ML061990473
ML061990473 | |
Person / Time | |
---|---|
Site: | Waltz Mill |
Issue date: | 07/12/2006 |
From: | Rich Smith CBS Corp |
To: | Document Control Desk, NRC/FSME |
References | |
Download: ML061990473 (12) | |
Text
- CBS CBS Corporation Richard K. Smith Vice President - Environmental Remediation II Stanwix Street, Room 370 Pittsburgh, PA 15222 Phone: 412-642-3285 Fax: 412-642-3957 E-mail: Richard.Smith@cbs.com July 12, 2006 Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
Subject:
Application to Amend TR-2 Final Decommissioning Plan, Rev. No. 1, NRC Docket No. 50-22
References:
- 1. Charles W. Emeigh, USNRC, letter to A. Joseph Nardi, dated March 10, 1999
- 2. Mark. J. Wetterhahn letter (on behalf of Westinghouse Electric Company LLC) to Patrick J. Isaac, USNRC, dated February 18, 2004
- 3. Martin G. Malsch letter (on behalf of Viacom, Inc.) to John Cordes, Solicitor, USNRC, dated December 3, 2004
- 4. John Cordes, Solicitor, USNRC, letter to Richard G. Murphy, Jr., Mark J.
Wetterhahn, Martin G. Malsch, and Michael F. McBride, dated March 17, 2006 This is an application by CBS Corp.("CBS") (formerly Viacom, Inc.) to amend the TR-2 Final Decommissioning Plan, Rev. No. 1 ("Plan"), as required by 10 C.F.R. §50.59(c)(2).' CBS is the holder of NRC License No. TR-2 for the former Westinghouse Test Reactor ("WTR")
located at the Waltz Mill Site in western Pennsylvania. The WTR is shut down and de-fueled, and the TR-2 license authorizes possession and decommissioning but not facility operation. This application is made as a logical consequence of references 3 and 4. As explained below, the purpose of the application is to revise the building remediation criteria in the Plan so that they conform to current NRC practice and policy which encourage a risk informed approach to nuclear decommissioning and remediation. The application would also result in remediation criteria that are consistent with similar criteria that currently apply in other buildings being used on the Site for NRC-licensed activities. This is important because the purpose of the Plan is to facilitate possible licensed use of the buildings, consistent with other licensed activities on the Site. Yet, as things now stand, the WTR buildings surfaces must be remediated to arbitrary pre-fixed contamination limits, based on instrument detection capabilities in the mid-I 970s, The TR-2 Final Decommissioning Plan, Rev. 0, was approved as an amendment to the Final Safety Analysis Report ("FSAR") by Amendment No. 8 to the TR-2 license on September 30, 1998. Rev. No. I was made pursuant to 10 C.F.R. § 50.59 on September 1, 1999. The change in remediation criteria applied for herein would constitute a departure from a method of evaluation described in the FSAR and used in the safety analysis. For this reason, CBS is applying for an amendment rather than making the change itself pursuant to 10 C.F.R. § 50.59.
Document Control Desk U.S. Nuclear Regulatory Commission July 12, 2006 regardless of dose or ALARA considerations, while other operational (restricted) areas on the Site are subject only to an ALARA-based standard with no pre-fixed acceptable levels for fixed contamination.
The Plan required certain WTR structures and components to be removed prior to the termination of the TR-2 license. NRC's March 17, 2006 letter (Reference 4) establishes that these removal activities have been completed. However, the TR-2 license is still in effect and CBS, as the licensee, remains subject to a related obligation to partially remediate remaining WTR structures in accordance with criteria set forth in paragraph (a) of the June 19, 1998 letter quoted in the NRC's March 17, 2006 letter. This obligation arises from the Plan, and therefore the TR-2 license, although it was contemplated that the remediation could (but need not) be completed some time after termination of the TR-2 license and the transfer of WTR residual radioactive material to the SNM-770 license currently held by Westinghouse Electric Company LLC ("Westinghouse"). See Plan at pp. 1-3, 2-1, 2-22 through 2-30.2 Indeed, the NRC's March 17, 2006 letter also makes it clear that this partial remediation obligation is part of CBS's obligations as the TR-2 licensee.
