Project, Units 1 and 2, Updated Final Safety Analysis Report, Revision 14, Chapter of 16, Technical Specifications
ML081500292
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/30/2008
From:
South Texas
To:
Office of Nuclear Reactor Regulation
References
NOC-AE-08002283, STI: 32284244
Download: ML081500292 (22)


Text

STPEGS UFSAR 16.1-1 Revision 13 16.0 TECHNICAL SPECIFICATIONS 16.1 TECHNICAL REQUIREMENTS MANUAL The Technical Requirements Manual is a document containing in part information that has been relocated from the Technical Specifications. Relocation of information from the Technical Specifications to the Technical Requirements Manual is based on the requirements of the "Final Policy Statement on Technical Specifications Improvements for Nuclear Power Reactors" issued by the NRC in 1993. The Technical Requirements Manual is considered a licensing basis document and as such overall control of the document is governed by applicable station requirements for control of licensing basis documents. Changes made to the Technical Requirements Manual are governed by the cr iteria of 10CFR50.59 to determine if changes require approval by the NRC prior to implementation.

STPEGS UFSAR 16.1-2 Revision 13 TABLE 16.1-1 CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) CONTAINMENT ISOLATION PHASE A M-51 CV0033A* CVCS Seal Water Injection 10 M-51 CV0033B* CVCS Seal Water Injection 10 M-52 CV0033C* CVCS Seal Water Injection 10 M-52 CV0033D* CVCS Seal Water Injection 10 M-46 XCV0023 CVCS Letdown 15 M-46 XCV0024 CVCS Letdown 15 M-48 XCV0025 CVCS Charging 15 M-47 CV0077 RCP Seal Water Leakoff Return 10 M-47 CV0079 RCP Seal Water Leakoff Return 10 M-72 ED0064 Containment Normal Sump Discharge 10 M-72 FV-7800 Containment Normal Sump Discharge 10 M-77 FP0756 Containment Fire Protection 10 M-72(1)FV-2453 Containment Sump Post Accident Sample 5 M-86(1)FV-2454 RHR Post Accident Sample 5 M-85(1)FV-2455 RCS Post Accident Sample 5 M-85(1)FV-2455A RCS Post Accident Sample 5

STPEGS UFSAR 16.1-3 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) CONTAINMENT ISOLATION PHASE A (Continued)

M-82(1)FV-2456 Containment Atmosphere Post Accident Sample 5 M-82(1)FV-2457 Containment Atmosphere Post Accident Sample 5 M-45(1)FV-2458 Liquid Post Accident Sample Discharge 5 M-45 FV-3651 Pressurizer Relief Tank Makeup 10 M-68 FV-3652 Pressurizer Relief Tank Vent 10 M-68 FV-3653 Pressurizer Relief Tank Vent 5 M-68 FV-3970 SIS Check Valve Test 10 M-68 FV-3971 SIS Check Valve Test 10 M-68 FV-3983 Accumulator Nitrogen Supply 10 M-80(1)FV-4135 Containment Hydrogen Monitoring 5 M-80(1)FV-4101 Containment Hydrogen Monitoring 5 M-82(1)FV-4104 Containment Hydrogen Monitoring 5 M-80(1)FV-4127 Containment Hydrogen Monitoring 5 M-80(1)FV-4128 Containment Hydrogen Monitoring 5 M-82(1)FV-4136 Containment Hydrogen Monitoring 5

STPEGS UFSAR 16.1-4 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) CONTAINMENT ISOLATION PHASE A (Continued)

M-82(1)FV-4133 Containment Hydrogen Monitoring 5 M-82(1)FV-4134 Containment Hydrogen Monitoring 5 M-85(1)FV-4450 Pressurizer Vapor Sample 5 M-85(1)FV-4451 Pressurizer Liquid Sample 5 M-85(1)FV-4452 Pressurizer Vapor Sample 10 M-85(1)FV-4451B Pressurizer Liquid Sample 10 M-85(1)FV-4454 RCS Hot Leg Sample 5 M-85(1)FV-4455 RCS Hot Leg Sample 5 M-85(1)FV-4456 RCS Hot Leg Sample 10 N.A. FV-1025 Personnel Air Lock Air Supply 10 N.A. FV-1026 Personnel Air Lock Air Supply 10 N.A. FV-1027 Personnel Air Lock Auto Leak Rate Monitoring 10 N.A. FV-1028 Personnel Air Lock Auto Leak Rate Monitoring 10 M-86(1)FV-4823 RHR Sample 5 M-86(1)FV-4461 RHR Sample 10 M-29(1)FV-4824 SI Accumulator Sample 5 M-29(1)FV-4466 SI Accumulator Sample 10 M-58 FV-8565 Containment Instrument Air 10 M-56 WL0312 RCDT Discharge 10 STPEGS UFSAR 16.1-5 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) CONTAINMENT ISOLATION PHASE A (Continued)

