10 CFR 50.59, and 10 CFR 72.48 Changes, Tests, & Experiments Summary Report
ML053410236
Person / Time
Site: Sequoyah  
Issue date: 11/17/2005
From: Pace P
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML053410236 (13)


Text

V _ 1-.5 Tennessee Valley Authority, Post Office Box 2000, Soddy-Daisy, Tennessee 37384-2000 November 17, 2005 10 CFR 50.59 10 CFR 72.48 U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C.

20555 Gentlemen:

In the Matter of Tennessee Valley Authority

)

Docket Nos.

50-327 50-328 SEQUOYAH NUCLEAR PLANT -

UNITS 1 AND 2 -

10 CFR 50.59, AND 10 CFR 72.48 CHANGES, TESTS, AND EXPERIMENTS

SUMMARY

REPORT The purpose of this letter is to provide the summary of the implemented safety evaluations, performed in accordance with 10 CFR 50.59(d)(2) and 10 CFR 72.48.

evaluations occurred since the last Unit 2 refueling report The outage.

If you should have any questions, please contact me at (423) 843-7170 or J. D. Smith at (423) 843-6672.

Sincerely, 4

P. L. Pace Manager, Site Licensing and Industry Affairs Enclosure

. t__ 4 q1 Printed on recyled paper

I ENCLOSURE SEQUOYAH NUCLEAR PLANT 10 CFR 50.59 AND 10 CFR 72.48

SUMMARY

REPORT

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT - 19 DCN J DESCRIPTION

}

SAFETY ANALYSIS l

D-20922-A This change involves the construction of a cask storage pad Construction of the access road from the Auxiliary Building to the ISFSI pad for the Independent Spent Fuel Storage Installation (ISFSI).

required installation of a thick layer of roller compacted concrete adjacent to Major modifications implemented as part of this change existing tornado missile protection slabs at a grade above existing safety-include the construction of the cask storage and fabrication related underground essential raw cooling water (ERCW) piping. The road pad including lighting, drainage features, grounding, a excavation required temporarily removal of soil to a depth below the bottom nuisance fence and an access road. Additional interface of the missile protection slabs. As such, a portion of the soil that provides the work involving grading rework equipment abandonment barrier against low missile flight paths to the ERCW piping was removed.

and potable water line rerouting was also performed as part This condition was temporary for the time from soil excavation to the of the change.

placement of the roller compacted concrete (which provides missile protection superior to the present soil barrier).

During this interim configuration, 80 percent of the possible tornado missile flight paths to the ERCW piping were blocked by the remaining soil and concrete slab.

The other 20 percent of the flight paths affected by soil removal were covered with 4.3 feet of soil. Protection against missiles larger than six inches is not diminished by this configuration.

For smaller size missiles to damage the ERCW piping in this configuration, the missiles must maintain a non-tumbling flight path, strike within the 20 percent angle range and penetrate 4.3 feet of soil.

While this is possible, such a missile will not damage two or more ERCW pipes.

All active components of the ERCW supply are redundant and can tolerate a single failure in the short or long tern.

The functional capabilities of the ERCW system were not affected by the construction configuration between excavation and placement of the roller compacted concrete.

D-21247-A This change involves the replacement of the original The CBECS functions to mitigate the radiological consequences of accidents D-21248-A electromechanical controls for the main control room to control building personnel.

The CBECS utilizes the control room (MCR) and electric board room (EBR) air conditioning emergency pressurization system and the control room emergency air cleanup (A/C) condensing units with replacement digital controls.

system to limit radiological exposure.

