March 2, 2007
SUBJECT:
ANNUAL ASSESSMENT LETTER - JAMES A. FITZPATRICK NUCLEAR POWER PLANT (REPORT 05000033/2007001)
Dear Mr. Dietrich,
On February 15, 2007, the NRC staff completed its performance review of the James A.
FitzPatrick Nuclear Power Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2006. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as "Exempt from Public Disclosure in accordance with 10 CFR 2.390," will include the physical protection review and resultant inspection plan.
Overall, FitzPatrick operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct Reactor Oversight Process (ROP) baseline inspections at your facility. We also plan to conduct a license renewal aging management inspection in April 2007.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through June 30, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5171 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Eugene W. Cobey, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket No. 50-333 License No. DPR-59 Enclosure: FitzPatrick Inspection / Activity Plan cc w/encl:
G. J. Taylor, Chief Executive Officer, Entergy Operations M. R. Kansler, President, Entergy Nuclear Operations, Inc.
J. T. Herron, Senior Vice President for Operations M. Balduzzi, Senior Vice President, Northeastern Regional Operations W. Campbell, Senior Vice President of Engineering and Technical Services C. Schwarz, Vice President, Operations Support K. Mulligan, General Manager, Plant Operations O. Limpias, Vice President, Engineering (ENO)
J. McCann, Director, Licensing (ENO)
C. Faison, Manager, Licensing (ENO)
M. Colomb, Director of Oversight (ENO)
D. Wallace, Director, Nuclear Safety Assurance J. Costedio, Manager, Regulatory Compliance T. McCullough, Assistant General Counsel (ENO)
P. Smith, President, New York State Energy Research and Development Authority P. Eddy, New York State Department of Public Service S. Lyman, Oswego County Administrator Supervisor, Town of Scriba C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law J. Sniezek, PWR SRC Consultant M. Lyster, PWR SRC Consultant S. Lousteau, Treasury Department, Entergy Services
FitzPatrick Inspection / Activity Plan 01/01/2007 - 06/30/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2007 08:43:35 Report 22
71121
- OCC RAD SAFETY Baseline Inspections 02/05/2007 02/09/2007
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 02/05/2007 02/09/2007
7112102 IP ALARA Planning and Controls
7111401
- EP EXERCISE & PI VERIFICATION Baseline Inspections 03/05/2007 03/09/2007
7111401 IP Exercise Evaluation Baseline Inspections 03/05/2007 03/09/2007
7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 03/05/2007 03/09/2007
71151-EP01 IP Drill/Exercise Performance Baseline Inspections 03/05/2007 03/09/2007
71151-EP02 IP ERO Drill Participation Baseline Inspections 03/05/2007 03/09/2007
71151-EP03 IP Alert & Notification System
71002
- LICENSE RENEWAL License Renewal Inspectio 04/09/2007 04/13/2007
71002 IP License Renewal Inspection License Renewal Inspectio 04/23/2007 04/27/2007
71002 IP License Renewal Inspection
7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections 04/09/2007 04/13/2007
7112202 IP Radioactive Material Processing and Transportation
711107B
- HEAT SINK INSP Baseline Inspections 05/14/2007 05/18/2007
7111107B IP Heat Sink Performance
7112201
- PUB RAD SAFETY - RETS Baseline Inspections 06/04/2007 06/08/2007
7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems
7111121
- CDBI Baseline Inspections 06/11/2007 06/15/2007
7111121 IP Component Design Bases Inspection Baseline Inspections 06/25/2007 06/29/2007
7111121 IP Component Design Bases Inspection Baseline Inspections 07/09/2007 07/13/2007
7111121 IP Component Design Bases Inspection Baseline Inspections 07/16/2007 07/20/2007
7111121 IP Component Design Bases Inspection
7112203
- PUB RAD SAFETY - REMP Baseline Inspections 06/18/2007 06/22/2007
7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program
71121
- OCC RADIATION SAFETY Baseline Inspections 11/05/2007 11/09/2007
7112103 IP Radiation Monitoring Instrumentation and Protective Equipment
3/31 EXM
- FITZPATRICK INITIAL EXAM Not Applicable 03/03/2008 03/07/2008
U01684 FY08 - FITZPATRICK INITIAL OPERATOR LICENSING EXAM Not Applicable 03/31/2008 04/11/2008
U01684 FY08 - FITZPATRICK INITIAL OPERATOR LICENSING EXAM
71121
- OCC RAD SAFETY Baseline Inspections 03/17/2008 03/21/2008
7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 03/17/2008 03/21/2008
7112102 IP ALARA Planning and Controls
TRI FIRE
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 04/21/2008 04/25/2008
7111105T IP Fire Protection [Triennial]
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
FitzPatrick Inspection / Activity Plan 01/01/2007 - 06/30/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2007 08:43:35 Report 22
TRI FIRE
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 05/12/2008 05/16/2008
7111105T IP Fire Protection [Triennial]
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.