ML082381167

From kanterella
Jump to navigation Jump to search
Exam 05000338-08-301 - Draft RO Written Exam
ML082381167
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 08/21/2008
From:
NRC/RGN-II
To:
References
ER-08-301
Download: ML082381167 (151)


See also: IR 05000338/2008301

Text

Draft Submittal

(Pink Paper)

Reactor Operator Written Exam

\

NORTH ANNA JUNE 2008 EXAM

05000338/2008301 & 05000339/2008301

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

1.001 G2.4.31 071INEW/IHIGHERI/ROINORTH ANNAl6/20081

Given the following:

  • During a Unit 1 load reduction for 1-PT-34.3, Turbine Valve Freedom Test, the

following alarm is received:

  • 1A-01, ROD CONTROL URGENT FAILURE
  • The Ramp has been held and power is approximately 93%.
  • Tave is 2.5 0 F higher than Tref.
  • Investigation reveals that a Logic Cabinet Oscillator Failure has occurred.

Which ONE of the following describes the effect on the unit, and the action that will be

taken to match Tave to Tref?

A. All rod motion is inhibited; adjust Turbine load ONLY to match Tave to Tref.

B!" All rod motion is inhibited; adjust Turbine load or adjust RCS boron concentration to

match Tave to Tref.

C. Rod motion is allowed in 'Bank Select'; adjust Turbine load ONLY to match Tave to

Tref.

O. Rod motion is allowed in 'Bank Select'; adjust Turbine load, adjust RCS boron

concentration, or use rods in Bank Select to match Tave to Tref.

A Incorrect. Change in RCS Cb is also allowable lAW the alarm response. Plausible

because the applicant may believe that chern shim is not advisable while rods are

frozen, and that changing turbine would be better course of action.

B Correct. A Logic Cabinet failure freezes all rod motion, and before attempting to

move rods, the problem must be corrected.

C Incorrect. Second half of choice plausibility same as option A, and also an urgent

failure in a Power Cabinet would allow the unaffected groups to be moved in Bank

Select, therefore choosing either C or 0 for this reason is credible.

o Incorrect same reasons as C, but second half of option is correct action, with the

exception of using rods. Plausibility is enhanced for this choice because the alarm

response allows use of rods in 'bank select' if a power cabinet failure has occurred.

Monday, June 30, 2008 3:34:29 PM 1

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Emergency Procedures / Plan: Knowledge of annunciator alarms, indications, or response

procedures.

Question Number:

Tier: 2

Group: 2

Importance Rating: 4.2

Technical Reference: 1A-D1, Rod Control LP section 9.2

Proposed references to be provided to applicants during examination: None

Learning Objective: U 6518

Question History:

10 CFR Part 55 Content: 41.7,10

Comments:

KA Match: Item directly evaluates the knowledge required by the selected topic because it

requires knowledge of both the effect of the annunciator, and the action contained in the alarm

response procedure

MCS Time: I Points: 1.00 Version: a I 2 345 6 7 8 9

Answer: BCDBACDBAC Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: IDGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:30 PM 2

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

2. 003 A4.07 OOIIBANKlROBINSON 2004IHIGHERJIRO/NORTH ANNN6/2008/

Given the following:

  • Unit 1 cooldown is in progress for refueling.
  • RCS temperature is 175 degrees F.
  • RCS pressure is 360 psig..
  • VCT pressure is 30 psig.
  • Seal Injection flows are 8 GPM to each RCP.

The following alarm is received:

  • 1C RCP se.al leakoff flow indicates 0.8 gpm and slowly decreasing.
  • 1C RCP Standpipe alarms are CLEAR.
  • 1C RCP #1 Seal Leakoff temperature is 180 degrees F and rising at 1 degree F

every 10 minutes.

Which ONE (1) of the following actions will be performed?

A'! OPEN 1-CH-HCV-1307, RCP Seal Bypass Isolation Valve, to increase sealleakoff

flow.

B. Raise RCS pressure to high in the allowable band to increase sealleakoff flow.

C. Trip operating RCPs and isolate sealleakoff due to insufficient seal DP.

D. Isolate #1 sealleakoff for 1C RCP to establish a pressure boundary at #2 seal.

A Correct. Opening the seal bypass valve under low pressure conditions will raise the

seal leakoff flow in accordance with the ARP.

B Incorrect. Raising RCS pressure would increase seal DP, and may increase seal

leakoff flow, but is not directed by the ARP. Further the LTOP limit at this temperature

per Tech Specs is 375# which will have a negligible effect on leakoff. The candidate

who does not recognize this may choose this distractor. Plausible because if pressure

could be raised a significant amount it would have the desired effect.

C Incorrect. DP is 330 psig, sufficient for continued RCP operation. Minimum DP for

ensuring desired seal leakoff flow as given by the AR is 275 psi. Plausible because

pressure is low.

o Incorrect. Isolating sealleakoff will decrease the #1 seal DP, placing a pressure

boundary at #2 seal. This would be performed for a seal failure. This condition is

expected for low pressure, and is not representative of a seal failure. Plausible because

at higher pressures, these indications would lead to seal isolation.

Monday. June 30, 2008 3:34:30 PM 3

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to manually operate and/or monitor in the control room: Rep seal bypass

Question Number:

ne~ 2

Group: 1

Importance Rating: 2.6

Reference(s) - ARP 1C-G8, 1-0P-5.2

Proposed References to be provided to applicants during examination - None

Learning Objective - U 3493

Question History -

10 CFR Part 55 Content - 41.7/10

Comments -

KA Match: Item evaluated knowledge of when and under what conditions seal bypass

may be used.

This item was taken from a Robinson item from 2004. Stem was changed to ensure

plant specific information, two options were changed for plausibility.

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: A BAD CDC ABC Scramble Range: A - D

Source: BANK Source If Bank: ROBINSON 2004

Cognitive Level: IDGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:30 PM 4

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 1508 RO ONLY

3. 004 G2.2.3 003INEW//LOWERlIROINORTH ANNAl61200SINO

Which ONE of the following describes a NORMAL Unit 2 BAST alignment?

A'! 'C' BAST through 1-CH-P-2D to Unit 2 Boric Acid Filter to Unit 2 BIT/Blender.

B. 'A' BAST through 1-CH-P-2A to Unit 2 Boric Acid Filter to Unit 2 BIT/Blender.

C. 'C' BAST through 1-CH-P-2D through recirc valve 1-CH-HCV-11 04 ONLY and back

to 'C' BAST.

D. 'B' BAST through 1-CH-P-2A to Unit 2 Boric Acid Filter to Unit 2 BIT/Blender.

A Correct. Lineup is correct for normal arangement of system (no equipment OOS) and

ensures BIT concentration and BIT remains full.

B Incorrect. A BAST is normally aligned to Unit 1; lineup thru BIT is correct.

C Incorrect. This lineup ONLY recircs the specified BAST and as noted above would

not be normal since it fails to include the BIT.

o Incorrect. In this case again the B BAST would only be used if the C BAST were

unavailable; the BIT lineup portion is correct.

All distractors are plausible since several lineups are possible for various evolutions.

The "normal" lineup is based on a configuration that maintains TRM requirements for

funtional sources and flowpaths. The normal on service tank and associated recirc

path is different between the Units.

Monday, June 30, 2008 3:34:30 PM 5

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

004 Chemical and Volume Control System

2.2.3 (multi-unit license) Knowledge of the design, procedural, and operational

differences between units.

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.8

Technical Reference: OP-8 series procedures

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History:

10 CFR Part 55 Content: CFR: 41.5 / 41.6 / 41.7 / 41.10/45.12

Comments:

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: A A A A A A A A A A Items Not Scrambled

Source: NEW Source If Banle

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?: NO

Monday, June 30, 2008 3:34:30 PM 6

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

4.005 KI.06 04IIMODIFIED/IHIGHERlIROINORTH ANNAJ61200S1

Given the following:

  • Unit 1 is in Mode 6.
  • The unit has been shutdown for 11 days.
  • Cavity level is 22 feet above the reactor vessel flange.
  • RCS temperature is 109 degrees F.
  • RHR Loop 1A is in service.

Which ONE of the following is the MINIMUM RHR flow required, and the reason for the

minimum flow, in accordance with 1-0P-14.1, Residual Heat Removal.

A. 2500 GPM; satisfies Technical Specification minimum flow requirements in Mode 6.

B~ 2500 GPM; prevents flow induced chatter on Sl Accumulator check valves.

C. 3000 GPM; satisfies Technical Specification minimum flow requirements in Mode 6.

D. 3000 GPM; prevents flow induced chatter on SI Accumulator check valves.

A Incorrect. Plausible because minimum RHR operability requirements are based on

cavity level.

B Correct. Flow induced chatter can damage SI Accumulator check valves, because

RHR discharge uses a portion of Sl Accumulator discharge piping.

C Incorrect. 3000 GPM would be the minimum flow requirement if cavity level was

higher than 23 feet or if RCS temperature was greater than 140 degrees F, and the

precaution is used to satisfy TS.

D Incorrect. Plausible because reason is correct, but flow is incorrect.

Monday, June 30, 2008 3:34:30 PM 7

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the physical connections and/or cause-effect relationships between the RHRS

and the following systems: ECCS

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.5

Technical Reference: 1-0P-14.1

Proposed references to be provided to applicants during examination: None

Learning Objective: U 10457, U 444

Question History:

10 CFR Part 55 Content: 41 .10

Comments:

KA Match: Item evaluates cause-effect relationship between RHR and SI systems because it

tests RHR flow requirement to prevent damage to SI components

MCS Time: I Points: 1.00 Version: a I 2 3 4 5 6 7 8 9

Answer: BADADCAADD Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:30 PM 8

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

5. 006 K2.02 043INEW/IHIGHERlIROINORTH ANNAl6/2oo8INO

Given the following:

  • Unit 1 is in Mode 4 with a plant cooldown to Mode 5 in progress.
  • RCS Pressure is 720 psig.
  • RCS temperature is 325°F.

Which ONE of the following states the power supply to 1-SI-MOV-1865A, 'A'

Accumulator Discharge Isolation Valve, and itls breaker position for the current plant

conditions?

480 Volt MCC...

A'!I 1H1; breaker is open.

B. 1H1; breaker is closed.

C. 1J1; breaker is open.

D. 1J1; breaker is closed.

A Correct. Correct power supply, and breaker is normally open; during RCS cooldown

in Mode 3, breaker is closed below 1990 psig until the valve is closed below 950 psig.

Once in Mode 4 below 350 degrees, power is again removed from the valve.

B Incorrect. See A above. Breaker would be opened below 950 psig after valve is

closed.

C Incorrect. Wrong power supply, but plausible supply. (Supplies MOV-1865C for 1C

SI Accumulator) Breaker is normally open, and is open in this condition.

D Incorrect. Wrong power supply, incorrect breaker position, but breaker would be

closed throughout most of the cooldown. It is opened below 950 psig. See description

of A and C above for detail.

Monday, June 30, 2008 3:34:30 PM 9

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of bus power supplies to the following: Valve operators for accumulators

Question Number:

Tier: 2

Group: 1

Importance Rating: 2.5

Technical Reference: NCRODP-52, Table 3;

51 LP;

1-0P-3.3, step 5.8

1-0P-26A

Proposed references to be provided to applicants during examination: None

Learning Objective: U 3887

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Topic asks power supply to Accumulator Valve Actuators; test item

evaluates knowledge of the MOVs and their operation

MCS Time: I Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: ABADDAC CDD Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: IDGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?: NO

Monday, June 30, 2008 3:34:30 PM 10

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

6. 007 A4.10 046IMODIFIED//LOWERlIROINORTH ANNN6/20081

Given the following:

  • Unit 1 is in Mode 3.
  • PRT level is 74% and INCREASING SLOWLY.
  • PRT pressure is 14 psig and INCREASING SLOWLY.
  • PRT temperature is 155°F and INCREASING SLOWLY.

Which ONE of the below is the cause of the conditions above, and the indications that

may be used to diagnose the cause?

A. Seat leakage from a Pressurizer Safety valve; Temperature indicator ONLY on the

Safety Valve Tailpipe.

B~ Seat leakage from a Pressurizer Safety valve; Temperature indicator and acoustical

monitor on the Safety Valve Tailpipe.

C. Seat Leakage from a Pressurizer PORV; Temperature indicator and acoustical

monitor on the Relief Valve Tailpipe.

D. Seat Leakage from a Pressurizer PORV; Acoustical monitor ONLY on the Relief

Valve Tailpipe.

A Incorrect. The safety valve has acoustic monitor indication and temperature

indication, but plausible because there are multiple temperature indications on the

Verical Board.

B Correct. The safety valve has 2 acoustic monitors and 1 temperature indication

C Incorrect. Plausible because of same reason as A, except that PORVs have

open/closed indicators, and are not provided with acoustic monitors.

D Incorrect same as C, except that if an applicant believes a PORV is leaking, these

are the indications available for a safety valve, so it can be confusing.

Monday, June 30, 2008 3:34:30 PM 11

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to manually operate and/or monitor in the control room: Recognition of leaking

PORV/code safety

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.6

Technical Reference: RCS LP, Annunciator Response

Proposed references to be provided to applicants during examination: None

Learning Objective: U 15844

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item evaluates recognition and determination of which valve is leaking into the PRT.

MCS Time: 1 Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: B B CBAACCAA Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:31 PM 12

QUESTIONS REPORT

fo'r NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

7. 007 K3.01 047lNEW/fHIGHERJIROINORTH ANNAl6120081NO

  • A calibration error during the refueling outage results in the PRT level transmitter

reading 20% lower than actual level.

  • The Unit is now at 100% power and PRT level indication is 72%.

Which ONE of the following describes the affect the calibration error will have

assuming multiple PORV lifts occur during recovery from a spurious 81 in which one

train failed to reset?

A. More volume will be available in the PRT to accommodate the PORV discharge so

it will take more time for the PRT rupture disk to rupture.

B. More volume will be available to accommodate the PORV discharge but this will not

affect the time it takes for the PRT rupture disk to rupture.

C~ Less volume will be available in the PRT to accommodate the PORV discharge so it

will take less time for the PRT rupture disk to rupture.

D. Less volume will be available in the PRT to accommodate the PORV discharge but

this will not affect the time it takes for the PRT rupture disk to rupture.

A Incorrect. Plausible since historically the effect of actual vs. indicated is often

confused, if candidate assumes more volume available this will tend to imply longer

time to reach setting (100#) dip so this distractor is plausible.

B Incorrect. As noted above operators maintain level based on their indication; for the

condition given maintaining the PRT at a typical indicated level of 72% means it is

actually 92% full, 2nd part is plausible since rupture disc is a function of pressure,

candidate may not connect that volume differences in PRT will affect how fast pressure

rises.

C Correct. As noted above in actuality the PRT is almost completely full (horizontal

cylindrical tank) as such for the conditions provided (PRT actually above normal

operating range and PORVs discharging) the PRT will rupture much sooner than would

be expected.

D Incorrect. As stated above the amount and given time for pressure rise is somewhat

dependent on initial volume, again the candidate may not equate this to the rupture

disc rupturing sooner since the 100# dip setpoint does not change with respect to the

calibration error discussed.

Monday, June 30, 2008 3:34:31 PM 13

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Pressurizer Relief Tank/Quench Tank System (PRTS)

Knowledge of the effect that a loss or malfunction of the PRTS will

have on the following: Containment

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.3

Technical Reference: RCS LP, AR, GFES

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History:

10 CFR Part 55 Content: 41.7/45.6

Comments:

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: C C C C C C C C C C Items Not Scrambled

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?: NO

Monday, June 30, 2008 3:34:31 PM 14

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

8. 008 AA2.24 002INEW//lllGHERlfROINORTH ANNA/6/2008/

Given the following:

  • Safety Injection is actuated.
  • RCS pressure is 1200 psig.
  • Containment pressure has peaked at 16 psia and is slowly trending down.
  • Pressurizer level is 100%.
  • The crew is performing 1-E-0, Reactor Trip or Safety Injection.

Which ONE of the following describes the method used to control RCS temperature

and the approximate Main Steam pressure maintained?

A'! Condenser Steam Dumps; 1010 psig.

B. Condenser Steam Dumps; 1050 psig.

C. SG PORVs; 1010 psig.

D. SG PORVs; 1050 psig.

A Correct. Main Steam pressure of approximately 1020 psia (1005 psig) corresponds

to 547 degrees F, 1010 is close based on readability of meters. No MSU, so

condenser remains available.

B Incorrect. Steam pressure is plausible because it is the pressure that th~ SG PORVs

will operate at to maintain 551 degrees F if Condenser dumps are not available.

C Incorrect. Since no MSU, SG PORVs do not have to control pressure. Plausible

because containment pressure is close to setpoint for MSU, and pressure is correct for

actual control point of 547 degrees.

D Incorrect same as C but if SG PORVs were controlling, then this would be the

pressure.

Monday, June 30, 2008 3:34:31 PM 15

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to determine and interpret the following as they apply to the Pressurizer Vapor Space

Accident: Value at which turbine bypass valve maintains header pressure after a reactor trip

Question Number:

Tier: 1

Group: 1

Importance Rating: 2.6

Technical Reference: E-O, pages 6-10

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12458, U 12463

Question History:

10 CFR Part 55 Content: 41.5,41.10

Comments:

KA Match: Item evaluates steam pressure maintained during a steam space LOCA, based on

whether MSLI has actuated and which Tave would be maintained.

Have developed similar items in the past evaluating steam dumps or PORVs, but not in this

context

MCS Time: Points: 1.00 Version: 0123456789

Answer: ADCDCABBCA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:31 PM 16

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

9.008 K4.01 047INEW/ILOWERlIROINORTH ANNAJ6120081

Given the following:

  • Unit 1 is at 100% power.
  • CC Pump 1A is running and CC Pump 1B is in standby.
  • 4160 V Bus 1H normal feeder is inadvertantly opened.
  • 1H EDG operates as designed.

Which ONE of the following describes the operation of CC Pumps for this event?

A. CC Pump 1B starts when Bus 1H is deenergized; CC Pump 1A starts as soon as

Bus 1H is reenergized.

Bl'" CC Pump 1B starts when Bus 1H is deenergized; CC Pump 1A restarts 15 to 20

seconds after Bus 1H is reenergized.

C. CC Pump 1B starts 15 to 20 seconds after Bus 1H is reenergized; CC Pump 1A

starts 15 to 20 seconds after Bus 1H is reenergized.

D. CC Pump 1B starts 15 to 20 seconds after Bus 1H is reenergized; CC Pump 1A

remains deenergized.

A Incorrect. CC Pump 1B does start when bus 1H is deenergized due to CC Pump 1A

Trip (Breaker disagreement) but since Bus 1H is deenergized, it requires 15 to 20

seconds of normal voltage to restart.

B Correct. CC Pump 1B starts when bus 1H is deenergized due to CC Pump 1A Trip

(Breaker disagreement), the associated time delay is correct and is a design feature to

ensure EDG is maintained within voltage and frequency as loads are connected.

C Incorrect. Plausible because Pump 1B would operate this way if Bus 1J feeder

tripped. The time delay is associated with the bus supplying the affected pump.

D Incorrect. Plausible as in C, and also that Pump 1A would not restart, since 1B

would already be running and 1A would not be required.

Monday, June 30, 2008 3:34:31 PM 17

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of CCWS design feature(s) and/or interlock(s) which provide for the following:

Automatic start of standby pump

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.1

Technical Reference: CCWLP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 3656

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: KA is matched because item tests knowledge of auto start interlocks for both

standby pumps and pumps reenergized from undervoltage

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: BDAABAB B B C Scramble Range: A - D

Source: NEW Source If Banle

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:31 PM 18

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

10. 009 G2.4.4 059IMODIFIED/IHIGHERlIROINORTH ANNN6/20081

Given the following:

  • A LOCA has occurred.
  • The crew is performing 1-E-1, Loss of Reactor or Secondary Coolant.
  • The following conditions exist:
  • All SG pressures - 930 psig and slowly trending down.
  • All SG levels - being controlled at 42% NR.
  • PZR level- off-scale low.
  • Containment Pressure - 23 psia.
  • Containment Radiation levels - Rising.
  • RWST level - 32% and decreasing at 1% every 4 minutes.
  • RCS pressure - 800 psig and decreasing slowly.
  • Core Exit TCs - 500 degrees F.
  • RVLlS Full Range indication 94%.

Based on these indications, which ONE of the following procedure entry requirements

are met?

A. 1-FR-C.2, Response to Degraded Core Cooling

Bl" 1-ES-1 .2, Post-LOCA Cooldown and Depressurization

C. 1-ES-1.3, Transfer to Cold Leg Recirculation

D. 1-E-2, Faulted Steam Generator Isolation

A-Incorrect. (see B) Subcooling below minimum limit, plausible because RVLlS is less

than 100%, but not low enough for entry to FR-C.2.

