R. E. Ginna Nuclear Power Plant - Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate
ML061320440
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/26/2006
From: Milano P
Plant Licensing Branch III-2
To: Korsnick M
Ginna
Milano P, NRR/DLPM , 415-1457
References
TAC MC7382
Download: ML061320440 (4)


Text

June 26, 2006 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT - FINAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RELATED TO PROPOSED EXTENDED POWER UPRATE (TAC NO. MC7382)

Dear Mrs. Korsnick:

Enclosed is a copy of the Final Environmental Assessment and Finding of No Significant Impact related to your application dated July 7, 2005, as supplemented on August 15, September 30, and December 6, 9, and 22, 2005, and January 11 and 25, February 16, March 3 and 24, and May 9 and 18, 2006, for the R.E. Ginna Nuclear Power Plant. The proposed amendment would authorize increasing the maximum steady-state reactor core power level from 1520 megawatts thermal (MWt) to 1775 MWt, which is an increase of approximately 16.8 percent. The proposed increase in power level is considered an extended power uprate.

The assessment is being forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosure:

Final Environmental Assessment cc w/encl: See next page

June 26, 2006 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT - FINAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT RELATED TO PROPOSED EXTENDED POWER UPRATE (TAC NO. MC7382)

Dear Mrs. Korsnick:

Enclosed is a copy of the Final Environmental Assessment and Finding of No Significant Impact related to your application dated July 7, 2005, as supplemented on August 15, September 30, and December 6, 9, and 22, 2005, and January 11 and 25, February 16, March 3 and 24, and May 9 and 18, 2006, for the R.E. Ginna Nuclear Power Plant. The proposed amendment would authorize increasing the maximum steady-state reactor core power level from 1520 megawatts thermal (MWt) to 1775 MWt, which is an increase of approximately 16.8 percent. The proposed increase in power level is considered an extended power uprate.

The assessment is being forwarded to the Office of the Federal Register for publication.

Sincerely,

/RA/

Patrick D. Milano, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosure:

Final Environmental Assessment cc w/encl: See next page Accession Number: ML061320440 Final EA: ML061600250 Package:ML061600253 OFFICE LPLI-1\\PM LPLI-1\\LA REBA\\BC OGC LPLI-1\\BC NAME PMilano SLittle RFranovich AHodgdon RLaufer DATE 06/12/06 06/12/06 06/16/06 06/26/06 06/26/06 Official Record Copy

DISTRIBUTION:

PUBLIC LPLI-1 Reading File C. Haney RidsNrrDorl C. Holden RidsNrrDorl R. Laufer RidsNrrDorlLpIa-1 P. Milano RidsNrrPMPMilano A. Kuger RidsNrrDlrReba A. Williamson OGC RidsOgcRp ACRS RidsAcrsAcnwMailCenter C. Anderson, R-I RidsRgn1MailCenter T. Alexion cc: Plant Mailing List

R.E. Ginna Nuclear Power Plant cc:

Mr. Michael J. Wallace President R.E. Ginna Nuclear Power Plant, LLC c/o Constellation Energy 750 East Pratt Street Baltimore, MD 21202 Mr. John M. Heffley Senior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401 Kenneth Kolaczyk, Sr. Resident Inspector R.E. Ginna Nuclear Power Plant U.S. Nuclear Regulatory Commission 1503 Lake Road Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Carey W. Fleming, Esquire Senior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Ms. Thelma Wideman, Director Wayne County Emergency Management Office Wayne County Emergency Operations Center 7336 Route 31 Lyons, NY 14489 Ms. Mary Louise Meisenzahl Administrator, Monroe County Office of Emergency Preparedness 1190 Scottsville Road, Suite 200 Rochester, NY 14624 Mr. Paul Eddy New York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY 12223