Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities NG-24-0004, 2023 Annual Radiological Environmental Operating Report2024-05-0808 May 2024 2023 Annual Radiological Environmental Operating Report NG-24-0003, Submittal of 2023 Annual Radioactive Material Release Report2024-04-24024 April 2024 Submittal of 2023 Annual Radioactive Material Release Report ML24072A0292024-03-29029 March 2024 Nextera Energy Duane Arnold, Llc. Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) NG-24-0002, 2023 Annual Exposure Report - Form 5s2024-03-0606 March 2024 2023 Annual Exposure Report - Form 5s NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) NG-23-0010, Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-12-0606 December 2023 Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule NG-23-0009, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment NG-23-0006, Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-05-23023 May 2023 Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update ML23137A1672023-05-11011 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report NG-23-0004, 2022 Annual Radioactive Material Release Report2023-04-25025 April 2023 2022 Annual Radioactive Material Release Report NG-23-0003, 2022 Annual Exposure Report - Form 5s2023-04-21021 April 2023 2022 Annual Exposure Report - Form 5s NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-23-0002, 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report2023-03-27027 March 2023 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22339A0012022-12-22022 December 2022 Acceptance of Requested Licensing Action Amendment Request for Common Emergency Plan IR 05000331/20220032022-12-13013 December 2022 NRC Inspection Report No. 05000331/2022003 (Drss) ML22285A0072022-10-13013 October 2022 NRC Analysis of NextEra Energy Duane Arnold'S Decommissioning Funding Status Report, Docket No. 50-331 IR 05000331/20220022022-07-13013 July 2022 NRC Inspection Report Nos. 05000331/2022002(DNMS) and 07200032/2022002(DNMS) ML22090A1922022-05-26026 May 2022 Letter to B. Coffey, FPL from M. Doell - Duane Arnold Post Shutdown Activities Report Review Letter ML22132A2872022-05-24024 May 2022 ISFSI DQAP Approval Letter ML22111A0332022-05-20020 May 2022 Operating License Page Correction Letter to B. Coffey, Florida Power and Light, from M. Doell NG-22-0055, Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan2022-05-20020 May 2022 Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan ML22089A0492022-05-12012 May 2022 Sfmp Review Letter NG-22-0053, 2021 Annual Radiological Environmental Operating Report2022-05-0606 May 2022 2021 Annual Radiological Environmental Operating Report NG-22-0052, Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative2022-05-0404 May 2022 Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative IR 05000331/20224012022-04-27027 April 2022 Decommissioning Security Inspection Report 05000331/2022401 NG-22-0050, Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 02022-04-26026 April 2022 Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 0 NG-22-0049, 2021 Annual Radioactive Material Release Report2022-04-26026 April 2022 2021 Annual Radioactive Material Release Report ML22066A7632022-04-25025 April 2022 ISFSI-Only Emergency Plan License Amendment Approval L-2022-068, NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 22022-04-25025 April 2022 NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 2 NG-22-0035, Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 02022-04-13013 April 2022 Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 0 NG-22-0047, Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2022-04-11011 April 2022 Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool NG-22-0042, Registration of Independent Spent Fuel Installation Storage Casks2022-04-0808 April 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0041, and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0030, Registration of Independent Spent Fuel Installation Storage Casks2022-03-23023 March 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0031, 2021 Annual Exposure Report - Form 5s2022-03-23023 March 2022 2021 Annual Exposure Report - Form 5s ML22080A1822022-03-22022 March 2022 Letter to B. Coffey from M. Doell - Duane Arnold ISFSI QAPD RAI Letter L-2022-012, Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3)2022-03-16016 March 2022 Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22059A7462022-03-10010 March 2022 ISFSI-Only Physical Security Plan License Amendment Approval NG-22-0025, Registration of Independent Spent Fuel Installation Storage Casks2022-03-0808 March 2022 Registration of Independent Spent Fuel Installation Storage Casks IR 05000331/20220012022-03-0404 March 2022 Subject: NRC Inspection Report Nos. 05000331/2022001(DNMS) and 07200032/2022001(DNMS) 2024-09-04
