Letter Sequence Other |
---|
TAC:MC7382, Steam Generator Tube Integrity (Approved, Closed) |
|
MONTHYEARML0519501232005-07-0707 July 2005 License Amendment Request Regarding Extended Power Uprate Project stage: Request ML0523101552005-08-15015 August 2005 Supplemental Information Related to Small Break (SB) Loss of Coolant Accident (LOCA) Analysis and Post-LOCA Boric Acid Precipitation Analysis Project stage: Request ML0524500902005-09-0202 September 2005 Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC (Ginna, Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0524504522005-09-15015 September 2005 Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing - Extended Power Uprate - R.E. Ginna Nuclear Power Plant Project stage: Other ML0529208222005-09-15015 September 2005 Presentation for 09/15/2005 Meeting with R. E. Ginna SBLOCA EPU Results Summary Project stage: Meeting ML0525502722005-09-30030 September 2005 Westinghouse Electric Company, Request for Withholding Information from Public Disclosure for R. E. Ginna Nuclear Power Plant Project stage: Withholding Request Acceptance ML0528002232005-09-30030 September 2005 R. E. Ginna, Large Transient Tests Associated with License Amendment Request Regarding Extended Power Uprate Project stage: Request ML0529205102005-10-24024 October 2005 Summary of Meeting with R.E. Ginna Extended Power Uprate Application Project stage: Meeting ML0530705682005-11-0303 November 2005 Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0530703792005-11-0303 November 2005 Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0531404202005-11-10010 November 2005 Supplemental Request for Additional Information Extended Power Uprate License Amendment Project stage: RAI ML0536201882005-11-17017 November 2005 Meeting with R. E. Ginna Nuclear Power Plant, LLC, Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0534803882005-12-0606 December 2005 Response to Requests for Additional Information Regarding Topics Described by Letter Dated October 25. 2005 Project stage: Response to RAI ML0536101852005-12-19019 December 2005 Response to Requests for Additional Information Re Increase of Maximum Steady-State Thermal Power Level Project stage: Response to RAI ML0536400802005-12-22022 December 2005 Response to Request for Additional Information Regarding Topics Described by Letter Dated November 10, 2005 Project stage: Response to RAI ML0535602452005-12-23023 December 2005 Summary of November 17, 2005, Meeting with R. E. Ginna Nuclear Power Plant, LLC, Regarding Extended Power Uprate Application Project stage: Meeting ML0601802622006-01-11011 January 2006 Supplemental Response to Requests for Additional Information Regarding Topics Described by Letters Dated August 24, 2005 and October 28, 2005 Project stage: Supplement ML0609604162006-01-25025 January 2006 R. E. Ginna - Response to Requests for Additional Information Regarding Topics Described in Meeting Minutes Project stage: Response to RAI ML0605403492006-02-16016 February 2006 Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls Project stage: Response to RAI ML0606806582006-03-0909 March 2006 Forthcoming Meeting with R. E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0607901132006-03-20020 March 2006 Cancellation - Forthcoming Meeting with R.E. Ginna Nuclear Power Plant, LLC Regarding Extended Power Uprate Amendment Application Project stage: Meeting ML0609403122006-03-24024 March 2006 R. E. Ginna - Response to BOP Systems Questions Discussed on March 2, 2006 Conference Call Project stage: Request ML0609300252006-04-0404 April 2006 Notice of Meeting with R. E. Ginna Nuclear Power Plant, LLC (Ginna Llc), Regarding Extended Power Uprated Amendment Application Project stage: Meeting ML0608003152006-04-0606 April 2006 R. E. Ginna Nuclear Power Plant - Draft Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Draft Other ML0608003472006-04-0606 April 2006 R. E. Ginna Nuclear Power Plant Draft Environmental Assessment and Finding of No Significant Impact Related to the Proposed License Amendment to Increase to Maximum Reactor Power Level Project stage: Draft Other ML0613503752006-05-0909 May 2006 R. E. Ginna, Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls for Extended Power Uprate (EPU) Project stage: Response to RAI ML0613706272006-05-12012 May 2006 Comment (1) of Kimberly A. Merchant on Draft Environmental Assessment and Findings of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Draft Other ML0614503812006-05-19019 May 2006 R. E. Ginna Final Response to Requests for Additional Information Regarding Topics Discussed on Conference Calls for Extended