These systems automatically actuate The MCR and EBR A/C condensing units are components upon receipt of a control room isolation (CR1) signal generated manually, of the MCR and EBR A/C subsystems. These subsystems automatically from a safety injection signal, or upon detection of high are part of the Control Building Environmental Control temperature or high radiation levels in the Control Building fresh air intake System (CBECS) which also includes the MCR emergency duct. The MCR and EBR A/C condensing units are not directly used to pressurization system, the MCR emergency air cleanup mitigate the consequences of any UFSAR Chapter 15 event and thei failure E-1

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT - 19 DCN

[

DESCRIPTION SAFETY ANALYSIS l

system, the battery room exhaust system, and miscellaneous would not create a Chapter 15 initiating event. However, as a subsystem of ventilating systems. The normal function of the MCR and the CBECS, the MCR and EBR A/C condensing units provide cooling to EBR A/C subsystems is to provide cooling to the designated designated areas of the Control Building to maintain temperatures in areas of the Control Building to maintain design accordance with environmental design requirements.

temperatures in accordance with environmental design requirements.

The MCR and EBR A/C system condensing units consist of trained, 100 percent redundant units. The replacement digital controllers are robust and The replacement digital control systems were designed provide diagnostic information to personnel for assessing and correcting specifically to replace the electromechanical control systems potential problems. In some cases, a single failure of a digital controller will used on the existing A/C packages.

The control system result in the loss of a single A/C condensing unit. Because the redundant unit changes included replacement of temperature, pressure, and in each system is unaffected, there is no corresponding loss of safety function.

motor current sensor inputs with units compatible with the This is similar to the existing electromechanical control scheme in that a digital control unit. Where possible, the digital control unit single failure results in loss of a single condensing unit.

Unlike the outputs drive existing interface relays, motor starters, and electromechanical controls which lack the ability to evaluate process solenoid valves. The digital controller for each train of A/C parameters or restart an A/C condensing unit following a trip, the digital condensing units is powered from an independent Class IE control system is designed to maximize system performance while minimizing power supply.

The digital controller interfaces with the operator intervention. It is therefore expected that the digital control system same power source used in the previous installation. Bus will provide more reliable operation of the A/C condensing units than the loading for the new controls remains within previous design existing electromechanical control system.

parameters with acceptable margin.

There was no modification of the power system or wiring to the The digital controller represents a potential common cause failure attributable controllers.

Therefore, there was no change in power to software.

Review of the software code, the software design process, system redundancy, independence, or separation.

operational history of similar units, and factory acceptance tests on the digital control system for each compressor supports the conclusion that the system The digital controller provides for improved control and control software does not increase the probability of a common cause failure.

operational flexibility of the A/C condensing units. System Replacing the existing electromechanical MCR and EBR A/C condensing unit reliability improvements are anticipated based on the ability controls with digital controllers does not increase the likelihood of equipment to discriminate and compensate between sensor malfunctions, change equipment failure modes, impact fission product malfunctions (and other minor problems) and actual barriers, alter the frequency of previously analyzed events, or create an event operational issues requiring the condensing units to be of a type not previously analyzed.

shutdown.

E-2

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT - 19 DCN DESCRIPTION SAFETY ANALYSIS D-21640-A This change involves the deletion/abandonment of eight None of the deleted monitors are used to mitigate or recover from a UFSAR D-21641-A radiation monitors as part of the Radiation Monitoring Chapter 15 accident. The radiation monitoring system at Sequoyah Nuclear System Optimization Project. The change also removes the Plant was designed early in plant construction. Some radiation monitors were automatic closure signal to the containment isolation valves included in the original design in response to industry events or were added in for the reactor coolant drain tank lines and the reactor anticipation of regulatory issues.

As a part of the Radiation Monitoring building floor and equipment drain sump lines based on System Optimization Project, all radiation monitors ware reviewed to signals from the deleted/abandoned radiation monitors.

determine if they were a) redundant with other monitors and could be The change was performed in five separate stages. The first eliminated, b) the function was accomplished by other means such as health four stages removed the high radiation isolation signal from physic surveys, or c) the function was not needed. It was concluded that the the affected containment isolation valves.

Stage 5 affected monitors could be eliminated based on the following considerations.

removed/abandoned all eight radiation monitoring instrumentation loops.