M-56 FV-4913 RCDT Discharge 10 M-30 FV-4919 RCDT Vent 10 M-30 FV-4920 RCDT Vent 5 CONTAINMENT VENTILATION ISOLATION M-43(2)FV-9776 Containment Supplementary Purge Supply 5 M-43(2)HC0003 Containment Supplementary Purge Supply 10 M-44(2)HC0005 Containment Supplementary Purge Exhaust 10 M-44(2)FV-9777 Containment Supplementary Purge Exhaust 5 M-42 HC0007 Containment Normal Purge Supply 60 M-42 HC0008 Containment Normal Purge Supply 60 M-41 HC0009 Containment Normal Purge Exhaust 60 M-41 HC0010 Containment Normal Purge Exhaust 60 M-80 RA0001 Containment Atmosphere Radiation Monitor 10 M-80 RA0003 Containment Atmosphere Radiation Monitor 10 STPEGS UFSAR 16.1-6 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) CONTAINMENT VENTILATION ISOLATION (Continued)

M-80 RA0004 Containment Atmosphere Radiation Monitor 10 M-80 RA0006 Containment Atmosphere Radiation Monitor 10 CONTAINMENT ISOLATION PHASE B M-39 CC0291 CCW to RCPs 10 M-39 CC0318 CCW to RCPs 10 M-40 CC0403 CCW from RCPs 10 M-40 CC0404 CCW from RCPs 10 M-40 CC0542 CCW from RCPs 10 M-40 FV-4493 CCW from RCPs 10 REMOTE MANUAL M-83(3)AF0019 AFW Supply N.A M-94(3)AF0048 AFW Supply N.A. M-95(3)AF0065 AFW Supply N.A. M-84(3)AF0085 AFW Supply N.A. M-33 CC0012 CCW to RHR HX and RHR Pump N.A. M-34 CC0049 CCW from RHR HX and RHR Pump N.A M-34 CC0050 CCW from RHR HX and RHR Pump N.A. M-25 CC0057 CCW to RCFC N.A. M-26 CC0068 Cooling Water from RCFC N.A STPEGS UFSAR 16.1-7 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) REMOTE MANUAL (Continued)

M-26 CC0069 CCW from RCFC N.A. M-35 CC0122 CCW to RHR HX and RHR Pump N.A. M-36 CC0129 CCW from RHR HX and RHR Pump N.A. M-36 CC0130 CCW from RHR HX and RHR Pump N.A. M-27 CC0136 CCW to RCFC N.A. M-28 CC0147 Cooling Water from RCFC N.A. M-28 CC0148 CCW from RCFC N.A. M-37 CC0182 CCW to RHR HX and RHR Pump N.A. M-38 CC0189 CCW from RHR HX and RHR Pump N.A. M-38 CC0190 CCW from RHR HX and RHR Pump N.A. M-24 CC0197 CCW to RCFC N.A. M-23 CC0208 Cooling Water from RCFC N.A. M-23 CC0210 CCW From RCFC N.A. M-1 (3)MS0143 Main Steam Supply to AFW Turbine N.A. M-1 (3)FV-0143 Bypass for MS Supply to AFW Turbine N.A. M-18 XSI0004A High Head SI Discharge N.A. M-14 XSI0004B High Head SI Discharge N.A. M-10 XSI0004C High Head SI Discharge N.A. M-22 XSI0016A Emergency Sump Recirculation N.A. M-21 XSI0016B Emergency Sump Recirculation N.A. M-20 XSI0016C Emergency Sump Recirculation N.A.

