ML053010255

From kanterella
Jump to navigation Jump to search
IR 050004242-05-04, IR 05000425-05-004, on 07/01/2005 - 09/30/2005, for Vogtle Electric Generating Plant; Radiation Monitoring Instrumentation and Protective Equipment
ML053010255
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 10/28/2005
From: Widmann M
NRC/RGN-II/DRP/RPB2
To: Grissette D
Southern Nuclear Operating Co
References
IR-05-004
Download: ML053010255 (39)


See also: IR 05000425/2005004

Text

October 28, 2005

Southern Nuclear Operating Company, Inc.

ATTN: D. E. Grissette, Jr.

Vice President - Vogtle Project

P. O. Box 1295

Birmingham, AL 35201-1295

SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NRC INTEGRATED INSPECTION

REPORT 05000424/2005004 AND 05000425/2005004

Dear Mr. Grissette:

On September 30, 2005, the U. S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Vogtle Electric Generating Plant (VEGP), Units 1 and 2. The enclosed

integrated inspection report documents the inspection results, which were discussed on

October 17, 2005, with Mr. Tom Tynan and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

This report documents one NRC-identified finding of very low safety significance which was

determined to involve a violation of NRC requirements. However, because of its very low safety

significance and because it has been entered into your corrective action program, the NRC is

treating this violation as a non-cited violation (NCV) consistent with Section VI.A of the NRC

Enforcement Policy. If you contest this NCV, you should provide a response within 30 days of

the date of this inspection report, with the basis for your denial, to the United States Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with

copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United

States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident

Inspector at VEGP.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document Room

SNC 2

or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA by Curt Rapp For/

Malcolm T. Widmann, Chief

Reactor Projects Branch 2

Division of Reactor Projects

Docket Nos.: 50-424, 50-425

License Nos.: NPF-68, NPF-81

Enclosure: Inspection Report 05000424/2005004 and

05000425/2005004

w/Attachment: Supplemental Information

cc w/encl: (See page 3)

SNC 3

cc w/encl:

J. T. Gasser Attorney General

Executive Vice President Law Department

Southern Nuclear Operating Company, Inc. 132 Judicial Building

Electronic Mail Distribution Atlanta, GA 30334

T. E. Tynan Laurence Bergen

General Manager, Plant Vogtle Oglethorpe Power Corporation

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Resident Manager

N. J. Stringfellow Oglethorpe Power Corporation

Manager-Licensing Alvin W. Vogtle Nuclear Plant

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Director, Consumers' Utility Counsel Arthur H. Domby, Esq.

Division Troutman Sanders

Governor's Office of Consumer Affairs Electronic Mail Distribution

2 M. L. King, Jr. Drive

Plaza Level East; Suite 356 Senior Engineer - Power Supply

Atlanta, GA 30334-4600 Municipal Electric Authority

of Georgia

Office of the County Commissioner Electronic Mail Distribution

Burke County Commission

Waynesboro, GA 30830 Reece McAlister

Executive Secretary

Director, Department of Natural Resources Georgia Public Service Commission

205 Butler Street, SE, Suite 1252 244 Washington Street, SW

Atlanta, GA 30334 Atlanta, GA 30334

Manager, Radioactive Materials Program Distribution w/encl: (See page 4)

Department of Natural Resources

Electronic Mail Distribution

_________________________

OFFICE RII/DRP RII/DRP RII/DRP RII/DRP RII/DRP RII/DRP RII/DRP

SIGNATURE CWR1 GJM1 email BCA1 email NXG fax DCA fax DSS email JAH5 email

NAME CRapp:rcm GMcCoy BAnderson NGarrett DArnett DSimpkins JHickey

DATE 10/28/05 10/28/05 10/27/05 10/27/05 10/27/05 10/27/05 10/27/05

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICE RII/DRP RII/DRP RII/DRS RII/DRS RII/DRS RII/DRS

SIGNATURE SPS email LRM for JXD2 LRM for ADN JLK1

NAME SSanchez WLoo JDiazVelez HGepford ANielsen JKreh

DATE 10/27/05 10/28/05 10/27/05 10/28/05 10/26/05 10/28/05 10/ /2005

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos.: 50-424, 50-425

License Nos.: NPF-68, NPF-81

Report Nos.: 05000424/2005004 and 05000425/2005004

Licensee: Southern Nuclear Operating Company, Inc.

Facility: Vogtle Electric Generating Plant

Location: 7821 River Road

Waynesboro, GA 30830

Dates: July 1 - September 30, 2005

Inspectors: G. McCoy, Senior Resident Inspector

B. Anderson, Resident Inspector

N. Garrett, Senior Resident Inspector, Surry

D. Arnett, Resident Inspector, Surry

D. Simpkins, Senior Resident Inspector, Hatch

J. Hickey, Resident Inspector, Hatch

S. Sanchez, Resident Inspector, St. Lucie

J. Kreh, Emergency Preparedness Inspector

(Sections 1EP2-1EP5 and 4OA1)

W. Loo, Senior Health Physicist (Sections 2OS1, 2OS3, 4OA1,

and 4OA5)

J. Díaz Vélez, Health Physicist (Section 2OS3)

H. Gepford, Health Physicist (Section 2PS3)

A. Nielsen, Health Physicist (Section 2PS1 and 4OA1)

Approved by: Malcolm T. Widmann, Chief

Reactor Projects Branch 2

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000424/2005-004, 05000425/2005-004; 07/01/2005 - 09/30/2005; Vogtle Electric

Generating Plant, Units 1 and 2; Radiation Monitoring Instrumentation and Protective

Equipment.

The report covered a three-month period of inspection by seven resident inspectors, one

emergency preparedness inspector, and three health physicists. One Green non-cited violation

was identified. The significance of most findings is indicated by their color (Green, White,

Yellow, or Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination

Process (SDP). Findings for which the SDP does not apply may be Green or be assigned a

severity level after management review. The NRCs program for overseeing the safe operation

of commercial nuclear power reactors is described NUREG-1649, Reactor Oversight Process,

Revision 3, dated July 2000.

A. NRC-Identified and Self-Revealing Findings

Emergency Preparedness Cornerstone

for the failure to provide adequate respiratory protection equipment for emergency

response, compromising the protective actions developed for the plume exposure

pathway for emergency workers.

This finding is greater than minor because it is associated with the Emergency

Preparedness cornerstone attribute of Response Organization Performance and

adversely affects the cornerstone objective of ensuring the licensee is capable of

implementing adequate measures to protect the health and safety of the public in the

event of a radiological emergency. Failure to provide appropriate respiratory

protective equipment for a required worker could result in the individual being unable

to perform his emergency response function. The finding was evaluated using the

Emergency Preparedness Significance Determination Process, Sheet 1. The finding

was a failure to comply that was a planning standard problem, was not a

risk-significant planning standard problem, and did not involve a planning standard

function failure. For these reasons, the inspectors concluded that the issue is of very

low safety significance. (Section 2OS3)

B. Licensee-Identified Violations

None

Enclosure

REPORT DETAILS

Summary of Plant Status

Unit 1 operated at essentially full rated thermal power (RTP) for this report period.

Unit 2 operated at essentially full RTP until September 18 when the unit was shutdown for a

planned refueling outage.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

1R04 Equipment Alignment

a. Inspection Scope

Partial Walk-downs. The inspectors performed partial walk-downs of the following three

systems to verify correct system alignment. The inspectors checked for correct valve

and electrical power alignments by comparing positions of valves, switches, and

breakers to the procedures and drawings listed in the Attachment. Additionally, the

inspectors reviewed the condition report (CR) database to verify that equipment

alignment problems were being identified and appropriately resolved. Documents

reviewed are listed in the Attachment.

C Unit 2 nuclear service cooling water (NSCW) system while the number 3 NSCW pump

was out of service for maintenance

C Unit 1 essential chilled water system after significant maintenance

C Unit 1 number 2 condensate storage tank while the number 1 condensate storage

tank was tagged out for maintenance

b. Findings

No findings of significance were identified.

1R05 Fire Protection

a. Inspection Scope

The inspectors walked down the following eight plant areas to verify the licensee was

controlling combustible materials and ignition sources as required by procedures

92015-C, Use, Control, and Storage of Flammable/Combustible Materials, and 92020-C,

Control of Ignition Sources. The inspectors assessed the observable condition of fire

detection, suppression, and protection systems and reviewed the licensees fire

protection Limiting Condition for Operation log and CR database to verify that the

corrective actions for degraded equipment were identified and appropriately prioritized.

The inspectors also reviewed the licensees fire protection program to verify the

requirements of Updated Final Safety Analysis Report (UFSAR) Section 9.5.1, Fire

Enclosure

2

Protection Program, and Appendix 9A, Fire Hazards Analysis, were met. Documents

reviewed are listed in the Attachment.

C Unit 1 train A cable spreading room

C Unit 1 control building level 2

C Unit 1 train A diesel generator

C Unit 1 auxiliary feedwater pump building

C North fire water pump house

C Technical support center

C Unit 2 train A NSCW pump house

C South fire water pump house

b. Findings

No findings of significance were identified.

1R08 Inservice Inspection (ISI) Activities

a. Inspection Scope

Piping Systems ISI. The inspectors reviewed the implementation of the licensees ISI

program for monitoring degradation of the reactor coolant system boundary and the risk

significant piping system boundaries for Unit 2. The inspectors selected a sample of

American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,

Section XI required examinations and Code components in order of risk priority as

identified in Section 03 of NRC inspection procedure 71111.08, Inservice Inspection

Activities, based upon the ISI activities available for review. The inspectors also

conducted an on-site review of nondestructive examination (NDE) activities to evaluate

compliance with Technical Specifications (TS), ASME Section XI, and ASME Section V

requirements, 1989 Edition, to verify that indications and any defects were appropriately

evaluated and dispositioned in accordance with the requirements of ASME Section XI,

IWB-3000 or IWC-3000 acceptance standards. The inspectors observed the following

examinations:

Ultrasonic Testing (UT)

C Component #: 21201-V6-001-B02R, Reactor Head Closure Studs

C Component #: 21201-V6-001-B26R, Reactor Head Closure Studs Weld #: 21201-B6-

003-W05, Lower Cone End Stub Barrel to Lower Shell Barrel-B

The inspectors reviewed the following examination records:

UT

C Weld #: 21201-031-3, Reactor Coolant System pipe to elbow

C Weld #: 21201-042-2, Reactor Coolant System pipe to elbow

C Weld #: 21201-046-2, Reactor Coolant System pipe to elbow

Enclosure

3

Visual Testing (VT):

C Reactor Vessel Head Penetrations above insulation

C Component #: 21201-V6-002W17, 6" Safety Nozzle to Safe End Weld

C Component #: 21201-V6-002W18, 6" Safety Nozzle to Safe End Weld

C Component #: 21201-V6-002W19, 6" Safety Nozzle to Safe End Weld

C Component #: 21201-V6-002W20, 6" Relief Nozzle to Safe End Weld

C Component #: 21201-V6-002W21, 4" Spray Nozzle to Safe End Weld

Magnetic Particle Testing

C Component #: 21201-B6-002-W19, 16" Main Feedwater Nozzle to Shell Weld

Liquid Penetrant Testing

C Component #: 21208P6-002-W01, Pump Casing To 6" Suction Nozzle Weld

C Component #: 21204-063-16, Support H006

C Component #: 21208-411-6, Support H006

The Inspectors reviewed examination records for the following recordable indications to

evaluate if the licensees acceptance was in accordance with acceptance standards

contained in Article IWB-3000 of ASME Section XI.