The Reactor Coolant Drain Tank Monitors and the Reactor Building Floor and Equipment Drain Sump Monitors automatically isolate the reactor coolant The radiation monitors affected by this change include the drain tank lines and the reactor building floor and equipment drain sump lines Reactor Coolant Drain Tank Monitors (2), the Reactor on detection of high radiation. These lines are also automatically isolated on Building Floor and Equipment Drain Sump Monitors (2) a Phase A containment isolation signal independent of the signal from the and -the Residual Heat Removal (RHR) Accident Line radiation monitors. Resetting the Phase A signal does not allow the valves to Monitors (4).

automatically reopen. Thus the lines are protected from inadvertent opening after an accident.

There is no regulatory requirement (NUREG-0737 or NUREG-0696) which requires these lines be isolated using a high radiation signal. Therefore these monitors have been eliminated.

The RHR Accident Line Monitors are area type monitors located adjacent to the RHR lines. These monitors were added in anticipation of a regulatory requirement that was not promulgated. Therefore, these monitors have been eliminated.

In summary, these radiation monitors were eliminated from the plant design because they provided redundant or unnecessary functions. Their deletion does not affect safe plant operation.

E-3

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT - 19 DCN DESCRIPTION SAFETY ANALYSIS A

A D-21854-A This change involves modification of the emergency diesel generator (DG) air starting system. Each DG engine is provided with an air starting system using two air accumulator tanks. In the original design, one of the tanks is connected to the air start system while the other is isolated from the system in a standby mode. Should the DG fail to start using the air in the primary tank, the standby tank can be aligned to the air start system by operator action (i.e., manually opening locally mounted isolation valves).

The tanks are maintained between 250-300 psig. Pressure control valves (PCVs) control pressure downstream of the tanks between 190-200 psig. During starts, the downstream pressure drops and is limited only by the back pressure in the starter set and associated piping. The large differential pressure across the PCVs when the air motors actuate occasionally causes the PCVs to malfunction. This causes the pressure in the aligned accumulator tank to fall below an acceptable level.

(It should be noted that when a malfunction occurs, it occurs after a successful DG start. A malfunction has never caused a failure to start the DG.)

To address this issue, this modification 1) changes the alignment of the accumulator tanks such that they are both normally aligned to the air start system in series, 2) removes the PCV between the air start motor and the first accumulator tank, 3) relocates the remaining PVC between the first accumulator tank and the second accumulator tank and 4) reduces the operational pressure in the first tank to 200 psig.

This modification will lower the differential pressure across the PCV and allows both tanks to be connected to the starting air system.

This increases the amount of available starting air and eliminates the operator action to manipulate the manual isolation valves.

The design function of the DG air start system is to maintain an air storage capacity sufficient to crank the engine five times without recharging. This modification enhances the capability of the air start system to meet this functional requirement based on the following considerations.

1. Although the total amount of stored energy in the accumulators will be reduced by reducing the pressure in one accumulator tank from 300 psig to 200 psig, the normal alignment of both air accumulator tanks to the air start motors will provide additional air capacity to meet the five-start requirement without operator action.
2. The operation/reliability of the air system PCV is improved by reducing the differential air pressure across the valve during air motor operation.

Improved reliability of the PVC reduces the likelihood of an inadvertent blow down of the air accumulator tanks.

3. Removal of the PCV between the air start motor and the first accumulator tank simplifies the design and eliminates a potential failure device between the accumulator tank and the air start motor. As a result of this modification, a PCV will no longer have to actuate to pass air from an accumulator to a start motor for the first start of the DG engines.
4. The air start system remains single failure proof as each DG set continues to be equipped with a redundant starting air system to ensure that a single failure will not prevent start of a DG set. As in the previous design, low pressure alarms in the MCR will alert operators to a failed closed condition of the PCV.