STPEGS UFSAR 16.1-8 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds)

REMOTE MANUAL (Continued)

M-19 XSI0018A Low Head SI Discharge N.A. M-15 XSI0018B Low Head SI Discharge N.A. M-11 XSI0018C Low Head SI Discharge N.A. M-17(6)XCS0001A Containment Spray to Ring Header N.A. M-13(6)XCS0001B Containment Spray to Ring Header N.A. M-9(6)XCS0001C Containment Spray to Ring Header N.A. MANUAL AND CHECK VALVES M-82(4)BA0004 Breathing Air to Containment N.A. M-82 BA0006 Breathing Air to Containment N.A. M-33 CC0013 CCW to RHR HX and RHR Pump N.A. M-25 CC0058 Cooling Water to RCFC N.A. M-35 CC0123 CCW to RHR HX and RHR Pump N.A. M-27 CC0138 Cooling Water to RCFC N.A. M-37 CC0183 CCW to RHR HX and RHR Pump N.A. M-24 CC0198 Cooling Water to RCFC N.A. M-39 CC0319 CCW to RCPs N.A. M-40 CC0446 CCW from RCPs N.A. M-46 CV0022 CVCS Letdown N.A. M-51 CV0034A CVCS Seal Water Injection N.A. M-51 CV0034B CVCS Seal Water Injection N.A.

STPEGS UFSAR 16.1-9 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES Penetration Valve No.

Function Maximum Isolation Time (seconds) MANUAL AND CHECK VALVES (Continued)

M-52 CV0034C CVCS Seal Water Injection N.A. M-52 CV0034D CVCS Seal Water Injection N.A. M-47 CV0078 CVCS Seal Water Leakoff Return N.A. M-48 XCV0026 CVCS Charging N.A. M-53 XCV0157 CVCS to RHR N.A. M-53 XCV0158 CVCS to RHR N.A. M-17 XCS0002 Containment Spray Header N.A. M-13 XCS0004 Containment Spray Header N.A. M-13 XCS0005 Containment Spray Header N.A. M-9 XCS0006 Containment Spray Header N.A. M-61 (4)DW0501 Demineralized Water Supply N.A. M-61 DW0502 Demineralized Water Supply N.A. M-58 IA0541 Instrument Air to Containment N.A. M-70 XFC0006C In Containment Spent Fuel Storage to SFP Pump N.A. M-70 XFC0007C In Containment Spent Fuel Storage to SFP Pump N.A. M-69 XFC0013E SFP HX Return to Containment N.A. M-69 XFC0013F SFP HX Return to Containment N.A. M-69 XFC0050 SFP HX Return to Containment N.A. M-77 FP0943 Containment Fire Protection N.A. M-2 (4)MS-0543 Main Steam Line Drain N.A. M-3 (4)MS-0544 Main Steam Line Drain N.A. M-4 (4)MS-0545 Main Steam Line Drain N.A. M-1 (4)MS-0546 Main Steam Line Drain N.A. M-45 XRC0046 Makeup to Pressurizer Relief Tank N.A.

STPEGS UFSAR 16.1-10 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) MANUAL AND CHECK VALVES (Continued)

M-88 RD0008 Reactor Coolant Vacuum Degassing N.A. M-88 RD0010 Reactor Coolant Vacuum Degassing N.A. M-55 XRH0063B Refueling Cavity to RWST N.A. M-76 XRH0063C Refueling Cavity to RWST N.A. M-55 XRH0064B Refueling Cavity to RWST N.A. M-76 XRH0064C Refueling Cavity to RWST N.A. M-57(4)SA0504 Service Air N.A. M-57 SA0505 Service Air N.A. M-16 SL0002 Sludge Lancing High Pressure N.A. M-16 SL0004 Sludge Lancing High Pressure N.A. M-79 SL0012 Sludge Lancing Low Pressure N.A. M-79 SL0014 Sludge Lancing Low Pressure N.A. M-12 SL0027 Chemical Cleaning Return N.A. M-12 SL0029 Chemical Cleaning Return N.A. M-81 Penetration has been capped M-75 P00217 RCP Oil Return N.A. M-75 P00218 RCP Oil Return N.A. M-18 XSI0005A High Head SI Discharge N.A. M-14 XSI0005B High Head SI Dishcharge N.A. M-10 XSI0005C High Head SI Discharge N.A.