B Correct. RCS Pressure is not stable, and at 1% per 3 minutes RWST reduction, it will

be more than 30 minutes to reach entry conditions for ES-1.3.

C Incorrect. RCS pressure and RWST level are high. Entry to ES-1.3 on low RWST

level plausible because eventually, entry conditions will be met. But they are met for

ES-1.2 now.

D Incorrect. SG pressures are trending down, which leads one to believe they must be

isolated in accordance with E-2, but incorrect because the RCS is leading the

cooldown, so SGs are not actully faulted, they are a heat source to the RCS.

Monday, June 30, 2008 3:34:31 PM 19

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Emergency Procedures / Plan: Ability to recognize abnormal indications for system operating

parameters which are entry-level conditions for emergency and abnormal operating

procedures.

Question Number:

Tier: 1

Group: 1

Importance Rating: 4.5

Technical Reference: E-O, F-O

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12203

Question History: WTSI Bank

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates system operating parameters (RCS, ECCS) related to entry to

EOPs, requiring the applicant to determine which entry requirements are met.

This item has been used before. Facility not identified, by nomenclature, it appears this item

was last used on the Wolf Creek AUDIT exam in 2006. Modified several values in stem and

changed option A

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: B B DAD D B B C B Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:31 PM 20

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

11.010 KS.OI 048INEW//lllGHERJIRO/NORTH ANNN6/2008/

Given the following:

  • The RCS is solid in Mode 5.
  • The crew is preparing to draw a bubble in accordance with 1-0P-1.1, Unit

Startup from Mode 5 at less than 140 degrees F to Mode 5 at less than 200

degrees F.

  • PZR pressure is approximately 325 psig.
  • PZR temperature is 335 degrees F.
  • RCS temperature is 180 degrees F.

Assuming PZR Heatup rate is at the administrative limit of 1-0P-1 .1, approximately

how long will it take to reach saturation conditions in the pressurizer, and what action

will be required when saturation conditions are reached?

A. 30 minutes; letdown flow will be manually increased to reduce Pressurizer level.

B. 30 minutes; the letdown backpressure control valve setpoint will be adjusted to

ensure charging and letdown flows are approximately equal while PZR pressure

rises.

Cr 60 minutes; letdown flow will be manually increased to reduce Pressurizer level.

D. 60 minutes; the letdown backpressure control valve setpoint will be adjusted to

ensure charging and letdown flows are approximately equal while PZR pressure

rises.

A Incorrect. Plausible because maximum tech spec heatup rate is 200 degrees F per

hour. Correct action for letdown flow (1-CH-PCV-1145 is in manual control).

B Incorrect. Plausible same reason as A. Incorrect action for letdown flow since

1-CH-PCV-1145 is in manual control and there must be a Charging/Ltdn mismatch to

drop level.

C Correct. Admin limit of 90 oF/hr means it will take approximately 60 minutes to reach

saturation in the PZR. Correct action for letdown flow (1-CH-PCV-1145 is in manual

control).

D Incorrect. Admin limit of 90o F/hr means it will take approximately 60 minutes to

reach saturation in the PZR so this part is Gorrect. Incorrect action for letdown flow

since 1-CH-PCV-1145 is in manual control and there must be a Charging/Ltdn

mismatch to drop level.

Monday, June 30, 2008 3:34:31 PM 21

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the operational implications of the following concepts as the apply to the PZR

PCS: Determination of condition of fluid in PZR, using steam tables

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.5

Technical Reference: 1-0P-1.1, Steam Tables

Proposed references to be provided to applicants during examination: Steam Tables

Learning Objective:

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates subcooling by asking how long it will take to reach saturation

conditions at a specified heatup rate that must be known by the applicant.

New item; have developed similar, but always have given actual heatup rate instead of asking

limit. Also, this facility draws a bubble in a different manner

MCS Time: I Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: CCDCDBDC BA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:31 PM 22

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

12. 011 EK2.02 004fNEW//LOWERlIRO/NORTH ANNA/6/2008/

Given the following:

  • A Large Break LOCA has occurred on Unit 1.
  • The crew has completed transition to 1-ES-1 .3, Transfer to Cold Leg

Recirculation.

Which ONE of the following describes the ECCS pump alignment when the initial

swapover to Cold Leg Recirculation is performed?

A~ Low Head SI Pump suction from Containment Sump; Charging Pump suction from

LHSI Pumps.

B. Low Head SI Pump discharge to RCS cold legs; Charging Pump suction from

Containment Sump.

C. Low Head SI Pump suction from Containment Sump; Charging Pump suction from

RWST.

D. Low Head SI Pump discharge to RCS Cold Legs; Charging Pump suction from

RWST.

A Correct. LHSI Pumps automatically swap to Containment Sump at 16% RWST level.

Alignment prior to returning to E-1 is to align LHSI to charging pump suction and to

close RWST suction valves for Charging Pumps.

B Incorrect. Plausible because ECCS does discharge to cold legs, and some LHSI flow

will go to cold legs, some will go to Charging, but Charging pumps are not aligned to

the sump. Plausible because LHSI does take suction from the sump.

C Incorrect. Plausible because suction source is correct, and also that charging is a

low volume injection, so the last step is to isolate Charging from the RWST, The

applicant may assume that the charging pumps are not realigned until the RWST

reaches 8%, as indicated by a caution in the procedure.

D. Incorrect. See explanations above.

Monday, June 30, 2008 3:34:31 PM 23

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 1508 RO ONLY

Knowledge of the interrelations between the Large Break LOCA and the following: Pumps

Question Number:

Tier: 1

Group: 1

Importance Rating: 2.6

Technical Reference: ES-1.3, through step 8

Proposed references to be provided to applicants during examination: None

Learning Objective: U 3412

Question History:

10 CFR Part 55 Content: 41 .10

Comments:

KA Match: Item evaluates operation of Charging and Low Head SI pumps following a Large

Break LOCA when swap to Cold Leg Recirculation is required. Therefore, the relationship

between the major pumps providing RCS makeup during a LOCA

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: A C B C B CAD A A Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:31 PM 24

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 041508 RO ONLY

13. 012 K6.04 050IMODIFIED//HIGHERI/ROINORTH ANNAl6120081

Given the following:

  • A plant load reduction is in progress.
  • Turbine First Stage Pressure Channel, 1-MS-PT-1446, sticks at a pressure

equivalent to 50% power.

  • Reactor power is currently 8%.

Which ONE of the following describes the RPS permissive affected, and the resulting

effect on the unit?

A. P-7 cannot be satisfied; the reactor would trip on loss of 1 RCP.

B. P-8 cannot be satisfied; the reactor would trip on loss of 1 RCP.

C,.. P-7 cannot be satisfied; the reactor would trip on loss of 2 RCPs.

D. P-8 cannot be satisfied; the reactor would trip on loss of 2 RCPs.

A Incorrect. The first part is true, P-7 cannot be satisfied in the current plant condition,

because one impulse pressure channel is stuck above 10%. This means that P-13

cannot be satisfied. P-7 requires input from P-13 and P-10. The second part is

incorrect but plausible because P-8 inputs the loss of flow trip on 2 RCPs.

B Incorrect. Plausible because the impulse channel is stuck at a value higher than the

P-8 power value. P-8 is input by power range instrumentation. Also plausible because

if the first half was true, the second half would also be true, because P-8 is the

permissive for the loss of flow trip - 1 RCP.

C Correct. P-7 cannot be satisfied because P-13 must be active (2/2 impulse

pressures <10%) for P-7 to be active. P-10 is active because 3/4 PR Nls are below

10%, but only solves half of the input for P-7 to be active.

o Incorrect. As described above P-8 is a function of NIS only. Low flow trip

combintation is incorrect, but could be chosen based purely on logic that with power

between 10% and 30% is the range for 2/3 10 flow trip.

Monday, June 30, 2008 3:34:32 PM 25

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the effect of a loss or malfunction of the following will have on the RPS:

Bypass/Block circuits

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.3

Technical Reference: RPS LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 16382

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item evaluates effect of a loss of P-7, Low Flow Reactor Trip block permissive, for a

plant condition that would require the that trip to be blocked.

Modified item previously developed by NRC; changed power level, and significantly changed

distractors.

MCS Time: Points: l.OO Version: 0 I 2 3 4 5 6 7 8 9

Answer: C C D D DCA A DC Scramble Range: A - D

Source: MODIFIED Source If Banle

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:32 PM 26

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

14. 013 AI.07 014INEW//HIGHER//ROINORTH ANNA/612008/

An event has occurred on Unit 1 resulting in core damage.

Containment pressure peaked at 28 psia and is now 16 psia and slowly trending down.

Containment radiation peaked at 2E+5R/hr and is now 1E+4R/hr and slowly trending

down.

Current Plant parameters are as follows:

  • RCS temperature is slowly trending down.
  • All SGs are 15% Narrow Range and rising.
  • AFW flow to each SG is 150 gpm.

The BOP recommends reducing AFW to 50 gpm to each SG to minimize RCS

cooldown.

Which ONE of the following describes how the crew should respond to the BOPs

recommendation and the Basis for their decision?

A. AFW may be reduced to 50 gpm to each SG since Adverse Containment Criteria

were cleared as Containment pressure decreased to the current value.

B. AFW may be reduced to 50 gpm to each SG since Adverse Containment Criteria

were cleared as Containment radiation decreased to the current value.

C. AFW must be maintained> 340 gpm total since Adverse Containment Criteria are

still in effect because of the Containment pressure transient.

D~ AFW must be maintained> 340 gpm total since Adverse Containment Criteria are

still in effect because of the Containment radiation transient.

Monday, June 30, 2008 3:34:32 PM 27

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

A Incorrect. Since CNTMT rad level exceeded 1E+5R1hr adverse numbers are still

required to be used; adverse criteria cannot be cleared when rad levels exceed

1E+5R1hr without an engineering evaluation. Would be correct if not for the

requirement to use adverse values.

B Incorrect. As noted above Adverse Containment criteria cannot be exited without an

Engineering Evaluation.

C Incorrect. First part of the distractor is true, however the reason adverse criteria is

required to be used is rad level going above 1E+5R1hr, NOT pressure.

D Correct. Because of the radiation transient adverse criteria cannot be exited so the

procedural requirement is to maintain 340 gpm total AFW flow.

013 Engineered Safety Features Actuation System (ESFAS)

A1.07 Ability to predict and/or monitor changes in parameters (to Prevent

exceeding design limits) associated with operating the ESFAS

controls including: Containment radiation

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.6

Technical Reference: E-O and ERG Background document

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History:

10 CFR Part 55 Content: 43.5

Comments:

Elevated containment radiation results in invoking of adverse CNTMT criteria; these criteria are

needed to ensure certain safety functions are met/maintained based on the assumed impact on

accident monitoring instrumentation. the operator must understand and correctly apply these

crieria in order to correctly operate this portion of ESFAS (AFW).

MCS Time: I Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: DDDDDDDDDD Items Not Scrambled

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:32 PM 28

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

15.013 K4.15 OOIINEW//LOWERlIROINORTHANNAl6/2008INO

The Unit is at 100% power.

Assume a failure of a semi-automatic tester board has occurred in the Solid State

Protection System resulting in a General Warning condition.

Which ONE of the following describes how the system is designed for the operator to

identify the condition and determine the affected Train?

A. A common Safeguards Trouble annunciator is provided in the control room;

indicating lights in Train A ONLY must be used to determine the affected Train.

B. Train specific Safeguards Trouble annunciators are provided in the control room;

indicating lights in Train A ONLY must be used to determine the affected Train.

C. A common Safeguards Trouble annunciator is provided in the control room;

indicating lights in Train A or Train B can be used to verify the affected Train.

Dr Train specific Safeguards Trouble annunciators are provided in the control room;

indicating lights in Train A or Train B can be used to verify the affected Train.

A Incorrrect. Plausible because many alarms have multiple inputs and the candidate

who is unfamiliar with the system is likely to default to the common alarm, similarly the

candidate may assume that one can only identify a general warning condition in the

affected train (this is NOT the case) and infer that train A is affected since this

distractor directs looking in one train to identify the condition.

B Incorrrect. First part is true train specific alarms are provided, as stated above the

candidate may assume that one can only identify a general warning condition in the

affected train (this is NOT the case) and infer that train A is affected since this

distractor directs looking in one train to identify the condition.

C Incorrrect. Plausible because many alarms have multiple input and the candidate

who is unfamiliar with the system is likely to default to the common alarm, 2nd part is

correct, as part of the design feature of the system status light in each train show the

status of both trains, although primarily intended as a means of monitoring status

during surveillance testing they will provided the same information for the conditions

given in the stem.

D Correct. The*trouble alarm will alert the operator to the problem, looking in either

rack will allow the operator to determine that the trouble annunciator is due to a general

warning and using the amber and green lights provided, verify which train is affected

and verify that the opposite train is unaffected.

Monday, June 30, 2008 3:34:32 PM 29

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

013 Engineered Safety Features Actuation System (ESFAS)

Knowledge of ESFAS design feature(s) and/or interlock(s) which provide for the following:

Continuous testing

Question Number:

Tier: 2

Group: 1

Importance Rating: 2.6

Technical Reference: AR, RPS Lesson Plan

Proposed references to be provided to applicants during examination: None

Learning Objective: 8958

Question History:

10 CFR Part 55 Content: 41.7

Comments:

NAPS does not have a continuous testing feature that is found in some plant designs. Per

discussion w/USNRC R-II, this meets the intent of the KA in that it tests the operators

knowledge of how the system is designed to alert the operator to an abnormal condition within

a train and how the affected train can be verified (verification of status of both trains relative to

a general warning condition)

MCS Time: 1 Points: 1.00 Version: a 1 2 345 6 7 8 9

Answer: DDDDDDDDDD Items Not Scrambled

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?: NO

Monday, June 30, 2008 3:34:32 PM 30

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

16. 015 AKl.07 005IBANKlIHIGHERlIROINORTH ANNN6/20081

Given the following:

  • Unit 1 is at 100% power.
  • The following alarm is received:
  • RCP 1B Seal Leakoff flow is 5.9 GPM and slowly rising.
  • RCP 1B No.1 Seal DP indicates 220 psid and lowering slowly.
  • Seal leakoff has lowered on RCP 1A and 1C.
  • Seal Return temperature is rising slowly.

Which ONE of the following describes the event in progress and the action required?

A'! RCP #1 seal failure; trip the reactor, trip the RCP, and isolate sealleakoff within

5 minutes.

B. RCP #1 seal degraded; monitor RCP bearing temperatures and initiate a plant

shutdown to Hot Standby.

C. RCP #2 seal failure; trip the reactor, trip the RCP, and isolate sealleakoff within

5 minutes.

D. RCP #2 seal degraded; monitor RCP bearing temperatures and initiate a plant

shutdown to Hot Standby.

A Correct. If the seal is not holding, leakoff will rise, and DP will go toward O. If #1 seal

has failed in this way, then a reactor trip is required.

B Incorrect. Plausible because this action would be taken for a seal failure where

leakoff flow was low <<.8 gpm).

C Incorrect. #2 Seal failure is indicated by a standpipe high level alarm. In this case,

the alarm is not lit. Plausibility is maintained because the applicant must determine

failure based on conditions, and also because the standpipe can be associated with #3

seal.

D Incorrect. As noted above degradation of #2 seal will cause decreased #1 seal

leakoff, however indications provided are indicative of athe more severe condition of

failure of the #1 seal. Candidate may choose this if they are unfamiliar with seal failure

diagnostics.

Monday, June 30, 2008 3:34:32 PM 31

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the interrelations between the Reactor Coolant Pump Malfunctions (Loss of RC

Flow) and the following: RCP seals

Question Number:

Tier: 1

Group: 1

Importance Rating: 2.9

Technical Reference: 1-AP-33.1

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11101

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: The item evaluates an RCP malfunction by evaluating an RCP seal failure,

demonstrating that the topic related to knowledge of interrelations between RCP Malfunctions

and RCP seals is met.

This item was developed without use of the bank but there are very similar bank items available

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: A C B B DC D D C C Scramble Range: A - D

Source: BANK Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:32 PM 32

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

17.016 Kl.02 072INEW//HIGHERlIROINORTH ANNA/6/2008/

Given the following:

  • Unit 1 is operating at 50% power.
  • All Control systems are in automatic.
  • Loop 1B Tcold RTD fails low.

Which ONE of the following describes the response of the Pressurizer Level Control

System and Rod Control System?

A. Charging flow decreases; Control rods step OUT.

B. Charging flow decreases; Control rods do not move.

C. Charging flow remains constant; Control rods step OUT.

D~ Charging flow remains constant; Control rods do not move.

A Incorrect. Applicant may misunderstand and assume the failure affects the control

circuit (not selected out by Median Signal Selector) since pzr Ivl program and rod

control program are both a funtion of temperature it is reasonable to assume both

would respond.

B Incorrect. Plausible as in A, but also takes into account the existence of OPdT and

OTdT rod stops, although logic is 2/3 the candidate may confuse woth the over power

rod stop which only requires a single channel, in that case it would be plausible for PZR

level program to be affected but rods to remain stationary.

C Incorrect. Plausible if candidate assumes that PZR level control sip is function of a

different process input (e.g. 1st stage pressure, N-44 power, etc..).

D Correct. The failure affects the subject protection channel but is selected out as a

function of the Median Signal Selector.

Monday, June 3D, 2008 3:34:32 PM 33

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the physical connections and/or cause-effect relationships between the NNIS

and the following systems: PZR LCS

Question Number:

Tier: 2

Group: 2

Importance Rating: 3.4

Technical Reference: PZR Press/Lvi Ctrl LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 10654

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item evaluates NNIS (RTD) failure for input to PZR level control

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: DADADAB C DA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:32 PM 34

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

18. 017 A4.02 074IMODIFIED/IlDGHERlIRO/NORTH ANNN6120081

Given the following:

  • A LOCA has occurred on Unit 1.
  • 1A Charging Pump is tripped.
  • 18 Charging Pump is running.
  • 80TH LHSI Pumps are tripped.
  • RCS pressure is 1600 psig and lowering.
  • Containment pressure peaked at 21 psia and is now slowly trending down.
  • Core Exit T/Cs are 545 degrees F.

Which ONE of the following describes the requirement for operation of RCPs in

the present condition, and the reason why?

A. RCPs should remain running because ECCS flow is inadequate to ensure adequate

core cooling.

8. RCPs should remain running because forced circulation provides sufficient core

cooling until RCP trip criteria is met.

C~ RCPs should be stopped because an inadequate core cooling condition could

develop if RCPs were tripped or lost later in the event.

O. RCPs should be stopped to prevent damage to the RCPs due to loss of cooling

water.

A Incorrect. One Charging pump is running. Only 1 charging pump is required to be

running to allow for RCP trip. Plausible because all other ECCS flow is lost and

applicant could believe that both must be running. Also, applicant may miss adverse

containment and believe they should be running because RCS subcooling is adequate

8 Incorrect. Statement is true if RCPs should remain running, but subcooling is below

85 degrees F, and they should be tripped because containment is >20 psia

C Correct. ERG executive volume contains RCP trip/restart discussion, and concern is

that if they are allowed to remain running under certain S8LOCA scenarios, and they

are tripped later in the event, the core could uncover.

o Incorrect. Containment pressure was never high enough for COA that would cause

the loss of cooling water. (28 PSIA). Plausible because other ESFAS actuations have

ocurred and the applicant may misunderstand that CC isn't lost until after COA.

Monday, June 30, 20083:34:32 PM 35

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to manually operate and/or monitor in the control room: Temperature values used to

determine RCS/RCP operation during inadequate core cooling (i.e., if applicable, average of

five highest values)

Question Number:

Tier: 2

Group: 2

Importance Rating: 3.8

Technical Reference: E-O Continuous action page, ERG Exec Volume

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12451

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: item evaluates RCP operation under a temperature-pressure relationship from

indications provided by the ICCM and other plant conditions. The KA is met because RCP

operation is being determined based on margin to saturation.

A question evaluating the exact wording of the KA would have been double jeopardy with

Question 82. NRC directed to develop an item on this topic instead of allowing KA swap.

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: CADAB CBCAD Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: IDGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:32 PM 36

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

19.022 A2.06 053INEW//lllGHERiIRO/NORTH ANNA/6/2008/

Given the following:

  • Unit 1 is at 100% power.
  • The Mechanical Chiller has tripped and cannot be restarted.
  • The crew enters 1-AP-35, Loss of Containment Air Recirculation Cooling.

