ML072780284
| ML072780284 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 08/06/2007 |
| From: | Nuclear Generation Group, Progress Energy Co |
| To: | Office of Nuclear Reactor Regulation |
| Oudinot D | |
| Shared Package | |
| ML072830337 | List:
|
| References | |
| Download: ML072780284 (7) | |
Text
NFPA 805 Implementation August Pilot Observation Meeting Harris Transition Status Jeff Ertman, Transition Project Manager August 6, 2007, Bethesda, MD
Page 2 NFPA 805 Status - Current Focus O Complete NEI 04-02 Appendix B-3 Z Prepared, under review Z NRC may have additional comments O Non-Power Operations Implementation O PRA quantification O Transition Program Change Process O Develop Draft LAR, FSAR outline O Selected FAQs to NRC by September Z NEI 04-02 revision to NRC mid January 2008
Page 3 NFPA 805 Harris Key Milestones O Internal Event PRA Limited Peer Review - September 2007 O Complete Rough in FSA - October 2007 Z Initial PRA Quantification complete Z Includes draft Transition Program Changes Z Initial strategies, mod scope identified O Fire PRA NRC Audit - February 2008 O LAR enter internal review - April 2008 Z Final FSA, program changes, strategies complete Z Baseline Fire PRA established O LAR - May 31, 2008 O NFPA 805 Program Implementation - mid 2009 O Full NFPA 805 compliance - December 31, 2010
Page 4 NFPA 805 Transition Change Process O See Transition process schedule provided separately -HNP Status Att1 change process
& FPRA scenarios.vsd O See Transition Process flow chart provided separately - HNP Status Att2 Change process flow.vsd
Page 5 NFPA 805 Transition Change Process O Inputs to change evaluation team to rough in phase Z B3 results Z Deterministic/CLB non-compliances by fire area Z Fire PRA scenario development by ignition source Z Preliminary Quantification ranking O Output Z PRA model updates / SSA model updates Z Transition change evaluation scenarios Z Potential plant modifications
Page 6 NFPA 805 Transition Change Process O First few fire areas/compartments exercise most of the tool box tools Z Expect to learn how to succinctly get to the resolutions - this will save time O Sent a sample to NRC Z FSA/Change Evaluation for fire area 1-BAL-C Z Supporting information:
XB-3 table XFire model input XProject procedures
Page 7 NFPA 805 Defining Licensing Basis O See Red Box Blue Box Summary HNP Status Att3 Red Box Blue Box Summary.vsd O See FSA Organization HNP Status Att4 FSA layout.vsd