CBS also shares responsibility with Westinghouse for the partial remediation of various "retired facilities" covered by Westinghouse's SNM-770 license. This remediation is also governed by paragraph (a) of the June 19, 1998 letter, which is incorporated into the SNM-770 license along with the SNM-770 Remediation Plan. CBS's responsibility for the partial remediation of these retired facilities is based on an Asset Purchase Agreement with Westinghouse's parent company. The NRC recognized CBS's role under this Asset Purchase Agreement when approved of the transfer of SNM-770 to Westinghouse in 1999. See Charles W. Emeigh, USNRC, letter to A. Joseph Nardi, dated March 10, 1999 (Reference 1).
CBS has spent over $90 million in remedial activities at the Waltz Mill Site under the Plan and SNM-770 Remediation Plan, while Westinghouse has spent little or nothing. CBS and Westinghouse disagreed over how the Plan and the June 19, 1998 letter should be interpreted, and this resulted in a delay in completing the decommissioning and remediation. In its December 3, 2004 letter (Reference 3), CBS presented facts and arguments in support of its interpretation of the Plan and letter, and also indicated that it would apply to amend the June 19, 1998 criteria if the NRC disagreed with CBS's interpretation of them. December 3, 2004 letter at pg. 5, note 21. These interpretation questions are now resolved; the NRC has now agreed with CBS's interpretation of the Plan but disagreed with CBS's interpretation of the letter. NRC has now clarified that, as written, the numerical remediation criteria for building surface contamination in the June 19, 1998 letter (based on Table I of NRC Reg. Guide 1.86) are not subject to any exception based on the ALARA principle or limitations in either the Plan or the related SNM-770 Remediation Plan. Accordingly, as indicated, CBS is submitting this 2 Page 1-3 of the Plan states that "[a]dditionally, decontamination and dismantlement activities of other structures and equipment associated with TR-2 may be performed in accordance with this plan," and that "[t]he approved acceptance criteria associated with the retired facilities in the SNM-770 Remediation Plan will also be used for these other area." Thus the acceptance criteria in the SNM-770 Remediation Plan (currently the June 19, 1998 letter) are incorporated into the Plan.
2
Document Control Desk U.S. Nuclear Regulatory Commission July 12, 2006 application to amend the criteria in the June 19, 1998 letter, as applicable to remediation of the WTR.
Specifically, CBS proposes to modify the criteria for remediation of buildings in paragraph (a) of the Attachment to the June 19, 1998 letter, as applied to the WTR.3 This modification would be accomplished by deleting the sentence "The approved acceptance criteria associated with the retired facilities in the SNM-770 Remediation Plan will also be used for these other areas" on page 1-3 (section 1.2) of the Plan and replacing it with the following: "Structures (buildings) will be decontaminated so that the residual radioactivity has been reduced to levels that are as low as reasonably achievable ("ALARA"). In addition, estimated (modeled) doses within buildings will not exceed 25 mrem total effective dose equivalent ("TEDE")/yr, to the extent such a dose is reasonably achievable, and in no case will estimated (modeled) doses within buildings exceed 100 mrem TEDE/yr. Doses will be estimated (modeled) using realistic exposure scenarios that assume the buildings are used for licensed activities." The support for this proposal is as follows.
- 1. The "as is" condition of the former WTR presents no undue risk to health and safety.
See "Westinghouse Test Reactor Licensed Facilities Radiological Status Report,"
previously submitted in this docket. The NRC's inspection reports confirm this. In fact, the radiological status of the former WTR generally resembles that of operational areas in other buildings on the site where licensed activities are currently conducted on a safe and routine basis. Moreover, the requested amendment applies only to the partial remediation of the WTR structures, not ultimate WTR decommissioning, and the NRC recognizes that "Westinghouse has agreed to meet the LTR requirements at the Waltz Mill site for all of the residual materials connected with operations (including the materials transferred from the TR-2 license) when it seeks license termination after all activity has ceased at the site." See letter from John F. Cordes, dated March 17, 2006 (Reference 4). Thus the requested amendment will have no effect on the ultimate radiological condition of the Site.