Which ONE of the following describes the MINIMUM containment temperature

requiring entry into a Technical Specification action statement, and the action required?

A. 105 degrees F; ensure steam chiller running or align Service Water to Containment

Air Recirc Fans.

B. 105 degrees F; ensure Containment Air Recirc Fans are running with backdraft

dampers closed.

C~ 115 degrees F; ensure steam chiller running or align Service Water to Containment

Air Recirc Fans.

D. 115 degrees F; ensure Containment Air Recirc Fans are running with backdraft

dampers closed.

A Incorrect. Temperature is incorrect but plausible because the procedure designates

105 degrees F as the minimum temperature.

8 Incorrect. Same as A, and also the action may be performed later but backdraft

dampers must be checked open. Plausible because it is reasonable to believe that a

backdraft damper should be closed to prevent short-cycling of air.

C Correct. TS LCO is 115 degrees F is correct. Procedure provides option of Steam

Chiller or Sevice Water to provide Containment cooling for the case where the

Mechanical Chiller is unavailable.

D Incorrect. TS LCO is 115 degrees F is correct. Incorrect for same reason as second

half of B.

Monday, June 30, 2008 3:34:32 PM 37

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

CNTMT Cooling: Ability to (a) predict the impacts of the following malfunctions or operations on the CCS;

and (b) based on those predictions, use procedures to correct, control, or mitigate the consequences of

those malfunctions or operations: Loss of CCS pump

Question Number:

Tier: 2

Group: 1

Importance Rating: 2.8

Technical Reference: 1-AP-35, tech specs

Proposed references to be provided to applicants during examination: None

Learning Objective: U 1958

Question History:

10 CFR Part 55 Content: CFR: 41.5 / 43.5 / 45.3 / 45.13

Comments:

KA Match: Item evaluates knowledge for the equivalent of a CCS pump at North Anna; it tests

knowledge of the effect and actions taken for trip of the Mechanical Chiller, which provides

normal containment cooling for CAR Fans. .

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: CDCBABACAC Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: mGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:33 PM 38

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

20. 022 AK3.03 006INEW/tmGHERJ/ROINORTH ANNA/6/2008/

Given the following:

  • Unit 1 is at 100% power following a refueling outage.
  • The crew has isolated a Letdown line leak in accordance with 1-AP-16,

Increasing Primary Plant Leakage.

  • The crew is preparing to place Excess Letdown in service.
  • Excess Letdown will be aligned to the VCT.

Which ONE of the following describes restrictions on the Excess Letdown Lineup, and

the reason for the restrictions?

A. Flow through ONLY one loop drain to prevent the possibility of bypassing 81 flow to

the 2 intact loops in a design basis accident;

reactor power should be monitored because a dilution may occur due to lower

boron concentrations in the Excess Letdown piping.

B~ Flow through ONLY one loop drain to prevent the possibility of bypassing 81 flow to

the 2 intact loops in a design basis accident;

reactor power should be monitored because a boration may occur due to higher

boron concentrations in the Excess Letdown piping.

C. Excess Letdown Pressure must NOT exceed 75 psig to prevent overpressurizing

the VCT;

reactor power should be monitored because a dilution may occur due to lower

boron concentrations in the Excess Letdown piping.

D. Excess Letdown Pressure must NOT exceed 75 psig to prevent overpressurizing

the VCT;

reactor power should be monitored because a boration may occur due to higher

boron concentrations in the Excess Letdown piping.

Monday, June 30, 2008 3:34:33 PM 39

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

A Incorrect. The first half is correct. The second half is incorrect but plausible because

a reactivity event may occur, and it is reasonable to assume that it is a dilution similar

to ion exchange beds being placed in service.

B Correct. Basis for using ONLY one loop is correct. 1-0P-8.5 cautions the operator

about the potential for boration based on the likely condition that excess letdown will

have likely last been used during the outage with boron concentration much higher than

current Cb.

C Incorrect. Excess Letdown is maintained less than 150 psig. VCT pressure is

maintained less than 75 psig. If the pressure was correct, the first half of this option

would be correct. As noted above the procedure addresses boration concern not

dilution.

o Incorrect. Same as C regarding pressure concern, but the reactivity caution is

correct.

Knowledge of the reasons for the following responses as they apply to the Loss of Reactor

Coolant Makeup: Performance of lineup to establish excess letdown after determining need

Question Number:

Tier: 1

Group: 1

Importance Rating: 3.1

Technical Reference: 1-0P-8.5

Proposed references to be provided to applicants during examination: None

Learning Objective: U 338, 340, 345

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Item evaluates knowledge of 2 precautions and further evaluates reason for the 2

precautions associated with establishing Excess Letdown, therefore meeting the KA topic

requirement.

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: B DB DBA A C B D Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:33 PM 40

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

21. 022 Kl.04 OOIINEW//IllGHERlIROINORTH ANNAl61200S/

Both Units are at 100%.

  • A fault on the Unit 2B station service bus results in a Main Generator Lockout

and Reactor Trip.

  • All Unit 2 Station Service Busses are deenergized due to the feeder breaker to

2B Station Service bus failing to open on the fault.

Which ONE of the following describes the status of Containment cooling to the Units?

A. Containment Air Recirc Fans remain running on BOTH Units; Chilled water flow to

Containment Air Recirc Fans is lost on Unit 2 ONLY.

B~ Containment Air Recirc Fans remain running on BOTH Units; Chilled water flow to

Containment Air Recirc Fans is lost on BOTH Units.

C. Containment Air Recirc Fans trip on Unit 2; Chilled water flow to Containment Air

Recirc Fans is lost on Unit 2 ONLY.

D. Containment Air Recirc Fans trip on Unit 2; Chilled water flow to Containment Air

Recirc Fans is lost on BOTH Units.

A Incorrect. Fans remain running since they are powered from emergency busses not

SS busses, chilled water flow is lost but both units are affected, plausible since the

electrical problem relates only to Unit 2.

B Correct. As noted above, the mechanical chiller is powered from Unit 2 SS bus and

supplies both units with chilled water.

C Incorrect. Plausible since candidate may assume the electrical fault would cause a

loss of power to the affected equipment and again may only consider Unit 2 affected by

the loss of power.

o Incorrect. Plausible since candidate may assume the electrical fault would cause a

loss of power to the affected equipment and again 2nd part of distractor is correct.

Monday, June 30, 2008 3:34:33 PM 41

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

CNTMT Cooling: Knowledge of the physical connections and/or cause-effect relationships

between the CCS and the following: Chilled water

Tier: 2

Group: 1

Importance Rating: 2.9

Technical Reference: 1-AP-35, O-AP-10

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11999

Question History:

10 CFR Part 55 Content: CFR: 41.5/43.5/45.3/45.13

Comments:

KA Match: The item evaluates the status of Chilled Water for Containment Cooling during a

loss of off-site power.

MCS Time: 1 Points: 1.00 Version: o 1 2 3 4 5 6 7 8 9

Answer: BBBBBBBBBB Items Not Scrambled

Source: NEW Source If Bank:

Cognitive Level: mGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:33 PM 42

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

22.025 AAl.12 098lNEW/IHIGHERJIROINORTH ANNAl612008INO

Given the following:

  • Unit 1 has just entered Mode 4 with cooldown to Mode 5 in progress.
  • RHR Pump 1A is in service.
  • The OATC notes the following:
  • RHR Pump 1A motor amps indicate10 and stable.
  • 1-RH-FCV-1605 in automatic indicates 100% demand.

Which ONE of the following describes the status of the RHR system and the additional

expected indications?

A. RHR pump 1A cavitating,1-RHR-FCV-1605 operating as designed; Core Exit TCs

increasing.

B. RHR pump 1A operating normally, 1-RHR-FCV-1605 failed closed; Core Exit TCs

decreasing.

C~ RHR pump 1A sheared shaft, 1-RHR-FCV-1605 operating as designed; Core Exit

TCs increasing.

D. RHR pump 1A operating normally, 1-RHR-FCV-1605 failed open; Core Exit TCs

decreasing.

A Incorrect. As given amps are low but stable, fluctuating amps are indication of

cavitation. For low flow 1-RH-FCV-1605 would be expected to open to try and maintain

flow. Inadequate flow would cause temperature to increase.

8 Incorrect. The value of 10 and stable is indicative of a sheared shaft NOT a pump

that is operating normally. For the sheared shaft 1-RH-FCV-1605 would be expected to

open to try and maintain flow. Inadequate flow would cause temperature to increase.

C Correct. Normal amps would be around 35, the value of 10 and stable is indicative of

a sheared shaft. For the sheared shaft 1-RH-FCV-1605 would be expected to open to

try and maintain flow. Inadequate flow would cause temperature to increase.

o Incorrect. The value of 10 and stable is indicative of a sheared shaft NOT a pump

that is operating normally. For the sheared shaft 1-RH-FCV-1605 would be expected to

open to try and maintain flow. Inadequate flow would cause temperature to increase

not decrease, however if flow were high temperature would decrease.

Monday, June 30, 2008 3:34:33 PM 43

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Loss of RHR: Ability to operate and / or monitor the following as they apply to the Loss of

Residual Heat Removal System: RCS temperature indicators

Question Number:

Tier: 3

Group: 4

Importance Rating: 3.8

Technical Reference: AP-11, Pages 2-13 actions

Proposed references to be provided to applicants during examination: None

Learning Objective: U430

Question History: Bank item with distractor modifications

10 CFR Part 55 Content: 41.10

Comments:

KA match: The KA is matched because the operational implication of loss of RHR during RCS

drain-down is that specific actions must be taken to mitigate the condition. This item evaluates

knowledge of the correct actions during this condition, choosing from actions that may be

performed for all conditions of loss of RHR

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: C A C D A C CDC D Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?: NO

Monday, June 30, 2008 3:34:33 PM 44

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

23. 026 A4.01 056INEW//LOWERlIROINORTH ANNA/6/2008/

Given the following:

  • RCS pressure is 1000 psig and stable.
  • Containment pressure is 23 psia and rising slowly.
  • The crew is performing 1-E-0, Reactor Trip or Safety Injection.

Which ONE of the following describes the appropriate operator action and the

SEQUENCE of the action required?

A. CDA is required; ensure CDA is actuated, stop RCPs, verify Quench Spray running,

and verify Containment Isolation Phase B.

B. CDA is required; ensure CDA is actuated, stop CC pumps, verify Quench Spray

running, verify Containment Isolation Phase B, and stop RCPs.

C~ Quench Spray is required; open Quench Spray Discharge Valves and then start

Quench Spray Pumps.

D. Quench Spray is required; start Quench Spray Pumps and then open Quench

Spray discharge valves.

A Incorrect. CDA would be required if containment pressure was >28 psia. Plausible

because if it was required, these are the correct actions.

B Incorrect because CDA is not required. Plausible because it contains all correct

actions, but not in the order required.

C Correct. Even though CDA is not required, facility has a step in E-O to initiate QSS if

containment is above 20 psia.

D Incorrect. Plausible because many pumps are started with discharge valves closed.

In this case, valves are opened first.

Monday, June 30, 2008 3:34:33 PM 45

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to manually operate and/or monitor in the control room: CSS controls

Question Number:

Tier: 2

Group: 1

Importance Rating: 4.5

Technical Reference: 1-E-O steps 11/12

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates the ability to determine if Quench Spray is required, and since it is

required, the actions required (operating the controls) to initiate it

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: C C BAD C B CAD Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:33 PM 46

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

24. 026 AA2.0 1 005IBANKINORTH ANNAlLOWERlIROINORTH ANNA/6/2008/

Given the following:

  • The unit is operating at 100% power.
  • CC Surge Tank level indication on 1-CC-L1-101 is 50% and lowering.

Which ONE (1) of the following is a possible source of the leak and the source of water

for maintaining CC System inventory?

A. 1A CC Heat Exchanger; PG water

B:' 1A CC Heat Exchanger; Condensate System

C. Non-Regenerative Heat Exchanger; PG water

D. Non-Regenerative Heat Exchanger; Condensate System

A Incorrect. First part is correct, Service Water pressure is less than CC pressure so

this would cause the loss of CC. PG water would not normally be used.

B Correct. Service Water pressure is less than CC pressure so this would cause the

loss of CC, condensate is used to fill CC if it is available.

C Incorrect. Surge tank level would rise since pressure at that point in the letdown

system (upstream of PCV-1145) is greater than CC system pressure, source of water

plausible but also not correct per the procedure.

o Incorrect. Surge tank level would rise since pressure at that point in the letdown

system (upstream of PCV-1145) is greater than CC system pressure, water source is

correct.

Monday, June 30, 2008 3:34:33 PM 47

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to determine and interpret the following as they apply to the Loss of Component Cooling

Water: Location of a leak in the CCWS

Question Number:

Tier: 1

Group: 1

Importance Rating: 2.9

Technical Reference: CC LP, 1-AP-16

Proposed references to be provided to applicants during examination: None

Learning Objective: U 3663

Question History:

10 CFR Part 55 Content: 41.5,7

Comments:

KA Match: Item evaluates knowledge of components served by CC, and further evaluates

knowledge of the makeup sources. The applicant must determine location of a leak in CC to

answer this item.

Considered BANK; although not identical to bank question this item has not been significantly

modified, thus it is classified as a bank question.

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: B C A A A A C B D B Scramble Range: A - D

Source: BANK Source If Bank: NORTH ANNA

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:33 PM 48

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

25. 026 K2.01 055lNEW/IHIGHERJIROINORTH ANNN6/2008INO

Given the following on Unit 1:

  • Safety Injection was actuated 11 minutes ago.
  • CDA was actuated 7 minutes ago.
  • RCS pressure is 1125 psig.
  • Containment pressure is 29 psia.
  • RWST level is 72% and lowering.

Which ONE of the following describes the operational status of Inside Recirculation

Spray Pump 1-RS-P-1 8?

A. Running; power is supplied directly from 480 volt bus 1J1.

8~ NOT running; power is available directly from 480 volt bus 1J1.

C. Running, power is supplied directly from 4160 volt bus 1J.

D. NOT running; power is available directly from 4160 volt bus 1J.

A Incorrect. The pump will not be running because RWST level is not below 60%.

Plausible because the start logic is associated with CDA and also has a time delay; if

candidate is unaware of the aditionallogic (RWST level < 60%) they may select this

distractor. Power supply is correct.

8 Correct. The pump will not be running because RWST level is not below 60%.

Power supply is correct.

C Incorrect. The pump will not be running because RWST level is not below 60%.

Plausible because the start logic is associated with CDA and also has a time delay; if

candidate is unaware of the aditionallogic (RWST level < 60%) they may select this

distractor. Power supply is correct for Outside Recirc Spray Pumps.

D Incorrect. Correct that the pump will not be running because RWST level is not

below 60%. Incorrect because power supply is wrong. Plausible because the power

supply is correct for Outside Recirc Spray Pumps.

Note: Change in RS pump logic is a recent plant mod making it more likely that the

candidate will confuse pump operational status based on past knowledge.

Monday, June 30, 2008 3:34:33 PM 49

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of bus power supplies to the following: Containment spray pumps

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.4

Technical Reference: Recirc Spray LP, NCRODP-54

1-E-O, Art. 2

1-0P-26A

Proposed references to be provided to applicants during examination: None

Learning Objective: U 6278

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: The KA requires knowledge of Spray Pump power supplies. The item evaluates

knowledge of Spray Pump power supply as well as operation under transient conditions

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: B DCA D D D A C A Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?: NO

Monday, June 30, 20083:34:33 PM 50

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

26. 027 G2.2.42 OlIIMODIFIED//LOWERJIROINORTH ANNAl61200S1

Given the following:

  • Unit 1 is operating at 100% power.
  • An instrument failure causes PORV 1-RC-PCV-1455C to lift.
  • RCS Pressure is recovering at a much slower rate than expected.
  • The operator closes the PORV Block Valve, 1-RC-MOV-1536, and pressure is

now 2100 psig and increasing as expected.

  • All other equipment appears to be operating normally.

Which ONE (1) of the following describes the action(s) required within ONE hour in

accordance with Technical Specifications?

A. Maintain closed and remove power from 1-RC-MOV-1536.

B. Restore RCS pressure to within limits of the COLA.

C~ Maintain closed and maintain power to 1-RC-MOV-1536.

D. Place and maintain the PORV in MANUAL control.

A Incorrect because for this condition, power does not have to be removed from the

block valve. Plausible because it is very close to the correct action, and an

interpretation must be made to determine if seat leakge is occurring.

B Incorrect. This action is taken, therefore plausible. However, 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> is allowed for

the action to be taken.

C Correct. PORV inoperability due to excessive seat leakage (as indicated by the

conditions provided) requires that the VALVE IS ISOLATED BY ITS ASSOCIATED

BLOCK VALVE. However power is maintained to the block to allow quick access if the

PORV were needed for pressure control.

D Incorrect. Action would be required if the block valve was inoperable, but plausible

because it is easily confused with inoperability of the PORV itself (controller not

functioning in auto, place in manual).

Monday, June 30, 2008 3:34:34 PM 51

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Equipment Control:: Ability to recognize system parameters that are entry-level conditions for

Technical Specifications.

Question Number:

Tier: 1

Group: 1

Importance Rating: 3.9

Technical Reference: TS 3.4.1, 3.4.11

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12363

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item evaluates LCO entry conditions for a condition where there is a failure of the

pressurizer pressure control system (PORV failure).

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: C A ADD B D B D C Scramble Range: A - D

Source: MODIFIED Source If Banle

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:34 PM 52

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

27.028 K3.01 027INEW//LOWERlIROINORTH ANNN6/2008INO

Given the following:

  • Both Units were initially at 100%.
  • The Site experiences a Loss of Offsite Power.
  • Unit 1 experiences a Design Basis Accident with a failure of 1H EDG.
  • Unit 2 is stable in Mode 3 with both Emergency Busses energized from their

respective EDGs.

Which ONE of the following describes the operation of the 1-HC-HC-1, Hydrogen

Recombiner?

A. 1-HC-HC-1 should be placed in service if Containment Hydrogen concentration is

less than 4%; Power MUST be restored to 1H Bus to place 1-HC-HC-1 in operation.

B~ 1-HC-HC-1 should be placed in service if Containment Hydrogen concentration is

less than 4%; Power is available to place 1-HC-HC-1 in operation.

C. 1-HC-HC-1 should be placed in service if Containment Hydrogen concentration

exceeds 4%; Power MUST be restored to 1H Bus to place 1-HC-HC-1 in operation.

D. 1-HC-HC-1 should be placed in service if Containment Hydrogen concentration

exceeds 4%; Power is available to place 1-HC-HC-1 in operation.

A Incorrect. Either of the two recombiners may be powered from any of the 4

Emergency Busses; plausible because the candidate may believe that since the

recombiners have unit specific mark numbers they also have unit specific power

supplies and most ESF equipment is powered from a dedicated train. The recombiner

is placed in service when CNTMT H2 cone. exceeds 0.5% but is less than 4%, so this

portion of the distractor is correct.

B Correct. As stated above, either of the two recombiners may be powered from any of

the 4 Emergency Busses. The recombiner is placed in service when CNTMT H2 cone.

exceeds 0.5% but is less than 4%.

C Incorrect. Either of the two recombiners may be powered from any of the 4

Emergency Busses; plausible because the candidate may believe that since the

recombiners have unit specific mark numbers they also have unit specific power

supplies and most ESF equipment is powered from a dedicated train. At greater than

4% the procedure directs consulting with TSC, NOT placing recombiner inservice.

D Incorrect. First part of distractor is correct as noted above. At greater than 4% the

procedure directs consulting with TSC, NOT placing recombiner inservice so this

portion is incorrect.

Monday, June 30, 2008 3:34:34 PM 53

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

028 K3.01

Knowledge of the effect that a loss or malfunction of the HRPS will

have on the following: Hydrogen concentration in containment

Question Number:

Tier: 2

Group: 2

Importance Rating: 3.3

Technical Reference: 1-E-1

1-0P-63.1

Proposed references to be provided to applicants during examination: None

Learning Objective:

10 CFR Part 55 Content: CFR: 41.7 / 45.6

Comments:

MCS Time: Points: 1.00 Version: a I 2 3 4 5 6 7 8 9

Answer: B B B B B B B B B B Items Not Scrambled

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?: NO

Monday, June 30, 2008 3:34:34 PM 54

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

28. 029 EKl.05 Ol2IBANKIROBINSON 2001ILOWERlIROINORTH ANNA/6/2008/

During an ATWS at 100% Reactor Power, EOl conditions, which ONE of the following

actions will insert the MOST negative reactivity within the FI RST 30 seconds of the

event?