STPEGS UFSAR 16.1-11 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) MANUAL AND CHECK VALVES (Continued)

M-19 XSI0030A Low Head SI Discharge N.A. M-15 XSI0030B Low Head SI Discharge N.A. M-11 XSI0030C Low Head SI Discharge N.A. M-68 SI0058 Accumulator Nitrogen Supply N.A. OTHER AUTOMATIC VALVES (SI Actuated Valves)

M-25 CC0059 RCFC Chilled Water Supply 10 M-26 CC0070 RCFC Chilled Water Return 10 M-26 FV-0862 RCFC Chilled Water Return 10 M-27 CC0137 RCFC Chilled Water Supply 10 M-28 CC0149 RCFC Chilled Water Return 10 M-28 FV-0863 RCFC Chilled Water Return 10 M-24 CC0199 RCFC Chilled Water Supply 10 M-23 CC0209 RCFC Chilled Water Return 10 M-23 FV-0864 RCFC Chilled Water Return 10 OTHER AUTOMATIC VALVES (Steam Line Isolation Actuated Valves)

M-2(3)FV-7412 Main Steam Isolation Bypass 5 M-3(3)FV-7422 Main Steam Isolation Bypass 5 M-4(3)FV-7432 Main Steam Isolation Bypass 5 M-1(3)FV-7442 Main Steam Isolation Bypass 5 M-2(3, 5)FSV-7414 Main Steam Isolation 5

STPEGS UFSAR 16.1-12 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) OTHER AUTOMATIC VALVES B (Steam Line Isolation Actuated Valves)

(Continued)

M-3(3, 5)FSV-7424 Main Steam Isolation 5 M-4(3, 5)FSV-7434 Main Steam Isolation 5 M-1(3, 5)FSV-7444 Main Steam Isolation 5 OTHER AUTOMATIC VALVES (Feedwater Isolation Actuated Valves)

M-6(3, 7)FV-7141 Feedwater Isolation 10 M-83(3)FV-7192 Feedwater Isolation - SG Preheater Bypass 10 M-7 (3, 7)-FV-7142 Feedwater Isolation 10 M-84(3)FV-7191 Feedwater Isolation - SG Preheater Bypass 10 M-8(3, 7)FV-7143 Feedwater Isolation 10 M-94(3)FV-7189 Feedwater Isolation - SG Preheater Bypass 10 M-5(3, 7)FV-7144 Feedwater Isolation 10 M-95(3)FV-7190 Feedwater Isolation - SG Preheater Bypass 10 M-5(3)FV-7145A Feedwater Isolation Valve Bypass 10 STPEGS UFSAR 16.1-13 Revision 13 TABLE 16.1-1 (Continued) CONTAINMENT ISOLATION VALVES

Penetration

Valve No.

Function Maximum Isolation Time (seconds) OTHER AUTOMATIC VALVES (Feedwater Isolation Actuated Valves) (Continued)

M-8(3)FV-7146A Feedwater Isolation Valve Bypass 10 M-7(3)FV-7147A Feedwater Isolation Valve Bypass 10 M-6(3)FV-7148A Feedwater Isolation Valve Bypass 10 OTHER AUTOMATIC VALVES (Auxiliary Feedwater Initiation Actuated Valves)

M-62(3)FV-4150 Steam Generator Blowdown 35 M-65(3)FV-4151 Steam Generator Blowdown 35 M-64(3)FV-4152 Steam Generator Blowdown 35 M-63(3)FV-4153 Steam Generator Blowdown 35 M-86(3)FV-4186 Steam Generator Sample 5 M-86(3)FV-4187 Steam Generator Sample 5 M-86(3)FV-4188 Steam Generator Sample 5 M-86(3)FV-4189 Steam Generator Sample 5

STPEGS UFSAR 16.1-14 Revision 13 Notes to Table 16.1-1

  • Valves isolate on concurrent Containment Phas e A isolation and low charging header pressure signals. 1. Valves opened only when sample needed.
2. Valve could be opened during normal operation, as needed.
3. Not subject to Type C Leakage Tests.
4. May be opened on an intermittent basis under administrative control.
5. These valves are included for table completeness. The requirements of Technical Specification 3/4.6.3 do not apply; instead, the requirements of Technical Specification 3/4.7.1.5 apply to the main steam isolation valves.
6. These valves are included for table completeness. The requirements of Technical Specification 3/4.6.3 do not apply; instead, the requirements of Tec hnical Specification 4.6.2.1 apply. Valve stroke times, where specified, will be tested pursuant to Technical Specification 4.0.5.
7. These valves are included for table completeness. The requirements of Technical Specification 3/4.6.3 do not apply; instead, the requirements of Technical Specification 3/4.7.1.7 apply to the feedwa ter isolation valves.