UT

C Component #: 2-CV-110, CVCS Orifice to Orifice Reducer

VT

C Component #: 21201-B6-003-I10, Steam Generator #3 Channel Head Drain Tube

(WCAP 12907)

C Component #: 21201-B6-001-I10, Steam Generator #1 Channel Head Drain Tube

(WCAP 12907)

C Component #: 21501-024-H003, Hanger U-bolt nuts

C Component #: 21201-P6-002-B25-B32, 1.5" Dia. Sealwater Housing Cap Screws

C Component #: 21501-024-H003, Restraint

The inspectors reviewed the Vogtle, Unit 2, Owners Report For Inservice Inspection,

Tenth Maintenance/Refueling Outage, dated August, 2004, which stated that there were

no reportable indications from last outage.

Qualification and certification records for examiners, inspection equipment, and

consumables along with the applicable NDE procedures for the above ISI examination

activities were reviewed and compared to requirements stated in ASME Section V and

Section XI.

The inspectors reviewed the following three pressure boundary welding activities

associated with ASME Class 1 and Class 2 components were reviewed to verify the

welding process and examinations were performed in accordance with the ASME Code

Sections III, V, IX, and XI requirements.

Enclosure

4

C Weld #: 1K2-1305-157-01, Main Feed Water pipe segment between weldolet and first

downstream elbow

C Weld #: 040502A, Auxiliary Feed Water Pipe to Sweepolet

C Weld #: 040502B, Auxiliary Feed Water Pipe to Elbow

The inspectors performed a review of piping system ISI related problems that were

identified by the licensee and entered into the corrective action program. The inspectors

reviewed these corrective action documents to confirm that the licensee had

appropriately described the scope of the problems. Additionally, the inspectors review

included confirmation that the licensee had an appropriate threshold for identifying

issues and had implemented effective corrective actions. The inspectors evaluated the

threshold for identifying issues through interviews with licensee staff and review of

licensee actions to incorporate lessons learned from industry issues related to the ISI

program. Documents reviewed are listed in the Attachment.

Boric Acid Corrosion Control (BACC) ISI. The inspectors reviewed the licensees BACC

program to ensure compliance with commitments made in response to NRC Generic Letter 88-05, Boric Acid Corrosion of Carbon Steel Reactor Pressure Boundary, and

Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant

Pressure Boundary Integrity.

The inspectors conducted a record review and walk-down of parts of the reactor building

that are not normally accessible during at-power operations to evaluate compliance with

licensee BACC program requirements. In particular, the inspectors verified that the

visual examinations focused on locations where boric acid leaks can cause degradation

of safety significant components and that degraded or non-conforming conditions were

properly identified in the licensees corrective action system.

The inspectors reviewed a sample of engineering evaluations completed for boric acid

found on reactor coolant system piping and components to verify that the minimum

design code required section thickness had been maintained for the affected

component(s). The inspectors also reviewed the following licensee corrective actions

implemented for evidence of boric acid leakage to confirm that they were consistent with

requirements of Section XI of the ASME Code.

C CR 205106370, Boron residue present on the pipe coupling between 2HV10953 and

the containment penetration

C CR 2005108224, Accumulation of boric acid build up surrounding nipple below pipe

cap on SI Accumulator #4

C CR 2005108220, Heavy boron build-up residue below pipe cap for series vent valves

2-1208-X4-461 and 2-1208-X4-478

Steam Generator (SG) Tube ISI. The inspectors reviewed the Unit 2 SG tube

examination activities conducted pursuant to TS and the ASME Code Section XI

requirements. The inspectors reviewed the SG examination scope, expansion criteria,

eddy current testing (ET) acquisition procedures, ET analysis procedures, the SG

Enclosure

5

Operational Assessment, in-situ tube pressure testing procedures and records and

examination reports to confirm that:

C The numbers and sizes of SG tube flaws/degradation identified was bounded by the

licensees previous outage Operational Assessment predictions. Also, the SG tube ET

examination scope and expansion criteria was sufficient to identify tube degradation

based on site and industry operating experience by confirming that the ET scope

completed was consistent with the licensees procedures and plant TS requirements.

Additionally, the inspectors reviewed the SG tube ET examination scope to determine

that it was consistent with that recommended in EPRI 1003138 Pressurized Water

Reactor Steam Generator Examination Guidelines and included tube areas which

represent ET challenges such as the tubesheet regions, expansion transitions, U-

bends and support plates.

C The SG tube repair criteria and process (plugging) implemented was consistent with

TS requirements and the licensee was only applying the TS plugging limit at tube wear

locations.

C The ET probes and equipment configurations used to acquire ET data from the SG

tubes were qualified to detect the known/expected types of SG tube degradation in

accordance with Appendix H Performance Demonstration for Eddy Current

Examination of EPRI 1003138 Pressurized Water Reactor Steam Generator

Examination Guidelines.

C The licensee adequately examined for loose parts indications.

C The licensee adequately evaluated for any contractor deviations from their ET data

acquisition or analysis procedures or EPRI 1003138, Pressurized Water Reactor

Steam Generator Examination Guidelines: Revision 6.

The inspectors performed a review of SG ISI related problems that were identified by

the licensee and entered into the corrective action program to confirm that the licensee

had appropriately described the scope of the problems. Additionally, the inspectors

review included confirmation that the licensee had an appropriate threshold for

identifying issues and had implemented effective corrective actions. The inspectors

evaluated the threshold for identifying issues through interviews with licensee staff and

review of licensee actions to incorporate lessons learned from industry issues related to

the ISI program. Documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were found.

Enclosure

6

1R11 Licensed Operator Requalification

a. Inspection Scope

Resident Quarterly Review. The inspectors evaluated operator performance on July 26,

2005 during licensed operator simulator training associated with Requalification

Segment 20054 and described on simulator exercise guide V-RQ-SE-05401. The

simulator scenario covered operator actions resulting from a loss of class 1E 125V DC

followed by an uncontrolled continuous rod motion and a failure of the plant to trip.

Procedures reviewed are listed in the attachment. The inspectors specifically assessed

the following areas:

C Correct use of the abnormal and emergency operating procedures

C Ability to identify and implement appropriate actions in accordance with the

requirements of the Technical Specifications

C Clarity and formality of communications in accordance with procedure 10000-C,

Conduct of Operations

C Proper control board manipulations including critical operator actions

C Quality of supervisory command and control

C Effectiveness of post-evaluation critique

b. Findings

No findings of significance were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed the following equipment problem and associated licensee CRs

to evaluate the effectiveness of the licensees handling of equipment performance

problems and to verify the licensees maintenance efforts met the requirements of 10

CFR 50.65 (the Maintenance Rule) and licensee procedure 50028-C, Engineering

Maintenance Rule Implementation. The reviews included adequacy of the licensees

failure characterization, establishment of performance criteria or 10 CFR 50.65 (a)(1)

performance goals, and adequacy of corrective actions. Other documents reviewed

during this inspection included control room logs, system health reports, the

maintenance rule database, and maintenance work orders (MWOs). Also, the

inspectors interviewed system engineers and the maintenance rule coordinator to

assess the accuracy of identified performance deficiencies and extent of condition.

Documents reviewed are listed in the Attachment.

C 2-2103-P4-003, Unit 2 train A number 3 component cooling water pump

b. Findings

No findings of significance were identified.

Enclosure

7

1R13 Maintenance Risk Assessments and Emergent Work Evaluation

a. Inspection Scope

The inspectors reviewed the following five plan of the day (POD) documents listed below

to verify that risk assessments were performed prior to components being removed from

service. The inspectors reviewed risk assessments and risk management controls

implemented for these activities to verify they were completed in accordance with

procedure 00354-C, Maintenance Scheduling, and 10 CFR 50.65(a)(4). The inspectors

also reviewed the CR database to verify that maintenance risk assessment problems

were being identified at the appropriate level, entered into the corrective action program,

and appropriately resolved.

C POD for the week of 7/23 - 7/29

C POD for the week of 7/30 - 8/5

C POD for the week of 8/6 - 8/12

C POD for the week of 8/20 - 8/26

C POD for the week of 9/10 - 9/16

b. Findings

No findings of significance were identified.

1R15 Operability Evaluations

a. Inspection Scope

The inspectors reviewed the following five evaluations to verify they met the

requirements of NMP-GM-002, Corrective Action Program, and NMP-002-GL02,

Corrective Action Program Details and Expectations Guideline. This scope included a

review of the technical adequacy of the evaluations, the adequacy of compensatory

measures, and the impact on continued plant operation.

C CR 2005106203, Unexpected Engine Not Available light during monthly surveillance

C CR 2005105732, Cooling water leak on unit 2 nuclear service cooling water pump 2

C CR 2005106036, Atmospheric relief valve 1PV3030 oil reservoir empty

C CR 2005106370, Boron residue on Unit 2 accumulator sample line

C CR 2005107704, 2HV0606 would not fully shut when residual heat removal (RHR)

train B was being placed in service.

b. Findings

No findings of significance were identified.

Enclosure

8

1R16 Operator Workarounds

a. Inspection Scope

The inspectors reviewed the licensees list of identified operator workarounds as of

August 15, 2005, to assess the cumulative effects of operator workarounds on the

reliability, availability, and potential for mis-operation of a system to verify that there was

no increase in overall plant risk. This assessment included increases of initiating event

frequencies, effects on multiple mitigating systems, and the ability of operators to

correctly respond to abnormal plant conditions.

b. Findings

No findings of significance were identified.