- 2. The criteria in the June 19, 1998 letter have no rational basis and need to be changed.
These criteria are four times NRC Regulatory Guide 1.86 Table I levels for areas within buildings that may be used for future use under the license, and Reg. Guide 1.86 Table I levels for areas that will not be so used (the so-called 4x and x criteria). The Regulatory Guide 1.86 Table I values were set decades ago on the basis of 1974 measurement capabilities for radiological surface contamination, and they do not equate to uniform doses or risks. In fact, the NRC dismissed the use of these levels when it promulgated the dose-based license termination rule in 10 C.F.R. Part 20, Subpart E. For this reason, 3Westinghouse has informed the NRC that "no licensed use is practical for the facilities at issue and Option
[paragraph] (b) of the June 19, 1998 letter apply." Mark J. Wetterhahn letter to Patrick J. Isaac, USNRC, dated February 18, 2004 (Reference 2). Accordingly, NRC could conclude that there is no need to entertain any amendment to paragraph (a) because issues regarding it are moot. However, depending on how pending disagreements between CBS and Westinghouse are finally resolved, amendments to paragraph (a) may be critical in defining the extent of CBS's partial remediation responsibilities under the Plan and, unless this application is entertained, those responsibilities will be left undefined by the NRC.
3
Document Control Desk U.S. Nuclear Regulatory Commission July 12, 2006 use of Regulatory Guide 1.86 is no longer required in modem decommissioning projects, which focus on radiation dose and the safety of workers and the public, except perhaps as a convenient screening tool for determining whether the surface of an object is radioactive for purpose of contamination control.
- 3. The purpose of the remediation project was to remove residual radioactivity so as to facilitate possible future licensed uses of the facilities. This is why the 4x criteria in the June 19, 1998 letter are the key ones.4 The 4x criteria are unique to Waltz Mill. They were chosen in response to an NRC request, dated June 10, 1998, to revise the previous remediation criteria to show that "a reasonable effort has been made to reduce residual contamination to as low as reasonably achievable levels." The licensee believed that 4x levels could be achieved effectively in all locations and were ALARA, and that they were therefore responsive to the NRC's request. This belief proved to be incorrect in some areas as the remediation progressed to the point where additional remediation to meet the 4x criteria proved to be prohibitively expensive. This was primarily because of the unexpected depth of the contamination on building surfaces and the need to address complex building structural issues before proceeding with substantial additional remediation. The NRC recognizes that such a material change in circumstances can be the basis for a change in NRC requirements. Ohio Edison Company (Perry Nuclear Power Plant, Unit 1), CLI-92-11, 36 NRC 47, 59 at note 42.
- 4. The 4x criteria are also arbitrary. They apply only to parts of buildings that may be used for future licensed activities, and they stand in stark contrast to the remediation criteria (contamination control program for operational areas) that apply to other areas of the Waltz Mill site that are being used by Westinghouse for licensed activities. See SNM-770, Application for Renewal USNRC License Number SNM-770, Docket Number 070-00698, Revision 1, June 6, 2002, at 10.7.2 (3) ("The amount of fixed contamination on surfaces of the restricted area will be controlled by maintaining the dose rate ALARA"). There is no reason why areas on the Waltz Mill within CBS's responsibility (as the TR-2 licensee) should be remediated to meet the 4x criteria while similar areas on the site within Westinghouse's responsibility (as the SNM-770 licensee) should be subject to ALARA-driven flexible contamination controls.
- 5. The NRC's current risk-informed approach to decommissioning encourages consideration of dose assessments and realistic exposure scenarios. See SECY-05-0199, Attachment 2, "Risk Informed Regulation Implementation Plan," Chapter 1-36; FMRI (Muskogee, Oklahoma Facility), LBP-04-8, 59 NRC 266, 278-281 (2004); SECY 4 Paragraph (a) of the June 19, 1998 letter applies to buildings "which may be used for future use under the license."