STPEGS UFSAR 16.1-15 Revision 13 TABLE 16.1-2 REACTOR VESSEL MATERIAL SURVEILLANCE PROGRAM -

WITHDRAWAL SCHEDULE Unit 1 CAPSULE NUMBER VESSEL LOCATION (degrees)LEAD FACTOR (Capsule)ACTUAL/RECOMMENDED WITHDRAWAL TIME (EFPY)

U 58.5 o 3.59(1)0.78 (Removed)(4)Y 241.0 o 3.28(1)4.9 (Removed)(4)V 61.0 o 3.04(2)10.6 (Removed)(4)X 238.5 o 3.28(3)16(5)W 121.5 o 3.24(3)16(5)Z 301.5 o 3.24(3)16(5)CN-2757 Unit 2 CAPSULE NUMBER VESSEL LOCATION (degrees)LEAD FACTOR (Capsule)ACTUAL/RECOMMENDED WITHDRAWAL TIME (EFPY)(c)V 61.0 o 3.09(1)0.90 (Removed)(4)Y 241.0 o 3.11(1)5.13 (Removed)(4)U 58.5 o 3.20(2)10.3 (Removed)(4)X 238.5 o 3.22(3)16(5)W 121.5 o 3.19(3)16(5)Z 301.5 o 3.19(3)16(5)CN-2757 CN-2757 1. Lead factor derived from reanalysis of sensor sets from previously withdrawn capsules 2. Lead factor calculated based on actual end of cycle fluence 3. Lead factor based on cycle specific exposure calculations for current fluence 4. Actual Effective Full Power Years (EFPY) at removal 5. Recommended removal time in EFPY. These values are approximate and are selected to ensure that excessive exposure is not attained.

STPEGS UFSAR 16.1-16 Revision 13 TABLE 16.1-3 REACTOR TRIP SYSTEM INSTRUMENTATION RESPONSE TIMES FUNCTIONAL UNITRESPONSE TIME

1. Manual Reactor Trip N.A. 2. Power Range, Neutron Flux 0.5 second*
3. Power Range, Neutron Flux, High Positive Rate 3.0 second*
4. Intermediate Range, Neutron Flux N.A. 5. Source Range, Neutron Flux 0.5 second*
6. Extended Range, Neutron Flux N.A. 7. Overtemperature T 10.0 seconds*
8. Overpower T 10.0 seconds*
9. Pressurizer Pressure - - Low 2 seconds
10. Pressurizer Pressure - - High 2 seconds
11. Pressurizer Water Level - - High 2 seconds STPEGS UFSAR 16.1-17 Revision 13 TABLE 16.1-3 (Continued) REACTOR TRIP SYSTEM INSTRUMENTATION RESPONSE TIMESFUNCTIONAL UNITRESPONSE TIME
12. Reactor Coolant Flow - - Low
a. Single Loop (Above P-8) 1 second
b. Two Loops (Above P-7 and below P-8) 1 second
13. Steam Generator Water Level - - Low - Low 2 seconds
14. Undervoltage - Reactor Coolant Pumps 1.5 seconds
15. Underfrequency - Reactor Coolant Pumps 0.6 second
16. Turbine Trip
a. Low Emergency Trip Fluid Pressure N.A. b. Turbine Stop Valve Closure N.A. 17. Safety Injection Input from ESFAS N.A. 18. Reactor Trip System Interlocks N.A. 19. Reactor Trip Breakers N.A. 20. Automatic Trip and Interlock Logic N.A.
  • Neutron detectors are exempt from response time testing. Response time of the neutron flux signal portion of the channel shall be measured from dete ctor output or input of first electronic component in channel.

STPEGS UFSAR 16.1-18 Revision 13 TABLE 16.1-4 ENGINEERED SAFETY FEATURES RESPONSE TIMES INITIATION SIGNAL AND FUNCTIONRESPONSE TIME IN SECONDS

1. Manual Initiation
a. Safety Injection (ECCS)

N.A. b. Containment Spray N.A. c. Phase "A" Isolation N.A. d. Phase "B" Isolation N.A. e. Containment Ventilation Isolation N.A. f. Steam Line Isolation N.A. g. Feedwater Isolation N.A. h. Auxiliary Feedwater N.A. i. Essential Cooling Water N.A. j. Reactor Containment Fan Coolers N.A. k. Control Room Ventilation N.A. l. Reactor Trip N.A. m. Start Diesel Generator N.A. 2. Containment Pressure - - High - 1

