Teleconf Held 4/30/08 Between NRC and Firstenergy Concerning the RAI Pertaining to the Refurbishment Activities at Beaver, Units 1 and 2, LRA
ML081230499
Person / Time
Site: Beaver Valley
Issue date: 06/03/2008
From: Kent Howard
NRC/NRR/ADRO/DLR
To:
Sayoc, Manny, NRR/DLR/RLRB 415-1924
References
Download: ML081230499 (6)


Text

June 3, 2008 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY:

Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON APRIL 30, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC) and representatives of FirstEnergy Nuclear Operating Company (FENOC) held a telephone conference call on April 30, 2008, to discuss follow-up questions for the refurbishment activities request for additional information concerning the Beaver Valley Power Station, Units 1 and 2, license renewal application. Enclosure 1 is a list of the conference call participants. Enclosure 2 is a summary of the discussion between FENOC and NRC staff.

If you have any questions concerning the NRC staffs summary of this telephone conference, please contact Mr. Kent Howard at 301-415-2989 or by e-mail at Kent.Howard@nrc.gov.

Sincerely,

\\RA\\

Kent Howard, Sr. Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosures:

As stated

ML081230499 OFFICE:

LA:DLR PM:DLR:RPB2 PM:DLR:RPB2 BC: DLR:RPB2 NAME:

IKing ESayoc KHoward RFranovich w/ edits to enclosure DATE:

6/2/08 6/2/08 5/8/08 6/3/08

LIST OF PARTICIPANTS FOR THE TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION April 30, 2008 PARTICIPANTS AFFILIATIONS Emmanuel Sayoc U.S. Nuclear Regulatory Commission Cliff Custer FirstEnergy Nuclear Operating Company (FENOC)

Jeffery Jeffries FENOC Steve Dort FENOC Mike Banko FENOC Catherine Sutton FENOC ENCLOSURE 1

SUMMARY

FOR THE TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION April 30, 2008 In this telephone conference call, the U.S. Nuclear Regulatory Commission (the NRC or staff) and representatives from FirstEnergy Nuclear Operating Company (FENOC) discussed the Request for Additional Information (RAI) for replacement activities of the Beaver Valley Power Station (BVPS) Unit 2 steam generators (SG) and associated refurbishment environmental impacts analysis. The NRC staff indicated that the response to the March 13, 2008, RAI ENV 3.0-1 (regarding Refurbishment Activities) had been received. The NRC staff added that the Draft Environmental Impact Statement (DSEIS) would summarize FENOCs response and position as well as the NRC staffs review of environmental impacts analysis related to the Unit 2 SG replacement. The NRC staff indicated that, although it was not specifically requested in the RAI and, as such, it was not addressed in the RAI response, the applicant needed to indicate if new or significant information had been identified during its review of Category 1 impacts associated with refurbishment. FENOC agreed to supplement the RAI response with the Category 1 information by May 30, 2008.

ENCLOSURE 2

Letter to FirstEnergy Nuclear Operating Company from K. Howard, dated June 3, 2008 DISTRIBUTION:

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MARCH 05, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING THE REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION HARD COPY:

DLR RF E-MAIL:

PUBLIC SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter KHoward ESayoc PBuckberg NMorgan MModes, RI PCataldo, RI DWerkheiser, RI

Beaver Valley Power Station, Units 1 and 2 cc:

Joseph J. Hagan President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 James H. Lash Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Nuclear Operating Company Mail Stop A-GO-15 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Ohio EPA-DERR ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 76 South Main Street Akron, OH 44308 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Drive Harrisburg, PA 17110-9364

Beaver Valley Power Station, Units 1 and 2 cc:

Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077