A. Manual Control Rod Insertion

B:' Manual Turbine Trip

C. Initiation of Emergency Boration

D. Automatic Control Rod Insertion

A Incorrect. Manual control rod insertion will be at 48 steps per minute. Plausible

because it is in the first step of FR-S.1 and it does insert negative reactivity.

B Correct. When the turbine is tripped, RCS temperature and fuel temperature will rise

rapidly, and cause reactor power to be sharply reduced.

C Incorrect. Initiation of Emergency Boration will also cause negative reactivity

insertion, but will not reach the RCS until several minutes have elapsed in the event.

D Incorrect. Auto rod insertion maximum speed is 72 steps per minute. Plausible

because it inserts reactivity and is the first control system response to the ATWS, but

does not insert as much negative reactivity as a turbine trip.

Monday, June 30, 2008 3:34:34 PM 55

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the operational implications of the following concepts as they apply to the

ATWS: definition of negative temperature coefficient as applied to large PWR coolant systems

Question Number:

Tier: 1

Group: 1

Importance Rating: 2.8

Technical Reference: FR-S.1 SD

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11570

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Item evaluates the action or plant response that would add the most negative

reactivity, which is a direct relation to negative temperature coefficient. Therefore, it evaluates

applicants knowledge of the definition of negative temperature coefficient

MCS Time: Points: l.00 Version: 0 I 2 3 4 5 6:] 8 9

Answer: B B D A A C C B D B Scramble Range: A - D

Source: BANK Source If Bank: ROBINSON 200 I

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:34 PM 56

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

29. 029 K4.03 077INEW/ILOWERJIRO/NORTH ANNAl6/20081

Given the following:

  • Both units are in Mode 5.
  • Containment Purge is in progress on each unit in preparation for Containment

entry.

  • Unit 1 Manipulator Crane Area Radiation Monitor RM-162 indication is rising.
  • Unit 1 Containment Particulate and Gaseous Radiation Monitors, RM-159 and

160 are in alarm.

  • Unit 2 containment conditions are normal.

Which ONE of the following describes the effect of these conditions on the

Containment Purge once all automatic actuations have taken place?

A. Purge Supply Fans 1-HV-F-4A and 1-HV-F-4B trip; Containment Purge Supply

isolation valves close on BOTH units.

B. ONLY Purge Supply Fan 1-HV-F-4A trips; ONLY Unit 1 Containment Purge Supply

isolation valves close.

C. Purge Supply Fans 1-HV-F-4A and 1-HV-F-4B remain running; ONLY Unit 1

Containment Purge Supply isolation valves close.

D~ Purge Supply Fans 1-HV-F-4A and 1-HV-F-4B trip and then automatically start;

ONLY Unit 1 Containment Purge Supply isolation valves close.

A Incorrect. Plausible because the Purge Supply fans do trip, but valves on unaffected

unit do not close.

B Incorrect. Plausible because the 4A fan control switch is on Unit 1 and the 4B on

Unit 2, and it is logical to believe that Unit 2 will be unaffected.

C Incorrect. Plausible because with 2 units being purged, the affected unit will isolate,

and there is still a flowpath for fans to operate as required without interuption.

o Correct. The purge fans will initially trip however once the valves on the affected unit

close the logic is satisfied for the fans to restart (valves on unaffected unit remain open

and the release flow path from the affected unit is isolated).

Monday, June 30, 2008 3:34:34 PM 57

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of design feature(s) and/or interlock(s) which provide for the following: Automatic

purge isolation

Question Number:

Tier: 2

Group: 2

Importance Rating: 3.2

Technical Reference: Primary Ventilation LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 4494, 4492

Question History:

10 CFR Part 55 Content: 41.11

Comments:

KA Match: Item evaluates an abnormal condition requiring an automatic containment purge

isolation, and therefore directly meets the required topic

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: DB BACACBDA Scramble Range: A - D

'Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:34 PM 58

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

30.032 AK3.01 026IBANKlHARRISIHIGHERJIROINORTH ANNA/6/2008/

Given the following conditions:

  • A reactor startup is in progress and operators have just completed a rod pull.
  • Both Intermediate Range channels indicate approximately 3 E -11 amps and

trending up.

  • Source Range Channel N-31 indicates 1X103 CPS and is trending down slowly.
  • Source Range Channel N-32 indicates approximately 6X1 03 CPS and trending

up slowly.

Which one of the following describes the required operator response and the reason

for the response?

A':' Suspend the reactor startup; with only one source range channel operable, there is

inadequate protection against an uncontrolled rod withdrawal.

B. Suspend the reactor startup; source range channels are currently not required to

trip the reactor, however, the source range monitoring functions must be available.

C. Continue the reactor startup; the Intermediate Range Neutron Flux Trip and the

Power Range Neutron Flux-Low Trip provide the necessary core protection.

D. Continue the reactor startup; with only one source range channel operable 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />

is allowed to restore two channels to service.

A Correct. With only 1 Source Range available below P-6, (10-10 amps), the startup

must be stopped because a single failure would now make the SR high flux trip

unavailable.

B Incorrect. Plausible because tech specs requires the SR in lower modes, and this

would be true if rod control was not capable of withdrawal.

C Incorrect. Plausible because the SR provides redundant protection to these trips.

D Incorrect. Plausible because this is the normal TS action statement if rods were not

capable of withdrawal.

Monday, June 30, 2008 3:34:34 PM 59

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the reasons for the following responses as they apply to the Loss of Source

Range Nuclear Instrumentation: Startup termination on source-range loss

Question Number:

Tier: 1

Group: 2

Importance Rating: 3.2

Technical Reference: TS 3.3.1 and basis

Proposed references to be provided to applicants during examination: None

Learning Objective: U 10390

Question History:

10 CFR Part 55 Content: 41.7,43.2

Comments:

KA Match: Item evaluates knowledge of the reason for startup termination as well as whether

termination is required, based on plant conditions that require operability of the instrument

Item was previously developed for Harris, but has been editorially modified with a different

reason on correct answer and shuffled distractors, as well as modified wording on plant

conditions.

MCS Time: Points: 1.00 Version: 0123456789

Answer: AC C C B DADB A Scramble Range: A - D

Source: BANK Source If Bank: HARRIS

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:34 PM 60

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

31. 033 K4.05 028IBANKINORTH ANNAILOWERJIRO/NORTH ANNN6/2008NES

Which ONE of the following describes the preferred method for maintaining Spent Fuel

Pool water volume and Subcriticality Margin?

Minimum required boron concentration is...

A. 2500 ppm. Leakage is compensated for by making up from the blender with PG

water.

B. 2500 ppm. Leakage is compensated for by making up from the blender with

blended flow.

C~ 2600 ppm. Evaporation is compensated for by making up from the blender with PG

water.

D. 2600 ppm. Evaporation is compensated for by making up from the blender with

blended flow.

A Incorrect. 2500 ppm is incorrect but plausible because it is the minimum boron

concentration allowed for SI Accumulators.

B Incorrect. 2500 ppm is incorrect but plausible because it is the minimum boron

concentration allowed for SI Accumulators. Boric Acid blender is used for makeup

when leakage is evident.

C Correct. Minimum boron concentration per TS-3.9.1 is 2600 ppm. PG water is used

to makeup for evaporation. Boric Acid blender is used for makeup when leakage is

evident.

o Incorrect. Minimum boron concentration per TS-3.9.1 is 2600 ppm, however normal

makeup for evaporation is with PG water since boron does not carry over with

evaporation.

Monday, June 30, 2008 3:34:34 PM 61

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of design feature(s) and/or interlock(s) which provide for the following: Adequate

80M (boron concentration)

Question Number:

Tier: 2

Group: 2

Importance Rating: 3.1

Technical Reference: T8 3.9.1, NCROOP-49-NA

1-0p-16.5

Proposed references to be provided to applicants during examination: None

Learning Objective: U 4472, U-3749

10 CFR Part 55 Content: 41

Comments:

KA Match: Item matches KA because it evaluates knowledge of T8 requirement for

minimum boron concentration, which provides for adequate 80M. PG water could

potentially reduce 80M, so boron concentration for 8FP has a T8 minimum.

Changed PPM for distractors for added plausibility; shuffled options

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: CDC B B C B DC C Scramble Range: A - D

Source: BANK Source If Bank:: NORTH ANNA

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?: YES

Monday, June 30, 2008 3:34:34 PM 62

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 1508 RO ONLY

32. 036 AAI.Ol 027INEW/IHIGHERlIROINORTH ANNN6/2008/

Given the following:

  • Unit 1 is in Mode 6 with Core offload in progress.
  • A fuel assembly becomes visibly damaged when removed from the core.
  • Containment radiation is rising slowly.
  • The assembly is returned to its location.
  • Containment evacuation has been initiated.

Which ONE of the following describes the expected indications and response of the

Primary Ventilation System?

A. Vent Stack 'B' Radiation Monitor indication increases; Containment Purge Exhaust

automatically isolates when Vent Stack 'B' Radiation Monitor exceeds alarm

setpoint.

B~ Vent Stack 'B' Radiation Monitor indication increases; Containment Purge Exhaust

should be manually diverted through the Auxiliary Building Iodine Filters.

C. Vent Stack 'A' Radiation Monitor indication increases; Containment Purge Exhaust

automatically isolates when Vent Stack 'A' Radiation Monitor exceeds alarm

setpoint.

D. Vent Stack 'A' Radiation Monitor indication increases; Containment Purge Exhaust

should be manually diverted through the Auxiliary Building .Iodine Filters

A Incorrect. First portion is correct Purge exhaust is directed through Vent Stack B.

Second portion of distractor is incorrect but plausible since several different functions

will isolate Containment Purge automatically.

B Correct. First portion is correct as noted above. Second portion is correct as

procedure AP-5 provides guidance to direct Purge Exhaust through the Iodine Filter

Bank to reduce release activity.

C Incorrect. First portion is incorrect Purge exhaust is directed through Vent Stack B,

but the candidate who is unfamiliar with Primary Ventilation System may select this

distractor. Second portion of distractor is incorrect but plausible since several different

functions will isolate Containment Purge automatically.

D Incorrect. First portion is incorrect as noted above. Second portion is correct as

procedure AP-5 provides guidance to direct Purge Exhaust through the Iodine Filter

Bank to reduce release activity.

Monday, June 30, 2008 3:34:34 PM 63

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to operate and / or monitor the following as they apply to the Fuel Handling Incidents:

Reactor building containment purge ventilation system

Question Number:

Tier: 1

Group: 2

Importance Rating: 3.3

Technical Reference: O-AP-30

Proposed references to be provided to applicants during examination: None

Learning Objective: None

Question History:

10 CFR Part 55 Content: 41 .10

Comments:

KA match because the item evaluates knowledge of the operation of the Containment Purge

system, specific to a Fuel Handling Accident. The item further evaluates containment isolation

by testing knowledge of allowable containment closure time.

MCS Time: Points: 1.00 Version: a I 2 3 4 5 6 7 8 9

Answer: B DC DCA B A A D Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:35 PM 64

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

33.039 G2.1.32 057INEW//LOWERlIROINORTH ANNA/6/20081

Which ONE of the following describes the reason for equalizing Main Steam pressure

when opening a Main Steam NRV that has been closed?

A. Prevent themal overload of breaker for NRV due to excessive DP when opening the

NRV.

B~ Prevent excessive swell of SG volume.

C. Prevent inadvertent Hi Steam Line Differential Pressure SI.

D. Prevent damage to valve internals due to excessive DP when opening the NRV.

A Incorrect. Plausible since there have been industry events related to rotor lockup,

however at this point in the procedure the concern is for swell and loss of level control.

B Correct. A rapid presssure drop would occur if the valve were opened against a

substantial DIP, this inturn would result in excessive swell and the potential to loose

control of Sg level.

C Incorrect. A high steam line differential pressure would not actually be received

when opening an NRV. Plausible because an isolated main steam line will have a

different pressure than in-service main steam lines.

D Incorrect. NRVs are designed to operate against high DPs, but plausible because

mechanical binding of valves due to excessive DP is a known occurrence.

Monday, June 30, 2008 3:34:35 PM 65

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Conduct of Operations: Ability to explain and apply all system limits and precautions.

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.8

Technical Reference: 1-0P-28.1

Proposed references to be provided to applicants during examination: None

Learning Objective: U 10085

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates knowledge of a main steam system precaution and correct answer

provides the explanation of why the caution is observed.

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: B BAD D C D D D D Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:35 PM 66

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

34. 041 K6.03 002INEW//HIGHER//RO/NORTH ANNA/6/2008/

Given the following:

  • Unit 1 is at 100% power.
  • Rod Control is in MANUAL.
  • All other controls are in AUTO.
  • A Turbine control valve failure results in a load rejection.
  • Tavg - Tref deviation indicates 11 degrees F.
  • 1M-D4, STEAM DUMP ARMED, is illuminated.

Which ON E of the following describes Steam Dump response?

A. Two banks of Steam Dumps are modulating open. Two banks of steam dumps are

closed.

B~ Two banks of Steam Dumps are tripped open. One bank of steam dumps is

modulating open.

C. Two banks of Steam Dumps are tripped open. Two banks of steam dumps are

modulating open.

D. Four banks of steam dumps are tripped open.

A Incorrect. At 10 degrees, 2 steam dump banks trip open in load reject mode. This

value is different for turbine trip mode. The 3rd bank of dump valves will be

modulating, and the 4th bank has not yet reached setpoint. Plausible because they are

modulating up to 10 degrees.

B Correct. As discussed above both the trip open and modulate functions of the load

rejection program are satisfied.

C Incorrect. Plausible because two banks are tripped open. One other bank is

modulating, but the 4th has not yet started to open. It would be opening in another 2

degrees, and if candidate is unaware of overlap within the banks they may choose this

distractor.

D Incorrect. Plausible, because the next trip open setpoint will be all 4 banks; 5

degrees additional will cause them to trip open.

Monday, June 30, 2008 3:34:35 PM 67

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the effect of a loss or malfunction on the following will have on the SDS:

Controller and positioners, including ICS, S/G, CRDS

Question Number:

Tier: 2

Group: 2

Importance Rating: 2.7

Technical Reference: Steam Dump LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 8865, U 8866

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Item evaluates failure of a turbine control valve (SG) on the operation of the steam

dump system. (Westinghouse has no ICS and CRDS has no different consequence (no control

input>>

MCS Time: Points: 1.00 Version: a I 2 3 4 5 6 7 8 9

Answer: B DAD D C BAD A Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:35 PM 68

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

35.054 AK3.01 015INEW/IHIGHERI/RO/NORTH ANNN6120081

Given the following:

  • Reactor power is 75%.
  • 1B MFW Pump is out of service for pump coupling repairs.
  • The following alarms are received:
  • 1F-F1 /F2/F3, SG 1A/1 B/1 C LEVEL ERROR
  • 1F-D1/D2/D3, STM GEN 1A/1B/1C FW<STM FLOW CH III-IV
  • The BOP determines that 1C MFW Pump is tripped.

Which ONE of the following describes the action required, and reason for the action?

A'I Trip the reactor; prevents a challenge to the Reactor Protection System from loss of

secondary heat sink.

B. Trip the reactor; prevents damage to operating Main Feedwater Pump due to pump

runout flow and cavitation.

C. Reduce load; reduces steam flow to within the capacity of the operating MFW

pump.

D. Reduce load; prevent operating MFW pump windings from overheating due to

excessive current.

A Correct. 1B MFW pump cannot be started and with power at 75% and only 1 MFW

pump available a reactor trip is initiated since one would otherwise occur automatically.

Basis for this reactor trip is the loss of secondary heat sink.

B Incorrect. Correct response for condition but although pump may experience runout

the basis is ensuring core protection, not equipment longevity which may be adversely

affected by a brief period of operation at high flow conditions.

C Incorrect. Power is at 75% and therefore only slightly above the value for which this

would be the correct response. The 2nd half of the distractor is true, power reduction

will reduce steam flow and thus ease the burden on the remaining MFW pump.

D Incorrect. As noted above and plausible since since increased flow demand will

causes significantly higher current if power remained at the edge of capacity of the

pump.

Monday, June 30, 2008 3:34:35 PM 69

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the reasons for the following responses as they apply to the Loss of Main

Feedwater (MFW): Reactor and/or turbine trip, manual and automatic

Question Number:

Tier: 1

Group: 1

Importance Rating: 4.1

Technical Reference: 1-AP-31, TS Basis 3.3.1 (SG LO-LO)

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History:

10 CFR Part 55 Content:

Comments:

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: A C C A A DB C B B Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:35 PM 70

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

36.055 A3.03 081INEW//LOWERlIROINORTH ANNA/6/20081

Initial Conditions:

  • Condenser Air Ejector Radiation Monitor 1-SV-RM-121 is in Hi-Hi alarm.

Current conditions:

  • Safety Injection is actuated.
  • The crew is performing actions of 1-E-0, Reactor Trip or Safety Injection.

Which ONE of the following describes the alignment of the Condenser Air Ejector

steam supply and exhaust for the current conditions?

A. Exhaust isolated on HI-HI radiation; steam supply to air ejectors isolated on HI-HI

radiation.

B. Exhaust diverted to Containment on HI-HI radiation; steam supply to air ejectors

isolated on HI-HI radiation.

C. Exhaust diverted to Containment on Phase A isolation; steam supply to air ejectors

isolated on Phase A isolation.

D~ Exhaust isolated on Phase A isolation; steam supply to air ejectors isolated on

Phase A isolation.

A Incorrect. Plausible because isolation of both supply and discharge is logical on a

hi-hi radition signal to prevent release.

B Incorrect. First half is correct and second half is plausible for same reason as A.

C Incorrect. Second half is correct and first half is plausible because it would prevent

radioactive release to the environment.

D Correct. Discharge aligns to Containment via 2 trip valves. Normal discharge valve

closes on hi-hi radiation. In the event of Phase A, discharge and steam supply isolate.

Monday, June 30, 2008 3:34:35 PM 71

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to monitor automatic operation of the CARS, including: Automatic diversion of CARS

exhaust

Question Number:

Tier: 2

Group: 2

Importance Rating: 2.5

Technical Reference: Condensate LP, 1-AP-24

Proposed references to be provided to applicants during examination: None

Learning Objective: U4007

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Item evaluates parameter that causes automatic divert of air ejector exhaust as well

as what causes complete isolation

MCS Time: I Points: 1.00 Version: o I 2 3 4 5 6 7 8 9

Answer: DACBABCCDB Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:35 PM 72

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

37.055 EAI.06 016INEW/IHIGHERlIROINORTH ANNA/6/2008/

Given the following:

  • A loss of all AC Power has occurred.
  • The crew is performing actions of 1-ECA-0.O, Loss of All AC Power.
  • 1H EDG has failed and CANNOT be restarted.
  • The crew is performing 1-ECA-0.0, Attachment 4, Attempting to restore power to

1H (1J) Emergency Bus.

  • Attempts to start EDG 1J are in progress.
  • RCP Seal Water Outlet temperature is 2000F and rising at 2°F per minute.

Which ONE of the following describes the action required in accordance with ECA-O.O?

A. Place Charging Pumps in PTL prior to attempting to start 1J EDG in MANUAL -

LOCAL.

B. Perform Attachment 3, RCP seal isolation, prior to attempting to start 1J EDG in

MANUAL- LOCAL.

C~ Place 1J EDG in MANUAL-LOCAL, press EMER GEN Alarm & Shutdown RESET

Button, and verify Shutdown Relay Status Light is lit. After one minute, place 1J

EDG in MANUAL - REMOTE and determine if the EDG starts.

D. Place 1J EDG in MANUAL-REMOTE, press EMER GEN Alarm & Shutdown

RESET Button, and verify Shutdown Relay Status Light is lit. After one minute,

place 1J EDG in MANUAL - LOCAL and determine if the EDG starts.

A Incorrect. This would be performed if RCP seal return temperature was

235 degrees F or greater. Plausible because it is an action that must be considered.

B Incorrect. As noted above this would be correct if RCPs crossed the 235 degree

threshold.

C Correct. Actions are correct for starting the EDG. They are not all inclusive but do

not need to be; based on the information in the stem it is reasonable to conclude that

RCP sealleakoff has not heated up excessively.

D Incorrect. The EDG must be reset in MANUAL LOCAL, and will not reset if these

actions are reversed. Plausible because it requires detailed knowledge of the

emergency shutdown circuitry of the EDG.