Power Uprate (EPU) Project stage: Response to RAI ML0613204402006-06-26026 June 2006 R. E. Ginna Nuclear Power Plant - Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Other ML0616002502006-06-26026 June 2006 Final Environmental Assessment and Finding of No Significant Impact Related to Proposed Extended Power Uprate Project stage: Acceptance Review ML0619205922006-07-11011 July 2006 Amendment 97, Renewed Facility Operating License Page No. 3 Regarding 16.8 Percent Power Uprate Project stage: Other ML0619205942006-07-11011 July 2006 R. E. Ginna, Tech Spec Pages for Amendment 97 Regarding 16.8 Percent Power Uprate Project stage: Other ML0613801032006-07-11011 July 2006 R. E. Ginna, License Amendment, 16.8 Percent Power Uprate Project stage: Other ML0613802492006-07-11011 July 2006 Table of Contents, Safety Evaluation Related to Extended Power Uprate at R. E. Ginna Nuclear Power Plant Project stage: Approval ML0629101322006-10-12012 October 2006 License Amendment Request: Spent Fuel Pool Storage Capacity Project stage: Request 2006-01-11
[Table View] |
Similar Documents at Ginna |
---|
Category:Letter
MONTHYEARIR 05000244/20243012024-10-22022 October 2024 Initial Operator Licensing Examination Report 05000244/2024301 ML24286A0022024-10-11011 October 2024 Core Operating Limits Report Cycle 45, Revision 0 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing RS-24-092, Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-09-25025 September 2024 Revised Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000244/20245012024-09-24024 September 2024 LLC - Emergency Preparedness Biennial Exercise Inspection Report 05000244/2024501 IR 05000244/20240052024-08-29029 August 2024 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant (Report 05000244/2024005) ML24234A0922024-08-21021 August 2024 Requalification Program Inspection IR 05000244/20240102024-08-19019 August 2024 Biennial Problem Identification and Resolution Inspection Report 05000244/2024010 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000244/20240022024-08-0505 August 2024 LLC - Integrated Inspection Report 05000244/2024002 and Independent Spent Fuel Storage Installation Report 07200067/2024001 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24170A3852024-07-16016 July 2024 R. E. Ginna Nuclear Power Plant - Alternative Associated with Inservice Testing of B Auxiliary Feedwater Pump - PR-03 ML24197A0302024-07-15015 July 2024 LLC - Operator Licensing Examination Approval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions IR 05000244/20244022024-06-20020 June 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000244/2024402 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24143A0752024-05-22022 May 2024 Re. Ginna Nuclear Power Plant and Independent Spent Fuel Storage Installation (ISFSI) Registration for Use of General License ISFSI Casks ML24136A1692024-05-14014 May 2024 And Independent Spent Fuel Storage Installation (ISFSI) - 2023 Annual Radioactive Effluent Release Report and 2023 Annual Radiological Environmental Operating Report ML24134A0042024-05-13013 May 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000244/2024010 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000244/20240012024-04-24024 April 2024 LLC - Integrated Inspection Report 05000244/2024001 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24101A0432024-04-10010 April 2024 2024 10 CFR 50.46 Annual Report IR 05000244/20240112024-04-10010 April 2024 LLC - Fire Protection Team Inspection Report 05000244/2024011 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24088A2042024-03-28028 March 2024 R. E. Ginna Nuclear Power Plant - Response to NRC Request for Additional Information Regarding Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump ML24110A0122024-03-28028 March 2024 2023 Report of Individual Monitoring for R.E. Ginna Nuclear Power Plant LLC, License DPR-18 05000244/LER-2023-003-01, Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam2024-03-0707 March 2024 Re. Ginna Nuclear Power Plant, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam IR 05000244/20230062024-02-28028 February 2024 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC, (Report 05000244/2023006) IR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of ‘B’ Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations 05000244/LER-2023-003, Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level2023-12-11011 December 2023 Manual Reactor Trip Due to Degraded Condenser Vacuum from Lowering Main Steam to Air Ejectors and Auxiliary Feedwater Actuation Due to Low Steam Generator Level ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums 05000244/LER-2023-002, Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure2023-11-0808 November 2023 Overtemperature Delta Temperature Reactor Protection System and Auxiliary Feedwater System Actuations on Due to 100% Load Rejection Caused by Turbine Overspeed Circuit Card Failure. IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) 2024-09-25