Both the Plan and the SNM-770 Remediation Plan are premised on continued licensed use. This is clear not only from the Plans themselves (see for example page 2-1 of the Plan), but also from the record of extensive interchanges between the licensee and NRC. See, for example, A. Joseph Nardi's statement to the NRC on January 22, 1999 that "The same way with buildings. We were saying that we would remediate them to a continuation -to a licensed use so that we could continue to use them under the license .... we weren't going to take it unrestricted use, that internally we could make decisions that would lead us toward extensive contamination or more extensive effort. But that would be our decision."
4
Document Control Desk U.S. Nuclear Regulatory Commission July 12, 2006 061, "Removal of Texas Instruments, Inc. From Site Decommissioning Management Plan"; SECY-98-117, "Shelwell Services, Inc., Risk Assessment." In the case of Shelwell, for example, the NRC concluded that it was acceptable to leave seventy building surface areas contaminated in excess of previously approved limits because the estimated dose was below 25 mrem/per year.
- 6. The fundamental objective of the revised criteria to reduce residual contamination to levels that are ALARA is in keeping with the NRC's direction in its June 10, 1998 letter.
The WTR is within a radiation controlled (restricted personnel access) area on a site with owner controlled access. See TR-2 Final Decommissioning Plan at pp. 8-2 4.
Moreover, the 4x criteria apply only to "Inactive Restricted Areas." Therefore, neither the 25 mrem TEDE per year criterion in the NRC's license termination rule (10 C.F.R. Part 20, Subpart E) nor the 100 mrem TEDE per year public exposure limit in 10 C.F.R
§20.1301 (a) apply here because the purpose of the Plan is to facilitate licensed use, not unrestricted public use. Instead, the applicable exposure limits are those in 10 C.F.R. Part 20, Subpart C relating to occupational exposures. The primary limit here is 5,000 mrem TEDE per year Nevertheless, 10 C.F.R. §20.1301 (a) and 10 C.F.R. Part 20, Subpart E imply clearly that a limit of 100 mrem TEDE per year is more than adequate to achieve the fundamental safety objective of the Plan and that 25 mrem TEDE per year is a suitable remediation objective if it is reasonably achievable. The dose from the residual radioactive materials will be separate from any dose delivered to workers from other licensed materials, such as reactor components being serviced, but the proposed 100 mrem TEDE/per year limit for the residual materials is a fraction of the applicable occupational exposure limit, and the combined dose should continue to be well below the 5,000 mrem TEDE/per year limit for workers. The ALARA remediation objective, together with procedures and engineering controls developed and implemented under 10 C.F.R. §20.1101 (b), will assure that radiation exposures to persons engaged in licensed activities in the buildings will always be ALARA.
- 7. Since the purpose of the remediation is to facilitate future licensed use, realistic exposure scenarios for the buildings covered by the proposed remediation limit (I 00mrem TEDE/yr) and ALARA goal (25 mrem TEDE/yr) may be limited to those associated with the conduct of reasonable licensed activities within the buildings. CBS proposes to assess compliance with the limit and goal by (a) using the RESRAD-Build model configured for the affected buildings in their current radiological condition, after appropriate radionuclide abstraction and decay, (b) assuming that the buildings are used for licensed activities similar to the licensed activities being conducted in other buildings on the Waltz Mill Site, and (c) assuming that the buildings will remain restricted areas.
CBS may also use the software code Microshield and actual exposure rate measurements to supplement or confirm the results of RESRAD-Build. No credit will be taken for additional access controls unless, putting radiological conditions aside, the physical nature of area in question renders it unsuitable for licensed activities (for example a small basement room with difficult access) or makes continuous worker presence unlikely (for example the constricted interior of a small tunnel or deep canal). No additional access controls will be assumed for areas (for example the WTR containment) where licensed 5
Document Control Desk U.S. Nuclear Regulatory Commission July 12, 2006 activities and continuous worker presence may reasonably be presumed. Additional remediation will be done if, using this approach, the 100 mrem/per year TEDE limit is not met.