1R19 Post-Maintenance Testing

a. Inspection Scope

The inspectors either observed post-maintenance testing or reviewed the test results for

the following four maintenance activities to verify that the testing met the requirements

of procedure 29401-C, Work Order Functional Tests, for ensuring equipment operability

and functional capability was restored. The inspectors also reviewed the test

procedures to verify the acceptance criteria was sufficient to meet the TS operability

requirements.

C MWO 10523854, Repair of 1-PV-3030, main steam LP4 atmospheric relief inlet

C MWO 20522642, Repair of cooling leak on Unit 2 number 2 NSCW pump

C MWO 20516270, Preventive maintenance of Unit 2 B train RHR pump

C MWO 20411014, Preventive maintenance of Unit 2 A train coolant charging pump

b. Findings

No findings of significance were identified.

1R20 Refueling and Outage Activities

a. Inspection Scope

Unit 2 Refueling Outage. The inspectors performed the inspection activities described

below for the Unit 2 refueling outage that began on September 18, 2005. The

inspectors reviewed the licensees outage risk control plan to verify that the licensee had

appropriately considered risk, industry experience and previous site specific problems,

and to confirm that the licensee had mitigation/response strategies for losses of key

safety functions. During the cooldown which preceded the outage, the inspectors

reviewed portions of the cooldown process to verify that technical specification cooldown

restrictions were followed. The inspectors confirmed that, when the licensee removed

Enclosure

9

equipment from service, the licensee maintained defense-in-depth commensurate with

the outage risk control plan for key safety functions and applicable technical

specifications, and that configuration changes due to emergent work and unexpected

conditions were controlled in accordance with the outage risk control plan. During the

outage, the inspectors:

C Reviewed reactor coolant system (RCS) pressure, level, and temperature instruments

to verify that the instruments provided accurate indication and that allowances were

made for instrumentation errors

C Reviewed the status and configuration of electrical systems to verify that those

systems met TS requirements and the licensees outage risk control plan

C Observed decay heat removal parameters to verify that the system was properly

functioning and providing cooling to the core

C Reviewed system alignments to verify that the flow paths, configurations, and

alternative means for inventory addition were consistent with the outage risk plan

C Reviewed selected control room operations to verify that the licensee was controlling

reactivity in accordance with the technical specifications

C Observed spent fuel pool operations to verify that outage work was not impacting the

ability of the operations staff to operate the spent fuel pool cooling system during and

after core offload

C Reviewed the outage risk plan to verify that activities, systems, and/or components

which could cause unexpected reactivity changes were identified in the outage risk

plan and were controlled

C Observed licensee control of containment penetrations to verify that the requirements

of the technical specifications were met

C Reviewed the licensees plans for changing plant configurations to verify that technical

specifications, license conditions, and other requirements, commitments, and

administrative procedure prerequisites had been met

b. Findings

No findings of significance were identified.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors reviewed the following five surveillance test procedures and either

observed the testing or reviewed test results to verify that testing was conducted in

accordance with the procedures and that the acceptance criteria adequately

demonstrated that the equipment was operable. Additionally, the inspectors reviewed

the CR database to verify that the licensee had adequately identified and implemented

appropriate corrective actions for surveillance test problems. Documents reviewed are

listed in the Attachment.

Surveillance Tests

C 24376-1 Main Steam Atmospheric Relief Valve Control 1PV3000 Channel Calibration

Enclosure

10

C 24705-2, Nuclear Instrumentation System, Power Range Channel 2N42 Channel

Calibration

C 14980B-2, Diesel Generator Operability Test

In-Service Tests

C 14805-2, Residual Heat Removal Pump and Check Valve IST

Containment Isolation Valve Tests

C 14349-2, Containment Penetration No. 49 Excess Letdown and Seal Water Leakoff

Local Leak Rate Test

b. Findings

No findings of significance were identified.

1R23 Temporary Plant Modifications

a. Inspection Scope

The inspectors evaluated the following two Temporary Modifications (TM) and

associated 10 CFR 50.59 screening against the system design basis documentation

and the Updated Final Safety Analysis Report (UFSAR) to verify that the modifications

did not adversely affect the safety functions of important safety systems. Additionally,

the inspectors reviewed licensee procedure 00307-C, Temporary Modifications, to

assess if the modification was properly developed and implemented.

  • TM 2052247801, Defeat Unit 2 A turbine exhaust hood low pressure alarm and trip
  • TM 2052084801, Unit 2 temporary hot leg RCS level sight glass

b. Findings

No findings of significance were identified.

Cornerstone: Emergency Preparedness

1EP2 Alert and Notification System (ANS) Testing

a. Inspection Scope

The inspectors evaluated the adequacy of licensee methods for testing the ANS. The

applicable planning standard 10 CFR 50.47(b)(5) and related requirements contained in

Section IV.D of Appendix E to 10 CFR Part 50 were used as reference criteria. The

evaluation criteria contained in NUREG-0654, Criteria for Preparation and Evaluation of

Radiological Emergency Response Plans and Preparedness in Support of Nuclear

Power Plants; Federal Emergency Management Agency (FEMA) Report REP-10, Guide

for the Evaluation of Alert and Notification Systems for Nuclear Power Plants; and the

Enclosure

11

licensees FEMA-approved ANS design report were also used as references.

Documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were identified.

1EP3 Emergency Response Organization (ERO) Augmentation

a. Inspection Scope

The inspectors reviewed the ERO augmentation staffing requirements and the process

for notifying the ERO to ensure the readiness of key staff for responding to an event and

timely facility activation. The results of the unannounced off-hour augmentation drill

conducted on November 8, 2004 were reviewed. The inspectors reviewed the

provisions for a backup notification system. The qualification records of key position

ERO personnel were reviewed to ensure all ERO qualifications were current. A sample

of problems identified from augmentation drills or system tests performed since the last

inspection were reviewed to assess the effectiveness of corrective actions. The

applicable planning standard 10 CFR 50.47(b)(2) and related requirements contained in

Appendix E to 10 CFR Part 50 were used as reference criteria. Documents reviewed

are listed in the Attachment.

b. Findings

No findings of significance were identified.

1EP4 Emergency Action Level (EAL) and Emergency Plan Changes

a. Inspection Scope

The inspectors evaluated the non-administrative Emergency Plan changes and the

associated 10 CFR 50.54(q) reviews for Revisions 38, 39, and 40, along with affiliated

implementing procedures changes. No EAL modifications were made in the referenced

revisions, which were issued during the period from December 2004 to May 2005. The

current Emergency Plan is Revision 40. The applicable planning standard 10 CFR

50.47(b)(4) and related requirements contained in Appendix E to 10 CFR Part 50 were

used as reference criteria. Documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were identified.

Enclosure

12

1EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies

a. Inspection Scope

The inspectors reviewed the corrective actions identified through the EP program to

ascertain the significance of the issues and to determine whether repetitive problems

were occurring. The facilitys self-assessments and audits were reviewed to assess the

licensees ability to be self-critical, thus avoiding complacency and degradation of its EP

program. In addition, the inspectors reviewed the licensees self-assessments and

audits to assess the completeness and effectiveness of a sample of EP-related

corrective actions. The applicable planning standard, 10 CFR 50.47(b)(14) and related

requirements contained in Appendix E to 10 CFR Part 50 were used as reference

criteria. Documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were identified.

1EP6 Drill Evaluation

a. Inspection Scope

The inspectors observed and reviewed the emergency plan drill on August 17 to verify

the licensee was properly classifying emergency events, making required notifications,

and making appropriate protective action recommendations in accordance with

procedures 91001-C, Emergency Classification and Implementing Instructions, 91002-

C, Emergency Notifications, and 91305-C, Protective Action Guidelines. Additionally,

the inspectors observed the licensees critique to verify that performance weaknesses

and improvements were identified.

b. Findings

No findings of significance were identified.

2. RADIATION SAFETY

Cornerstone: Occupational Radiation Safety

2OS1 Access Control To Radiologically Significant Areas

a. Inspection Scope

Access Control. Licensee activities for monitoring workers and controlling access to

radiologically significant areas were inspected. The inspectors evaluated procedural

guidance and directly observed implementation of administrative and physical controls;

appraised radiation worker and technician knowledge of, and proficiency in

implementing Radiation Protection (RP) program activities; and assessed worker

exposures to radiation and radioactive material.

Enclosure

13

Radiological postings and material labeling were directly observed during tours of the

Auxiliary Building and external buildings. Inspectors conducted independent surveys in

the Auxiliary Building to verify posted radiation levels and to compare with current

licensee survey records. During plant tours, control of High Radiation Area (HRA) with

dose rates greater than 15 rem per hour and Very HRA keys and the physical status of

HRA doors were examined. In addition, the inspectors observed radiological controls for

non-fuel items stored in the spent fuel pools. The inspectors also reviewed selected RP

procedures and radiation work permits (RWPs), and discussed current access control

program implementation with RP supervisors.

During the inspection, radiological controls for select work activities in HRAs were

observed and discussed. These activities included the change out of the Unit 2 Spent

Fuel Pool (SFP) filter, activities associated with items being removed from the SFP, and

items being moved into the railroad bay. The inspectors observed workers adherence

to RWP guidance and Health Physics Technician (HPT) proficiency in providing job

coverage. Controls for limiting exposure to airborne radioactive material were reviewed

and operation of ventilation units and positioning of air samplers were also observed.

The inspectors evaluated electronic dosimeter alarm set points for consistency with

radiological conditions in Auxiliary Building. In addition, the inspectors interviewed

workers to assess knowledge of RWP requirements.

The inspectors evaluated worker exposures through review of data associated with

discrete radioactive particle and dispersed skin contamination events. Controls used for

monitoring extremity doses and the placement of dosimetry when work involved

significant dose gradients were reviewed. The inspectors discussed the processes that

would be used if an individual were to have an uptake of radioactive materials.

RP program activities were evaluated against 10 CFR Part 20; Regulatory Guide (RG)

8.38, Control of Access to High and Very High Radiation Areas in Nuclear Power Plants;

and approved licensee procedures. Documents reviewed are listed in the Attachment.

Problem Identification and Resolution. CRs and audits associated with radiological

controls, personnel monitoring, and exposure assessments were reviewed and

discussed with RP supervisors. The inspectors assessed the licensees ability to

identify, characterize, prioritize, and resolve the identified issues. Documents reviewed

are listed in the Attachment.

b. Findings

No findings of significance were identified.