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 ML22094A1072022-06-22022 June 2022 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 151 Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML22119A0942022-06-21021 June 2022 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 150 Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B ML22145A5862022-06-0303 June 2022 R. E. Ginna Correction to Pages Issued for Amendments Nos. 225, 225, 227, 227, & 148, Respectively, Regarding Issues Identified in Westinghouse Documents ML22090A0862022-04-29029 April 2022 Amendments to Adopt TSTF-541,Rev.2,Add Exceptions to Surveillance Requirements for Valves,Dampers Locked in Actuated Position ML22021B6602022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000)-Enclosure 1 ML22031A2762022-02-0101 February 2022 Issuance of Indemnity Agreement Amendments-Enclosure 2 ML22021B6592022-02-0101 February 2022 Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000) (Letter) ML21347A0382022-01-13013 January 2022 Issuance of Amendments to Revise Reactor Coolant Leakage Requirements ML21175A0012021-07-27027 July 2021 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 145 Regarding Technical Specifications Change to Make a One-Time Exception to the Steam Generator Tube Inspection Requirements ML20353A1262021-03-11011 March 2021 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 144 Implementation of WCAP-14333 and WCAP-15376, TSTF-411-A, and TSTF-418-A to Revise Reactor Trip and Engineered Safety Feature Actuation System Instrumentation ML20167A0072020-09-11011 September 2020 R. E. Ginna - Issuance of Amendment Nos. 216, 216, 220, 220, and 143 - Adoption of TSTF-567, Rev. 1, Add Containment Sump Technical Specifications to Address GSI-191 Issues ML20141L6362020-07-10010 July 2020 Issuance of Amendments Based on TSTF-427,Allowance for Nontechnical Specification Barrier Degradation on Supported System Operability,Rev 2 ML20134H9402020-07-0808 July 2020 Issuance of Amendments Revising the High Radiation Area Administrative Controls ML20021A0702020-04-0606 April 2020 Issuance of Amendments to Delete License Conditions for Decommissioning Trusts ML20057E0912020-04-0303 April 2020 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 139 Add a One-Time Note for Use of Alternative Residual Heat Removal Method ML20034G5462020-03-12012 March 2020 Issuance of Amendments Revising Instrument Testing and Calibration Definitions ML19325D8242019-12-23023 December 2019 R. E. Ginna Nuclear Power Plant Issuance of Amendment No. 136 to Revise Technical Specification 5.5.15, Containment Leakage Rate Testing Program, to Extend Containment Integrated Leak Rate Test Frequency ML19252A2462019-10-29029 October 2019 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 134 to Revise the Emergency Response Organization Staffing Requirements ML19204A3492019-07-23023 July 2019 R. E. Ginna Nuclear Power Plant: License Amendment Request - Increase the Main Steam Safety Valve Lift Setpoint Tolerance RS-19-017, Application to Remove the Table of Contents from Technical Specifications and Place It Under Licensee Control2019-06-14014 June 2019 Application to Remove the Table of Contents from Technical Specifications and Place It Under Licensee Control ML18309A3012018-11-15015 November 2018 R. E. Ginna - Issuance of Amendment Nos. 327, 305, 232, 173, and 133, Respectively, Eliminating the Nuclear Advisory Committee Requirements ML18213A3692018-11-13013 November 2018 Issuance of Amendment No. 132 Revise Technical Specifications 3.3.1, Reactor Trip System Instrumentation, and 3.3.2, Engineered Safety Feature Actuation System Instrumentation ML18309A2632018-11-0909 November 2018 R. E. Ginna Nuclear Power Plant - Correction to Amendment No. 131 Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler 547, Clarification of Rod Position Requirements ML18295A6302018-10-31031 October 2018 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 131 Revise Technical Specifications to Adopt Technical Specifications Task Force (TSTF) Traveler TSTF 547, Clarification of Rod Position Requirements ML18214A1762018-08-31031 August 2018 Issuance of Amendment No. 130, Revise Technical Specification Surveillance