- 8. Previous evaluations suggest that doses from residual contamination have already been reduced to levels that are ALARA. Nevertheless, these evaluations will be reviewed for consistency with the occupational use scenarios assumed for the 100 mrem TEDE/per year limit and 25 mrem TEDE/per year ALARA goal. If doses from residual contamination levels are not ALARA, then additional measures will always be taken so that they are ALARA.
As indicated above, the June 19, 1998 letter also includes (in paragraph (b) of the Attachment) criteria for surface contamination (fixed plus removable) that apply to areas within buildings and separate buildings "that are being converted over from inactive (retired) areas to unrestricted areas within the controlled area of the Waltz Mill Site." These criteria correspond to the levels in Table I of Regulatory Guide 1.86. CBS does not believe that its responsibility extends to cleaning up buildings or building areas to facilitate unrestricted (possibly public) use, because the purpose of both the Plan and the SNM-770 Remediation Plan was to facilitate possible licensed use, not unrestricted use. Therefore, CBS does not believe it has standing to request a change to the criteria in Paragraph (b) of the June 19, 1998 letter.
However, CBS recognizes that it would be inconsistent to apply a modem risk informed approach to amending paragraph (a) of the June 19, 1998 letter while declining to do so for paragraph (b). Accordingly, if NRC believes CBS has standing to request an amendment to paragraph (b) of the June 19, 1998 letter, CBS would be prepared to do so promptly, as applied to the WTR, using a risk informed approach. Alternatively, if NRC grants CBS's request to amend paragraph (a), NRC could express a willingness to consider a Westinghouse request to amend paragraph (b).
In further support of this application, attached as Exhibit A are findings (with supporting reasons) that the proposed amendment will not involve any significant hazards consideration.
Sincerely, Richard K. Smith Vice President, Environmental Remediation Attachment 6
Copies transmitted: 3 notarized and 5 conformed COMMONWEALTH OF PENNSYLVANIA )
) SS:
COUNTY OF ALLEGHENY )
Before me, the undersigned notary public, this day personally appeared Richard K. Smith, Vice President, Environmental Remediation, CBS Corporation, 11 Stanwix Street, Pittsburgh, PA 15222-1384, to me known, who being duly sworn according to law, deposes and says that the statements sworn to in this letter and attachment are correct and accurate to the best of his knowledge.
Signature of Affiant Subscribed and sworn to before me this 12 th day of July, 2006 Notary Public COMMONWEALTH OF PENNSYLVANIA Notarial Seal Marie A.Podvorc Notary Pubic City Of P*tsbugh, Allegheny County My CornmssIon Expirs Dec. 8,2007 Member. Pennsylvania Association Of Notaries
Cc: Regional Administrator U.S. Nuclear Regulatory Commission, Region I 475 Allendale Road King of Prussia, PA 19406-1415 Mr. Patrick Isaac, Project Manager Research and Test Reactors Section Office of Nuclear Reactor Regulation Mail Stop O-12G13 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Mr. Mark Roberts Project Manager, Decommissioning Branch U.S. Nuclear Regulatory Commission, Region I 475 Allendale Road King of Prussia, PA 19406-1415 Mr. Robert Maiers, Chief Decommissioning Section Commonwealth of Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O Box 8469 Harrisburg, PA 17105-8469 Mr. James G.Yusko, Regional Manager Radiation Protection Commonwealth of Pennsylvania Department of Environmental Protection 400 Waterfront Drive Pittsburgh, PA 15222-4745 Mr. Wayne Vogel, Radiation Safety Officer Westinghouse Electric Company LLC P.O. Box 158 Madison, PA 15663-0158 Mr. Richard G. Murphy, Jr., Esq.
Sutherland, Asbill & Brennan, L.L.P.
1275 Pennsylvania Avenue, N.w.
Washington, DC 20004-2415 Mr. A. Joseph Nardi Supervisory Engineer - Environment, Health and Safety Westinghouse Electric Company LLC P.O. Box 355 Pittsburgh, PA 15230-0355
EXHIBIT A NO SIGNIFICANT HAZARDS CONSIDERATION EVALUATION PURSUANT TO 10 C.F.R §50.92 FOR THE AMENDMENT TO THE TR-2 FINAL DECOMMISSIONING PLAN, REV. 1, NRC DOCKET NO. 50-22 The proposed amendment is limited to a change in the remediation criteria (currently four times the levels in Table I of NRC Regulatory Guide 1.86) for the former Westinghouse Test Reactor ("WTR") on the Waltz Mill Site in western Pennsylvania, so that (1) criteria for remediation of building surfaces will be consistent across the Site and (2) the need for any additional remediation of the WTR structures can be determined in a risk informed manner.