a. Safety Injection (ECCS) 27(1)/12(5) 1).Reactor Trip 2 (3) 2).Feedwater Isolation 12(3) 3).Phase "A" Isolation 33(1) / 23(2) 4).Containment Ventilation Isolation (18-inch lines) 23(1) / 13(2) 5).Auxiliary Feedwater 60 6).Essential Cooling Water 62(1) / 52(2) 7).Reactor Containment Fan Coolers 38(1) / 28(2) 8).Control Room Ventilation N.A. 9).Start Standby Diesel Generators 12 STPEGS UFSAR 16.1-19 Revision 13 TABLE 16.1-4 (Continued) ENGINEERED SAFETY FEATURES RESPONSE TIME INITIATION SIGNAL AND FUNCTIONRESPONSE TIME IN SECONDS
3. Pressurizer Pressure - - Low
a. Safety Injection (ECCS) 27(1)/12(5)1) Reactor Trip 2 (3)2) Feedwater Isolation 12(3)3) Phase "A" Isolation 33(1) / 23(2)4) Containment Ventilation Isolation N.A 5) Auxiliary Feedwater 60 6) Essential Cooling Water 62(1) / 52(2)7) Reactor Containment Fan Coolers 38(1) / 28(2)8) Control Room Ventilation N.A. 9) Start Standby Diesel Generators 12 4. Deleted 5. Compensated Steam Line Pressure -- Low
a. Safety Injection (ECCS) 22(4)/12(5)1) Reactor Trip 2 (3)2) Feedwater Isolation 12(3)3) Phase "A" Isolation 33(1) / 23(2)4) Containment Ventilation Isolation N.A. 5) Auxiliary Feedwater 60 6) Essential Cooling Water 62(1) / 52(2)7) Reactor Containment Fan Coolers 38(1) / 28(2)8) Control Room Ventilation N.A. 9) Start Diesel Generators 12 b. Steam Line Isolation 8(3)

STPEGS UFSAR 16.1-20 Revision 13 TABLE 16.1-4 (Continued) ENGINEERED SAFETY FEATURES RESPONSE TIMESINITIATION SIGNAL AND FUNCTIONRESPONSE TIME IN SECONDS

6. Containment Pressure - - High - 3
a. Containment Spray 30(1) / 20(2)b. Phase "B" Isolation 28(1) / 18(2)7. Containment Pressure - - High - 2 Steam Line Isolation 7(3)8. Steam Line Pressure - Negative Rate - - High N.A Steam Line Isolation
9. Steam Generator Water Level - - High - High
a. Turbine Trip 2.5(3)b. Feedwater Isolation 12(3)10. Steam Generator Water Level - - Low - Low
a. Motor-Driven Auxiliary Feedwater Pumps 60 b. Turbine-Driven Auxiliary Feedwater Pump 60 11. RWST Level - - Low-Low Coincident with Safety Injection Automatic Switchover to Containment Sump 32(2)12. Loss of Power
a. 4.16 kV ESF Bus Undervoltage (Loss of Voltage) 12(7)b. 4.16 kV ESF Bus Undervoltage (Tolerable Degraded Voltage Coincident with Safety Injection) 49(7)c. 4.16 kV ESF Bus Undervoltage (Sustained Degraded Voltage) 65(7)

STPEGS UFSAR 16.1-21 Revision 13 TABLE 16.1-4 (Continued) ENGINEERED SAFETY FEATURES RESPONSE TIMES INITIATION SIGNAL AND FUNCTIONRESPONSE TIME IN SECONDS

13. RCB Purge Radioactivity--High
a. Containment Ventilation Isolation (48-inch lines) 72.7(2)b. Containment Ventilation Isolation (18-inch lines) 23(2)14. Deleted 15. Deleted 16. T avg - Low Coincident with Reactor Trip Feedwater Isolation N.A. 17. Control Room Intake Air Radioactivity--High Control Room Ventilation N.A. 18. Spent Fuel Pool Exhaust Radioactivity --High FHB Exhaust Isolation Damper Closure 42(2)19. Charging Header Pressure - Low N.A.

STPEGS UFSAR 16.1-22 Revision 13 TABLE 16.1-4 (Continued)

TABLE NOTATIONS (1) Diesel generator starting and se quence loading delays included.

(2) Diesel generator starting delay not included, sequence loading delay is included. Offsite power available.

(3) Not dependent upon diesel generator starting or se quence loading delays.

(4) Diesel generator starting and sequence loading delay included. Low Head Safety Injection pumps not included.

(5) Diesel generator starting delays not included, sequence loading delay is included. Low Head Safety Injection pumps not included.

(6) Actuation times for Control Room Ventilation do not include the opening times for the modulating damper.

(7) Diesel generator starting delay is include d, sequence loading delay is not included.