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML22111A0332022-05-20020 May 2022 Operating License Page Correction Letter to B. Coffey, Florida Power and Light, from M. Doell ML22028A2822022-02-0303 February 2022 Defueled Physical Security Plan License Amendment Approval ML21067A6422021-05-13013 May 2021 Cyber Security License Amendment Approval ML20219A0882020-08-0707 August 2020 Correction Letter for Amendment No. 312 Removal of License Condition 2.C.(3), Fire Protection Program ML20184A0032020-07-30030 July 2020 Issuance of Amendment No. 312 Removal of License Condition 2.C.(3), Fire Protection Program ML20134J1042020-07-10010 July 2020 Issuance of Amendment No. 311 to Revise Operating License and Technical Specifications for Permanently Defueled Conditions ML20083G0082020-04-29029 April 2020 Issuance of Amendment No. 310 Changes to the Post-Shutdown Emergency Plan for Duane Arnold Energy Center ML19310C2042020-01-0202 January 2020 Issuance of Amendment No. 309 to Align Technical Specifications Staffing and Administrative Requirements ML18292A5662018-11-30030 November 2018 Issuance of Amendment 308 to Upgrade Emergency Action Level Scheme for Duane Arnold Energy Center (DAEC) ML18241A3832018-10-31031 October 2018 Issuance of Amendment 307 to Revise Technical Specifications to Adopt TSTF-551, Revision 3 ML18179A1842018-08-16016 August 2018 Issuance of Amendment 306 to Revise Technical Specification 3.5.1, ECCS-Operating ML18081A0742018-05-0707 May 2018 Correction of Error to Implementation Date Associated with License Amendment No 303 ML18016A6272018-03-0909 March 2018 Issuance of License Amendment No. 304 Revision to Technical Specification 3.1.2, Reactor Anomalies ML18011A0592018-03-0707 March 2018 Issuance of License Amendment No. 303 Revision to Technical Specification Table 3.3.2.1-1, Control Rod Block Instrumentation ML18032A4832018-03-0101 March 2018 Correction of Errors in Safety Evaluation Associated with License Amendment No. 301 ML17212A6462017-10-18018 October 2017 Issuance of Amendment to Modify the Plume Exposure Pathway Emergency Planning Zone Boundary ML17220A0262017-09-21021 September 2017 Issuance of Amendment 301 to Revise Emergency Plan ML17027A0782017-04-0707 April 2017 Issuance of Amendments Regarding Technical Specifications for Inservice Testing Programs (CAC Nos. MF8202 Through MF8209) ML17072A2322017-03-30030 March 2017 Issuance of Amendment to Revise Technical Specifications Fuel Storage Requirements ML16263A2452016-10-17017 October 2016 Issuance of Amendment to Technical Specifications Section 5.5.6 for the Inservice Testing Program ML16211A5142016-09-12012 September 2016 Issuance of Amendment to Revise Technical Specifications 2.1.1.2, Safety Limit Minimum Critical Power Ratio ML16210A0082016-08-30030 August 2016 Issuance of Amendment to Extend Containment Leakage Test Frequency ML16153A0912016-08-18018 August 2016 Issuance of Amendment to Revise the Value of Reactor Steam Dome Pressure ML16180A0862016-07-25025 July 2016 Issuance of Amendment to Revise and Relocate Pressure and Temperature Limit Curves to a Pressure and Temperature Limits Report ML16174A2812016-07-13013 July 2016 Issuance of Amendment (TSCR-154) to Correct Examples in Technical Specifications Section 1.4, Frequency ML15310A0822015-12-22022 December 2015 Issuance of Amendment to Adopt Technical Specifications Task Force (TSTF)-501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML15169A2612015-08-18018 August 2015 Issuance of Amendment Concerning Extension of Cyber Security Plan Milestone 8 Completion Date ML15014A2002015-02-10010 February 2015 Issuance of Amendment to Revise Technical Specifications to Adopt Technical Specifications Task Force - 523 Generic Letter 2008-01, Managing Gas Accumulation (Tac No. MF4358) ML13301A7052013-11-27027 November 2013 Issuance of Amendment Adopting TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs. ML13192A4232013-10-0707 October 2013 Issuance of Amendment to