Monday, June 30, 2008 3:34:35 PM 73

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to operate and monitor the following as they apply to a Station Blackout: Restoration of

power with one ED/G

Question Number:

Tier: 1

Group: 1

Importance Rating: 4.1

Technical Reference: ECA-O.O

Proposed references to be provided to applicants during examination: None

Learning Objective: U 5687

Question History:

10 CFR Part 55 Content: 41.10,41.7

Comments:

KA Match: Item evaluates operation of the EDG that is being used to restore power. Part of the

procedure for restoration requires knowledge of RCP seal status as well as switch manipulation

for restoration

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: C A C B A CDC DC Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:35 PM 74

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

38. 056 AA2.72 018lNEW/IHIGHERlIROINORTH ANNA/6/20081

Given the following:

  • Severe weather causes a Loss of Off-Site power.
  • An electrical fault on 1H Bus has caused a bus lockout.

Which ONE of the following describes the response of the AFW System during this

event?

A. AFW flow available through the HCV header; flow initiates as soon as the 4160 Volt

emergency bus is energized.

B~ AFW flow available through the MOV header; flow initiates as soon as the 4160

Volt emergency bus is energized.

C. AFW flow available through the HCV header; flow initiates approximately 20

seconds after the 4160 Volt emergency bus is energized.

D. AFW flow available through the MOV header; flow initiates approximately 20

seconds after the 4160 Volt emergency bus is energized.

A Incorrect. Bus 1H supplies power to the MDAFW Pump 3A which is normally aligned

to the HCV header. Plausible because each MDAFW pump is aligned to 1 header, and

the applicant may not know which is which.

B Correct. 450 GPM AFW flow is available on the MOV header from MDAFW 3B and

will be supplied without delay since this is a LOOP vice LOOP/LOCA scenario.

C Incorrect. Plausible as in A, and also plausible because AFW is on a 20 second time

delay for SI initiation. Applicant may confuse sequencer operation for LOOP.

D Incorrect. Plausible as described in C, but correct header provided in this distractor.

Monday, June 30, 2008 3:34:35 PM 75

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to determine and interpret the following as they apply to the Loss of Offsite Power:

Auxiliary feed flow

Question Number:

Tier: 1

Group: 1

Importance Rating: 4.1

Technical Reference: NCRODP-26, AFW LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 6035 U 6037

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Item evaluates AFW flow alignment in an event specific to loss of off-site power as

opposed to a safety injection signal. Additionally, the applicant must determine which header

the flow will be from.

MCS Time: 1 Points: 1.00 Version: o 1 2 3 4 5 6 7 8 9

Answer: BABCABBBAA Scramble Range: A - D

Source: NEW Source If Banle

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:35 PM 76

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

39. 057 G2.4.45 039lNEW/IHIGHERlIROINORTH ANNAl612008INO

The Unit is in MODE 3 preparing to startup.

10 minutes ago a loss of vital bus 1-1 occurred and power has not yet been restored.

Which ONE of the following describes the correct response and required notifications?

A"! Monitor RCP temperatures due to loss of CC flow; Notification of State and Local

authorities is NOT yet required.

B. Monitor RCP temperatures due to loss of CC flow; Notification of State and Local

authorities is required within the next 15 minutes.

C. Monitor SG PORVs due to loss of condenser steam dumps; Notification of State

and Local authorities is NOT yet required.

D. Monitor SG PORVs due to loss of condenser steam dumps; Notification of State

and Local authorities is required within the next 15 minutes.

A Correct. AP-10 att.24 directs the need to monitor RCPs which will overheat in - 10

minutes with no CC flow. Loss of all control room annunciators is E-plan entry but not

until 15 minutes has elapsed.

B Incorrrect. First part is ok but threshold for notification not crossed.

C Incorrect. This action is correct for loss of bus 1-111, not 1-1. Loss of all control room

annunciators is E-plan entry but not until 15 minutes has elapsed.

D Incorrect. This action is correct for loss of bus 1-11I, not 1-1. As noted above no

E-plan threshold has been crossed.

Monday, June 30, 2008 3:34:35 PM 77

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Loss of Vital AC Bus: Emergency Procedures / Plan: Ability to prioritize and interpret the significance of

each annunciator or alarm.

Question Number:

Tier: 1

Group: 1

Importance Rating: 4.1

Technical Reference: 0-AP-10, EPIP 1.01

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History:

10 CFR Part 55 Content: CFR: 41.10 / 43.5 / 45.3 / 45.12

Comments:

MCS Time: Points: l.00 Version: o 123 4 5 6 7 8 9

Answer: AAAAAAAAAA Items Not Scrambled

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?: NO

Monday, June 30, 20083:34:36 PM 78

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

40. 058 AKI.OI 039IMODIFIED//IllGHER//ROINORTH ANNA/6/2008/

Given the following:

  • Unit 1 is at 100% power.
  • All DC Bus voltages are approximately 131 VDC.
  • The following alarm is received in the control room:
  • 1H-B3, BATIERY CHGR 1-111 TROUBLE
  • Battery Charger 1-111 DC Output breaker has tripped and CANNOT be reset.
  • DC Bus 1-111 voltage is 118 volts and lowering.

Which ONE of the following describes the action that will be taken to restore DC Bus

1-1I1?

A. Place Swing Battery Charger 1C-I in service with the NORMAUEQUALIZE switch in

NORMAL.

B. Place Swing Battery Charger 1C-I in service with the NORMAUEQUALIZE switch in

EQUALIZE.

C~ Place Swing Battery Charger 1C-II in service with the NORMAUEQUALIZE switch

in NORMAL.

D. Place Swing Battery Charger 1C-II in service with the NORMAUEQUALIZE switch

in EQUALIZE.

A. Incorrect. Swing Charger 1-1 would be placed in service for a loss of Charger 1-1 or

1-11. DC Bus 1-111 and 1-IV are supplied by Swing Charger 1-11. Switch position is

correct.

B Incorrect. Switch position would be equalize only if the battery charger that tripped

was in equalize mode. By all DC Bus voltage being 131 VDC prior to the charger trip,

applicant should be able to determine that the chargers were all in NORMAL.

C Correct. DC Bus 1-111 and 1-IV are supplied by Swing Charger 1-11. Switch position is

correct.

D Incorrect. Wrong switch position is indicated. As noted in B voltage being 131 VDC

prior to the charger trip, applicant should be able to determine that the chargers were

all in NORMAL.

Monday, June 30, 2008 3:34:36 PM 79

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the operational implications of the following concepts as they apply to Loss of

DC Power: Battery charger equipment and instrumentation

Question Number:

Tier: 1

Group: 1

Importance Rating: 2.8

Technical Reference: 1-0P-26.4.3,0-AP-10

Proposed references to be provided to applicants during examination: None

Learning Objective: U 5509

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evluates knowledge of Charger equipment by evaluating position of

the NORMAUEQUALIZE switch based upon conditions given in the stem.

Item was modified from 2006 test item. Different bus failure and different 2nd half of

options

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: C B D C CD A D CD Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: IDGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:36 PM 80

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

41 . 059 KI.02 059IMODIFIEDIIHIGHERlIROINORTH ANNN6120081

Given the following:

  • The plant is at 25% power.
  • A Condensate header rupture occurs, and the following conditions are present:
  • 10 seconds later SG levels are 30% narrow range and lowering.
  • Reactor power remains at 25%.

Which ONE of the following describes the operation of the Reactor Protection System

and the Auxiliary Feedwater (AFW) Pumps for this condition?

A. A reactor trip setpoint has been exceeded; AFW Pumps are running.

B. A reactor trip setpoint has been exceeded; AFW Pumps are NOT running.

C~ A reactor trip setpoint has NOT been exceeded; AFW Pumps are running.

D. A reactor trip setpoint has NOT been exceeded; AFW Pumps are NOT running.

A Incorrect. RPS trip setpoint was not exceeded, because the steam flow/feed flow

mismatch is not active until SG level reaches 25%. Plausible because the steam

flow/feed flow mismatch causes a trip at higher than normal SG level trip setpoints.

AFW pumps started when all 3 Feed Pumps were tripped.

B Incorrect. See A. AFW pumps are running, but plausible because the applicant

may apply the auto start at 18% in any SG level and omit the loss of all feed pumps

start.

C Correct. Logic for Reactor trip is not met as noted above, but AFW auto start met

based on information provided in stem.

D Incorrect. Logic for Reactor trip is not- met as noted above, AFW pumps are running,

but plausible because the applicant may apply the auto start at 18% in any SG level

and omit the loss of all feed pumps start.

Monday, June 30, 2008 3:34:36 PM 81

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the physical connections and/or cause-effect relationships between the MFW

and the following AFW system

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.4

Technical Reference: NCRODP-26, AFW LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 6035, 6037

Question History:

10 CFR Part 55 Content: 41.7,41.5

Comments:

KA Match: Item evaluates cause-effect releationship of Main Feed Pump trip vs. AFW pump

auto start circuitry.

MCS Time: 1 Points: 1.00 Version: o 1 2 345 6 7 8 9

Answer: CCACBAAABB Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:36 PM 82

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

42.060 AAl.05 029INEW//LOWERlIRO/NORTH ANNN6/20081

Given the following:

  • Release of Waste Gas Decay Tank 1B is in progress.
  • 1-GW-RI-178-1, Process Vent Normal Range Monitor, indication is rising.
  • 1-GW-RI-178-2, Process Vent High Range Monitor, indication is just coming on

scale.

  • The following alarms are received:
  • 2B-A5, PROCESS VENT VNT STACK A&B LOW RAD MON

ALERT/RAD

  • 2B-B5, PROCESS VENT VNT STACK A&B HI HI RADIATION

Which ONE of the following describes the status of of the Gas Decay Tank release

lineup?

A~ Flow Control valve 1-GW-FCV-101 closed when 1-GW-RI-178-1 high radiation

alarm was received. Pressure Control valve 1-GW-PCV-117 does NOT receive a

close signal.

B. Flow Control valve 1-GW-FCV-101 AND Pressure Control valve 1-GW-PCV-117

closed when 1-GW-RI-178-1 high radiation alarm was received.

C. Flow Control valve 1-GW-FCV-101 remained open UNTIL 1-GW-RI-178-2 high

radiation alarm was received. Pressure Control valve 1-GW-PCV-117 does NOT

receive a close signal.

D. Flow Control valve 1-GW-FCV-101 AND Pressure Control valve 1-GW-PCV-117

remained open until1-GW-RI-178-2 high radiation alarm was received.

A Correct. 178-1 initiates closure of the flow control valve, but the pressure control

valve does not receive a close signal.

B Incorrect. 178-1 initiates cloure but the PCV does not receive a close signal.

Plausible because the pressure control valve is at the inlet to the FCV and part of the

discharge flow path.

C Incorrect. The discharge flowpath will already be closed when the high range

monitor goes into alarm. Plausible because it is logical to believe that the high range

monitor will initiate control action.

D Incorrect. See C as well as B for plausibility.

Monday, June 30, 2008 3:34:36 PM 83

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 1508 RO ONLY

Ability to determine and interpret the following as they apply to the Accidental Gaseous

Radwaste: That the automatic safety actions have occurred as a result of a high ARM system

signal

Question Number:

Tier: 1

Group: 2

Importance Rating: 3.7

Technical Reference: NCRODP-45, GW LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 10705

Question History:

10 CFR Part 55 Content: 41.11

Comments:

KA Match: Item evaluates isolation of gaseous waste release on high radiation. (Accidental

release occurring if abnormal radiation is present)

MCS Time: I Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: ACB CDC CDDD Scramble Range: A - D

Source: ~vv Source If Bank:

Cognitive Level: . LOVVER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 20083:34:36 PM 84

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

43.061 G2.4.3 030INEW//LOWER//RO/NORTH ANNN61200S/

Given the following:

  • A LOCA occurred on Unit 1 thirty minutes ago.
  • The crew is performing 1-E-1, Loss of Reactor or Secondary Coolant.
  • 1-RM-RMS-165 and 1-RM-RMS-166, Containment High Range Radiation

Monitors, both have amber and red lights illuminated in the control room.

Which ONE of the following describes the additional indications observed if an actual

high radiation condition exists?

A. Monitor green light ON; annunciator received on Unit 1.

B,... Monitor green light ON; annunciator received on Unit 2.

C. Monitor green light OFF; annunciator received on Unit 1.

D. Monitor green light OFF; annunciator received on Unit 2.

A Incorrect. Green monitor light would be on and plausible because it is logical to

assume that the high radiation alarm (RAD TROUBLE) is on the associated unit.

B Correct. Green monitor light would be on and high radiation alarm (RAD TROUBLE)

is on Unit 2.

C Incorrect. Amber and red lights indicate alarm, but green light off (SAFE/RESET

LIGHT) would indicate a monitor failure. Plausible also because it is logical to assume

that the high radiation alarm (RAD TROUBLE) is on the associated unit.

D Incorrect. Amber and red lights indicate alarm, but green light off (SAFE/RESET

LIGHT) would indicate a monitor failure. Correct Unit for annunciator provided in this

distractor.

Monday, June 30, 2008 3:34:36 PM 85

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Emergency Procedures / Plan: Ability to identify post-accident instrumentation.

Question Number:

Tier: 1

Group: 2

Importance Rating: 3.7

Technical Reference: NCRODP-46, RMS LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 5248, 5250

Question History:

10 CFR Part 55 Content: 41.11

Comments:

KA Match: item evaluates recognition of alarm status of the post accident monitor required by

technical specifications, therefore KA is met. (identification of indication and alarm)

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: BADCCADB CA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday. June 30, 2008 3:34:36 PM 86

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

44. 061 K2.01 060lNEW/ILOWERJIROINORTH ANNAl6/2008INO

Which ONE of the following states the power supplies to AFW Discharge MOVs,

1-FW-MOV-100A, B, C?

A. MCC 1H1-2N

B:o'" MCC 1J1-2N

C. 1A Semi-Vital Bus

D. 1B Semi-Vital Bus

A Incorrect. The AFW discharge HCVs are powered from 1H bus through semi vital

bus 1A. Plausible because the valves are safety related and all valves are ultimately

powered from either H or J trains.

B Correct all valves listed powered from this MCC.

C Incorrect. AFW Discharge HCVs (1-FW-HCV-1 OOA, B, C) are powered from this

source. Plausible because the valves and power supplies are easily confused, since

there are no train designators.

D Incorrect. Semi-Vital1A supplies AFW Discharge HCVs. Semi-Vital1B does not

provide power to AFW discharge valves, but since the opposite bus does, and there

are no train designators, this supply is credible.

Knowledge of bus power supplies to the following:AFW system MOVs

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.2

Technical Reference: NCRODP-26, Table 26-3; AFW Lesson Plan

1-0P-26A

Proposed references to be provided to applicants during examination: None

Learning Objective: U 5980

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Topic directly matches the KA as it evaluates knowledge of the power supply to

AFW discharge MOVs, as required by KA topic.

Monday, June 30, 2008 3:34:36 PM 87

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: BADAAABABA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?: NO

Monday, June 30, 2008 3:34:36 PM 88

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

45. 062 G2.1.27 061 IBANKINORTH ANNAILOWER//ROINORTH ANNN6120081

A disconnect switch is at the output of vital bus inverters 1-1 and 2-1 in order to

A. dedicate the associated Sola transformer to supply power to its vital bus only

B~ dedicate the associated inverter to supply power to the opposite unit's channel 1

ex-core flux monitor

C. isolate the associated inverter from its vital bus for maintenance

D. isolate the associated Appendix-R power panel for maintenance

A Incorrect. Purpose of bypass switch is for SOLA to supply the vital bus. Plausible

because the bypass and disconnect could be confused.

B Correct. This is a design feature for Safe Sutdown function that ensures capability to

monitor reactor subcriticallity.

C Incorrect. The Inverter Output breaker would be used to disconnect the inverter from

the bus. Plausible because the function could potentially be used, but is not the

purpose.

o Incorrect. Appendix R panels are isolated by transfer switches. Plausible because

disconnects do perform an isolation function, and the disconnects are provided in case

of a fire that destroys the vital bus.

Conduct of Operations: Knowledge of system purpose and / or function.

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.9

Technical Reference: Vital AC LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 5534

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Item evaluates one of the functions of the 120 VAC vital distribution system, in that

cross-tie between units is available

Monday, June 30, 2008 3:34:36 PM 89

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: B A A C C DB DB B Scramble Range: A - D

Source: BANK Source If Bank: NORTH ANNA

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:36 PM 90

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

46. 062 K3.03 062INEW//LOWERlIROINORTH ANNN6120081

Given the following:

  • Both Units are at 100% power.
  • A Fire in RSST 'A' causes an overcurrent lockout on Transfer Bus D.

Which ONE of the following describes the battery chargers that are temporarily

deenergized?

A. 1-1 and 1-11

B~ 1-111 and 1-IV

C. 2-1 and 2-11

D. 2-111 and 2-IV

A Incorrect. Chargers 1-1 and 1-11 are supplied from 480 volt bus 1H, which is supplied

from 4.16KV Bus 1H, which is supplied from Transfer Bus F. Plausible because each

of the 4 KV busses have a normal supply from transfer bus D, E, or F. Alternate

supplies are from SSTs or from Emergency Diesel Generators.

B Correct. Chargers 1-111 and 1-IV are supplied from Bus 1J, which receives power

from Transfer Bus D. If Transfer Bus D is deenergized, alternate power will be supplied

from Unit 2 SST 2B or from 1J EDG. Power will be temporarily interrupted to the bus.

C Incorrect. Loss of transfer Bus E would cause loss of the 2-1 and 2-11 chargers.

Plausible same reason as A, all are supplied from the Transfer Busses.

D Incorrect. Plausible as in A, Transfer Bus F is the normal supply to 2J, which

supplies chargers 2-111 and 2-IV.

Monday, June 30, 2008 3:34:37 PM 91

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the effect that a loss or malfunction of the ac distribution system will have on the

following: DC system

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.7

Technical Reference: NCRODP Figure 35-1 NA

1-0P-26A

O-AP-10

Proposed references to be provided to applicants during examination: None

Learning Objective: U 5511

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item directly evaluates a loss of AC power to the DC distribution system by

evaluating knowledge of which Transfer Bus supplies the emergency bus that provides power

to specific vital battery chargers, thus demonstrating knowledge of the effect of a loss of AC on

the DC distribution system.

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: B A A BAD A C B D Scramble Range: A - D

Source: NEW Source If Bank::

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:37 PM 92

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

47. 063 K4.01 063IBANKINORTH ANNAlHIGHERlJROINORTH ANNA/6/2008/

If a loss of Battery Charger 1-1 were to occur, what would be the effect on the operation

of its associated inverter and the vital DC bus?

A. Static switch transfer occurs; vital DC bus voltage initially decreases by several

volts and then continues to decrease at a faster rate over time.

B. Static switch transfer occurs; vital DC bus voltage initially decreases by several

volts and then continues to decrease at the same rate over time.

C~ NO static switch transfer; vital DC bus voltage initially decreases by several volts

and then continues to decrease at a faster rate over time.

D. NO static switch transfer; vital DC bus voltage initially decreases by several volts

and then continues to decrease at the same rate over time.

A Incorrect. If the charger is lost, battery will supply the inverter due to the changed

bias on the blocking diode. Plausible because loss of inverter input (both) results in

static switch transfer. Second part is true rate of voltage decay increases over time due

to cell reversal.

B Incorrect. As noted above conditions DO NOT exist to warrant a transfer. Second

part is incorrect but plausible since the candidate may not be aware of the effect of cell

reversal on the battery.

C Correct. Inverter will remain powered by it's associated DC bus so no transfer will

occur. Second part is also true as the rate of voltage decay increases over time due to

cell reversal.

D Incorrect. Inverter will remain powered by it's associated DC bus so no transfer will

occur. Second part is incorrect but plausible since the candidate may not be aware of

the effect of cell reversal on the battery.

Monday, June 30, 2008 3:34:37 PM 93

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of dc electrical system design feature(s) and/or interlock(s) which provide for the

following: Manual/automatic transfers of control

Question Number:

Tier: 2

Group: 1

Importance Rating: 2.7

Technical Reference: Vital Electrical LP/SD

Proposed references to be provided to applicants during examination: None

Learning Objective: U 9619

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item evaluates knowledge of a failure of the DC Electrical Distribution system and its

effect on the transfer of vital AC inverters. The question in effect is asking knowledge of an

automatic transfer of control to the battery when a charger fails, against the automatic transfer

of control to a regulating transformer via static switch

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: CD B B ABC DCA Scramble Range: A - D

Source: BANK Source If Bank: NORTH ANNA

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:37 PM 94

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

48. 064 K3.02 064INEW//HIGHER//ROINORTH ANNAl612008/

Given the following:

  • A lightning strike has occurred resulting in a loss of the North Anna Switchyard.
  • The 1J EDG Battery and Battery Charger are BOTH lost.
  • 125 VDC Bus 1-1 is lost.
  • A spurious SI occurs.
  • The crew has entered 1-E-0, Reactor Trip or Safety Injection, and manually

actuated SI.

Which ONE of the following describes the reason that no J Train ESF equipment is

running?