2OS3 Radiation Monitoring Instrumentation and Protective Equipment

a. Inspection Scope

Radiation Monitoring Instrumentation and Post-Accident Sampling. During tours of the

Auxiliary Building and SFP area, the inspectors observed installed radiation detection

Enclosure

14

equipment including the following instrument types: Area Radiation Monitors,

Continuous Air Monitors, Personnel Contamination Monitors (PCMs), and components

of the Post-Accident Sampling System. The inspectors observed the physical location

of the components, noted the material condition, and compared sensitivity ranges with

the information contained in the UFSAR.

During equipment walk-downs, the inspectors observed functional checks of various

fixed and portable radiation monitoring/detection instruments. The observations

included source/response checks of PCM and portal monitoring (PM) equipment,

portable ion chambers and telepoles, Small Article Monitors (SAMs), and a Whole Body

Counter (WBC). The inspectors reviewed calibration records and discussed the

functional testing and testing intervals for selected PCM and PM equipment located at

the Radiologically Controlled Area (RCA) exits. PCM equipment detection capabilities

were demonstrated using a low-level mixed radionuclide source that was passed

through the equipment. The inspectors also observed demonstrations of instrument

calibrations, including a WBC, a telepole, a REM ball, and an Eberline RM-14. The

10 CFR Part 61 analysis for Dry Active Waste was reviewed to determine if calibration

and response check sources are representative of the plant source term.

The inspectors reviewed calibration records for select PCMs, PMs, SAMs, WBCs, and

Eberline RM-14s. In addition, calibration records were reviewed for Unit 2 RE-0005,

Unit 2 RE-0006, Unit 2 RE-0001 and Unit 2 RE-0008 radiation monitors. The records

were evaluated to determine frequency and adequacy of the calibrations. Calibration

stickers on portable survey instruments were noted during inspection of storage areas

for ready-to-use equipment.

Operability and reliability of selected radiation detection instruments were reviewed

against details documented in the following: 10 CFR Part 20; NUREG-0737, Clarification

of TMI Action Plan Requirements; TS Section 3; UFSAR Chapter 12; and applicable

licensee procedures. Documents reviewed are listed in the Attachment.

Self-Contained Breathing Apparatus (SCBA) and Protective Equipment. Selected SCBA

units staged for emergency use in the Control room and other locations were inspected

for material condition, air pressure, and number of units available. The inspectors also

reviewed maintenance records for components of selected SCBA units for the past five

years and certification records associated with supplied air quality.

Qualifications for licensee staff responsible for testing and repairing SCBA equipment

were evaluated through a review of manufacturer training certificates. In addition,

selected Control room operators were interviewed to determine their knowledge of

available SCBA equipment locations, including spectacles (corrective lens inserts) if

needed, and their training on bottle change-out during periods of extended SCBA use.

Respirator qualification records were reviewed for several Control room operators and

Maintenance department personnel assigned emergency response duties.

Licensee activities associated with maintenance and use of respiratory protection

equipment were reviewed against 10 CFR Part 20; RG 8.15, Acceptable Programs for

Enclosure

15

Respiratory Protection; American National Standards Institute (ANSI)-Z88.2-1992,

American National Standard for Respiratory Protection; and applicable licensee

procedures. Documents reviewed are listed in the Attachment.

Problem Identification and Resolution. CRs associated with instrumentation and

protective equipment were reviewed and assessed. The inspectors evaluated the

licensees ability to identify, characterize, prioritize, and resolve the identified issues.

Documents reviewed are listed in the Attachment.

b. Findings

Introduction. A NRC-identified Green non-cited violation (NCV) of 10 CFR 50.47(b)(10)

was identified for the failure to provide adequate respiratory protection equipment for

emergency response, compromising the protective actions developed for the plume

exposure pathway for emergency workers.

Description. During evaluation of SCBA units staged in the Control room for emergency

use, the inspectors observed ten units fitted with medium respirator masks. On top of

an adjacent emergency planning storage cabinet were two small respirator masks and

three large respirator masks. Through discussions with the licensee, it was determined

that these masks were placed on top of the storage cabinet on about May 2005, when

the licensee had identified the need to provide mask sizes other than medium. The

licensee identified this need based on control room staffing, which included personnel fit

tested for small, medium, and large-sized masks. Prior to May 2005, only medium-sized

masks had been staged in the control room. The inspectors noted that the licensee had

not entered this problem into their corrective action program.

Selected control room operators interviewed by the inspectors were knowledgeable in

the use and operation of SCBA units; however, some of the operators were not aware of

the location of the small and large masks.

A review of Licensee Procedure No. 47013-C, Inspection, Repair, Storage of Self

Contained Breathing Apparatus, showed that the monthly checks did not include the

inspection and storage of respirator masks in the control room which are separate from

the SCBA units. Although HPTs had been inspecting the extra masks during monthly

checks, it was not in their procedure to do so nor had they create any record of these

inspections. The inspectors noted that the licensee provided additional respirator masks

in small and large sizes for SCBA units used by the fire brigade and that these masks

were inside sealed bags with current inspection tags and were placed in a closed

cabinet with a tamper proof seal. In contrast, the extra masks in the Control room were

stored in the manufacturers boxes inside of open plastic bags that had no inspection

tags or a tamper proof seal.

Regulatory Guide 8.15, Acceptable Programs for Respiratory Protection, Section 4.5,

states in part, that persons may only be issued face-sealing respirators for which they

have been tested. Prior to May 2005, in the event of an emergency requiring immediate

respiratory protection, the individuals who were fit tested using small or large masks

Enclosure

16

would not have been qualified to use the pre-staged, SCBA equipment and may have

been unable to perform their function as emergency responders. A licensed operator

may need an SCBA in the event the control room becomes uninhabitable, must

evacuate the control room, or must perform emergency response functions in a

hazardous environment outside of the control room.

Analysis. This finding is greater than minor because it is associated with the Emergency

Preparedness cornerstone attribute of Response Organization Performance and

adversely affects the cornerstone objective in that failure to provide appropriate

respiratory protective equipment could result in control room operators being unable to

perform their emergency response functions. The finding was evaluated using the

Emergency Preparedness Significance Determination Process, Sheet 1. The finding

was a failure to comply that was a planning standard problem, was not a risk-significant

planning standard problem, and did not involve a planning standard function failure. For

these reasons, the inspectors concluded that the issue is of very low safety significance.

Although the licensee identified the need for additional respirator mask sizes in the

control room, the licensees corrective actions were incomplete in that operators were

not made aware of the location of the new masks and Procedure No. 47013-C was not

updated to include them on the monthly surveillance check. The licensee was not

aware of these additional issues until they were identified by the inspectors. Therefore,

this finding is being treated as an NRC-identified finding. This finding involved the

cross-cutting aspect of problem identification and resolution in the area of resolution.

Enforcement. 10 CFR 50.47(b)(10) states, in part, that a range of protective actions will

be developed for the plume exposure pathway Emergency Planning Zone (EPZ) for

emergency workers. Contrary to the above, prior to May 2005, the licensee failed to

provide adequate respiratory protective equipment, i.e., small and large size SCBA

respirator masks, for licensed plant operators with emergency response functions.

Because the failure to comply with 10 CFR 50.47(b)(10) is of very low safety

significance and has been entered into the licensees corrective action program (CRs

2005107596 and 2005107597), this violation is being treated as a non-cited violation

(NCV), consistent with Section VI.A of the NRC Enforcement Policy: NCV

05000424,425/2005004-01, Failure to Provide Adequate Respiratory Protection

Equipment for Emergency Response.

Cornerstone: Public Radiation Safety

2PS1 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems

a. Inspection Scope

Effluent Monitoring and Radwaste Equipment. During inspector walk-downs, accessible

sections of the Unit 1/Unit 2 liquid and gaseous Radioactive Waste (Radwaste) and

effluent systems were assessed for material condition and conformance with system

design diagrams. The inspection included floor drain tanks, liquid waste system piping,

Waste Liquid Effluent Monitor (RE-18), Nuclear Service Water Process Monitors (RE-

Enclosure

17

20A & B), waste gas decay tanks, Containment Vent Effluent Monitors (RE-2565A, B, &

C), Plant Vent Effluent Monitors (RE-12442A, B, & C), and associated airborne effluent

sample lines. The inspectors interviewed chemistry supervision regarding Radwaste

equipment configuration and effluent monitor operation.

The inspectors reviewed performance records and calibration results for selected

radiation monitors, flowmeters, and air filtration systems. For Unit 1/Unit 2 monitors RE-

20 and RE-2565 the inspectors reviewed Control room channel check logs for June

2005 and the two most recent isotopic calibration records. The last two surveillances on

the Unit 1/Unit 2 Containment Purge High Efficiency Particulate Air/charcoal air

treatment system were also reviewed. The inspectors evaluated out-of-service effluent

monitors and compensatory action data for the period August 2003 - September 2005.

In addition, 2-RE-2565A and 2-RE-12442A stack versus sample line flow rates were

reviewed and discussed with chemistry staff to evaluate the adequacy of isokinetic

sampling.

Installed configuration, material condition, operability, and reliability of selected effluent

sampling and monitoring equipment were reviewed against details documented in the

following: 10 CFR Part 20; RG 1.21, Measuring, Evaluating and Reporting Radioactivity

in Solid Wastes and Releases of Radioactive Materials In Liquid and Gaseous Effluents

from Light-Water Cooled Nuclear Power Plants; ANSI - N13.1-1969, Guide to Sampling

Airborne Radioactive Materials in Nuclear Facilities; TS Section 5; the Offsite Dose

Calculation Manual (ODCM), Rev. 21; and UFSAR, Chapter 11. Procedures and

records reviewed are listed in the Attachment.

Effluent Release Processing and Quality Control (QC) Activities. The inspectors directly

observed the weekly collection of airborne effluent samples from the Unit 2 Plant Vent

(monitors 2-RE-12442 and 2-RE-12444). Chemistry technician proficiency in collecting,

processing, and counting the samples, as well as preparing the applicable release

permits was evaluated.

QC activities regarding gamma spectroscopy and beta-emitter detection were discussed

with count room technicians and Chemistry supervision. The inspectors reviewed daily

QC data logs from January 1, 2005, to September 14, 2005, for High Purity Germanium

(HPGe) detectors No. 1 & 3, and reviewed licensee procedural guidance for count room

QC. The inspectors also reviewed the two most recent calibration records for HPGe

detector No. 1 and the Beckman 6500 liquid scintillation counter. In addition, results of

the 2004 and 2005 radiochemistry cross-check program were reviewed.

