NFPA 805 Implementation August Pilot Observation Meeting Harris Transition Status Jeff Ertman, Transition Project Manager August 6, 2007, Bethesda, MD

NFPA 805 Discussion Outline O Harris Transition Status O Overview Meeting Topics Z Transition Change Process Z Fire Safety Analysis (FSA)

Z Define NFPA 805 compliance Z Fire PRA input to Change Process Z Fire Scenario Target Selection Z FAQ Resolution Z Resolution of Previous comments Page 2

NFPA 805 Status - Current Focus O Complete NEI 04-02 Appendix B-3 Z Prepared, under review Z NRC may have additional comments O Non-Power Operations Implementation O PRA quantification O Transition Program Change Process O Develop Draft LAR, FSAR outline O Selected FAQs to NRC by September Z NEI 04-02 revision to NRC mid January 2008 Page 3

NFPA 805 Harris Key Milestones O Internal Event PRA Limited Peer Review - September 2007 O Complete Rough in FSA - October 2007 Z Initial PRA Quantification complete Z Includes draft Transition Program Changes Z Initial strategies, mod scope identified O Fire PRA NRC Audit - February 2008 O LAR enter internal review - April 2008 Z Final FSA, program changes, strategies complete Z Baseline Fire PRA established O LAR - May 31, 2008 O NFPA 805 Program Implementation - mid 2009 O Full NFPA 805 compliance - December 31, 2010 Page 4

NFPA 805 Transition Change Process O See Transition process schedule provided separately -HNP Status Att1 change process

& FPRA scenarios.vsd O See Transition Process flow chart provided separately - HNP Status Att2 Change process flow.vsd Page 5

NFPA 805 Transition Change Process O Inputs to change evaluation team to rough in phase Z B3 results Z CLB deficiencies by fire area Z Fire PRA scenario development by ignition source Z Preliminary Quantification ranking O Output Z PRA model updates / SSA model updates Z Transition change evaluation scenarios Z Potential plant modifications Page 6

NFPA 805 Transition Change Process O First few fire areas/compartments exercise most of the tool box tools Z Expect to learn how to succinctly get to the resolutions - this will save time O Sent a sample to NRC Z FSA/Change Evaluation for fire area 1-BAL-C Z Supporting information:

X B-3 table X Fire model input X Project procedures Page 7

NFPA 805 Defining Licensing Basis O See Red Box Blue Box Summary HNP Status Att3 Red Box Blue Box Summary.vsd O See FSA Organization HNP Status Att4 FSA layout.vsd Page 8