Category:Inspection Report
MONTHYEARIR 05000022/20070012007-07-26026 July 2007 IR 05000022-07-001, on 03/14/2007 & 03/15/2007-07/10/2007, Former Westinghouse Test Reactor TR-2 Facility - NRC Inspection Report IR 05000022/20032012003-11-21021 November 2003 IR 05000022-03-201, on 10/6 - 10/7/2003, for Viacom, Inc. on Site Review of Various Aspects of Licensee'S Programs Concerning Operations, Emergency Preparedness, Physical Security, Radiation Protection & Transportation Activities IR 05000022/19992022002-09-0606 September 2002 IR 05000022-99-202, October 27-28, 1999, January 17-20, April 19-21, and May 14-16, 2000, Westinghouse Test Reactor at Waltz Mills. No Violations Noted IR 05000022/19992011999-03-0505 March 1999 Insp Rept 50-022/99-201 on 990201-03.No Violations Noted. Major Areas Inspected:Various Aspects of Reactor Operations, Maint,Safety & Emergency Preparedness Program IR 05000022/19970011997-03-0606 March 1997 Forwards Insp Rept 50-022/97-01 on 970203-05.No Noncompliance Noted IR 05000022/19930011993-09-29029 September 1993 Insp Rept 50-022/93-01 on 930913.No Safety Concerns or Violations Noted.Major Areas Inspected:Review Current Status of Reactor Equipment & to Discuss Plans for Decommissioning 2007-07-26
[Table view] Category:Letter
MONTHYEARML1000700732009-11-19019 November 2009 USNRC 10CFR Part 21 Notification - Flowserve Figure 848 Disk/Disk Nut Separation ML0834704002008-12-12012 December 2008 Westinghouse Electric Company, LLC, Return of Financial Documents (LLC Waltz Mills Site and CBS Former Reactor Site, Madison, PA) Return Receipt ML0832901022008-11-21021 November 2008 Westinghouse Electric Corporation, LLC, on 11/21/08, Waltz Mills Site and the CBS Former TR-2 Test Reactor Facility in Madison, PA, Return of Financial Assurance Documents, Public Letter ML0813303982008-09-19019 September 2008 R. Smith Ltr. Termination of the TR-2 License and the Granting of an Exemption from 10 CFR 50.82(b)(6)(ii), Docket No. 50-022 (TAC No. J60621) ML0826904212008-09-17017 September 2008 Response to Request for Additional Information Letter No. 007 Related to Identification of Potential Hazards in Site Vicinity ML0808702752008-03-19019 March 2008 Westinghouse Letter Requesting License Termination Letter for TR-2 Recognize That CBS Letters of Credit Have Been Returned to CBS ML0806408292008-02-27027 February 2008 Withdrawal of the Request for a Name Change Amendment to License No. TR-002 ML0727000942007-09-18018 September 2007 Westinghouse Electric Co. Ltr Dated 09/18/07, Request for Meeting to Discuss Transfer of TR Facility to SNM-770 License IR 05000022/20070012007-07-26026 July 2007 IR 05000022-07-001, on 03/14/2007 & 03/15/2007-07/10/2007, Former Westinghouse Test Reactor TR-2 Facility - NRC Inspection Report ML0715603502007-07-16016 July 2007 Rickard Smith Ltr Request to Modify Technical Specification 5.0 of the TR-2 License, Docket No. 50-022 ML0702200022007-01-26026 January 2007 National Organization of Test, Research and Training Reactors(Trtr) Input on Fingerprinting Requirements for Unescorted Access to Research and Test Reactors ML0629800772006-10-23023 October 2006 E-mail to Research and Test Reactor from M. Mendonca Draft Directors Decision on Uncontrolled/Unmonitored Releases ML0621304062006-08-0909 August 2006 G20060639 - Ltr Remediation of the Waltz Mill Site ML0619904732006-07-12012 July 2006 Application to Amend TR-2 Final Decommissioning Plan, Rev. No. 1 ML0615902642006-06-0101 June 2006 Waltz Mill Facility - 2005 Annual Report ML0607507302006-03-17017 March 2006 Westinghouse Electric Company, LLC and Viacom Inc., Case 16V 192 0093702, American Arbitration Association, NRC File No. TR-04-123 ML0601804602006-01-10010 January 2006 Request for a Name Change Amendment to License No. TR-2 ML0513704422005-05-10010 May 2005 