Given the considerations, the modification replaces a required manual operator action with an adequate and reliable automatic action, reduces the likelihood of equipment malfunctions and has no affect on equipment failure modes. The modification does not adversely affect safe operation of the plant.

E-4

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT - 19 l

DCN DESCRIPTION I

SAFETY ANALYSIS E-21761-A This engineering-only change documents the acceptability The function of the EGTS moisture separators is to reduce moisture loading of the as-installed configuration of the moisture separators on the pre-filters and high efficiency particulate air (HEPA) filters installed in contained in the air cleanup subsystem of the Emergency the air cleanup system downstream of the separators. The original design of Gas Treatment System (EGTS). As designed, the EGTS the air cleanup system assumed that the EGTS filter housings would be moisture separator assembly is composed of two functional located in a high relative humidity environment. Subsequent environmental elements.

The first element is composed of louvers (or condition calculations determined that the relative humidity of the air entering wave/bent plate demister blades) which are designed to the EGTS air cleanup units is low (45%) during accident conditions. (NRC remove large (50-1000pim) liquid droplets.

The second RG 1.52 defines low relative humidity as less than 70% relative humidity.)

element is composed of fiber-glass, non-woven fiber mat These calculations were previously used to establish that the EGTS duct pads (i.e., demister pads) which remove the finer, sensible heaters included in the original system design are not required to meet system moisture droplets (1-100unm). During an inspection of the functional requirements (refer to Sequoyah License Amendment Nos. 103 EGTS filter housings (where the moisture separators are (Unit 1) and 92 (Unit 2) issued in response to Technical Specification Change installed), it was determined that the demister pads were not Request Nos. TS 80 and TS 136). These calculations do not take credit for installed in the moisture separator assembly. Upon review, any moisture removal by the moisture separators.

it was determined that the demister pads were not installed during original plant construction Based on this result, deletion of the moisture separator functional requirement does not aversely affect the operation of the EGTS system. The moisture This change documents the acceptability of the as-installed separators are not needed to protect the downstream filters and charcoal configuration to meet the functional requirements of the air absorbers due to the low relative humidity service conditions.

The cleanup system and revises the design basis documentation non-functional moisture separators will not prevent the EGTS air cleanup unit to eliminate the requirement for moisture separators in the from performing the required safety functions of 1) keeping a negative EGTS air cleanup system.

pressure within the containment building annulus and 2) reducing the radioactive nuclides in the annulus air released to the environment within acceptable levels.

E-5

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT -

19 PROCEDURE l

SUMMARY

OF DESCRIPTION SAFETY ANALYSIS ES-1.3, Step 2 of Emergency Procedure No. ES-1.3, "Transfer to The function of the containment spray system is to reduce containment pressure Revision 12 Residual Heat Removal Containment Sump" was revised to following ice bed depletion for the long term containment integrity analysis permit one train of containment spray to be removed from described in the UFSAR. Containment pressure suppression is provided by the operation if both trains of containment spray are operating ice condenser until the ice mass is depleted for a large break loss of coolant at the initiation of emergency core cooling system (ECCS) accident (i.e., the design basis containment pressurization transient). Following pump suction swapover from the refueling water storage ice bed depletion, the long term containment integrity analysis credits one train of tank (RWST) to the reactor building recirculation sump.

containment spray flow for containment pressure suppression.

The analysis requires that the ECCS and containment spray pump suction be aligned to the This change reduces the flow rate out of the RWST and reactor building recirculation sump before the ice mass in the ice condenser is allows for increased operator action time to complete the depleted to ensure continued pressure suppression. As such, termination of one realignment of the ECCS pump suction from the RWST to train of containment spray flow during the swapover from RWST injection to the reactor building recirculation sump.

containment sump recirculation is acceptable because 1) the ice condenser is providing containment pressure suppression during this interval and 2) the Following alignment of the containment spray pump suction containment integrity analysis only assumes operation of one train of to the reactor building recirculation sump, both containment containment spray during the entire event.

spray pumps will be returned to service.