Requirement 3.8.4.3, DC (Direct Current) Sources - Modes 1, 2, 3, and 4 ML18206A2822018-08-0202 August 2018 Issuance of Amendments to Relocate the Staff Qualification Requirements ML18190A4722018-07-12012 July 2018 R.E Ginna - Correction to Amendment No. 127 Related to Request to Delete a Modification Associated with the Risk-Informed, Performance Based Fire Protection Program in Accordance with 10 CFR 50.48(c) (CAC No. MF9948; EPID L-2017-LLA-0253) ML18137A6142018-06-26026 June 2018 Calvert Cliffs Independent Spent Fuel Storage Installation; Nine Mile Point Nuclear Station; and R. E. Ginna Nuclear Power Plant - Issuance of Amendments Revising Emergency Action Level Schemes ML18114A0252018-06-25025 June 2018 Issuance of Amendment No. 127, Modify License Condition 2.C.(3) Related to Commitment Associated with Implementation of National Fire Protection Association Standard 805 (CAC MF9948; EPID L-2017-LLA-0253) ML17163A3552017-08-31031 August 2017 Calvert Cliff, Clinton, Dresden, LaSalle, Limerick, Nine Mile Point, Peach Bottom, Quad Cities, R. E. Ginna, and Three Miles Island - Issuance of Amendments to Adopt TSTF-529, Clarify Use and Application Rules(Cac Nos. MF9470-MF9490) ML17131A0662017-06-21021 June 2017 R. E. Ginna Nuclear Power Plant - Issuance of Amendment Regarding Use of Optimized Zirlo ML17073A0672017-05-26026 May 2017 Issuance of Amendments Revising the Technical Specification Requirements for the Inservice Testing Program (CAC Nos. MF8238 - MF8256) ML16358A4242017-02-0909 February 2017 R. E. Ginna Nuclear Power Plant - Issuance of Amendment to Adopt TSTF-490, Revision 0, Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML16125A4852016-06-28028 June 2016 R. E. Ginna Nuclear Power Plant - Issuance of Amendment Request to Relocate Specific Surveillance Frequency Requirements to a Licensee Controlled Program - Adoption of TSTF-425, Revision 3 ML15352A1642016-03-17017 March 2016 Calvert Cliffs, Units 1 & 2 and Independent Spent Fuel Storage Installation; Nine Mile, Units 1 & 2 and R. E. Ginna - Issuance of Amendments Regarding the Emergency Plan Requalification Training Frequency for Emergency Response Organization Personnel ML14260A1512016-01-0505 January 2016 Issuance of Order and Conforming Amendments Concerning Pre-emption Authority (Tac Nos. MF2618 and MF2623) ML15271A1012015-11-23023 November 2015 Issuance of Amendment Regarding Transition to a Risk Informed, Performance-Based Fire Protection Program in Accordance with Title 10 of the Code of Federal Regulations Section 50.48(c) ML15223B2502015-08-14014 August 2015 and Nine Mile Point Nuclear Station, Unit No. 2- Copy of License Amendment Nos. 313, 291, 118, and 150 ML15161A3802015-07-30030 July 2015 R. E. Ginna and Nine Mile Point, Unit 2 - Issuance of Amendments Regarding Implementation of Technical Specification Task Force Traveler 523, Generic Letter 2008-01, Managing Gas Accumulation (TAC Nos. MF4405 - MF4409) ML15153A2822015-07-30030 July 2015 Issuance of Amendments Revising the Completion Date for Milestone 8 of the Cyber Security Plan (TAC Nos. MF4728, MF4729, MF4730, MF4731, MF4732, MF4733, MF4734, MF4735, MF4736, MF4737, MF4738, MF4739, MF4740 ML14232A3312014-08-21021 August 2014 Non-Proprietary, Correction to Amendment No. 116 Issued August 12, 2014, Revision to Technical Specification Section 3.6.5, 'Containment Air Temperature ML14232A1252014-08-12012 August 2014 R. E. Ginna Nuclear Power Plant - Redacted, Issuance of Amendment Revision to Technical Specification Section 3.6.5 Containment Air Temperature ML14091A3662014-04-0101 April 2014 Issuance of Amendment to Conform the Renewed Facility Operating License to Reflect the Direct Transfer of Operating Authority ML14106A1192014-03-25025 March 2014 R. E. Ginna Nuclear Power Plant - Order Approving Direct Transfer of Renewed Operating License and Conforming License Amendment 2024-05-23
[Table view] |
Text
July 11, 2006 Mrs. Mary G. Korsnick Vice President R.E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519
SUBJECT:
R.E. GINNA NUCLEAR POWER PLANT - AMENDMENT RE: 16.8 PERCENT POWER UPRATE (TAC NO. MC7382)
Dear Mrs. Korsnick:
The Commission has issued the enclosed Amendment No. 97 to Renewed Facility Operating License No. DPR-18 for the R.E. Ginna Nuclear Power Plant. This amendment consists of changes to the Renewed Facility Operating License and Technical Specifications (TSs) in response to your application transmitted by letter dated July 7, 2005, as supplemented by letters dated August 15, September 30, and December 6, 9, and 22, 2005, and January 11 and 25, February 16, March 3 and 24, and May 9 and 19, 2006.
