Operator Licensing Examination Approval (Peach Bottom Atomic Power Station)
ML070310224
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 01/30/2007
From: Marvin Sykes
Operations Branch I
To: Braun R
Exelon Generation Co
Shared Package
ML060800089 List:
References
Download: ML070310224 (3)


Text

January 30, 2007 Mr. R. C. Braun Site Vice President Peach Bottom Atomic Power Station Exelon Generation Company, LLC 1848 Lay Road Delta, PA 17314

SUBJECT:

OPERATOR LICENSING EXAMINATION APPROVAL (PEACH BOTTOM ATOMIC POWER STATION)

Dear Mr. Braun:

The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Peach Bottom Atomic Power Station.

The NRC has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. A. Wasong, Director of Training. Note that any examination waivers have been addressed in separate correspondence.

The NRC has approved the subject examinations and hereby authorizes you to administer the written examinations in accordance with Revision 9 of NUREG-1021, Operator Licensing Examinations Standards for Power Reactors, on February 16, 2007. The NRC staff will administer the operating tests during the weeks of February 5 and 12, 2007.

Please contact your Chief Examiner, Mr. T. Fish, at 610-337-5369, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant.

Sincerely,

/RA/

Marvin D. Sykes, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-277; 50-278 License Nos.: DPR-44, DPR-56

R. C. Braun cc w/encl:

President and CNO, Exelon Nuclear Plant Manager, Peach Bottom Atomic Power Station Regulatory Assurance Manager - Peach Bottom Associate General Counsel, Exelon Generation Company Manager, Financial Control & Co-Owner Affairs Manager Licensing, PBAPS Director, Training T. Vanwyen, Manager, Operations Training Correspondence Control Desk Director, Bureau of Radiation Protection (PA)

R. McLean, Power Plant and Environmental Review Division (MD)

G. Aburn, Maryland Department of Environment T. Snyder, Director, Air and Radiation Management Administration, Maryland Department of the Environment (SLO, MD)

Public Service Commission of Maryland, Engineering Division Board of Supervisors, Peach Bottom Township B. Ruth, Council Administrator of Harford County Council Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance TMI - Alert (TMIA)

J. Johnsrud, National Energy Committee, Sierra Club Mr. & Mrs. Kip Adams Vice President, Licensing and Regulatory Affairs Vice President, Operations Mid-Atlantic Senior Vice President, Nuclear Services Director, Licensing and Regulatory Affairs J. Fewell, Assistant General Counsel E. Epstein, TMI Alert

R. C. Braun Distribution:

A. R. Blough, DRS DRS Master Exam File (C. Bixler) (w/concurrences)

T. Fish, DRS, Chief Examiner M. Sykes, DRS E-Mail Distribution:

S. Collins, RA M. Dapas, DRA M. Gray, DRP C. Khan, DRP F. Bower, DRP - NRC Senior Resident Inspector M. Brown - NRC Resident Inspector S. Schmitt, DRP - NRC Resident OA J. Lamb, RI OEDO J. Shea, PM, NRR J. Kim, PM, NRR (Back up)

H. Chernoff, NRR Region I Docket Room (with concurrences)

ROPreports@nrc.gov (All Irs)

SUNSI Review Complete: MDS (Reviewers Initials)

ADAMS PKG: ML060800089 DOCUMENT NAME:

C:\FileNet\ML070310224.wpd After declaring this document An Official Agency Record it will be released to the Public.