclear Condition Report for Tritium in Groundwater NEI 04-02, NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2, Lessons Learned - NEI 04-02 B-2 Table2008-09-12012 September 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2, Lessons Learned - NEI 04-02 B-2 Table ML0825904662008-09-12012 September 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2, Lessons Learned - NEI 04-02 B-2 Table ML0914201382008-09-0909 September 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 2 - Clean Version ML0821000342008-07-24024 July 2008 NFPA 805 Transition Pilot Plant FAQ 07-0038, Revision 1 ML0813006972008-05-0909 May 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 2 ML0809101362008-03-28028 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 1, Lessons Learned - NEI 04-02 B-2 and B-3 Tables ML0807004112008-03-10010 March 2008 NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 1, Clarification of 10 CFR 50.48(c), 50.48(a), and GDC 3. ML0807001572008-03-10010 March 2008 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 5 ML0806704192008-03-0707 March 2008 CDBI Findings ML0735500252007-12-20020 December 2007 NFPA 805 Transition Pilot Plant FAQ 07-0036, Revision 1 ML0735500212007-12-20020 December 2007 NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 4 2022-02-16
[Table view] |
Text
FAQ Number 06-0019 FAQ Revision 3 FAQ Title Definition of Power Block and Plant Plant: Harris Nuclear Plan (HNP) Date: 09-28-07
Contact:
Alan Holder Phone: 919-546-3372 Email: alan.holder@pgnmail.com Distribution: (NEI Internal Use) 805 TF FPWG FPRATF Purpose of FAQ:
Provide specific clarification within NEI 04-02 as to the definition of power block and plant used in NFPA 805, such that the terms are applied to Structures, Systems and Components associated with Nuclear Safety Performance Criteria.
Is this Interpretation of guidance? Yes / No Proposed new guidance not in NEI 04-02? Yes / No Details:
NEI 04-02 guidance needing interpretation (include section, paragraph, and line numbers as applicable):
NEI 04-02, Section 4.3.1, Fundamental Fire Protection Program and Design Elements Transition Review, Table B-1 uses NFPA 805 chapter 3 as part of the transition review. Specific clarification is requested for certain terms and phrases found in NFPA 805.
Circumstances requiring guidance interpretation or new guidance:
Interpretive guidance is needed to clarify the meaning and application of the term power block as found in, NFPA-805, Standard for Fire Protection for Light Water Reactor Electric Generating Plants (2001 Edition), Chapter 3, Section 3.3.1.2 Control of Combustibles, Section 3.5 Water Supply, Section 3.6 Standpipes and Hose Stations and Section 3.11.1 Building Separation.
Specifically, the definition of Power Block and Plant and how these will be applied when reviewing Chapter 3 transition.
Page 1 of 2
FAQ Number 06-0019 FAQ Revision 3 FAQ Title Definition of Power Block and Plant Detail contentious points if licensee and NRC have not reached consensus on the facts and circumstances:
NA Potentially relevant existing FAQ numbers:
FAQ #06-0007 Response Section:
Proposed resolution of FAQ and the basis for the proposal:
This FAQ provides interpretive guidance to clarify the term Power Block where used in NFPA 805, Chapter 3. NFPA 805, Section 1.6.46 defines Power Block as Structures that have equipment required for nuclear plant operations. Although not endorsed by Regulatory Guide 1.205, NFPA 805, Section A.1.6.46 further describes the term Power Block as, Containment, auxiliary building, service building, control building, fuel building, rad waste, water treatment, turbine building and intake structure are examples of power block structures.
If appropriate, provide proposed rewording of guidance for inclusion in the next Revision:
As follows; Clarification of NFPA 805 specific sections as applied under NEI 04-02, to be Deleted: Specific clarification to NFPA included in (New) Appendix K, to NEI 04-02 upon approval of specific clarification Chapter 3, from FAQ 06-0019,¶ (final formatting to be provided by NEI). Where used in Chapter 3, power block and plant refer to structures that have equipment required for nuclear plant Where used in Chapter 3, power block and plant refer to structures that have operations , such as Containment, auxiliary building, service building, equipment required for nuclear plant operations, such as Containment, auxiliary control building, fuel building, rad waste, building, service building, control building, fuel building, rad waste, water treatment, water treatment, turbine building, and intake structure, or structures that are turbine building, and intake structure, or structures that are identified in the facilitys identified in the facilitys current license current license basis (CLB). The scope of equipment required for plant operations is basis (CLB). The scope of equipment required for plant operations is defined by defined by components and cables selected per NFPA 805 2.4.2. Applicable components and cables selected per structures will be identified in the 10CFR50.48(c) License Amendment Request as NFPA 805 2.4.2.
submitted for transition Formatted: Space Before: 0 pt, After: 0 pt Deleted: Absent of, or in lieu of the above, the power block are those Deleted: Applicable structures will be identified in the 10CFR50.48(c) License Amendment Request as submitted for transition.