Change Renewed Facility Operating License Condition C.12 ML13210A4492013-09-10010 September 2013 Issuance of Amendment Regarding Transition to a Risk-Informed Performance-Based Fire Protection Program in Accordance with 10 CFR 50.48(c) ML13189A0712013-07-25025 July 2013 Issuance of Amendment to Revise Technical Specifications to Adopt TSTF-522 ML12321A2662012-11-28028 November 2012 Issuance of Amendment Revised Cyber Security Plan Implementation Schedule Milestone 6 ML12249A3172012-09-27027 September 2012 Issuance of Amendment One-Time Technical Specification Change Regarding Core Spray Operability During Shutdown ML1219803602012-08-27027 August 2012 Issuance of Amendment Technical Specification Changes Regarding Alternative Testing of Safety/Relief Valves ML12125A3152012-06-0101 June 2012 Issuance of Amendment Concerning Approval of Upgrade of Emergency Action Level Scheme ML1201102822012-02-24024 February 2012 Issuance of Amendment Adoption of Technical Specifications Task Force Traveler (TSTF-425) to Relocate Specific Surveillance Frequencies to a Licensee-Controlled Program ML1115202312011-09-0808 September 2011 Issuance of Amendment Pertaining to Deletion of Decommissioning Funding Parent Guarantee License Condition ML1119402242011-07-29029 July 2011 Issuance of Amendment Pertaining to Cyber Security Plan (TAC No. 4287) ML1104104552011-02-28028 February 2011 Issuance of Amendment Pertaining to Technical Specification Changes to Add LCO 3.0.9 on the Unavailability of Barriers (TSTF-427) ML1029305862010-12-16016 December 2010 Nextera Energy Duane Arnold, LLC Central Iowa Power Cooperative Corn Belt Power Cooperative, Duane Arnold Energy Center Renewed Facility Operating License ML0530503092010-12-16016 December 2010 Current Facility Operating License DPR-49, Tech Specs, Revised 03/17/2018 ML1029305242010-12-16016 December 2010 Issuance of Renewed Facility Operating License No. DPR-49 for Duane Arnold Energy ML1006211692010-03-31031 March 2010 License Amendment, Issuance of Amendment Pertaining to Changes to Technical Specifications 5.5.12 (Primary Containment Leakage Rate Testing Program) & 3.6.1.3 (Primary Containment Isolation Values), Associated with Main .. ML0930301132009-11-13013 November 2009 Issuance of Amendment Pertaining to Name Chance of Licensee and Co-Owner ML0919003812009-09-18018 September 2009 Issuance of Amendment Pertaining to Adoption of TSTF-511, Revision 0, Eliminate Working Hour Restrictions from Technical Specification 5.2.2 to Support Compliance with 10 CFR Part 26. ML0912605512009-05-15015 May 2009 License Amendment, Revision of the 4160 Volt Bus Undervoltage (Degraded Voltage) Maximum Allowed Value ML0831901082008-12-0303 December 2008 License Amendment, Issuance of Amendment to Change Surveillance Requirements of the Cedar River Depth to Assure Ultimate Heat Sink Operability ML0826908352008-11-0606 November 2008 Issuance of License Amendment Regarding Control Rod Notch Testing Frequency and Clarification of a Frequency Example ML0822601162008-09-0909 September 2008 Issuance of Amendment Regarding License Amendment Request to Remove the Emergency Diesel Generator Surveillance Requirement for Preplanned Preventive Maintenance and Testing 2022-05-20
[Table view] |
Text
June 28, 2006 Mr. J. A. Stall Senior Vice President Nuclear and FPL Energy Duane Arnold LLC PO Box 14000 Juno Beach, FL 33408-0420 and Mr. Gary Van Middlesworth Vice President Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324-9785
SUBJECT:
DUANE ARNOLD ENERGY CENTER - CORRECTION TO AMENDMENT NO. 260
Dear Mr. Stall and Mr. Van Middlesworth:
On December 23, 2005, the Nuclear Regulatory Commission (NRC) issued an Order approving the transfer of the Facility Operating License for Duane Arnold Energy Center (DAEC) to the extent held by the Interstate Power and Light Company (IPL) as owner, and the Nuclear Management Company, LLC (NMC) as the licensed operator of DAEC, to FPL Energy Duane Arnold, LLC (FPLE Duane Arnold), a subsidiary of FPL Energy, LLC. The Order also approved the conforming amendment. Thereafter, on January 27, 2006, the NRC issued the conforming amendment following the consummation of the direct license transfers.
Due to an administrative oversight, the NRC staff did not exercise proper signature authority when issuing the conforming amendment. Therefore, the staff is reissuing the enclosed amendment page for Amendment No. 260.