Selected parts of three procedures for effluent sampling, processing, and release were

evaluated for consistency with licensee actions. Two liquid and four gaseous release

permits were reviewed against ODCM specifications for pre-release sampling and

effluent monitor setpoints. For two of the gaseous releases, independent calculations

were performed to evaluate reported doses to the public from airborne radionuclides.

The inspectors also reviewed the 2003 and 2004 annual effluent reports to evaluate

reported doses to the public and to review ODCM changes.

Enclosure

18

Observed task evolutions, count room activities, and offsite dose results were evaluated

against details and guidance documented in the following: 10 CFR Part 20 and

Appendix I to 10 CFR Part 50; ODCM; RG 1.21; RG 1.109, Calculation of Annual Doses

to Man from Routine Releases of Reactor Effluents for the Purpose of Evaluating

Compliance with 10 CFR Part 50 Appendix I; RG 1.33, Quality Assurance Program

Requirements (Operation); and TS Section 5. Procedures and records reviewed are

listed in the Attachment.

Problem Identification and Resolution. Four CRs and one Quality Assurance Audit

associated with effluent release activities were reviewed and assessed. The inspectors

evaluated the licensees ability to identify, characterize, prioritize, and resolve selected

issues. Documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were identified.

2PS3 Radiological Environmental Monitoring Program (REMP) and Radioactive Material

Control Program

a. Inspection Scope

REMP Implementation. The inspectors observed collection of environmental samples

and surveillance of sampling instruments during the licensees weekly environmental

run. The inspectors noted the material condition and operability of airborne particulate

and iodine sampling stations at monitoring location Nos. 3, 7, 10, 12, 16, and 35.

Environmental thermoluminescent dosimeter (TLD) Nos. 6, 7, 12, 15, 16, 35, 44, and 47

were checked for material condition. The inspectors also observed the collection of a

milk sample from Dixon Dairy. The inspectors determined the current location of

selected air samplers, TLDs, and vegetation sampling stations using NRC global

positioning system instrumentation and compared the results with ODCM data. Land

use census results and sample collection/processing activities were discussed with

environmental technicians.

The inspectors reviewed the previous calibration records for the environmental air

samplers and observed performance of the current rotameter calibrations at each air

sampling location by the technicians. The inspectors also reviewed the 2003 and 2004

REMP reports, results of the 2003 and 2004 interlaboratory cross-check program, and

procedures for environmental sample collection and processing. The inspectors

discussed missed samples/inoperable samplers reported in the REMP reports, detection

capabilities, and cross-check results with cognizant personnel.

Program implementation, sampling locations, and environmental monitoring results were

reviewed against: 10 CFR Part 20; Appendix I to 10 CFR Part 50; TS 5.5; ODCM; RG

4.15, Quality Assurance for Radiological Monitoring Programs (Normal Operation) -

Effluent Streams and the Environment; and Branch Technical Position, An Acceptable

Enclosure

19

Radiological Environmental Monitoring Program - 1979. Documents reviewed are listed

in the Attachment.

Meteorological Monitoring Program. During a walk-down of the meteorological tower

and associated equipment, the inspectors observed the physical condition of the tower

and discussed equipment operability and maintenance history with cognizant licensee

personnel. The inspectors compared locally generated meteorological data with

information available to control room operators. For the primary meteorological

measurements of wind speed, wind direction, and temperature, the inspectors reviewed

calibration records for applicable tower instrumentation and evaluated measurement

data recovery for calendar years 2003 and 2004.

Licensee procedures and activities related to meteorological monitoring were evaluated

against: ODCM; UFSAR Section 2.3; ANSI/ANS-2.5-1984, Standard for Determining

Meteorological Information at Nuclear Power Sites; and Safety Guide 23, Onsite

Meteorological Programs. Documents reviewed are listed in the Attachment.

Unrestricted Release of Materials from the RCA. The inspectors observed surveys of

material and personnel being released from the RCA using SAM, PCM, and PM

instruments. The inspectors also observed source checks of these instruments and

discussed equipment sensitivity and release program guidance with licensee staff.

To evaluate the appropriateness and accuracy of release survey instrumentation,

radionuclides identified within recent waste stream analyses were compared against the

radionuclides used in current calibration sources and performance check sources. The

inspectors also reviewed the last two calibration records for SAM instruments at the HP

Control Point and Unit 2 Containment.

Licensee programs for monitoring materials and personnel released from the RCA were

evaluated against: 10 CFR Part 20 and IE Circular 81-07, Control of Radioactively

Contaminated Material. Documents reviewed are listed in the Attachment.

Problem Identification and Resolution. The inspectors reviewed audits and CRs

involving environmental monitoring, meteorological monitoring, and release of

radioactive materials. The inspectors evaluated the licensees ability to identify,

characterize, prioritize, and resolve the identified issues. Documents reviewed are listed

in the Attachment.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA1 Performance Indicator (PI) Verification

a. Inspection Scope

Enclosure

20

The inspectors sampled licensee records to verify the accuracy of reported PI data for

the periods listed below. To verify the accuracy of the reported PI elements, the

reviewed data were assessed against guidance contained in NEI 99-02, "Regulatory

Assessment Indicator Guideline," Revision (Rev.) 3, and the NEI Frequently Asked

Questions list.

Occupational Radiation Safety Cornerstone

  • Occupational Exposure Control Effectiveness

The inspectors reviewed the PI results for the period of May 2004 through June 2005.

The inspectors reviewed HP shift log entries, electronic dosimeter alarm logs, and

licensee procedural guidance for collecting and documenting PI data. CRs were

reviewed for uptakes and abnormal TLD results. Documents reviewed are listed in the

Attachment.

Public Radiation Safety Cornerstone

  • Radiological Effluent Technical Specifications (RETS)/ODCM Effluent Occurrences

The inspectors reviewed the PI results for the April 2004 through June 2005. The

inspectors reviewed cumulative and projected doses to the public, out-of-service effluent

radiation monitor data logs, and two CRs related to Radiological Environmental

Technical Specifications/ODCM issues. The inspectors also reviewed licensee

procedural guidance for collecting and documenting PI data. Documents reviewed are

listed in the Attachment.

b. Findings

No findings of significance were identified.

4OA2 Identification and Resolution of Problems

a. Inspection Scope

Daily Screening. As required by Inspection Procedure 71152, Identification and

Resolution of Problems, and in order to help identify repetitive equipment failures or

specific human performance issues for follow-up, the inspectors performed a daily

screening of items entered into the licensees corrective action program. This review

was accomplished by either attending daily screening meetings that briefly discussed

major CRs, or accessing the licensees computerized corrective action database and

reviewing each CR that was initiated.

Annual Sample Review. The inspectors reviewed CR 2005103739 to evaluate the

effectiveness of the licensees corrective actions associated with the licensees failure to

obtain a relaxation of the requirements for NRC Order EA-03-009 prior to the restart of

Unit 1 on April 9, 2005, following a refueling outage. This NRC order required the

Enclosure

21

performance of specific inspections of the reactor pressure vessel head and head

penetration nozzles to be completed prior to the end of the 1R12 refueling outage. The

licensee had performed inspections of the reactor pressure vessel head and head

penetration nozzles during an outage in October 2004. In a written response dated

March 8, 2004, the licensee noted that the visual inspections were limited by

inaccessible areas of the reactor pressure vessel head. In this response, the licensee

requested relaxation from some specific requirements of the order and provided

justification for the request. This relaxation was required in order to restart Unit 1 after

refueling outage 1R12. On May 16, 2005, during a record review following the

completion of 1R12, the licensee discovered that the required relaxation had not been

received from the NRC. The licensee contacted the NRC to determine the status of the

relaxation. On September 13, 2005, the NRC completed an evaluation of the licensees

request and granted the requested relaxation from Order EA-03-009. The inspectors

reviewed the condition report and discussed the resulting corrective actions with the

licensee.

b. Findings and Observations

No findings of significance were identified. The fact that the licensee restarted Unit 1 on

April 9, 2005, but had not received a relaxation from order EA-03-009 is a violation of

NRC requirements. This is considered a minor violation because it is a licensing issue

with no safety significance. The licensee had properly submitted a request for the

relaxation in a timely manner with suitable justification. The inspectors determined that

the licensees corrective actions were adequate and would reasonably prevent the issue

from occurring in the future.

4OA5 Other

.1 (Closed) Temporary Instruction (TI) 2515/160, Pressurizer Penetration Nozzles and

Steam Space Piping Connections in U.S. Pressurized Water Reactors (NRC Bulletin

2004-01)

The inspectors reviewed the licensees 60-day response to NRC Bulletin 2004-01, dated

July 27, 2004, to verify that the licensees inspection activities conducted during this

outage were consistent with the their response. The inspectors conducted an

independent walk-down of the top of the pressurizer to ensure that the physical

conditions of the pressurizer penetrations and welds were clean and accessible for the

prescribed inspections and that there were no debris, insulation, dirt, boron from other

sources, physical layout, or viewing obstructions which could have interfered with the

identification of relevant indications. The inspectors observed or reviewed

documentation for the following components:

C Component #: 21201-V6-002W17, 6" Safety Nozzle to Safe End Weld

C Component #: 21201-V6-002W18, 6" Safety Nozzle to Safe End Weld

C Component #: 21201-V6-002W19, 6" Safety Nozzle to Safe End Weld

C Component #: 21201-V6-002W20, 6" Relief Nozzle to Safe End Weld

C Component #: 21201-V6-002W21, 4" Spray Nozzle to Safe End Weld

Enclosure

22

Reporting Requirements are as follows:

a. For each of the examination methods used during the outage, was the examination:

1. Performed by qualified and knowledgeable personnel? (Briefly describe the

personnel training/qualification process used by the licensee for this activity.)

The licensee used knowledgeable staff members certified as Level II, VT-1

examiners.

2. Performed in accordance with demonstrated procedures?

The inspectors reviewed records and photographs of the bare metal inspection of

the pressurizer penetrations in accordance with procedure ES-MISN-V-715,

Version 1.0, Visual Examination (VT-1). The inspectors also performed and

independent walk-down of the top of the pressurizer to verify the licensees

results.

3. Able to identify, disposition, and resolve deficiencies?

The inspectors concluded that the licensees direct visual examinations were

capable of detecting leakage from cracking in pressurizer penetrations if it had

existed. This conclusion was based upon the inspectors' direct observations of

pressurizer penetration locations, which were free of debris or deposits that could

mask evidence of leakage in the areas examined. The inspectors also verified

that the licensees procedures included guidance for proper disposition and

investigation of any identified deficiencies.

4. Capable of identifying the leakage in pressurizer penetration nozzle or steam

space piping components, as discussed in NRC Bulletin 2004-01?

