MONTHYEARML0516603262005-06-10010 June 2005 Response to First Revised Order EA-03-009 and Bulletin 2003-02 Project stage: Other ML0519501232005-07-0707 July 2005 License Amendment Request Regarding Extended Power Uprate Project stage: Request ML0523101552005-08-15015 August 2005 Supplemental Information Related to Small Break (SB) Loss of Coolant Accident (LOCA) Analysis and Post-LOCA Boric Acid Precipitation Analysis Project stage: Request ML0523104332005-08-24024 August 2005 Extended Power Uprate Acceptance Review Results Project stage: Acceptance Review ML0524500902005-09-0202 September 2005 Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC (Ginna, Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0529208222005-09-15015 September 2005 Presentation for 09/15/2005 Meeting with R. E. Ginna SBLOCA EPU Results Summary Project stage: Meeting ML0524504522005-09-15015 September 2005 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing - Extended Power Uprate - R.E. Ginna Nuclear Power Plant Project stage: Other ML0525502722005-09-30030 September 2005 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for R. E. Ginna Nuclear Power Plant Project stage: Withholding Request Acceptance ML0528002232005-09-30030 September 2005 R. E. Ginna, Large Transient Tests Associated with License Amendment Request Regarding Extended Power Uprate Project stage: Request ML0529205102005-10-24024 October 2005 Summary of Meeting with R.E. Ginna Extended Power Uprate Application Project stage: Meeting ML0528501372005-10-25025 October 2005 RAI, Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0529300412005-10-25025 October 2005 Request for Additional Information Related to the Proposed Extended Power Uprate for Ginna Nuclear Power Plant Project stage: RAI ML0530703792005-11-0303 November 2005 Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0530705682005-11-0303 November 2005 Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0531404202005-11-10010 November 2005 Supplemental Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0536201882005-11-17017 November 2005 Meeting with R. E. Ginna Nuclear Power Plant, LLC, Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0534803882005-12-0606 December 2005 Response to Requests for Additional Information Regarding Topics Described by Letter Dated October 25. 2005 Project stage: Response to RAI ML0536101852005-12-19019 December 2005 Response to Requests for Additional Information Re Increase of Maximum Steady-State Thermal Power Level Project stage: Response to RAI ML0536400802005-12-22022 December 2005 Response to Request for Additional Information Regarding Topics Described by Letter Dated November 10, 2005 Project stage: Response to RAI ML0535602452005-12-23023 December 2005 Summary of November 17, 2005, Meeting with R. E. Ginna Nuclear Power Plant, LLC, Regarding Extended Power Uprate Application Project stage: Meeting ML0601802622006-01-11011 January 2006 Supplemental Response to Requests for Additional Information Regarding Topics Described by Letters Dated August 24, 2005 and October 28, 2005 Project stage: Supplement ML0609604162006-01-25025 January 2006 R. E. Ginna - Response to Requests for Additional Information Regarding Topics Described in Meeting Minutes Project stage: Response to RAI ML0605403492006-02-16016 February 2006 Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls Project stage: Response to RAI ML0606806582006-03-0909 March 2006 Forthcoming Meeting with R. E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0607901132006-03-20020 March 2006 Cancellation - Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0609403122006-03-24024 March 2006 R. E. Ginna - Response to BOP Systems Questions Discussed on March 2, 2006 Conference Call Project stage: Request MN 06-019, NRC Slides for Annual Assessment Public Meeting with R. E. Ginna Nuclear Power Plant, LLC to Discuss CY2005 Performance2006-04-0404 April 2006 NRC Slides for Annual Assessment Public Meeting with R. E. Ginna Nuclear Power Plant, LLC to Discuss CY2005 Performance Project stage: Request ML0609000892006-04-0404 April 2006 Public Meeting Notice for Ginna Station Annual Assessment to Discuss CY2005 Performance Project stage: Request ML0609300252006-04-0404 April 2006 Notice of Meeting with R. E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprated Amendment Application Project stage: Meeting ML0608003152006-04-0606 April 2006 R. E. Ginna Nuclear Power Plant - Draft Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Draft Other ML0608003472006-04-0606 April 2006 R. E. Ginna Nuclear Power Plant Draft Environmental Assessment and Finding of No Significant Impact Related to the Proposed License Amendment to Increase to Maximum Reactor Power Level Project stage: Draft Other ML0613503752006-05-0909 May 2006 R. E. Ginna, Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls for Extended Power Uprate (EPU) Project stage: Response to RAI ML0613706272006-05-12012 May 2006 Comment (1) of Kimberly A. Merchant on Draft Environmental Assessment and Findings of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Draft Other ML0613601522006-05-12012 May 2006 Summary of May 9, 2006, Annual Assessment Meeting with Constellation Energy, R. E. Ginna Nuclear Power Plant, LLC Project stage: Request ML0614503812006-05-19019 May 2006 R. E. Ginna Final Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls for Extended Power Uprate (EPU) Project stage: Response to RAI ML0613204402006-06-26026 June 2006 R. E. Ginna Nuclear Power Plant - Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Other ML0616002502006-06-26026 June 2006 Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Other ML0619205922006-07-11011 July 2006 Amendment 97, Renewed Facility Operating License Page No. 3 Regarding 16.8 Percent Power Uprate Project stage: Other ML0619205942006-07-11011 July 2006 R. E. Ginna, Tech Spec Pages for Amendment 97 Regarding 16.8 Percent Power Uprate Project stage: Other ML0613801032006-07-11011 July 2006 R. E. Ginna, License Amendment, 16.8 Percent Power Uprate Project stage: Other ML0613802492006-07-11011 July 2006 Table of Contents, Safety Evaluation Related to Extended Power Uprate at R. E. Ginna Nuclear Power Plant Project stage: Approval ML0629101322006-10-12012 October 2006 License Amendment Request: Spent Fuel Pool Storage Capacity Project stage: Request 2005-09-02
[Table View] |
Similar Documents at Ginna |
|---|
|
Text
(b)
Pursuant to the Act and 10 CFR Part 70, to possess and use four (4) mdxed oxide fuel assemblies in accordance with the RG&E's application dated December 14, 1979 (transmitted by letter dated December 20, 1979), as supplemented February 20, 1980 and March 5, 1980; (3)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70 to receive, possess, and use at any time any byproduct, source, and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source, or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C.
This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; and is subject to all applicable provisions of the Act and rules, regulations and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below:
(1)
Maximum Power Level Ginna LLC is authorized to operate the facility at steady-state power levels up to a maximum of 1775 megawatts (thermal).
(2)
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 97, are hereby incorporated in the renewed license. The I licensee shall operate the facility in accordance with the Technical Specifications.
(3)
Fire Protection (a)
The licensee shall implement and maintain in effect all fire protection features described in the licensee's submittals referenced in and as approved or modified by the NRC's Fire Protection Safety Evaluation (SE) dated February 14, 1979 and Amendment No. 97