Westinghouse Test Reactor, 2004 Annual Report ML0412602062004-04-29029 April 2004 Viacom Inc., Westinghouse Test Reactor TR-2; 2003 Annual Report ML0404402242004-02-0606 February 2004 Response of Viacom Inc. to Letters from Westinghouse Electric Company LLC, Dated January 26, 2004 IR 05000022/20032012003-11-21021 November 2003 IR 05000022-03-201, on 10/6 - 10/7/2003, for Viacom, Inc. on Site Review of Various Aspects of Licensee'S Programs Concerning Operations, Emergency Preparedness, Physical Security, Radiation Protection & Transportation Activities ML0404402202003-09-26026 September 2003 Viacom Inc. Response to Request for Additional Information to Viacom Regarding Application to Terminate 10 CFR Part 50 Portion of Westinghouse Test Reactor TR-2 License ML0322507292003-08-26026 August 2003 Request for Additional Information to Viacom Regarding Application to Terminate 10 CFR Part 50 Portion of Westinghouse Test Reactor TR-2 License ML0322502122003-08-26026 August 2003 G20020629 - M. Malsch Ltr. Final Director'S Decision on 10 CFR 2.206 Petition Submitted on Waltz Mill Service Center, Madison, PA ML0317608482003-07-0101 July 2003 Change of Facility Manager, Various Addressees. Informs That Patrick J. Isaac Will Be New Project Manager ML0312900112003-05-0101 May 2003 2002 Annual Report for Westinghouse Test Reactor ML0236100612002-12-20020 December 2002 G20020629 - Transmittal of Response of Westinghouse Electric Co., LLC to Request of Viacom, Inc. for Orders & Petition Pursuant to 10 CFR 2.206 ML0231201102002-10-29029 October 2002 Viacom, Inc, Westinghouse Test Reactor TR-2 Application for NRC Orders; Terminating 10 CFR Part 50 Portion of TR-2 and Declaring That Decommissioning of TR-2 Structure Has Been Satisfactorily Completed IR 05000022/19992022002-09-0606 September 2002 IR 05000022-99-202, October 27-28, 1999, January 17-20, April 19-21, and May 14-16, 2000, Westinghouse Test Reactor at Waltz Mills. No Violations Noted ML0217805942002-05-0808 May 2002 Mail Control Form Attaching Letter from J. Simpson, Westinghouse, to R. Lowenstein, AEC, Application for Amendment to TR-2 to Permit Possession Only & Stating That All Previous Applications for Amendment Are Withdrawn ML0209306042002-03-25025 March 2002 Viacom Inc. Westinghouse Test Reactor TR-2; 2001 Annual Report 2009-11-19
[Table view] |
Text
ber 21, 2003
SUBJECT:
NRC INSPECTION REPORT NO. 50-22/2003-201
Dear Mr. Smith:
This letter refers to the inspection conducted on October 6-7, 2003, at your Westinghouse Test Reactor at Waltz Mill. The inspection included a review of activities authorized for your facility.
The enclosed report presents the results of that inspection.
Areas examined during the inspection are identified in the report. Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations of activities in progress. Based on the results of this inspection, no safety concerns or noncompliances of NRC requirements were identified.
No response to this letter is required.
In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at (the Public Electronic Reading Room) http://www.nrc.gov/reading-rm/adams.html.
Should you have any questions concerning this inspection, please contact Stephen Holmes at 301-415-8583.
Sincerely,
/RA by Marvin Mendonca Acting for/
Patrick M. Madden, Section Chief Research and Test Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-22 License No. TR-2 Enclosure: NRC Inspection Report No. 50-22/2003-201 cc w/encl.: Please see next page
Westinghouse/Waltz Mill Docket No. 50-22 cc:
Mr. James G. Yusko Pennsylvania Department of Environmental Protection 400 Waterfront Drive Pittsburgh, PA 15222 Joseph Nardi, License Administrator Westinghouse Electric Company Box 355 Pittsburgh, PA 15230-0355 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611
November 21, 2003 Mr. Richard