The inspectors verified that the licensees examination personnel were capable of

identifying any leakage in pressurizer penetration nozzles or steam space piping

components.

b. What was the physical condition of the penetration nozzle and steam space piping

components in the pressurizer system (e.g., debris, insulation, dirt, boron from other

sources, physical layout, viewing obstructions)?

Through discussions with licensee personnel, the inspectors verified that the

insulation had been removed so as not to disrupt any potential indications of boric

acid leakage from the pressurizer at these penetration locations. The licensee

personnel performed a direct visual inspection of these pressurizer penetrations.

c. How was the visual inspection conducted (e.g., with video camera or direct visual by

the examination personnel)?

Enclosure

23

The licensees inspection personnel used the direct visual examination technique

along with a handheld mirror.

d. How complete was the coverage (e.g., 360° around the circumference of all the

nozzles)?

The licensee was able to view the entire circumference around each penetration.

e. Could small boron deposits, as described in the Bulletin 2004-01, be identified and

characterized?

The examination personnel were appropriately trained and qualified to identify small

boron deposits as described in the bulletin.

f. What material deficiencies (i.e., cracks, corrosion, etc.) were identified that required

repair?

There were no deficiencies identified that required repair.

g. What, if any, impediments to effective examinations, for each of the applied

methods, were identified (e.g., centering rings, insulation, thermal sleeves,

instrumentation, nozzle distortion)?

There were no impediments for an effective examination.

h. If volumetric or surface examination techniques were used for the augmented

inspections examinations, what process did the licensee use to evaluate and

dispose any indications that may have been detected as a result of the

examinations?

No augmented surface or volumetric examinations were performed.

I. Did the licensee perform appropriate follow-up examinations for indications of boric

acid leaks from pressure-retaining components in the pressurizer system?

There were no indications of boric acid leaks.

.2 (Closed) TI 2515/163, Operational Readiness of Offsite Power

Completion of this TI was documented in NRC Inspection Report

05000424,425/2005003. However, after an NRC headquarters review of the data

provided, additional information related to the TI was requested. The inspectors

collected this information from licensee discussions, site procedures and licensee

documentation. The information was subsequently provided to the headquarters staff

for further analysis.

Enclosure

24

.3 Temporary Instruction 2515/161, Transport of Control Rod Drive (CRD) in Type A

Packages

a. Inspection Scope

The inspectors reviewed shipping logs and discussed shipment of CRDs in Type A

packages with shipping staff. No shipments of CRDs in Type A packages were made

since January 1, 2002.

b. Findings

No findings of significance were identified.

4OA6 Meetings, Including Exit

On October 17, 2005, the resident inspectors presented the inspection results to Mr.

Tom Tynan and other members of his staff, who acknowledged the findings. The

inspectors confirmed that proprietary information was not provided or examined during

the inspection.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel:

R. Brown, Training and Emergency Preparedness Manager

C. Buck, Chemistry Manager

J. Robinson, Operations Manager

K. Dyar, Security Manager

T. Tynan, Nuclear Plant General Manager

I. Kochery, Health Physics Manager

J. Williams, Assistant General Manager - Plant Support

S. Swanson, Engineering Support Manager

R. Dedrickson, Assistant General Manager - Operations

NRC personnel:

M. Widmann, Chief, Reactor Project Branch 2

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000424,425/2005004-01 NCV Failure to Provide Adequate Respiratory Protection

Equipment for Emergency Response (Section 2OS3)

Closed

2515/160 TI Pressurizer Penetration Nozzles and Steam Space Piping

Connections in U.S. Pressurized Water Reactors (NRC

Bulletin 2004-01) (Section 4OA5.1)

2515/163 TI Operational Readiness of Offsite Power (Section 4OA5.2)

LIST OF DOCUMENTS REVIEWED

Section 1R04: Equipment Alignment

Procedures

13150-2, Nuclear Service Water Cooling System

13744-1, Essential Chilled Water System

13610-1, Auxiliary Feedwater System

13625-1, Condensate Storage and Degassifier System

Drawings

2X4D133-1, Nuclear Service Water Cooling System P&ID

2X4D133-2, Nuclear Service Water Cooling System P&ID

AX4AJ04-104, Cooled Motor Hot Gas Bypass P&ID

AX4AJ04-139, Emergency Safety Feature Chillers Line Diagram

AX4AJ04-140, ESF Chillers Line Diagram

AX4AJ04-141, ESF Chillers Line Diagram

1X4DB161-1, Auxiliary Feedwater System

Attachment

2

Section 1R05: Fire Protection

Procedures

92795-1, Zone 95 - Control Building Level A Fire Fighting Preplan

92820-1, Zone 120 - Control Building Level 2 Fire Fighting Preplan

92833B-1, Zone 133B, Control Building Level 2 Fire Fighting Preplan

92861-1, Zone 161, Diesel Generator Building Fire Fighting Preplan

92855-1, Zone 155, Auxiliary Feedwater Pumphouse - Train B Fire Fighting Preplan

92856-1, Zone 156, Auxiliary Feedwater Pumphouse Fire Fighting Preplan

92857A-1, Zone 157A, Auxiliary Feedwater Pumphouse - Train C Fire Fighting Preplan

92756B-1, Zone 56B, Control Building Level B Fire Fighting Preplan

92777B-1, Zone 77B, Control Building Level B Fire Fighting Preplan

92778B-1, Zone 78B, Control Building Level B Fire Fighting Preplan

92779B-1, Zone 79B, Control Building Level B Fire Fighting Preplan

92780-1, Zone 80, Control Building Level B Fire Fighting Preplan

92930-1, Zone 530, North Fire Water Pumphouse Fire Fighting Preplan

92931B-1, Zone 531, South Fire Water Pumphouse Fire Fighting Preplan

92921-1, Zone 601, Technical Support Center Fire Fighting Preplan

92860A-2, Zone 160A, NSCW Pumphouse - Train A Fire Fighting Preplan

Section 1R08: Inservice Inspection (ISI) Activities

Nondestructive Examination

ES-MISN-V-411, Version 2.0, Manual Ultrasonic Examination of Pressure Vessel Welds

(greater than 2" in thickness)

ES-MISN-V-715, Version 1.0, Visual Examination (VT-1)

ES-MISN-V-307, Version 1.0, Preservice and Inservice Inspection Documentation

ES-MISN-V-465, Version 1.0, Ultrasonic Thickness Examination Procedure

ES-MISN-V-735, Visual Examination (VT-3)

ES-MISN-V-505, Version 1.0, Magnetic Particle Testing

85060-C, Revision 11.1, Visual Examination For Leakage

14864-2, Revision 1.0, Containment General Leak Inspection

83201-C, Revision 6, Corrosion Assessment

Steam Generator

Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 2, Transmittal of

2R11 Steam Generator Degradation Assessment, September 9, 2005

Vogtle Electric Generating Plant, Units 1 and 2 Re: Issuance of Amendments Regarding the

Steam Generator Tube Surveillance Program, September 21, 2005

MRS 2.4.2 GPC-37, Revision 11, Steam Generator Eddy Current Data Analysis Techniques For

Vogtle Units 1 & 2

SGS-06-026, Vogtle Data Cop Guidelines

Corrective Action Documents

CR 2004001842, Ultrasonic thickness measurements for ISI Point 2CV-110 were below the

12.5% , mill spec. tolerance.

CR 2005108176, Reduction in wall thickness for piping between CVCS letdown orifices

(2FO0200, 2FO0201, 2FO0202) an valves 2HV8149A, B, C.

CR 2005106370, Boron residue on the pipe coupling between 2HV10953 and the containment

penetration.

CR 2205108220, Significant amount of boron on 2-1208-X4-478 and 2-1208-X4-461, CVCS

letdown Regen HX Inlet valves

3

CR 2005107942, White reside present on the Bottom Channel Head Drain Tube and Weld on

S/G 1 and 3.

CR 2005107560, While performing procedure 31105-C, Collection of Data for Hideout Return

Calculation, the Unit 2 steam generator sample valves 1-4 (upper and lower) were closed to

assess leakage

CR 2005108378, Hydraulic pump for s/g manway tensioner device was found to be leaking at a

fitting.

CR 2005107322,

Self-Assessments and Audits

Inservice Inspection Program Self-Assessment Report, January 10, 2002

Response Report for 2002 ISI Program Self Assessment, February 7, 2003

Boric Acid Corrosion Control Program Focused Self Assessment, August 17-19, 2004

Other Documents

Vogtle Electric Generating Plant- Units 1 and 2 CVCS Letdown Line Minimal Wall Thickness

and Evaluation Supporting ISI, April 28, 2004

Owners Report For Inservice Inspection (2R10)

NMP-ES-019, Version 1.0, Boric Acid Corrosion Control Program

NMP-ES-GL01, Version 1.0, Boric Acid Corrosion Control Implementation Guideline

NMP-ES-GL02, Version 1.0, Boric Acid Corrosion Control Health Report Guideline

NMP-ES-GL03, Version 2.0, Boric Acid Deposit Sampling, Analysis, and Data Evaluation

Program Health Report, August 13, 2004

Program Health Report, May 12, 2005

Corrosion Assessment Leak #: 1208-2005-036

Section 1R11: Licensed Operator Requalification

Procedures

18003-1, Rod Control System Malfunction

18034-1, Loss of Class 1E 125V DC Power

19211-C, FR-S.1 Response to Nuclear Power Generation/ATWT

91001-C, Emergency Classification and Implementing Instructions

Section 1R12: Maintenance Effectiveness

Condition Reports

1997037686, 1997037687, 1998000730, 1998000819, 1998000828, 1998000915,

1998000915, 1998000946, 1999000785, 1999001698, 1999001090, 1999001725,

2001000529, 2002002122, 2001002960, 2002003533, 2003002006, 2003002282,

2004151120, 2004151620, 2004151707, 2005106222, 2005106256, 2005103841,

2005106336

Work Orders

00146810, 00146811, 00146812, 20000617, 20001903, 20002199, 20002332, 20003132,

20003239, 20100487, 20101614, 20103011, 20201996, 20202028, 20202029, 20202030,

20202031, 20202032, 20202586, 20302079, 20370476, 20410474, 20410930, 20410934,

20410937, 20450221, 20450216, 20450217, 20501854, 29703180, 29703216, 29703217,

29703248, 29800663, 29802189, 29802190, 29802383, 29802410, 29802516, 29900096,

29900101, 29900097, 29900098, 29900100

Procedures

27080-C, Ingersoll Rand Model 10 X 18 SE CCW Pump Maintenance

System Health Report, Component Cooling Water

4

Section 1R20: Refueling and Outage Activities

Procedures

00309-C, Control of Unattended Temporary Material in Containment in Modes 1-4

11899-2, RCS Draindown Configuration Checklist

12000-C, Post Refueling Operations (Mode 6 to Mode 5)