Under the proposed amendment, WTR structures (buildings) will be decontaminated so that the residual radioactivity has been reduced to levels that are as low as reasonably achievable ("ALARA"). In addition, estimated (modeled) doses within buildings will not exceed 25 mrem total effective dose equivalent ("TEDE") per year, to the extent such a dose is reasonably achievable, and in no case will estimated (modeled) doses within buildings exceed 100 mrem TEDE/per year. Doses will be estimated (modeled) using realistic exposure scenarios that assume the buildings are used for licensed activities.
The fundamental objective to reduce residual contamination to levels that are ALARA is in keeping with the NRC's direction in its June 10, 1998 letter to the licensee. The WTR is within a radiation controlled (restricted personnel access) area on a site with owner controlled access. See TR-2 Final Decommissioning Plan at pp. 8-2-8-4.
Moreover, the 4x criteria apply only to "Inactive Restricted Areas." Therefore, neither the 25 mrem TEDE per year criterion in the NRC's license termination rule (10 C.F.R. Part 20, Subpart E) nor the 100 mrem TEDE per year public exposure limit in 10 C.F.R
§20.1301 (a) apply here because the purpose of the Plan is to facilitate licensed use, not unrestricted public use. Instead, the applicable exposure limits are those in 10 C.F.R. Part 20, Subpart C relating to occupational exposures. The primary limit here is 5,000 mrem TEDE per year. Nevertheless, 10 C.F.R. §20.1301 (a) and 10 C.F.R. Part 20, Subpart E imply clearly that a limit of 100 mrem TEDE per year is more than adequate to achieve the fundamental safety objective of the Plan and that 25 mrem TEDE per year is a suitable remediation objective if it is reasonably achievable. The dose from the residual radioactive materials will be separate from any dose delivered to workers from other licensed materials, such as reactor components being serviced, but the proposed 100 mrem TEDE/per year limit for the residual materials is a fraction of the applicable occupational exposure limit, and the combined dose should continue to be well below the 5,000 mrem TEDE/per year limit for workers. The ALARA remediation objective, together with procedures and engineering controls developed and implemented under 10 C.F.R. §20.1101 (b), will assure that radiation exposures to persons engaged in licensed activities in the buildings will always be ALARA.
Since the purpose of the remediation is to facilitate future licensed use, realistic exposure scenarios for the buildings covered by the proposed 100 mrem TEDE/per year dose limit and 25 mrem TEDE/per year ALARA goal may be limited to those associated with the conduct of reasonable licensed activities within the buildings. CBS proposes to assess compliance with the limit and goal by (a) using the RESRAD-Build model configured for the affected buildings in their current radiological condition, after appropriate radionuclide abstraction and decay, (b) assuming that the buildings are used for licensed activities similar to the licensed activities being conducted in other buildings on the Waltz Mill Site, and (c) assuming that the buildings will remain restricted areas.
CBS may also use the software code Microshield and actual exposure rate measurements to supplement or confirm the results of RESRAD-Build. No credit will be taken for additional access controls unless, putting radiological conditions aside, the physical nature of area in question renders it unsuitable for licensed activities (for example a small basement room with difficult access) or makes continuous worker presence unlikely (for example the constricted interior of a small tunnel or deep canal). No additional access controls will be assumed for areas (for example the WTR containment) where licensed activities and continuous worker presence may reasonably be presumed. Additional remediation will be done if, using this approach, the 100 mrem TEDE/per year limit is not met. Additional remediation will always be conducted so that doses and residual levels of contamination are ALARA.
The proposed amendment has been evaluated against the standards in 10 C.F.R.