The amendment revises the Renewed Facility Operating License and TSs to authorize an approximately 16.8 percent increase in the licensed steady-state thermal power level from 1520 megawatts thermal (MWt) to 1775 MWt. This level of power increase is considered an extended power uprate.
A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Register notice.
Sincerely,
/RA/
Patrick D. Milano, Sr. Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244
Enclosures:
- 1. Amendment No. 97 to Renewed License No. DPR-18
- 2. Safety Evaluation cc w/encls: See next page
July 11, 2006 Mrs. Mary G. Korsnick Vice President R. E. Ginna Nuclear Power Plant R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519
SUBJECT:
R.E. GINNA NUCLEAR POWER PLANT - AMENDMENT RE: 16.8 PERCENT POWER UPRATE (TAC NO. MC7382)
Dear Mrs. Korsnick:
The Commission has issued the enclosed Amendment No. 97 to Renewed Facility Operating License No. DPR-18 for the R.E. Ginna Nuclear Power Plant. This amendment consists of changes to the Renewed Facility Operating License and Technical Specifications (TSs) in response to your application transmitted by letter dated July 7, 2005, as supplemented by letters dated August 15, September 30, and December 6, 9, and 22, 2005, and January 11 and 25, February 16, March 3 and 24, and May 9 and 19, 2006.
The amendment revises the Renewed Facility Operating License and TSs to authorize an approximately 16.8 percent increase in the licensed steady-state thermal power level from 1520 megawatts thermal (MWt) to 1775 MWt. This level of power increase is considered an extended power uprate.
A copy of the related Safety Evaluation is also enclosed. A Notice of Issuance will be included in the Commission's biweekly Federal Register notice.
Sincerely,
/RA/
Patrick D. Milano, Sr. Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244
Enclosures:
- 1. Amendment No. 97 to Renewed License No. DPR-18
- 2. Safety Evaluation cc w/encls: See next page Accession Number: ML061380103 OFFICE LPLI-1\PM LPLI-1\LA SPWB\BC SBPB\BC CSGB\(A)BC CPNB\BC CVIB\BC NAME PMilano SLittle JNakoski DSolorio EMurphy TChan MMitchell DATE 07/05/06 07/ /06 04/04/06 03/23/06 02/17/06 04/03/06 02/02/06 OFFICE CFEB\BC EEMB\BC EICB\BC EEEB\(A)BC EQVA\BC IOLB\BC IHPB\BC NAME KGruss KManoly AHowe EBrown DThatcher DTrimble TFrye DATE 02/15/06 02/24/06 02/23/06 02/02/06 03/03/06 03/23/06 02/10/06 OFFICE AADB\BC APLA\BC AFPB\BC ACVB\BC TechEd OGC LPLI-1\BC NAME MKotzalas MRubin SWeerakkody RDennig HChang JMoore RLaufer DATE 02/15/06 02/23/06 01/31/06 01/01/06 06/14/06 07/05/06 07/09/06 OFFICE DORL\D NRR\D NAME CHaney JDyer DATE 07/10/06 07/10/06 Official Record Copy
DATED: July 11, 2006 AMENDMENT NO. 97 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-18 R.E. GINNA NUCLEAR POWER PLANT PUBLIC LPLI-1 R/F J. Dyer RidsNrrWpcMail M. Webber RidsNrrOd S. Collins, RI RidsRgn1MailCenter B. Boger RidsNrrAdro C. Haney RidsNrrDorl C. Holden RidsNrrDorl R. Laufer RidsNrrDorlLpla S. Little RidsNrrLASLittle P. Milano RidsNrrPMPMilano J. Nakoski RidsNrrDssSpwb D. Solorio RidsNrrDssSbpb T. Bloomer RidsNrrDciCsgb T. Chan RidsNrrDciCpnb M. Mitchell RidsNrrDciCvib K. Gruss RidsNrrDciCfeb K. Manoly RidsNrrDeEemb A. Howe RidsNrrDeEicb G. Wilson RidsNrrDeEeeb D. Thatcher RidsNrrDeEqva N. Salgado RidsNrrDirsIolb T. Boyce RidsNrrDirsItsb T. Frye RidsNrrDirsIhpb M. Kotzalas RidsNrrDraAadb M. Rubin RidsNrrDraApla S. Weerakkody RidsNrrDraAfpb R. Dennig RidsNrrDraAcvb G. Hill (2)
OGC RidsOgcRp ACRS RidsAcrsAcnwMailCenter S. Hansel, RI RidsRgn1MailCenter cc: Plant Service list
R.E. Ginna Nuclear Power Plant cc:
Mr. Michael J. Wallace Ms. Thelma Wideman, Director President Wayne County Emergency Management R.E. Ginna Nuclear Power Plant, LLC Office c/o Constellation Energy Wayne County Emergency Operations 750 East Pratt Street Center Baltimore, MD 21202 7336 Route 31 Lyons, NY 14489 Mr. John M. Heffley Senior Vice President and Ms. Mary Louise Meisenzahl Chief Nuclear Officer Administrator, Monroe County Constellation Generation Group Office of Emergency Preparedness 1997 Annapolis Exchange Parkway 1190 Scottsville Road, Suite 200 Suite 500 Rochester, NY 14624 Annapolis, MD 21401 Mr. Paul Eddy Kenneth Kolaczyk, Sr. Resident Inspector New York State Department of R.E. Ginna Nuclear Power Plant Public Service U.S. Nuclear Regulatory Commission 3 Empire State Plaza, 10th Floor 1503 Lake Road Albany, NY 12223 Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Carey W. Fleming, Esquire Senior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271
R.E. GINNA NUCLEAR POWER PLANT, LLC DOCKET NO. 50-244 R.E. GINNA NUCLEAR POWER PLANT AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 97 Renewed License No. DPR-18
- 1. The Nuclear Regulatory Commission (the Commission or the NRC) has found that:
A. The application for amendment filed by the R.E. Ginna Nuclear Power Plant, LLC (the licensee) dated July 7, 2005, as supplemented on August 15, September 30, and December 6, 9, and 22, 2005, and January 11 and 25, February 16, March 3 and 24, and May 9 and 19, 2006, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended by changes to the Renewed Facility Operating License and Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. DPR-18 is hereby amended to read as follows:
(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 97, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.
- 3. This license amendment is effective as of the date of its issuance and shall be implemented prior to startup from the fall 2006 refueling outage. Implementation shall include: (a) the revisions to plant operating procedures and the completion of operator training on the proposed power uprate, (b) incorporation of licensing basis changes into the next revision of the Updated Final Safety Analysis Report required by 10 CFR 50.71(c), and (c) inclusion of the commitments, as described in the licensees application, as supplemented, and the staffs safety evaluation dated July , 2006, in the licensees Commitment Management Program.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
J. E. Dyer, Director Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications Date of Issuance: July 11, 2006
ATTACHMENT TO LICENSE AMENDMENT NO. 97 RENEWED FACILITY OPERATING LICENSE NO. DPR-18 DOCKET NO. 50-244 Replace the following page of the Renewed Facility Operating License with the attached revised page. The revised page is identified by amendment number and contains marginal lines indicating the areas of change.
Remove Insert 3 3 Replace the following pages of the Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert 1.1-1 1.1-1 1.1-2 1.1-2 1.1-3 1.1-3 1.1-4 1.1-4 1.1-5 1.1-5 1.1-6 1.1-6 3.3.1-1 3.3.1-1 3.3.1-2 3.3.1-2 3.3.1-3 3.3.1-3 3.3.1-4 3.3.1-4 3.3.1-5 3.3.1-5 3.3.1-6 3.3.1-6 3.3.1-7 3.3.1-7 3.3.1-8 3.3.1-8 3.3.1-9 3.3.1-9 3.3.1-10 3.3.1-10 3.3.1-11 3.3.1-11 3.3.1-12 3.3.1-12 3.3.1-13 3.3.1-13 3.3.1-14 3.3.1-14 3.3.1-15 3.3.1-15 3.3.1-16 3.3.1-16 3.3.2-1 3.3.2-1 3.3.2-2 3.3.2-2 3.3.2-3 3.3.2-3 3.3.2-4 3.3.2-4 3.3.2-5 3.3.2-5 3.3.2-6 3.3.2-6
Remove Insert 3.3.2-7 3.3.2-7 3.3.2-8 3.3.2-8 3.3.2-9 3.3.2-9 3.3.2-10 3.3.2-10 3.4.10-1 3.4.10-1 3.4.10-2 3.4.10-2 3.7.6-1 3.7.6-1