A. 1J EDG did NOT start due to loss of the auxiliary fuel oil pump.

B:' 1J EDG did NOT start due to loss of power to both start circuits.

C. 1J EDG started, but the EDG ouput breaker did NOT close due to loss of DC field

flash capability.

D. 1J EDG started and the EDG ouput breaker is closed, but no control power is

available to 1J Bus load breakers.

A Incorrect. Plausible since although the EDG Aux Fuel Oil pump is not needed to start

the EDG the candidate who is unfamiliar with the EDG System may assume this

constitutes a valid reason for the EDG not starting.

B Correct. Without the EDG Battery or Battery Charger there is no power available to

the start circuits and thus the EDG will not attempt to start despite the presence of

automatic start signals.

C Incorrect. Plausible because the candidate may assume that the EDG is capable of

starting but that DC for field flash is unavailable. While the later part is true, as

discussed above the EDG will not attempt to start based on the total loss of DC

support.

D Correct. Plausible because the candidate may assume that the EDG is capable of

starting and obtaining required voltage and frequency. The candidate who is unfamiliar

with DC control power to the ESF busses may conclude that this is a logical reason for

none of the ESF equipment to be loaded. The control power to 1J Bus is from DC Bus

1-111.

Monday, June 30, 2008 3:34:37 PM 95

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the effect that a loss or malfunction of the ED/G system will have on the

following: ESFAS controlled or actuated systems

Question Number:

Tier: 2

Group: 1

Importance Rating: 4.2

Technical Reference: EDG LP/SD (Not a good reference)

Proposed references to be provided to applicants during examination: None

Learning Objective: U 6310 (Partial)

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item evaluates malfunction of EDG based on multiple control power failures, and the

resulting effect on the sequencer, which implies effect on the systems controlled by the

sequencer

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: B D C C C B- B C A A Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:37 PM 96

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

49. 065 AK3.03 022IBANKINORTH ANNAILOWERJIROINORTH ANNAl61200S/

Unit 1 is operating at 100% power.

  • The following alarm is received:
  • The OATC notes instrument air pressure is 85 psig and rapidly decreasing.
  • The crew initiates 1-AP-28, LOSS OF INSTRUMENT AIR.
  • Instrument Air pressure continues to lower.
  • The SRO directs tripping the reactor and closing Main Steam Trip Valves.

Which ONE of the following describes the reason for this action?

A. To avoid a High PZR Pressure reactor trip due to closure of all main steam trip

valves.

B. To avoid a Lo-Lo SG level reactor trip due to closure of all main steam trip valves.

C~ To avoid a High Steam Flow safety injection due to closure of a single main steam

trip valve.

D. To avoid a High Steam Line Delta P safety injection due to closure of a single main

steam trip valve.

A Incorrect. Plausible because RCS pressure would rise significantly on closure of all

MSTVs at 100% power.

8 Incorrect. Plausible because if MSTVs close, the SGs would shrink and reach the

low level trip setpoint.

C Correct. If one MSTV drifts closed (at 100% power) , a high steam flow and 10 SG

presssure would occur on the other 2 SGs (as steam load does not change), causing a

safety injection actuation.

D Incorrect. The high steam flow wllo SG pressure SI would occur prior to steam line

DP SI due to the rate sensitive nature of the pressure component of the logic.

Monday, June 30, 2008 3:34:37 PM 97

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the reasons for the following responses as they apply to the Loss of Instrument

Air:Knowing effects on plant operation of isolating certain equipment from instrument air

Question Number:

Tier: 1

Group: 1

Importance Rating: 2.9

Technical Reference: AP-28, AP LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11662

Question History:

10 CFR Part 55 Content: 41 .10

Comments:

KA is matched because it evaluates knowledge of the effect of losing air to an MSIV, and the

safety system actuation that will occur.

North Anna Bank item with significant editorial changes

MCS Time: I Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: C B A B DB D D D B Scramble Range: A - D

Source: BANK Source If Bank: NORTH ANNA

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:37 PM 98

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

50. 071 A2.02 082lNEW/IIllGHERlIROINORTH ANNAl612008/

Given the following:

  • The crew is preparing to release WGDT 1B.
  • The maximum allowed flowrate per the release permit is 300 SCFM.

Which ONE of the following describes the preferred method for controlling the WGDT

release flow rate?

A. 1-GW-FCV-1 01, WGDT to Process Vent, should be placed in MANUAL and

adjusted to control flow rate at 290 +/- 5 SCFM.

B. 1-GW-FCV-1 01, WGDT to Process Vent, should be placed in AUTOMATIC and

adjusted to control flow rate at 290 +/- 5 SCFM.

C. 1-GW-FCV-1 01, WGDT to Process Vent, should be placed in MANUAL and

adjusted to control flow rate at less than 3 SCFM.

D~ 1-GW-FCV-101, WGDT to Process Vent, should be placed in AUTOMATIC and

adjusted to control flow rate at less than 3 SCFM.

A Incorrect. Preferred mode of operation is AUTOMATIC, and maximum indicated flow

rate is 3 SCFM; Plausible if operator believes MANUAL control is preferred for

radioactive releases, or if operator confuses the normal Process Vent flow rate with the

WGDT release flow rate.

B Incorrect. Maximum indicated flow rate is 3 SCFM; Plausible if operator confuses the

normal Process Vent flow rate with the WGDT release flow rate.

C Incorrect. Preferred mode of operation is AUTOMATIC; Plausible if operator

believes MANUAL control is preferred for radioactive releases.

o Correct. 0-OP-23.2 stipulates a flow rate of < 3 SCFM and operating 1-GW-FCV-101

in AUTOMATIC; Operation of 1-GW-FCV-101 in manual is only permitted with

permission from the SRO based on Commitment, P&L, and procedure body, thus

AUTOMATIC is clearly preferred.

Monday, June 30, 2008 3:34:37 PM 99

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to (a) predict the impacts of the following malfunctions or operations on the Waste Gas

Disposal System; and (b) based on those predictions, use procedures to correct, control, or

mitigate the consequences of those malfunctions or operations: Use of waste gas release

monitors, radiation, gas flow rate, and totalizer

Question Number:

Tier: 2

Group: 2

Importance Rating: 3.3

Technical Reference: 0-OP-23.2, Gaseous Waste LP

Proposed references to be provided to applicants during examination:

Learning Objective: U 4160

Question History:

10 CFR Part 55 Content:

Comments:

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: D A A A CD D C C B Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:37 PM 100

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

51. 073 Al.OI OOIIBANKINORTH ANNAILOWERlIROINORTH ANNAl6/20081YES

Given the following:

  • Each Unit has a containment vacuum pump running.
  • 1-GW-RI-178-3, Process Vent particulate radiation Monitor indication spiked,

causing an ALERT and HIGH alarm to lock in.

Which ONE of the following describes the plant response?

A. ONLY the unit 1 vacuum pump will trip.

B. Both units' vacuum pumps will trip; discharge valves remain open.

C~ Both units' vacuum pump discharge valves will automatically close.

D. ONLY the unit 1 vacuum pump discharge valve will automatically close.

A Incorrect. Both units' vacuum pump discharge valves will close and pumps will then

trip. Plausible because the alarm is on Unit 1.

B Incorrect. Discharge valves will close. Plausible because the vacuum pump tripping

would stop the discharge.

C Correct. Discharge valves for both units vacuum pumps will close.

D Incorrect. Condition affects both Units (See A).

Monday, June 30, 2008 3:34:37 PM 101

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits)

associated with operating the PRM system controls including: Radiation levels

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.2

Technical Reference: NCRODP-46-NA

Proposed references to be provided to applicants during examination: None

Learning Objective: U 17679

Question History: NA 5164

10 CFR Part 55 Content: 41.11

Comments:

KA Match: item evaluates process radiation monitoring controls for securing potential

discharge in progress.

MCS Time: I Points: 1.00 Version: o I 2 345 6 7 8 9

Answer: C DB DC B C A C B Scramble Range: A - D

Source: BANK Source If Bank: NORTH ANNA

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?: YES

Monday, June 30, 2008 3:34:37 PM 102

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

52. 073 KS.02 065JMODIFIEDIHARRIS 2003ILOWERlIROINORTH ANNN61200S1

Given the following:

Monitor indication is rising.

  • Area Surveys 5 feet from a letdown piping hot spot indicate 10 mREM/hr.
  • An operator must hang a Tagout on a valve that is located 10 feet from the

hotspot.

What is the dose rate in the area where the operator will be hanging the Tagout?

(Assume the hot spot is a point source)

A. 1 mRem/hr

B~ 2.5 mRem/hr

C. 5 mRem/hr

D. 7.5 mRem/hr

A Incorrect. Mathematical error would have to be introduced to arrive at this value but

plausible because it is within range and closest to the correct answer.

B Correct. Twice the distance is 1/4 the dose rate.

C Incorrect but plausible if the applicant fails to square the distance to arrive at dose

rate.

D Incorrect but plausible if the applicant takes the dose rate and subtracts it from the

current dose rate.

Monday, June 30, 2008 3:34:37 PM 103

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 1508 RO ONLY

Knowledge of the operational implications as they apply to concepts as they apply to the PRM

system: Radiation intensity changes with source distance

Question Number:

Tier: 2

Group: 1

Importance Rating: 2.5

Technical Reference:

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History: Modified from Harris 2003 exam. Developed by others

10 CFR Part 55 Content: 43.11

Comments:

KA Match: The item intends to evaluate a situation in which an operator must be aware of

changing dose rates and the relationship between distance and dose rate from a radioactive

source

MCS Time: Points: 1.00 Version: o I 2 345 6 7 8 9

Answer: B C B B B B C C A C Scramble Range: A - D

Source: MODIFIED Source If Bank: HARRIS 2003

Cognitive Level: LOWER Difficulty Level :

. Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:38 PM 104

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

53. 076 A 1.02 067INEW/IHIGHERlIROINORTH ANNA/6/2008/

Given the following:

  • Unit 1 is at 100% power.
  • Computer alarms are received on several components cooled by the Bearing

Cooling System.

  • Subsequently, the following alarms are received 90 seconds apart:
  • The crew enters 1-AP-19, Loss of Bearing Cooling Water, and verifies a Bearing

Cooling Pump is running.

Which ONE of the following describes the initial action required?

A. Place Bearing Cooling in Lake - to - Lake Mode and verify the operation of the Circ

Water System to ensure cooling requirements are met.

B~ Start available Bearing Cooling Tower Fans or shift fans to high speed; verify

Bearing Cooling temperatures are decreasing.

C. Verify Generator Hydrogen temperature is above the alarm setpoint and initiate a

plant load reduction until the alarm is clear.

D. Bypass 1-BC-TCV-104, Generator Hydrogen Cooler TCV, to lower hydrogen

temperature. If temperature exceeds the limit, trip the reactor.

A Incorrect. Lake to Lake mode may be initiated after evaluation and after attempting

to start all fans; therefore, plausible because it may be performed.

B Correct. AR for basin temperture HI is confirmed by annunciator for Hydrogen

temperature so the initial response would be to maximize system cooling and assess if

additional cooling is adequate to control system supply temperature.

C Incorrect. Verify temperature but for the Generator Hydrogen cooler, would attempt

to bypass the TCV before anything else. Generator Hydrogen Cooler is a priority

component in this situation.

D Incorrect. Would bypass the TCV if the BC fans did not solve the problem, but would

reduce load instead of trip the reactor if temperature exceeded the limit.

Monday, June 30, 2008 3:34:38 PM 105

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to predict and/or monitor changes in parameters (to prevent exceeding design limits)

associated with operating the SWS controls including: Reactor and turbine building closed

cooling water temperatures.

Question Number:

Tier: 2

Group: 1

Importance Rating: 2.6

Technical Reference: 1T-C1, 1A-F4, 1-AP-19

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11413

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Facility has a secondary system called Bearing Cooling that serves the same

function as the Service Water system at other facilities. KA is met because the item requires

operating the system controls to prevent exceeding temperature limits

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: BCD B A ADD A B Scramble Range: A - D

Source: NEW Source If Banle

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:38 PM 106

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

54. 076 AK2.01 032INEW//LOWERlIROINORTH ANNA/6/2008/

Given the following:

  • A Turbine runback occurred 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> ago on Unit 1.
  • The unit is stable at 55% power.
  • Chemistry sample indicates that RCS activity has increased significantly.

Which ONE of the following radiation monitors provides the primary confirmation of the

Chemistry sample results?

A. SG and Main Steam N-16 monitors

B~ Reactor Coolant Letdown Radiation monitor

C. Auxiliary Building and Vent Stack Radiation monitors

D. Containment Particulate and Gaseous Radiation monitors

A Incorrect. High N-16 activity would show as a secondary or backup indication of high

RCS activity where SG Tube Leakage is occurring. These detectors are not sensitive

to RCS Activity changes. Plausible because it is logical that an increase in activity

would show an increase on the monitor.

B Correct. The letdown line monitor is the primary confirmation that RCS activity has

increased.

C Incorrect. Monitors are checked in AP-5 to verify that no release is occurring if the

Letdown Monitor is in alarm.

D Incorrect. RCS activity would provide elevated reading in containment for conditions

where a small RCS leak is occurring, but not primary indication for fuel failure/RCS

activity increase.

All distractors plausible because a high RCS activity could result in an increased

indication on the given monitors depended on plant conditions (e.g. RCS leakage,

SGTL, CVCS leakage outside CNTMT).

Monday, June 30, 2008 3:34:38 PM 107

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the interrelations between the High Reactor Coolant Activity and the following:

Process radiation monitors

Question Number:

Tier: 1

Group: 2

Importance Rating: 2.6

Technical Reference: 1-AP-5, Att. 8

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11666

Question History:

10 CFR Part 55 Content: 55.41.12

Comments:

KA Match: Item directly evaluates KA topic by matching the plant condition of high RCS activity

based on Chemistry sample with the high rad alarms caused by the Letdown Rad Monitor

MCS Time: I Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: B CAABDAABA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:38 PM 108

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

55. 077 AAl.Ol 024INEW//LOWERlIROINORTH ANNN61200S1

Given the following:

  • Both units are at 100% power.
  • Due to voltage and frequency fluctuations on the grid, the crew is performing

actions contained in 0-AP-8, Response to Grid Instability.

  • The crew has verified equipment operability.

Which ONE of the following describes the operation of the Main Generator Voltage

Regulators and the condition that requires the offsite power source to be declared

inoperable?

A. Maintain voltage regulators in AUTO; grid voltage increases to 536 kV

B. Place voltage regulators in MANUAL; grid voltage increases to 536 kV

C,.- Maintain voltage regulators in AUTO; grid voltage decreases to 504 kV

D. Place voltage regulators in MANUAL; grid voltage decreases to 504 kV

A Incorrect. Plausible because 536 kV is above the procedural limit of 535 kV,

however the procedure directs EVALUATION of the offsite source against GDC 17 and

continued operability, but does not require the crew to declare it inoperable.

B Incorrect. Plausible same as A, and VR is not placed in manual. Note in procedure

says to leave in AUTO because VR problems have minimal effect. Manual is logical

when voltage problems exist.

C Correct. Conditions do not warrant placing VR in manual and 504 kV is the threshold

for declaring offsite sources inoperable.

D Incorrect. Plausible because voltage is correct, and placing in manual is logical when

there are voltage problems. .

Monday, June 30, 2008 3:34:38 PM 109

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to operate and/or monitor the following as they apply to Generator Voltage and Electric

Grid Disturbances: Grid frequency and voltage

Question Number:

Tier: 1

Group: 1

Importance Rating: 3.6

Technical Reference: O-AP-8

Proposed references to be provided to applicants during examination: None

Learning Objective: U 9364

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match because the item evluates control of voltage (auto or manual) as well as monitoring

voltage for LOW VOLT conditions

MCS Time: 1 Points: 1.00 Version: o 1 2 3 4 5 6 7 8 9

Answer: CDDCABBBAB Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:38 PM 110

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

56. 078 A4.01 003IBANKINORTH ANNAILOWERlIROINORTH ANNA/612008/

Which ONE (1) of the following describes the operation of Instrument Air Compressor

11-IA-C-1" when it is placed in AUTO?

A. Compressor will start and load when pressure drops to 103 psig. Compressor will

unload and shut down when pressure increases to 109 psig.

B. Compressor will start and run continuously for an indefinite period of time.

Unloader valves will CLOSE when pressure drops to 103 psig. Unloader valves will

OPEN when pressure rises to 109 psig.

C~ Compressor will start and load when pressure drops to 98 psig. Compressor will

unload when pressure rises to 106 psig.

D. Compressor will start and run continuously for an indefinite period of time.

Unloader valves will CLOSE when pressure drops to 98 psig. Unloader valves will

OPEN when pressure rises to 106 psig.

A Incorrect Plausible because it is a description of how the Service Air Compressor will

operate in AUTO, with IA setpoints.

B Incorrect. Plausible because the Service Air Compressor will run in MANUAL in this

manner, but IA setpoints used.

C Correct. In AUTO, the lAC will start when pressure is reduced to 98 psig, and unload

when pressure reaches 106 psig.

D Incorrect. Plausble because the correct setpoints are used, but in AUTO the

compressor would shut down after 15 minutes running unloaded.

Monday, June 30, 2008 3:34:38 PM 111

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to manually operate and/or monitor in the control room: Pressure gauges

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.1

Technical Reference: Compressed Air LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 4271

Question History:

10 CFR Part 55 Content: 41.5

Comments:

KA Match: Item evaluates pressure setpoints for operation of air compressors, which are the

pressures that would be seen if an applicant was monitoring the pressure gauges

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: C C DAD B D B C B Scramble Range: A - D

Source: BANK Source If Bailie NORTH ANNA

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:38 PM 112

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

57.078 K4.03 068INEW//LOWERlIROINORTH ANNA/6/2008/

Instrument Air Compressor 1-IA-C-1 has been running loaded for the past 15 minutes.

Which ONE of the following choices contains ONLY alarms that will result in a trip of

the Air Compressor?

A~ Low Oil Pressure AND Cooling System Fault caused by low cooling system DP

B. High Discharge Pressure AND Cooling System Fault caused by low cooling system

DP

C. High Temperature HP Outlet AND Cooling System Fault caused by high pressure

on surge line

D. High Oil Temperature AND Cooling System Fault caused by high pressure on surge

line

A Correct. A Cooling System Fault alarm will be received either on low DP or on high

surge line presure (SW leak) The low DP will trip the compressor but the high surge

line pressure will not.

8 Incorrect. High discharge pressure does not trip the compressor, but does cause an

alarm. Plausible because most alarms do result in compressor trip.

C Incorrect. See A for description of compressor trip on low DP only for Cooling

system Fault. The first alarm listed will trip the compressor.

D Incorrect. See A and C. The first alarm listed will trip the compressor.

Monday, June 30, 2008 3:34:38 PM 113

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of lAS design feature(s) and/or interlock(s) which provide for the following: Securing

of SAS upon loss of cooling water

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.1

Technical Reference: Compressed Air LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U4272

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match because the item evaluates knowledge of an interlock to trip the air compressor

based upon low cooling water flow.

MCS Time: I Points: 1.00 Version: o I 2 3 4 5 6 7 8 9

Answer: ACDCAADBAA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:38 PM 114

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

58.079 Kl.Ol OOllMODIFIED/IHIGHERJIROINORTH ANNN6120081

Given the following:

  • A loss of Instrument Air is occurring on Unit 1.
  • Instrument Air pressure is 88 psig and dropping slowly.
  • The actions of 1-AP-28, Loss of Instrument Air, are being performed.

Which ONE (1) of the following describes the Instrument Air System alignment and the

action to be taken based on the system pressure?

A. All available Instrument and Service Air Compressors running; Verify Instrument Air

supplied to Containment by verifying open 1-IA-TV-102A and 1-IA-TV-1028,

Containment Instrument Air Trip Valves.

8~ All available Instrument and Service Air Compressors running; Isolate Instrument

Air to Containment by closing 1-IA-TV-1 02A or 1-IA-TV-1 028, Containment

Instrument Air Trip Valves.

C. All Service Air Compressors running; Instrument Air Compressors either running or

in standby; Verify Instrument Air supplied to Containment by verifying open

1-IA-TV-1 02A and 1-IA-TV-1 028, Containment Instrument Air Trip Valves.

D. All Service Air Compressors running; Instrument Air Compressors either running or

in standby; Isolate Instrument Air to Containment by closing 1-IA-TV-102A or

1-IA-TV-1028, Containment Instrument Air Trip Valves.

A Incorrect. Immediate action is to start all available Service Air, Instrument Air, and

Containment Instrument Air Compressors. No other immediate actions. Plausible but

at 94 psig, the procedure directs isolation of the Containment Air Header to try and

identify where the leak is.