§50.92 (c) and it has been determined that no significant hazards consideration are involved. CBS notes that the remediation criteria for the WTR were changed previously when the NRC approved of the revised criteria in the June 19, 1998, letter, based on an application by Westinghouse Electric Company LLC, without any significant hazards consideration evaluation.
Specifically, the amendment does not involve any irreversible consequences and it:
(1) Would not involve a significant increase in the probability or consequences of an accident previously evaluated.
The TR-2 license for the WTR is a possession only license. The reactor fuel has been removed, the pressure vessel and vessel internals have been removed, other reactor equipment has been removed, and at the appropriate time, coincident with TR-2 license termination, remaining residual radioactivity will be transferred to the SNM-770 license (held by Westinghouse Electric Company LLC) in accordance with the TR-2 Final Decommissioning plan, Rev. 1 ("Plan"), approved by the NRC as an amendment to the FSAR in Amendment No. 8 to the TR-2 license on September 30, 1998. The WTR is being maintained in a safe condition in accordance with the license and technical specifications. The current radiological status of the facility is described in the "Westinghouse Test Reactor Licensed Facility Radiological Status Report (Docket No.
50-22), October 2003. The technical specifications provide in section 3.2.4. that "the 2
extremely small source term at the [WTR] is adequately confined by the containment building." The amendment will not change this status.
The "Accident Analysis" in section 3.4. of the Plan analyzes four accident scenarios: dropping of contaminated concrete block/rubble; fire/explosion; canal sediment criticality; and rupture of a HEPA vacuum bag. The first scenario involved a worst case drop of a 50-ton contaminated concrete block from the biological shield, resulting in 1000 pounds of concrete dust becoming airborne, and a dose 100 meters downwind of 22 mrem. The second scenario involved the ignition of contaminated and combustible material (rags, wipes, contaminated clothing, etc.) in a sealand container, resulting conservatively in a release of 0.1 percent of the activity to the atmosphere, and a resulting dose 100 meters downwind of less than 1 mrem. The third scenario involved a possible criticality event in the course of removing canal sediment and water, an event presumed to be impossible based on expected criticality evaluations. The fourth scenario assumed that a HEPA vacuum collection bag ruptures when full, resulting in a dose 100 meters downwind of less than 1 mrem. These accident evaluations were reviewed independently and the results confirmed by the NRC in its September 30, 1998 Safety Evaluation Report in support of Amendment No. 8 to TR-2. Substantial remediation has taken place since the Plan was prepared, resulting in a much smaller source term, and canal sediment and water have been removed. Therefore the consequences of these postulated accidents will not be increased. Moreover, the requested amendment will not lead to any different or additional remediation of WTR that could increase the probability of the accidents evaluated.
Rev. 1 of the Plan (made pursuant to 10 C.F.R. §50.59) was supported by an evaluation of possible accidents associated with additional techniques for removing the reactor vessel or tank. This evaluation concluded that the original accident evaluation was still controlling and that no unreviewed safety question was presented by the change.
The vessel has since been removed.
In sum, given the foregoing, the amendment will not affect any accident initiators and will not affect any matter that could increase the consequences of any accident. The already low probability and small consequences of an accident previously evaluated will not be significantly increased by the requested amendment.
(2) Would not create the possibility of a new or different kind of accident from any accident previously evaluated.
The amendment only affects remediation criteria. No changes in the technical specifications are involved, there is no change in expected remediation methods, and access to the WTR will continue to be controlled. In accordance with NRC's March 17, 2006 letter, additional remediation to meet the amended criteria (if needed) will be performed only in accordance with work packages that will assure that no different kind of accident is credible. These work packages will be submitted to the NRC for review before the work commences.
3
In sum, remediation activities will continue to be conducted in accordance with the same procedures and license conditions as before. No new accident initiators will be introduced. For these reasons, and for the reasons given in (1) above, the amendment does not create the possibility of a new or different kind of accident from any accident previously evaluated.
(3) Would not involve a significant reduction in a margin of safety.
The criteria change will not involve a significant reduction in a margin of safety for the reasons given in (1) and (2) above.
4