12005-C, Reactor Shutdown to Hot Standby (Mode 2 to Mode 3)

12006-C, Unit Cooldown to Cold Shutdown

12007-C, Refueling Operations (Entry into Mode 6)

12008-C, Midloop Operations

13005-2, Reactor Coolant System and Refueling Cavity Draining

14210-2, Containment Building Penetrations Verification - Refueling

14406-2, Boron Injection Flow Path Verification - Shutdown

14900-C, Containment Exit Inspection

18019-C, Loss of Residual Heat Removal

27504-C, Equipment Hatch Emergency Closure

29540-C, Risk Assessment Monitoring

29542-C, Shutdown Risk Assessment

93300-C, Conduct of Refueling Operations

Section 2OS1: Access Control To Radiologically Significant Areas

Procedures, Manuals, and Guides

00008-C, Plant Lock and Key Control, Revision (Rev.) 15

00930-C, Radiation and Contamination Control, Rev. 23.1

43000-C, Radiation and Contamination Surveys, Rev. 20

43005-C, Establishing and Posting Radiation Controlled Areas and High Radiation Area Access

Control, Rev. 31

43007-C, Issuance Use and Control of Radiation Work Permits, Rev. 22

43014-C, Special Radiological Controls, Rev. 32

43019-C, Spent Filter Handling Special Radiological Controls, Rev. 7

43300-C, Personnel Decontamination, Rev. 25

45016-C, Investigation, Evaluation and Management of Damaged, Lost, Malfunctioning, or

Alarming Dosimetry, Rev. 6.1

46017-C, Control and Monitoring of Materials in Radiation Controlled Areas, Rev. 30

NMP-GM-002, Corrective Action Program, Version (Ver.) 4.0

Radiation Work Permits (RWPs)

RWP 05-100, Perform HP Surveys to Assess Radiological Conditions, Provide Multiple RWP

Job Coverage Activities, and Perform Routine Functions, Rev. 0

RWP 05-0109, Minor Work Task and Surveillances in High Radiation Areas, High

Contamination Areas, and/or Airborne Areas, Rev. 0

RWP 05-0110, Changeout Reactor Coolant Filters in 1-AB-B-15 and 2-AB-B-179 Filter Pits,

Spent Fuel Pool Filters in 1-AB-B-145 and 2-AB-B-176 Filter Pits and Spent Fuel Skimmer

Filters in 1-AB-D-94 and 2-AB-D-83, and All Associated Work Including Transfer to the RPF or

1-AB-D-43 for Filter Disposal, Rev. 2

RWP 05-0113, All Sluices from Demins to Spent Resin Storage Tank in Unit 1 and Unit 2

Auxiliary Building, Rev. 0

RWP 05-0121, Decon Activities Performed in High Radiation Areas, Rev. 0

RWP 05-0148, Remove Tri-Nuke Filters from Spent Fuel Pool and Transfer to the RPF For

Survey/Segregation/and Disposal, Rev. 0

RWP 05-0149, Perform Corrective Maintenance on Ultrasonic Fuel Cleaning Equipment and All

5

Associated Work, Rev. 0

Records and Data

Accumulated Dose for Entry > to Dose Alarm Setpoint Since August 2003

Plant Vogtle Radiological Information Survey Numbers (Nos.) 76006, 76944, 76946, 76957,

and 76971

Corrective Action Program Documents/Audits

Condition Report (CR) 2003002872, A contractor working on RCPs failed to log in on his RWP

and obtain an electronic dosimeter prior to entering containment

CR 2003002966, Carpenter entered the S/G #3 primary platform without HP permission while

looking for a scaffold in loop #3

CR 2005100382, The keys to the Very HRA key box were left in the RPF tool monitor for ~30

minutes by the HP Duty Foreman when exiting the RCA

CR 2005100692, Upon issuance of the Unit 1 Containment cage door key (#1C1), the locked

high radiation area key cabinet was noted to be closed but unlocked

CR 2005103949, Individual received an accumulated dose alarm while calibrating pressure flow

transmitters in 2-AB-A-103

Self Assessment of Health Physics Measuring and Test Equipment (MT&E), Assessment Date:

05/16 - 05/20/05, Plant Vogtle

SNC Fleet High Radiation Area Control Self-Assessment, 12/20/04

Section 2OS3: Radiation Monitoring Instrumentation and Protective Equipment

Procedures

00971-C, Selection and Use of Respirators for Nonradiological Applications, Rev. 2

18035-C, Abnormal Operating Procedures, Rev. 9

24138-C, Isotopic Channel Calibration of the Fuel Handling Building Area Monitor 2RE-0008,

Rev. 2

24171-2, Control Room (2RE-0001) Area Monitor 2RX-0001 Channel Calibration, Rev. 7

24624-2, Containment High Range (2RE-0005) Area Monitor 2RX-0005 Channel Calibration,

Rev. 20

24988-2, Isotopic Channel Calibration of the Control Room Area Monitor 2RE-0001, Rev. 2

24989-2, Isotopic Channel Calibration of the Containment High Range Area Monitors 2RE-0005

and 2RE-0006, Rev. 3

34330-C, Surveillance of the DRMS (Digital Radiation Monitoring System), Rev. 31

43631-C, Calibration of the IPM-7A/8/9 Contamination Monitors, Rev. 24

43634-C, Calibration of the HFM-7A Hand and Foot Monitor, Rev. 10

43651-C, Calibration of the SPM Personnel Portal Monitors, Rev. 12

43657-C, Operation, Use and Calibration of the Ludlum 22OO Scaler Ratemeter, Rev. 8

43669-C, Operation and Calibration of MGPI Dose Rate Instruments, Rev. 6

43670-C, Calibration of Dose Rate Meters, Rev. 22

43673-C, Calibration of the Ludlum 177, Eberline Model RM-14, Eberline Model RM-25 Count

Rate Meters, Rev. 7

43680-C, Calibration of the Eberline Model RM-14S Radiation Monitor, Rev. 4

43689-C, Calibration of the (SAM) Small Articles Monitor, Rev. 4

44022-C, Operation and Calibration of the Whole Body Counter, Rev. 9

47001-C, Selection and Use of Respiratory Protection Equipment Used for Radiological

Purposes, Rev. 12

47002-C, Cleaning and Surveying Respiratory Protection Equipment, Rev. 6

47003-C, Qualitative and Quantitative Fit Testing of Individuals for Respirator Use, Rev. 18.1

6

47004-C, Breathing Air Analysis, Rev. 8

47005-C, Inspection, Repair, and Storage of Respiratory Protection Equipment, Rev. 7

47006-C, Control Issuance and Return of Radiological Respiratory Protection Equipment,

Rev. 11

47013-C, Inspection, Repair, Storage of Self Contained Breathing Apparatus, Rev. 16

91702-C, Emergency Equipment and Supplies, Rev. 27

NMP-GM-002, Corrective Action Program, Ver. 4.0

Calibrations, Surveillance Tests, and Licensee Records

2005 OPS Dept Shift Schedule Report, Shift Coverage Week 09/10/05, Four Weeks at a

Glance 08/27/05, 09/03/05, 09/10/05, and 09/17/05.

24138-1, Isotopic Channel Calibration of the Fuel Handling Building Area Monitor 1RE-0008,

24138-2, Isotopic Channel Calibration of the Fuel Handling Building Area Monitor 2RE-0008,

24171-2, Control Room (2RE-0001) Area Radiation Monitor 2RX-0001 Channel Calibration,

24174-1, Control Room (1RE-0001) Area Radiation Monitor 1RX-0001 Channel Calibration,

24174-2, Fuel Handling Room (RE-0008) Area Monitor 2RX-0008 Channel Calibration, pages

24624-1, Containment High Range (1RE-0005) Area Monitor 1RX-0005 Channel Calibration,

24624-1, Containment High Range (1RE-0005) Area Radiation Monitor 1RX-0005 Channel

24624-2, Containment High Range (2RE-0005) Area Monitor 2RX-0005 Channel Calibration,

24625-1, Containment High Range (1RE-0006) Area Monitor 1RX-0006 Channel Calibration,

24625-2, Containment High Range (2RE-0006) Area Monitor 2RX-0006 Channel Calibration

24988-1, Isotopic Channel Calibration of the Control Room Area Monitor 1RE-0001

24988-2, Isotopic Channel Calibration of the Control Room Area Monitor 2RE-0001

24989-1, Isotopic Channel Calibration of the Containment High Range Area Radiation Monitors

1RE-0005 and 1RE-0006

24989-2, Isotopic Channel Calibration of the Containment High Range Area Radiation Monitors

2RE-0005 and 2RE-0006

34330-C Data Sheet 5-1, Surveillance of the DRMS, for surveillance dates between 01/16/03

and 07/29/05

34330-C Data Sheet 5-2, Surveillance of the DRMS, for surveillance dates between 01/15/03

and 07/28/05

34330-C Data Sheet 9-1, Surveillance of the DRMS, Dated 02/15/04, 08/16/04, and 02/21/05

34330-C Data Sheet 9-2, Surveillance of the DRMS, Dated 02/19/04, 02/27/04, 08/22/04, and

08/23/04

43673-C, Calibration of the Ludlum 177, Eberline Model RM-14, Eberline Model RM-25 Count

Rate Meters, Data Sheet 1 for RM-14, Serial Number (S/N) 0104, Dated 09/13/05

47013-C, Data Sheet 2, Inspection and Maintenance of SCBA Units, for Unit HP-0019, Dated

11/1999 to 07/005, Unit FP-019, Dated 02/04 to 07/05, Unit HP-0009, Dated 11/99 to 08/00

and 01/04 to 07/05, Unit FP-009, Dated 07/00 to 09/05, Unit HP-030, Dated 10/99 to 06/05,

and Unit FP-030, Dated 11/03 to 09/05

47013-C, Data Sheet 3, Inspection and Maintenance of SCBA Units (ProCheck3 Test Results),

for facepiece S/N 72127, Dated 06/06/05

47013-C, Data Sheet 1, Monthly SCBA Cylinder Surveillance for FP-XXX and HP-XXX

cylinders (current, unsigned, used for tracking of hydro-test due dates only)