8 Correct. Immediate action is to start all available Service Air, Instrument Air, and

Containment Instrument Air Compressors. No other immediate actions. At 94 psig, the

procedure directs isolation of the Containment Air Header to try and identify where the

leak is.

C Incorrect. Plausible because Service Air Compressors are normal supply to

Instrument Air, and Instrument Air Compressors are only used for backup. Also,

Containment Air trip valves are normally open to supply air to Containment.

D Incorrect. Plausible because Service Air Compressors are normal supply to

Instrument Air, and Instrument Air Compressors are only used for backup. Also,

Containment Air will be split at 94 psig.

Monday, June 30, 2008 3:34:38 PM 115

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the physical connections and/or cause-effect relationships between the SAS and

the following lAS

Question Number:

Tier: 2

Group: 2

Importance Rating: 3.0

Technical Reference: 1-AP-28, NCRODp*17

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11662

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates connections between Service Air, Instrument Air, and Containment

Instrument Air diuring an abnormal event. Service and Instrument Air systems are always

cross-tied; Containment Air may be automatically or manually isolated

Modified because air pressure was added to stem, and status of Containment Air was also

added to options. Correct answer changed based on modifications

MCS Time: Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: BCD D C C D B D A Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: mGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:38 PM 116

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 1508 RO ONLY

59. 103 A3.01 070INEW//LOWERlIROINORTH ANNN61200S1

Given the following:

  • A LOCA has occurred on Unit 1.
  • The following conditions exist:
  • RCS pressure is 1700 psig.
  • Containment pressure has peaked at 21 psia and is now slowly decreasing.
  • The crew is performing 1-E-0, Reactor Trip or Safety Injection.
  • The RO is performing Attachment 5, Verification of Phase A Isolation.
  • The following valves are identified as OPEN:
  • 1-CH-MOV-1115B, RWST To Charging Pumps Isolation
  • 1-CH-MOV-1289B, Normal Charging Line Isolation
  • 1-SV-TV-100A, MSR Vent to First Point Heater

For the current plant conditions, which ONE of the following valves must be

repositioned to place it in the required accident configuration?

A. 1-CH-MOV-1115B

B~ 1-CH-MOV-1289B

C. 1-SV-TV-100A

D. 1-SW-MOV-108A

A Incorrect. Valve is normally closed but will open on SI. Plausible because it is

normally closed and the applicant must determine from conditions and procedure step

that SI is actuated, and that VCT valves with same numbers will be open during normal

operation (Same designator, different letter).

B Correct. Normal Charging isolates on SI, but plausible that it should be open,

because a loss of inventory has occurred, and Charging provides makeup.

C Incorrect. Valve must be closed manually as part of Attachment 5, but does not

receive an auto close signal, and not required for safety related function. The MSRs

are realigned to the condenser manually.

D Incorrect. Valve will close on CDA (CIB) Conditions do not exist for CIB. Plausible

because they do get a close signal on Hi-Hi containment pressure.

Monday, June 30, 2008 3:34:38 PM 117

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to monitor automatic operation of the contain-ment system, including: Containment

isolation

Question Number:

Tier: 2

Group: 1

Importance Rating: 3.9

Technical Reference: 1-E-O, Attachment 5

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12021

Question History:

10 CFR Part 55 Content: 41.7

Comments:

KA Match: Item evaluates knowledge of the components that are required to reposition on

containment isolation Phase A. Each option has a unique actuation or manipulation to ensure

that each is plausible.

MCS Time: I Points: 1.00 Version: a I 2 3 4 5 6 7 8 9

Answer: BDCADCCDDC Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:39 PM 118

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

60. E03 EA1.2 036INEW//HIGHER//RO/NORTH ANNA/6/2008/

Given the following:

  • A LOCA has occurred on Unit 1.
  • The crew is performing 1-ES-1.2, Post LOCA Cooldown and Depressurization.
  • During the SI flow reduction sequence, the following conditions exist:
  • 1C RCP is running.
  • Two Charging Pumps are running.
  • RCS pressure is 1100 psig and stable.
  • RCS Subcooling based on Core Exit TCs is 320F
  • Pressurizer level is 44%.
  • Containment pressure is 17.9 psia.

Which ONE of the following describes the action required for the SI flow reduction

sequence in accordance with 1-ES-1.2?

A. RCS subcooling is adequate to prevent the RCS from reaching saturation

conditions when one Charging Pump is stopped; maintain RCS temperature stable

while stopping one Charging Pump.

B. RCS subcooling is adequate to prevent the RCS from reaching saturation

conditions when one Charging Pump is stopped; continue the RCS cooldown while

stopping one Charging Pump.

C. RCS subcooling is NOT adequate to prevent the RCS from reaching saturation

conditions when one Charging Pump is stopped; one Charging Pump may be

stopped ONLY IF at least one Low Head SI pump is running. .

D~ RCS subcooling is NOT adequate to prevent the RCS from reaching saturation

conditions when one Charging Pump is stopped; Charging Pumps must remain

running with flow aligned to the BIT until RCS subcooling is sufficient to stop a

Charging Pump.

Monday, June 30, 2008 3:34:39 PM 119

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 041508 RO ONLY

A Incorrect. RCS subcooling is sufficient for normal EOP conditions (>25 Degrees F)

but not sufficient <<50 Degrees F) for Sl flow reduction. Therefore, this option is

plausible. Maintaining temperature (plant conditions) stable is a logical action to

perform while stopping a pump that will change RCS subcooling.

B Incorrect. See A above, and also the action is correct for the conditions given if an

applicant chose the first part of this option.

C Incorrect. Plausible because this is the RNO action for the step in question. If Hot

Leg temperatures were below 345 Degrees F, this would be a correct option.

D Correct. ERG Rev. 2 Basis for SI reduction sequence. With a leak in progress

additional subcooling is required to ensure subcooling does not decrease to SI

reinitiation criteria when injection flow is reduced. The increased subcooling required is

intended to ensure adequate subcooling when new equilibrium conditions establish

after a Charging pump is stopped.

Ability to operate and / or monitor the following as they apply to the (LOCA Cooldown and

Depressurization) Operating behavior characteristics of the facility.

Question Number:

Tier: 1

Group: 2

Importance Rating: 3.7

Technical Reference: E5-1.2 and SD

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12208

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item r~quires knowledge of the operating behavior characteristics of the facility in

order to eliminate distractors, as well as determine correct answer. The applicant must

understand subcooling requirements in an abnormal EOP arrangement, and understand the 51

flow reduction process related to stopping a Charging Pump in order to correctly answer.

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: DDDB BACDDC Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:39 PM 120

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

61. E05 EK3.4 023lNEW/IHIGHERJIROINORTH ANNN6/20081

Initial Conditions:

  • 1B SG pressure is 220 psig and lowering due to a stuck open safety valve.
  • 1A and 1C SG pressures are 700 psig and stable.
  • RCS pressure 1600 psig and stable.

Current conditions:

  • All AFW flow has been lost.
  • 1A and 1C SG Wide Range levels are 30% and lowering.
  • 1B SG Wide Range level, indicates 0%.
  • RCS pressure is 1750 psig and rising.
  • All actions of 1-E-2, Faulted SG Isolation, have been performed.
  • The crew has just transitioned to 1-FR-H.1, Loss of Secondary Heat Sink.

Which ONE of the following describes the strategy for recovery of Heat Sink in

accordance with 1-FR-H.1, and the reason for the strategy?

A. Establish AFW flow to ANY SG; establishing Heat Sink takes priority over any

previous EOP action.

B~ Establish AFW flow to 1A OR 1C SG; 1B SG should remain isolated to prevent

potential SG tube damage.

C. Establish bleed and feed and if AFW becomes available, then establish AFW to

ANY SG; establishing Heat Sink takes priority over any previous EOP action.

D. Establish bleed and feed and if AFW becomes available, then establish AFW to 1A

OR 1C SG; 1B SG should remain isolated to prevent potential SG tube damage.

Monday, June 30, 2008 3:34:39 PM 121

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 1508 RO ONLY

A Incorrect. Actions of FRPs do take precedence over other procedures, but a caution

prior to step 1 of FR-H.1 requires use of intact SGs for initiation of feed instead of

faulted SGs. Plausible because a loss of heat sink is in progress.

8 Correct. The caution referenced in FR-H.1 is standard throughout the EOP network

and is intended to alert the operator to the potential for damage as well as the difficulty

involved in attempting to control RCS temperature with a faulted SG; either condition

can result in adverse consequences and has the potential to complicate recovery

actions.

C Incorrect. SG WR level is below the adverse value, but above the normal value for

initiation of bleed and feed; therefore, plausible option. Recovery with AFW would

follow the caution to leave the faulted SG isolated.

D Incorrect and plausible same as C. Actions for restoration of AFW are correct.

Knowledge of the reasons for the following responses as they apply to the (Loss of Secondary

Heat Sink) RO or SRO function as a witnin the control room team as appropriate to the

assigned position, in such a way that procedures are adhered to and the limitations in the

facilities license and amendments are not violated.

Question Number:

Tier: 1

Group: 1

Importance Rating: 3.7

Technical Reference: FR-H.1 and background doc

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11276

Question History:

10 CFR Part 55 Content: 41 .10

Comments:

KA Match: The item evaluates plant conditions where an applicant must observe a caution in

order to perform the correct action during a loss of feedwater. The applicant is presented with

2 plausible options for initial action, as well as 2 plausible options for reasons, both contained in

EOPs

MCS Time: Points: 1.00 Version: 0123456789

Answer: BCBACBDAAD Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:39 PM 122

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

62. E09 EA2.l 037INEW//HIGHERJIROINORTH ANNA/6/2008/

Given the following:

  • A loss of off-site power due to a Tornado hitting the switchyard.
  • The crew has stabilized the Unit using 1-ES-0.1, Reactor Trip Response.
  • Operations Management has directed performance of a Natural Circulation

Cooldown.

Which ONE of the following procedures will be used to perform the RCS Cooldown,

and which ONE of the following is the MAXIMUM cooldown rate allowable in

accordance with the EOP that will be used?

A~ ES-0.2A, Natural Circulation Cooldown with CRDM Fans; 25 degrees F/Hr.

B. ES-0.2A, Natural Circulation Cooldown with CRDM Fans; 15 degrees F/Hr.

C. ES-0.2B, Natural Circulation Cooldown without CRDM Fans; 25 degrees F/Hr.

D. ES-0.2B, Natural Circulation Cooldown without CRDM Fans; 15 degrees F/Hr.

A Correct. With loss of off-site power, power is still available to operate CRDM cooling

fans, so the crew will use ES-0.2A for the cooldown. Specified cooldown rate is

correct.

B Incorrect. The procedure selected is correct, but the cooldown rate is incorrect but

plausible because it is associated with selection of ES-0.2B for the cooldown.

C Incorrect. Incorrect procedure; ES-0.2B is performed after the first 5 steps of

ES-0.2A are completed, and ONLY if less than 3 CRDM fans are in operation. In this

case, 3 CRDM fans are operating/available. The candidate who is unfamiliar with

CRDM fan power supplies may assume they are unavailable is they are not Safety

Related loads. The cooldown rate is for use of ES-0.2A, but plausible since candidate

who is unfamiliar with procedure difference may default to the 25 degree per hour

value.

D Incorrect. Incorrect procedure as in C, but cooldown rate is correct if ES-0.2B were

the correct procedure to use.

Monday, June 30, 2008 3:34:39 PM 123

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to determine a~d interpret the following as they apply to the (Natural Circulation

Operations) Facility conditions and selection of appropriate procedures during abnormal and

emergency operations.

Question Number:

Tier: 1

Group: 2

Importance Rating: 3.1

Technical Reference: ES-0.2A, ES-0.2B

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12030

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates facility conditions where a Natural Circulation Cooldown is required,

and provides the applicant with 2 plausible choices of procedure based upon abnormal plant

alignment, and 2 plausible choices for RCS cooldown rate

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 45 6 7 8 9

Answer: ADC C C B ADAC Scramble Range: A - D

Source: NEW Source If Banle

Cognitive Level: mGHER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:39 PM 124

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

63. E!2 EK2.! OS3IMODIFIED//LOWERlIROINORTH ANNAl61200S1

Upon entry into 1-ECA-2.1, Uncontrolled Depressurization of All Steam Generators, the

crew determines that RCS cooldown rate is 10goF/Hr.

Which ONE (1) of the following describes how the crew is directed to control AFW

flow?

A. Total flow is maintained >340 gpm until ALL SG narrow range levels are >11%.

B. Total flow is maintained >340 gpm until ANY SG narrow range level is >11 %.

C. Flow is reduced to 100 gpm to each SG, and narrow range level is controlled at

greater than 11 %.

D~ Flow is reduced to 100 gpm to each SG, and narrow range level is controlled at less

than 50%.

A Incorrect but plausible because it is similar to the action contained in E-O, and also

the level that all SGs are maintained in EOPs. Also, applicant must understand that

AFW requirements change based upon RCS cooldown rate in ECA-2.1 .

B Incorrect but plausible because it is the normal level control in EOPs and is normally

required to avoid transition and implementation of FR-H.1.

C Incorrect but plausible because the flow rate is correct. The level value is incorrect,

the applicant must understand that level may not be maintained adequately when

throttling AFW due to RCS cooldown for different sized breaks, and that FR-H.1 will not

be implemented under these circumstances as specific allowance is contained in the

procedure to address this situation.

D Correct. Above 100 degrees F RCS cooldown rates, AFW is throttled to minimum.

The criteria for raising AFW flow is hot leg temperature increasing, not going below

minimum SG level.

Monday, June 30, 20083:34:39 PM 125

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the interrelations between the (Uncontrolled Depressurization of all Steam

Generators) and the following: Components, and functions of control and safety systems,

including instrumentation, signals, interlocks, failure modes, and automatic and manual

features.

Question Number:

Tier: 1

Group: 1

Importance Rating: 3.4

Technical Reference: ECA-2.1, E-O

Proposed references to be provided to applicants during examination: None

Learning Objective: U 13843

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates function and control (as well as manual operation) of AFW

system for a condition where an excessive RCS cooldown rate has occurred due to

multiple SG depressurization.

Have developed similar with different distractors. None found previous NRC. Original

provided from VC Summer previous AUDIT exam

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: DCDBDDBBAC Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:39 PM 126

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

64. E 15 EK2.I 034IBANKINORTH ANNA 2006IHIGHERJ/RO/NORTH ANNAl6/2008NES

Given the following:

  • A Steam Break has occurred inside Unit 1 Containment.

actuated.

  • The crew has completed 1-E-2, Faulted SG Isolation.
  • An ORANGE condition exists on the Containment CSF Status Tree.
  • The crew transitions to FR-Z.2, Containment Flooding.

Which ONE of the following describes the source of leakage that will require action to

isolate?

A. Chilled Water

B~ Service Water

C. Primary Grade Water

D. Component Cooling Water

A Incorrect. Chilled Water will be isolated during CDA, so it would not be causing the

level change.

B Correct. With CDA actuated, RS Heat Exchangers are supplied with Service Water

flow.

C Incorrect. Primary Grade Water will be isolated in the current plant condition.

D Incorrect. Component Cooling water is isolated on Phase B caused by Hi-Hi

Containment pressure (CDA).

All of the above systems are plausible because they are identified as sources by

FR-Z.2

Monday, June 30, 2008 3:34:39 PM 127

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the interrelations between the (Containment Flooding) and the following:

Components, and functions of control and safety systems, including instrumentation, signals,

interlocks, failure modes, and automatic and manual features.

Question Number:

Tier: 1

Group: 2

Importance Rating: 2.8

Technical Reference: FR-Z.2, Chilled Water LP, CC LP, PG LP, SW LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 13869

Question History: 2006 Retake; Editorially modified; stem changed, distractors

re-ordered (see original)

10 CFR Part 55 Content: 41.5,7

Comments:

KA Match: This item evaluates the function of safety systems as they apply to FR-Z.2 because

ESF actuations occur based upon Containment pressure. The applicant must determine which

systems are servicing Containment in the current plant condition, to be able to answer the

question.

MCS Time: Points: 1.00 Version: 0123456789

Answer: BDDBDAAACD Scramble Range: A - D

Source: BANK Source If Bank: NORTH ANNA 2006

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?: YES

Monday, June 30, 2008 3:34:39 PM 128

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

65. E16 EK3.1 035IBANKlILOWERlIROINORTH ANNN61200S1

A Small Break LOCA has occured on Unit 1.

The following plant conditions exist:

  • Complications in recovery have resulted in some core damage.
  • Containment Pressure peaked at 13 psia and is slowly decreasing.
  • The team has transitioned to 1-FR-Z.3, Response to High Containment

Radiation Level.

Which ONE of the following describes the actions provided by 1-FR-Z-3 to mitigate the

condition?

A. Evaluate starting Outside Recirc Spray pumps and injecting the CAT.

B. Evaluate starting Inside Recirc Spray pumps and injecting the CAT.

C~ Evaluate placing Containment Atmosphere Filtration System in service.

D. Evaluate venting Containment via the Iodine Filter banks.

A Incorrect. Plausible based on the abnormal Containment conditions. Both cold spray

water and the NAOH solution in the CAT help maintain Iodine in solution, thus the

candidate who is unfamilliar with FR-Z.3 may default to this as a logical solution.

B incorrect. Plausible based on the abnormal Containment conditions. Both cold spray

water and the NAOH solution in the CAT help maintain Iodine in solution, thus the

candidate who is unfamilliar with FR-Z.3 may default to this as a logical solution. Since

there are obvious differences with ISRS and OSRS, candidate may assume one is

preferential to the other for the conditions given in the, stem.

C Correct. As described in FR-Z.3 ERG Background Document, use of spray is not

appropriate for the given conditions, thus Containment Atmospheric Filtration System is

the only viable option.

D Incorrect. Plausible; since the Iodine filters do remove Iodine the candidate who is

unfamilliar with FR-Z.3 may default to this as a logical solution.

Monday, June 30, 2008 3:34:39 PM 129

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Knowledge of the reasons for the following responses as they apply to the (High Containment

Radiation) Facility operating characteristics during transient conditions, including coolant

chemistry and the effects of temperature, pressure, and reactivity changes and operating

limitations and reasons for these operating characteristics.

Question Number:

Tier: 1

Group: 2

Importance Rating: 2.9

Technical Reference: FR-l.3, FR-l.3 SD

Proposed references to be provided to applicants during examination: None

Learning Objective: U 13871

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluated reason for elevated radiation levels after a LOCA, as well as action

required to mitigate. The reason is based on temperature, as indicated in the KA statement

MCS Time: I Points: 1.00 Version: 0 I 2 3 45 6 7 8 9

Answer: CAB CDC CCAD Scramble Range: A - D

Source: BANK Source If Banle

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:39 PM 130

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

66. G2.1.20 084IMODIFIED//LOWERlIROINORTH ANNAi6/2008/

In Emergency Operating Procedure 1-E-0, Reactor Trip or Safety Injection, steps

designated with an asterisk (*) next to the step are ~ _

these steps apply from the time they are encountered until -----

A. Continuous Action Steps;

the EOP Network is exited

B. Decision Making Steps;

the EOP Network is exited

C~ Continuous Action Steps;

transition from 1-E-0 is made

D. Decision Making Steps;

transition from 1-E-0 is made

A Incorrect. Asterisk is used for continuous actions but the requirements to perform

the step end when a transition from the procedure in effect is made.

B Incorrect. Circled steps are decision making steps and only apply at the time read.

C Correct. An asterisk is used for continuous actions but the requirements to perform

the step end when a transition from the procedure in effect is made.

D Incorrect. Circled steps are decision making steps and only apply at the time read.

Monday, June 30, 2008 3:34:40 PM 131

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Conduct of Operations: Ability to interpret and execute procedure steps.

Question Number:

Tier: 3

Group: 1

Importance Rating: 4.6

Technical Reference: DNAP-0509 Procedure Use, EP LP

Proposed references to be provided to applicants during examination: None

Learning Objective: U 12039

Question History: Modified from North Anna 2004 Exam, question provided

10 CFR Part 55 Content: 41.10

Comments:

KA is matched because the item evaluates whether the applicant understands the designators

for steps and how they are applied

MCS Time: 1 Points: 1.00 Version: o 1 2 345 6 7 8 9

Answer: CABDBDDABA Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:40 PM 132

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

67. G2.1.37 086INEW//HIGHERI/RO/NORTH ANNAl612008/

In accordance with OP-AP-300, Reactivity Management, reactor power is required to

be reduced below 100% PRIOR to performing which ONE of the following evolutions?