Additionally, the assumption of one train of ECCS and containment spray operation maximizes the drain down time of the RWST.

It establishes the limiting margin between the completion of sump recirculation swapover and ice bed meltout. The termination of one train of containment spray flow during the injection to recirculation transition time will not affect the transition time completion to ice bed meltout margin established by the analysis.

Based on these considerations, the procedure change does not adversely affect safe operation of the plant.

E-6

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT -

19 TACF I

SUMMARY

OF DESCRIPTION

[

SAFETY ANALYSIS 1-05-002-063 This change involves the temporary installation of a continuous vent line for the residual heat removal (RHR) discharge piping. The alteration involves the installation of a check valve and a valve station (which includes a pressure reducing valve with upstream and downstream isolation valves, a parallel by-pass valve and a parallel throttle valve).

The check valve (which supports a piping classification transition) will be installed downstream of an existing RHR Train B emergency core cooling system (ECCS) high point vent valve (normally closed).

The check valve will be connected between the existing vent valve and the skid mounted valve station with stainless steel tubing. Discharge from the valve station will be routed via a floor drain to the Reactor Building Floor and Equipment Drain Sump (RBFEDS).

Two additional normally closed ECCS vent valves will be opened such that the RHR pump discharge piping will vent continuously through the valves, the temporary check valve and valve station into the RBFEDS.

This temporary alteration is required to mitigate the effects of a leaking primary system check valve which requires operator action to periodically vent the RHR discharge piping. The continuous vent will reduce but not eliminate the need to manually depressurize the RHR discharge piping. The continuous vent will remain in place until the leaking check valve can be repaired/replaced during the next refueling outage.

The design of the temporary alteration is consistent with existing design requirements for interfacing with safety-related systems, structures, and components (SSC's). The design does not affect RHR system operation, it satisfies the normal and post accident limitations for drainage to the RBFEDS and meets all containment isolation requirements For RHR system operation, each RHR pump is credited for supplying a nominal flow 3000 gpm. The maximum RHR inventory lost to the RBFEDS through the temporary vent line (approximately 750 gpd) does not have a significant affect on system operation.

In the event of a primary system loss-of-coolant accident, the temporary vent line would allow a portion of the RHR flow to be diverted from the active reactor building recirculation sump to the RBFEDS (i.e., outside the containment building polar crane wall).

The portion of the ECCS flow diverted to the RBFEDS will not be available to the long-term ECCS recirculation inventory. A conservative calculation of the recirculation inventory lost through this line for 100 days of post-accident operation confirmed that there is sufficient active sump inventory to support ECCS operation (i.e.,

to meet pump NPSH and vortex safety limits) when the temporary vent line loss is considered.

Changing the position of the ECCS high point vent valves from normally closed to normally open to allow the continuous vent was reviewed relative to the containment isolation function established for Containment Penetration No.

X-20A. The evaluation concluded that the temporary change does not affect the containment isolation function for Containment Penetration X-20A. The classification and testing of the temporary materials/components which interface with the established containment isolation boundary were equal to or better than the classification and testing of the existing X-20A pressure boundary components.

Based on these considerations, the temporary change does not adversely affect safe operation of the plant.

E-7

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT -

19 W

TACF I

SUMMAT'RY OF DESCRIPTION l

SAFETY ANALYSIS 1-05-013-063 This change involves the temporary installation of a commercial grade, low volume, high pressure pump in the safety injection system to fill the Cold Leg Accumulators (CLAs). The temporary pump is air driven and operates at station air header pressure (70-100 psig).

It consumes approximately 100 scfm while providing a maximum outlet pressure of 850 psig (relief valve setpoint). The pump is manually operated under local operator control.

The temporary pump is located in the Auxiliary Building.

The pump discharge ties into an existing manual valve in the accumulator fil/test line. An in-line check valve is also installed at the tie-in valve to prevent back flow into the temporary equipment The temporary pump takes suction from an existing pressure gauge tap on the tube side of the Train A containment spray system (CSS) heat exchanger.