Sincerely,
/RA/
Deirdre W. Spaulding, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
Amendment No. 260 to DPR-49 Page 2 cc: See next page
June 28, 2006 Mr. J. A. Stall Senior Vice President Nuclear and FPL Energy Duane Arnold LLC PO Box 14000 Juno Beach, FL 33408-0420 and Mr. Gary Van Middlesworth Vice President Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324-9785
SUBJECT:
DUANE ARNOLD ENERGY CENTER - CORRECTION TO AMENDMENT NO. 260
Dear Mr. Stall and Mr. Van Middlesworth:
On December 23, 2005, the Nuclear Regulatory Commission (NRC) issued an Order approving the transfer of the Facility Operating License for Duane Arnold Energy Center (DAEC) to the extent held by the Interstate Power and Light Company (IPL) as owner, and the Nuclear Management Company, LLC (NMC) as the licensed operator of DAEC, to FPL Energy Duane Arnold, LLC (FPLE Duane Arnold), a subsidiary of FPL Energy, LLC. The Order also approved the conforming amendment. Thereafter, on January 27, 2006, the NRC issued the conforming amendment following the consummation of the direct license transfers.
Due to an administrative oversight, the NRC staff did not exercise proper signature authority when issuing the conforming amendment. Therefore, the staff is reissuing the enclosed amendment page for Amendment No. 260.
Sincerely,
/RA/
Deirdre W. Spaulding, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
Amendment No. 260 to DPR-49 Page 2 cc: See next page DISTRIBUTION:
PUBLIC RidsNrrLPLIII-1 R/F RidsRgn3MailCenter RidsNrrOd RidsNrrDorlLple RidsAcrsAcnwMailCenter RidsNrrDorl RidsNrrDorlLplf RidsNrrLATHarris RidsNrrPMDSpaulding RidsOgcRp SCampbell ADAMS Accession Number: ML060620511 OFFICE NRR/LPL3-1/PM NRR/LPL3-1/LA NRR/LPL3-1/BC OGC NRR/DORL/D NRR/D NAME DSpaulding THarris LRaghavan CHaney JDyer DATE 6/19/06 6/19/06 6/20/06 6/22/06 6/13/06 6/28/06 OFFICIAL RECORD COPY
INTERSTATE POWER AND LIGHT COMPANY CENTRAL IOWA POWER COOPERATIVE CORN BELT POWER COOPERATIVE NUCLEAR MANAGEMENT COMPANY, LLC DOCKET NO. 50-331 DUANE ARNOLD ENERGY CENTER AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 260 License No. DPR-49
- 1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A. The application for amendment by Nuclear Management Company, LLC (the licensee) dated August 1, 2005, as supplemented by letters dated October 11, November 1, November 2, and November 28, 2005, complies with the standards and requirements of the Atomic Energy Act of l954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (I) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
- 2. Accordingly, the license is amended as indicated in the attachment to this license amendment.
- 3. This license amendment is effective as of its date of issuance and shall be implemented within 30 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
J. E. Dyer, Director Office of Nuclear Reactor Regulation
Attachment:
Changes to the Facility Operating License DPR-49 Date of Issuance: January 27, 2006
Duane Arnold Energy Center cc:
Mr. J. A. Stall Regional Administrator, Region III Senior Vice President, Nuclear and Chief U.S. Nuclear Regulatory Commission Nuclear Officer Suite 210 Florida Power & Light Company 2443 Warrenville Road P. O. Box 14000 Lisle, IL 60532-4351 Juno Beach, FL 33408-0420 Mr. M. Warner Mr. M. S. Ross Vice President, Nuclear Operations Managing Attorney Support Florida Power & Light Company Florida Power & Light Company P. O. Box 14000 P. O. Box 14000 Juno Beach, FL 33408-0420 Juno Beach, FL 33408-0420 Mr. R. E. Helfrich Mr. D. A. Curtland Senior Attorney Plant Manager Florida Power & Light Company Duane Arnold Energy Center P. O. Box 14000 3277 DAEC Rd.
Juno Beach, FL 33408-0420 Palo, IA 52324-9785 Mr. W. E. Webster Mr. R. S. Kundalkar Vice President, Nuclear Operations Vice President, Nuclear Engineering Florida Power & Light Company Florida Power & Light Company P. O. Box 14000 P. O. Box 14000 Juno Beach, FL 33408-0420 Juno Beach, FL 33408-0420 John Bjorseth Daniel McGhee Site Director Utilities Division Duane Arnold Energy Center Iowa Department of Commerce 3277 DAEC Road Lucas Office Buildings, 5th Floor Palo, IA 52324 Des Moines, IA 50319 Steven R. Catron Chairman, Linn County Manager, Regulatory Affairs Board of Supervisors Duane Arnold Energy Center 930 1st Street SW 3277 DAEC Road Cedar Rapids, IA 52404 Palo, IA 52324 U. S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1 Palo, IA 52324