A. Performing a blended makeup to the RCS

B. Reducing Steam Generator Blowdown Flow Rate

C. Raising Letdown temperature

D~ Operating the Steam Driven Aux Feed Pump Turbine

A Incorrect. While this action might be considered desirable if power was close to

100%, there is no specific requirement in OP-AP-300 to do so. Plausible because past

plant issues with blender components have led to lighter than desired blended

makeups.

B Incorrect. Reducing SG blowdown flow rate will result in actual power lowering. The

guideline requires reducing power if blowdown flow is raised, as that would result in

actual power rising above indicated power. Plausible because power changes with a

change in blowdown flow and the applicant must understand which way it does change.

C Incorrect. Raising letdown temperature will actually lower power as the letdown

demins will release boron at higher temperatures. Plausible because changing letdown

temperature does have an effect on reactor power, and the applicant must know which

way it will change for a change in temperature.

D Correct. Starting the TDAFW Pump turbine will result in a larger heat removal from

RCS, lowering temperature, and causing an increase in reactor power. OP-AP-300

lists starting the TDAFW pump as an evolution requiring power reduction.

Monday, June 30, 2008 3:34:40 PM 133

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Conduct of Operations: Knowledge of procedures, guidelines, or limitations associated with

reactivity management.

Question Number:

Tier: 3

Group: 1

Importance Rating: 4.3

Technical Reference: OP-AP-300 Attachment 2

Proposed references to be provided to applicants during examination: None

Learning Objective: U 13307

Question History:

10 CFR Part 55 Content: 41.5, 10

Comments:

KA Match: Item directly evaluates knowledge of the required topic based on a facility

procedure, Reactivity Management, for operation at 100% power.

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: DCBB B B CBDA Scramble Range: A - D

Source: NEW Source If Banle

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:40 PM 134

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

68. G2.1.41 085lNEW/IHIGHERlIROINORTH ANNN61200S1

Given the following:

Unit 1 is shut down in preparation for Refueling in accordance with 1-0P-4.1,

Controlling procedure for Refueling.

In accordance with 1-0P-4.1, which ONE of the following choices describes

(1) the method of filling the Refueling Cavity

and

(2) which evolution constitutes the FI RST Core Alteration?

A. (1) Gravity fill from RWST, then LHSI pump

(2) Lifting of the Reactor Vessel Upper Internals

B~ (1) Gravity fill from RWST, then LHSI pump

(2) Control Rod Drive Shaft unlatching

C. (1) LHSI pump ONLY

(2) Lifting of the Reactor Vessel Upper Internals

D. (1) LHSI pump ONLY

(2) Control Rod Drive Shaft unlatching

A Incorrect. Gravity fill is the method used to fill the cavity if RWST is at normal level.

Upper internals lift is considered a core alteration however it can not occur until after

rod unlatching. Candidates who are unfamiliar with the sequence of reactor

disassembly may choose this distractor.

B Correct. Method of filling is correct, as stated above unlatching is performed before

the upper internals are lifted, so it constitutes the first core alteration.

C Incorrect. LHSI fill is performed after the gravity fill flow rate drops below 1600 GPM.

Plausible because it is the method used once gravity fill is no longer effective. As

stated above the upper internals lift follows rod unlatching, but candidates who are

unfamiliar with the sequence of reactor disassembly may choose this distractor.

D Incorrect. LHSI fill is performed after the gravity fill flow rate drops below 1600 GPM.

Plausible because it is the method used once gravity fill is no longer effective. First

core alteration is correct.

Monday, June 30, 2008 3:34:40 PM 135

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Conduct of Operations: Knowledge of the refueling process.

Question Number:

Tier: 3

Group: 1

Importance Rating: 2.8

Technical Reference: 1-0P-4.1

Proposed references to be provided to applicants during examination: None

Learning Objective: U 9025

Question History:

10 CFR Part 55 Content: 41.10,43.6

Comments:

KA Match: This item directly matches the KA topic because it evaluates actions contained in

the refueling process, specifically the first core alteration and the method of filling the refueling

cavity. Both evolutions are covered in the controlling procedure fior refueling

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: BDB CDB CCCA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 612008 Previous NRC?:

Monday, June 30, 2008 3:34:40 PM 136

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

69. G2.2.1 089lNEW/IHIGHERlIROINORTH ANNAl6120081

Given the following:

  • An approach to criticality is in progress in accordance with 1-0P-1.7, Unit

Startup from Mode 3 to Mode 2 Following Refueling.

  • Control Banks are at their estimated critical position.
  • RCS dilution has been secured.
  • Criticality is imminent above the ECC Upper Boron Limit.

Which ONE of the following actions is required in accordance with 1-0P-1.7?

A. Wait approximately 20 minutes to ensure mixing of PG water; establish a startup

rate below 1 DPM using additional dilution or Control Bank D withdrawal.

B. Reinitiate RCS dilution in approximately 200 gallon batches; ensure Control Bank D

is above the rod insertion limit; when criticality is declared, establish a startup rate

below 1 DPM using additional dilution or Control Bank D withdrawal.

C. Stop the reactor startup; stabilize reactor power level, and direct Reactor

Engineering to reevaluate parameters and values used to calculate the ECC prior to

continuing.

D~ Insert Control Bank D to 5 steps; manually trip the reactor and verify Shutdown

Margin requirements are met.

A Incorrect. If criticality is achieved above the upper boron limit, that means that the

reactor will be critical significantly prior to when it is supposed to be. Plausible because

this is an infrequently performed evolution, and it is easy to confuse 'above' and 'below'

as well as 'upper' and 'lower' boron concentration limits. Actions are consistent with

normal startup actions.

B Incorrect. This would also be consistent with normal startup actions. Applicant may

confuse 'above upper' and 'below lower' and believe that a normal startup is in

progress. If wording was changed in stem to 'slightly below the upper limit' this would

be true.

C Incorrect. RE will evaluate the ECC, but reactor would be tripped, not stabilized.

Plausible, because stabilizing power places the plant in a safe condition with RILs met,

as stem describes.

D Correct. See discussion above and procedure.

Monday, June 30, 2008 3:34:40 PM 137

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Equipment Control: Ability to perform pre-startup procedures for the facility, including operating

those controls associated with plant equipment that could affect reactivity.

Question Number:

Tier: 3

Group: 2

Importance Rating: 4.5

Technical Reference: 1-0P-1.7 and attachment 3

Proposed references to be provided to applicants during examination: None

Learning Objective: U 15997

Question History:

10 CFR Part 55 Content: 41.10,5

Comments:

KA is matched because this item evaluates operating controls that could affect reactivity,

whether inserting or withdrawing rods, or initiation of dilution. Inserting rods to 5 steps and

manually tripping the reactor on a premature criticality mets the intent of this KA

MCS Time: I Points: 1.00 Version: 0 1 2 3 45 6 7 8 9

Answer: DADDC C C C B B Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:40 PM 138

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

70. 02.2.39 091IMODIFIED//LOWERlIROINORTH ANNAl612008INO

Given the following:

  • Unit 1 is at 45% power.
  • Plant startup is in progress.
  • No other evolutions are in progress

Which ONE of the following indications requires Technical Specification action within

ONE (1) hour?

A. RWST temperature 38 degrees F.

B~ Containment air partial pressure 12.9 psia.

C. Quadrant Power Tilt Ratio 1.022.

D. RCS UNIDENTIFIED LEAKAGE is 1.20 gpm.

A Incorrect. RWST temperature requires action within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. Plausible because

RWST inoperability for any reason other than temperature or boron concentration

requires action within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

B Correct. Applicant must determine that the value will exceed the tech spec limit

based on the curve under all conditions.

C Incorrect. QPTR requires action within 30 minutes if it is greater than 1.02, but only

applies with the unit >50% power. Plausible because it would require action if power

were higher.

D Incorrect. RCS operational leakage Tech Spec allows 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to restore leakage to

within limits. Plausible since an operator who is unfamiliar with Tech Specs may feel

that 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is appropriate based on urgency of the situation.

Monday, June 30, 2008 3:34:40 PM 139

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Equipment Control: Knowledge of less than one hour technical specification action statements

for systems.

Question Number:

Tier: 3

Group: 2

Importance Rating: 3.9

Technical Reference: TS 3.6.4

Proposed references to be provided to applicants during examination: None

Learning Objective: U 10698

Question History:

10 CFR Part 55 Content: 43.2

Comments:

MCS Time: Points: 1.00 Version: o 1 2 3 4 5 6 7 8 9

Answer: BACBBADACD Scramble Range: A - D

Source: MODIFIED Source If Bank:

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?: NO

Monday, June 30, 2008 3:34:40 PM 140

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

71. G2.2.7 090lNEW/ILOWERJIROINORTH ANNN6/20081

Given the following:

  • A mid-cycle reactor startup is planned for Unit 1.
  • NO special tests or evolutions are required during the startup.

In accordance with OP-AA-106, Infrequently Conducted or Complex Evolutions, which

ONE of the following describes the category of ICCE, and the level of supervision

required for the ICCE?

Note:

Category II - Tests or Evolutions That Have the Potential to Degrade Safety Due

to the Complexity or Unpredictably of the Test or Evolution

Category III - Routine Tests or Evolutions That Are Complex Due to Abnormal

Initial Conditions, Concurrent Tests, or Infrequent Performance

A. Category II; Shift Manager, OMOC Qualified

B. Category II; Department Manager, presently or previously SRO licensed

C~ Category III; Shift Manager, OMOC Qualified

D. Category III; Department Manager, presently or previously SRO licensed

A Incorrect. Category II would be for tests performed during a reactor startup that

would degrade or potentially degrade plant performance. Plausible because reactor

startup-related tasks are given as examples of Category II ICCEs.

8 Incorrect. Same reason as A and Dept. Mgr would be correct if the ICCE was a

category II.

C Correct. Reactor startup noted as a category IIIICCE, and SM (OMOC qualified)

must be provided for oversight.

D Incorrect. Plausible because category is correct, but level of supervision would be

required for category II or I ICCE.

Monday, June 30, 2008 3:34:40 PM 141

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Equipment Control: Knowledge of the process for conducting special or infrequent tests.

Question Number:

Tier: 3

Group: 2

Importance Rating: 2.9

Technical Reference: OP-AA-106, section 5.3

Proposed references to be provided to applicants during examination: None

Learning Objective:

Question History:

10 CFR Part 55 Content: 41 .10

Comments:

KA is matched because item directly evaluates knowledge of the process and hierarchy of

ICCEs, providing for selection of level as well as required supervision for an operationally

relevant evolution

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: C C B B D D D C B C Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:40 PM 142

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

72. G2.3.15 095IBANKINORTH ANNA 6135ILOWERJIROINORTH ANNAl612008INO

Given the following:

  • Unit 1 is defueled and the fuel assembly insert shuffle is in progress.
  • Annunciator 1 K-D3, RAD MONITOR SYSTEM FAILURE TEST, actuates.
  • The new fuel storage area radiation monitor is noted to be pegged high and

unresponsive to source check.

  • The fuel pit bridge radiation monitor indication has not changed.
  • Health Physics reports radiation levels in the fuel building have not changed.

Which ONE of the following describes the FIRST action that will be required?

A. Verify the fuel pit bridge radiation monitor is operable.

B. Verify the fuel building ventilation exhaust is aligned to the charcoal filter.

C~ Place the fuel building radiation automatic interlock key switch in DISABLE.

D. Reset the new fuel storage area radiation monitor by pulling and reinserting fuses.

A Incorrect. SFP bridge monitor does not show indication of inoperability, supported by

HP determination of radiation levels. Plausible because it is logical to use redundant

indication for a monitor in alarm.

B Incorrect. The Fuel Building Ventilation system and doors are normally in

Configuration B. High radiation would cause ventilation alignment to filtered exhaust.

Verification is not required based on the failure presented, but would be required for an

actual high radiation condition lAW AP-30.

C Correct. ARP will send the operator to 0-AP-5.1, which will place switch in DISABLE

prior to bottled air dump.

D Incorrect. Subsequent action in attachment 3 will attempt to reset the radiation

monitor by pulling and reinserting fuses.

Monday, June 30, 2008 3:34:40 PM 143

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Radiation Control: Knowledge of radiation monitoring systems, such as fixed radiation monitors

and alarms, portable survey instruments, personnel monitoring equipment, etc.

Question Number:

Tier: 3

Group: 3

Importance Rating: 2.9

Technical Reference: 1K-D3, 0-AP-5.1 steps 1, 2, and attachment 3

Proposed references to be provided to applicants during examination: None

Learning Objective: U 10705

Question History:

10 CFR Part 55 Content: 41.11

Comments:

KA match: Item directly evaluates the radiation monitoring system for the Fuel Handling

system by requiring knowledge of actuation based on alarm status, and action required to

prevent actuation based upon 'the alarm status of a fixed radiation monitor',

MCS Time: 1 Points: 1.00 Version: 0 1 2 3 4 5 6 7 8 9

Answer: C CAD B A A A A C Scramble Range: A - D

Source: BANK. Source If Bank: NORTH ANNA 6135

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?: NO

Monday, June 30, 2008 3:34:41 PM 144

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

73. G2.3.4 094INEW//LOWER//RO/NORTH ANNN6/2008/

Given the following:

  • An explosion and fire occurred in the Auxiliary Building.
  • The fire has been extinguished.
  • Process Vents radiation monitor indication is increasing.
  • Auxiliary Building radiation monitor indications are increasing..
  • After the explosion, the Auxiliary Building watchstander informed the Shift

Manager that he was injured and unable to move.

The Station Emergency Manager (SEM) is evaluating dispatching a team to the

Auxiliary Building.

Which ONE of the following is CORRECT concerning the SEM's decision making

process?

A. The SEM should authorize no more than 10 rem TEDE for each search and rescue

individual to retrieve the injured watchstander.

B. The SEM should authorize no more than 10 rem TEDE combined dose for the

search and rescue team to retrieve the injured watchstander.

Cr The SEM should authorize no more than 25 rem TEDE for each search and rescue

individual to retrieve the injured watchstander.

D. The SEM should authorize no more than 25 rem TEDE combined dose for the

search and rescue team to retrieve the injured watchstander.

A Incorrect. Plausible because there is a limit of 10 Rem TEDE, but that limit is

applicable to save valuable equipment or limit off-site releases.

B Incorrect. Plausible; as stated above the limit of 10 Rem TEDE is applicable to save

valuable equipment or limit off-site releases. Further, since most ALARA practices are

concerned with total dose; the candidate who is unfamiliar with the specific guidance of

the EPIP may default to this since with a team of people, allowing each one to get up to

10 rem seems excessive.

C Correct. The limit of 25 Rem TEDE is applicable for search and rescue, first aid, and

(as given in the stem) removal of injured personnel. Limit is for each individual.

o Incorrect. The limit of 25 Rem TEDE is applicable for search and rescue, first aid,

and (as given in the stem) removal of injured personnel. Plausible since most ALARA

practices are concerned with total dose; the candidate who is unfamiliar with the

specific guidance of the EPIP may default to this since with a team of people, allowing

each one to get up to 25 rem seems excessive.

Monday, June 30, 20083:34:41 PM 145

QUESTIONS REPORT

for NORTH ANNA NRC exam - RavO 04 15 08 RO ONLY

Knowledge of radiation exposure limits under normal or emergency conditions

Question Number:

Tier: 3

Group: 3

Importance Rating: 3.2

Technical Reference: VPAP 2101

Proposed references to be provided to applicants during examination: None

Learning Objective: 13583

Question History: This is called a Bank question, although it is written new. Items

are in the bank containing similar attributes and context

10 CFR Part 55 Content: 41.12

Comments:

KA Match: Item directly evaluates administrative exposure limits, which is the topic addressed

by the KA

MCS Time: Points: 1.00 Version: o 1 2 345 6 7 8 9

Answer: CADDABCBCA Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:41 PM 146

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

74. G2.4.32 097INEW//LOWERJ/RO/NORTH ANNN6/2008/

Given the following:

  • Both Units are at 100% power.
  • The following alarm is received on Unit 2 Panel F:
  • UNIT #1 ANN SYS POWER SUPPLY FAILURE
  • Unit 1 determines that the control room annunciators have stopped functioning.
  • The crew enters 1-AP-6, Loss of Main Control Room Annunciators.

Which ONE of the following actions is required in accordance with 1-AP-6 if the Unit 1

Annunciators are not immediately restored?

A. Initiate a controlled plant shutdown to Mode 3; log AFD every 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

B. Maintain reactor power stable; log AFD every 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

C. Initiate a controlled plant shutdown to Mode 3; log AFD hourly.

D~ Maintain reactor power stable; log AFD hourly.

A Incorrect. Power would be maintained stable with increased monitoring of plant

parameters. Operations that upset plant stability will be stopped or not performed. The

AFD is required to be logged hourly not every 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

B Incorrect. Maintaining power stable is correct, but frequecy of logging AFD is greater

than that allowed by procedure.

C Incorrect. Power reduction is incorrect as noted in A above. Plausible as frequency

provided for logging AFD is correct.

o Correct. Unit is maintained in stable condition. Increased monitoring of AFD is

required as the AFD alarm is inoperable and frequency provided is correct.

Monday, June 30, 2008 3:34:41 PM 147

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Emergency Procedures / Plan: Knowledge of operator response to loss of all annunciators.

Question Number:

Tier: 3

Group: 4

Importance Rating: 3.6

Technical Reference: 1-AP-6 (Whole procedure)

Proposed references to be provided to applicants during examination: None

Learning Objective: U 11667

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: This item directly evaluates operator response to loss of control room annunciators

at 100% power.

MCS Time: 1 Points: 1.00 Version: o 1 2 3 4 5 6 7 8 9

Answer: DCDBBCCBDD Scramble Range: A - D

Source: NEW Source If Bank:

Cognitive Level: LOWER Difficulty Level :

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:41 PM 148

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

75. G2.4.9 OOllBANKINORTH ANNAlHIGHERlIROINORTH ANNN6120081

Given the following:

  • Unit 1 is in Mode 5.
  • RCS Drain Down to Mid Loop is in progress in preparation for welding on a Hot

Leg opening.

  • RHR Pump 1A is in service.
  • During the drain down, RHR amps and discharge pressure begin fluctuating

erratically.

  • RCS temperature has risen from 121 degrees F to 127 degrees F.
  • The crew enters 1-AP-11, Loss of RHR, and stops the RCS drain down.

Which ONE (1) of the following describes the next actions that will be required in

accordance with 1-AP-11?

A. Reduce RHR flow to minimum required to maintain RCS temperature and maximize

CC flow to inservice RHR heat exchangers.

B:'" Reduce RHR flow to minimum required to maintain RCS temperature and/or raise

RCS level to ensure at least 10 inches above the Hot Leg centerline.

C. Stop RHR Pump 1A and start RHR Pump 1B and verify that RCS temperature

stabilizes.

D. Stop RHR Pump 1A and initiate the appropriate attachment for Alternate Core

Cooling to control RCS temperature.

A Incorrect. Actions appear correct and are very close to the required actions, except

that level must be raised higher than 10 inches above Centerline.

B Correct. Actions provided minimize required net possitive suction head and increase

available NPSH and are directed by the procedure to assess the condition of the RHR

System prior to taking more radical actions.

C Incorrect. Plausible because stopping the pump would be performed subsequently

for the case where reducing flow was ineffective. Since the pump would be air-bound,

the other pump would not be started without venting.

D Incorrect. Plausible same as C, and also that alternate core cooling could be

performed if that condition was reached. Again these actions are subsequent to those

that attempt to maintain the system in operation is the preferred method of decay heat

removal.

Monday, June 30, 2008 3:34:41 PM 149

QUESTIONS REPORT

for NORTH ANNA NRC exam - RevO 04 15 08 RO ONLY

Ability to operate and / or monitor the following as they apply to the Loss of Residual Heat

Removal System: RCS temperature indicators

Question Number:

Tier: 1

Group: 1

Importance Rating: 3.6

Technical Reference: 1-AP-11

Proposed references to be provided to applicants during examination: None

Learning Objective: None

Question History:

10 CFR Part 55 Content: 41.10

Comments:

KA Match: Item evaluates action required for a loss of RHA. One part of this is the indication of

RCS temperature rising. While the item does not isolate 'monitoring of RCS temperature

indicators', the actions would be the same and the procedure does not differentiate any actions

based on temperature alone.

MCS Time: Points: 1.00 Version: 0 I 2 3 4 5 6 7 8 9

Answer: B A ADD CD B D C Scramble Range: A - D

Source: BANK Source If Bank: NORTH ANNA

Cognitive Level: HIGHER Difficulty Level:

Job Position: RO Plant: NORTH ANNA

Date: 6/2008 Previous NRC?:

Monday, June 30, 2008 3:34:41 PM 150