An existing instrument isolation valve is used for suction supply isolation.

The water source for the pump is the refueling water storage tank (RWST) via the Train A CSS heat exchanger.

All connections and added valves are consistent with the permanent piping system design.

Hydraulic modeling predicts a pump flow of 3.5 to a maximum of 5.4 gpm in this configuration.

This temporary alteration is required to mitigate the effects of a leaking primary system check valve which requires operator action to periodically fill the Loop 3 CLA. The CLAs are normally filled by operation of the safety injection pumps.

This temporary alteration will be used as an alternate CLA fill method in order to minimize the number of starts on the safety injection pumps.

The pump will remain in place until the leaking check valve can be repaired/replaced during the next refueling outage.

The design of the temporary alteration is consistent with existing design requirements for interfacing with safety-related systems, structures, and components (SSC's).

A flow path to the centrifugal charging pump (CCP) suction is prevented by existing check valves and normally closed manual valve alignments. Flow from the temporary pump is isolated from the safety injection system flow by containment isolation valves. Backflow from the safety injection system test header into the CSS, the residual heat removal (RHR) pump, safety injection (SI) pump or the temporary pump connection is prevented by an added inline check valve. The fill pressure is greater than CLA pressure but is much less than normal Reactor Coolant System (RCS) pressure.

The CLA will not be overpressurized by the temporary pump because of the low capacity which provides sufficient time for operator action prior to actuation of a CLA relief valve. If pressure were to increase to the point of actuating a CLA relief valve, the relief valves have sufficient capacity to relieve any overpressure.

The low pump flow rate also provides sufficient time to secure the pump should a leak develop or an equipment malfunction occur within the fill path.

When the temporary pump is aligned for fill operation, administrative controls are in place which require operator action to ensure that the post accident sump inventory is not communicated to the Auxiliary Building via the attachment at the CSS heat exchanger.

The operator action ensures that there are no changes to the consequences of any analyzed accident. The failure to perform the manual action does not result in an accident or new malfunction, and does not exceed the consequences already evaluated in the UFSAR.

E-8

I.

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT -

19 UFSAR _

SUMMARY

OF DESCRIPTION SAFETY ANALYSIS REVISION I___I Section 10.4,7 This change involves a revision to the Steam Generator Blowdown (SGBD) system automatic isolation logic described in Section 10.4.7 of the UFSAR. The current logic description indicates that the SGBD system automatically isolates when the auxiliary feedwater (AFW) pumps receive an automatic start signal.

A design review of the as-installed isolation logic established that the SGBD isolation valves will not receive an automatic closure signal concurrent with an AFW automatic pump start when the AFW pumps are in operation (Le., when the pumps are operating during startup or shutdown operations or during pump surveillance testing performed during full power operation).

The SGDB isolation valves will receive an automatic isolation signal when 1) the AFW pumps receive an automatic start signal when they are not in operation and 2) upon receipt of a Phase A containment isolation signal.

Review of the as-installed SGBD isolation logic determined the AFW system functional capabilities are not affected by the isolation logic change.

The UJFSAR (and other design basis documents) have been revised accordingly.

The AFW system safety function involves the supply feedwater to the steam generators to remove reactor coolant system (RCS) decay heat and other stored energy by steaming through the main steam safety valves. The AFW system is required to provide feedwater when the non-safety grade main feedwater (MFW) system is unavailable and the RCS is above the maximum pressure/temperature for initiation of residual heat removal (RHR) system operation. The specific safety functions and flowrate requirements of the AFW system vary with each design basis event (DBE). The DBEs which impose safety-related performance requirements on the AFW system include the loss of MFW transient, main feedline break (MFLB), main steamline break (MSLB), loss of all alternating current power (station blackout) and a small break loss of coolant accident (SB LOCA). The AFW system performs safety functions to both mitigate and recover from these transients. These transients are divided into two broad classes which include 1) primary system cooldown events which limit the maximum amount of AFW flow and 2) primary system heatup events which establish minimum AFW flow requirements.