47013-C, Table 1, SCBA Cylinder Location List, dated 12/15/04, manually updated (unknown

date) to incorporate codes 7 (Chem Lab), 8 (RPF), 9 (OSC), 10 (PESB), 12 (OOS), 11 (OOS

Hydro), and 13 (Plant Wilson), still not incorporated in Rev. 15

Calibration of IPM-7A/8/9, S/N VEGP-HP-0636, 07/07/05

Calibration of IPM-7A/8/9, S/N VEGP-HP-0640, 06/03/05

Respirator Qualification Report by Department, Dated September 14, 2005

7

VEGP-FSAR-11 and VEGP-FSAR-12

VMS Quality Assurance Report V1.3, Generated September 13, 2005 (Demonstration of

calibration source check for September 13, 2005), including WBC Daily Calibration Source

Check (energy and efficiency check) for WBC #1 @Dosimetry and WBC #2 @HP Access

Point

Work Order (WO) No. 10202551, Temporary Jumper to 1RX-0001 per Procedure No. 20429-C,

Dated 03/19/03

WO No. 1040174601, 1RE-0001 Area Monitor Control Room, Dated 03/13/03

WO No. 2040123801, 2RE-0008 Area Monitor Fuel Handling Bldg, Dated 04/15/03

WO No. 2040176101, 2RE-0001 Area Monitor Control Room, Dated 08/06/03

CAP Documents/Audits

CR No. 2004151659, HP WBC not functioning properly

CR No. 2005101263, SCBA Spectacles come loose

CR No. 2005101781, Late PM on 2RE008 Isotopic Calibration

CR No. 2005103730, Facial injury while donning an SCBA

CR No. 2005104066, SCBA unit found with "Vogtle Training" cylinder

CR No. 2005107596, Lack of documentation of monthly control room respirators inspections

CR No. 2005107597, Lack of small and large control room respirators masks

CR No. 2005107598, HP Tech responses to portal monitors not consistent

Section 2PS1: Radioactive Gaseous and Liquid Effluent Treatment and Monitoring

Systems

Procedures, Guidance Documents, and Operating Manuals

24972-2, Isotopic Channel Calibration of the Containment Vent Effluent Air Monitors

2RE-2565A, 2RE-2565B and 2RE-2565C, Rev. 6

33015-2, Obtaining Gaseous Samples for Radioactivity Analysis Unit #2, Rev. 1

33037-C, Daily Quality Control of the Gamma Spectroscopy System, Rev. 9

36015-C, Radioactive Liquid Effluent Release Permit Generation and Data Control Computer

Method, Rev. 23

36020-C, Radioactive Gaseous Effluent Release Permit Generation and Data Control

Computer Method, Rev. 20

NMP-GM-002, Corrective Action Program, Ver. 4.0

Records, Data, and Drawings

Annual Radioactive Effluent Release Report, 2003 and 2004.

Germanium Detector #1 Calibrations (effluent sample geometries), 10/21/98, 11/8/01, 04/18/03,

04/22/03, 04/23/03, 01/25/04, 01/26/04, and 03/11/04

Germanium Detectors No. 1 and 3, Daily Source Check and Trend Logs, 01/01/05 - 09/14/05

Gaseous Radioactive Waste Release Permit Nos. 50137.020.025.G (06/13 - 06/20/05),

50142.026.024.G (06/21/05), 50199.021.037.G (09/07 - 09/14/05), and 50204.021.038.G

(07/14 - 07/21/05, pre-release only)

Liquid Radioactive Waste Release Permit Nos. 50129.002.057.L (09/14/05) and

50072.001.025.L (05/30/05)

Liquid Scintillation Detector Calibrations, 05/17/04 and 05/17/05

Out-of-service data for Unit 1 and Unit 2 radiation monitors RE-12442 and RE-18, 08/01/03 -

09/01/05

Radiation Monitor 1-RE-2565 A, B, C, Isotopic Calibrations, 10/28/03 and 01/27/05

Radiation Monitor 2-RE-2565 A, B, C, Isotopic Calibrations, 09/10/02 and 01/14/04

Radiation Monitor 1-RE-20 A, B, Isotopic Calibrations, 07/31/03 and 11/08/04

Radiation Monitor 2-RE-20 A, B, Isotopic Calibrations, 05/05/02, 05/21/02, and 01/12/04

8

Radiation Monitor 1-RE-20A, B, Channel Check Logs, June 2005

Radiation Monitor 2-RE-2565A, B, C, Channel Check Logs, June 2005

Results of Radiochemistry Cross-Check Program, 2004 and 2005

Unit 1 Containment Purge Flowmeter Calibrations, 02/05/02 and 07/29/04

Unit 1 Containment Purge System Functional Test, 09/29/03 and 06/17/05

Unit 2 Containment Purge System Functional Test, 10/16/03 and 06/20/05

Unit 2 Containment Purge Flowmeter Calibrations, 06/12/01 and 11/21/03

CAP Documents/Audits

Audit No. VQA-2005-029, QA Audit of Chemistry and Radioactive Waste, 06/27/05

CR 2004001547, Two consecutive points in the upper warning region for efficiency @

1332 KeV on HpGe detector No. 2, 04/20/04

CR 2004003774, Apparent trend in repetitive failures with paper drive associated with

2-RE-2565A, 09/13/04

CR 2004150102, Interlaboratory crosscheck results disagreed with outside vendor lab,

10/08/04

CR 2005101890, Pre-release permit limit of 18000 CFM for the Unit 1 containment purge was

exceeded according to flow transmitter 1FT2565, 03/18/05

Section 2PS3: Radiological Environmental Monitoring Program (REMP) and Radioactive

Material Control Program

Procedures and Guidance Documents

36030-C, Meteorological Tower Monitoring and Data Control, Rev. 16

46024-C, Release of Materials from the RCA, Rev. 7.1

ENV-861, Collection and Handling of Drinking Water Samples for Radiological Analysis,

Rev. 10

ENV-860, Collection and Handling of Milk Samples for Radiological Analysis, Rev. 12

ENV-859, Collection and Handling of River Water Samples for Radiological Analysis, Rev. 11

ENV-858, Collection and Handling of Grass Samples for Radiological Analysis, Rev. 10

ENV-856, Collection and Handling of Sediment Samples for Radiological Analysis, Rev. 9

ENV-855, Collection and Handling of Fish Samples for Radiological Analysis, Rev. 9

ENV-851, Radiological Monitoring - Air Dust/Gaseous Iodine Air Sampling Flow Calibration,

Rev. 6

ENV-850, Collection and Handling of Airborne Dust and Gaseous Iodine Samples, Rev. 11

ENV-612, Quality Control Program, Rev. 7

NMP-GM-002, Corrective Action Program, Ver. 4.0

Reports, Manuals, and Audits

CQA 2003-81, Southern Nuclear Operating Company Audit of GPC Environmental Laboratory,

May 28, 2003

CQA 2004-126, Southern Nuclear Operating Company Audit of GPC Environmental Laboratory,

June 16, 2004

Offsite Dose Calculation Manual for Southern Nuclear Operating Company, Vogtle Electric

Generating Plant, Rev. 22

Plant Vogtle 2003 and 2004 Annual Meteorological Reports

Vogtle Electric Generating Plant Annual Radiological Environmental Operating Reports for 2003

and 2004

Instrument Calibration and Environmental Data Records

10 CFR 61 Waste Analysis, 1st and 2nd Quarters, 2005

Calibration of SAM-9: S/N 0868, 01/21/05

Calibration of SAM-11: S/N 1159 (05/24/05, 04/29/05, 11/01/04), S/N 1223 (05/23/05,

9

12/04/04), S/N 1152 (05/23/05, 12/02/04), S/N 1151 (05/23/05, 12/02/04), and S/N 1158

(05/24/05, 12/02/04)

Surveillance 24681-C, Semi-Annual Meteorological Station 10M Wind Direction Channel

Calibration, 06/29/05 and 01/07/05

Surveillance 24683-C, Semi-Annual Meteorological Station 10M Wind Speed Channel

Calibration, 07/01/05 and 01/06/05

Surveillance 24684-C, Semi-Annual Meteorological Station 60M Wind Speed Channel

Calibration, 06/30/05 and 01/05/05

Surveillance 24686-C, Semi-Annual Meteorological Station 60M Wind Direction Channel

Calibration, 06/30/05 and 01/05/05

Surveillance 24688-C, Semi-Annual Meteorological Station 10M Ambient and 10-60M Delta T

Channel Calibration, 06/30/05 and 01/07/05

VEGP Rotameter Air Flow Calibration Field Sheets, Rotameters #1,3,7,2,6,8,5, 03/15/04

CAP Documents

2003002432, 10m wind speed not responding to expected changes, 09/04/03

2003002996, Found met tower 10m primary wind direction not responding, 10/12/03

2004003089, Met tower chart recorder 60 m wind direction pen is sticking, 07/22/04

2004000287, Met tower 10m and 60m wind speed not reading due to sleet, 01/26/04

2004000867, Met tower aspirator has gone into alarm and appears unreliable, 03/08/04

2004002515, 10m wind direction on primary met tower not functioning properly, 06/11/04

2004003942, Met tower 10m backup temperature on IPC reading high, 09/27/04

2005103153, Review of 2004 meteorological data indicate an abnormally low number of hours

of Stability Class A atmospheric conditions, 05/04/05

2005105684, Air conditioner leaking water inside instrument room, 07/29/05

Section 4OA1: Performance Indicator Verification

Procedures

00163-C, NRC Performance indicator and Monthly Operating Report Preparation and

Submittal, Rev. 8.1

Records and Data

Gaseous effluent release permit No. 50199.021.037.G (09/07 - 09/14/05)

Liquid effluent release permit No. 50129.002.057.L (09/14/05)

Out-of-service data for Unit 1 and Unit 2 radiation monitors RE-12442 and RE-18, 08/01/03 -

09/01/05

CAP Documents

CR 2003002418, 1-RE-020A, B went into low voltage power supply alarm, 09/03/03

CR 2003002792, Two mechanics entered the labyrinth area at the west entrance to the

bioshield in search of a snubber and their teledosimeters alarmed when they got near a hot

spot on a reactor cavity drain line

CR 2005101890, Pre-release permit limit of 18000 CFM for the Unit 1 containment purge was

exceeded according to flow transmitter 1FT2565, 03/18/05

CR 2005103166, Individual received a dose rate alarm when he entered into 1-AB-C-94

Section 4OA5: Other Activities

Temporary Instruction 2515/161, Transport of Control Rod Drive (CRD) in Type A Packages

Records

Radioactive Material Shipment Log, 01/02 - 08/05