The MSLB is the limiting RCS cooldown event and establishes the maximum AFW flow limit (2250 gpm AFW flow delivered to a faulted loop until isolated). The loss of MFW and MFLB transients are the limiting RCS heatup events and establish the minimum AFW flow requirement (410 gpm to at least two steam generators one minute following the initiation of a low-low steam generator water level reactor trip signal). In addition to the DBE mitigation, the AFW system supports recovery from all of the DBEs listed above by providing sufficient flow to remove decay heat, stored energy and reactor coolant pump heat until such time as the RHR system can be placed in service.

The requirements for performing this recovery function are identical to the minimum AFW requirements for RCS heatup transient mitigation.

Based on a detailed evaluation of AFW system operation with the existing SGBD isolation logic, it was determined that all system functional requirements continue to be met. This conclusion is based on 1) the ability of the AFW system to provide adequate RCS cooling during nornal startup and shutdown operations E-9

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT -

19 UFSAR

SUMMARY

OF DESCRIPTION SAFETY ANALYSIS REVISION with minimum pump capacities and a bounding SGBD flow rate, 2) the availability of diverse SGBD flow isolation signals to maintain system operation consistent with safety analysis assumptions, and 3) the availability of additional AFW flow capacity from the turbine driven AFW pump which is not credited by the loss of normal feedwater transient analysis but is required for system operability.

Based on these results, the isolation logic change does not adversely affect safe operation of the plant.

Section This change involves a revision to Section 15.2.10 of the IJFSAR The revised analysis uses methodology and computer codes approved by NRC 15.2.10 to incorporate a revised analysis of the feedwater system and is in compliance with the conditions and restrictions placed on their malfunction transient. The revised analysis demonstrates that the application. It does not represent a departure from an approved method of reactor coolant system temperature-pressure response to the evaluation. As a result, the revised analysis was adopted as the analysis of record transient is well within the system design limits, confirms that the under the current licensing basis.

minimum calculated departure from nucleate boiling (DNB) ratio is above the established safety limit and confirms that the steam generator does not overfill and flood the main steam piping. The results meet all of the previously established transient acceptance criteria.

The revised analysis differs from the existing analysis in that it uses an NRC-approved evaluation methodology developed by Framatome Advanced Nuclear Power (FANP). The FANP methodology establishes feedwater flow rates, core power and reactor coolant system temperature and pressure conditions using the RELAP5/MOD2-B&W computer code and the resultant DNB conditions using the LYNXT computer code. The current analysis uses a methodology developed by Westinghouse Electric Company which establishes the core power transient using the LOFTRAN computer code and is based on a bounding, maximum feedwater flow rate.

E-10

SEQUOYAH NUCLEAR PLANT CHANGES IN THE FACILITY FOR AMENDMENT -

19 UFSAR

SUMMARY

OF DESCRIPTION I

SAFETY ANALYSIS REVISION The reanalysis was performed to make the methodology used for the feedwater malfunction analysis consistent with other transient analyses which use methodologies developed by FANP. FANP is the current supplier of reload fuel and reload analysis services for Sequoyah.

ISFSI

SUMMARY

OF DESCRIPTION SAFETY ANALYSIS CHANGE SQN-04-01 Temporarily removing the HI-STROM 100S, Version B, lower The evaluation concluded that temporary removal of the gamma shields results inlet vents gamma shields. The temporary removal assists the in no increase in off-site consequences. The site-specific calculations for the annual inspection and if needed, reapplication of a sealant between SQN ISFSI conservatively did not credit the use of inlet vent gamma shields in the overpack baseplate and ISFSI storage pad.

the model, therefore, the temporary removal does not affect the existing off-site consequence.

E-11