I I EXHIBIT A WILMINGTON AREA 2005 LOCATION AND DESCRIPTION OF WORK Reclear all of the wooded sections of the right-of-way of the following lines as described in the detail descriptions:
Line Mow Hand Total Brunswick - Castle Hayne East 230kV Line 125 18 143 Brunswick - Cumberland 230kV Line 854 33 887 Brunswick - Jacksonville 230kV Line 433 57 490 Sutton - Castle Hayne 230kV Line 122 18, 140 Sutton - Castle Hayne North 115kV Line 113 5
118 Sutton - Wallace 230kV Line 481 70 551 TOTAL 2,128 201 2,329 The above are estimated acres. The acres to be hand cut were areas that equipment did not work during previous reclearing operations. The acres to be mowed were areas that were mowed during previous reclearing operations.
All of the wooded sections of the right-of-way are to be recleared with rotary mowers where possible and the remaining areas are to be hand cut orl d
to the full width as noted in detail description. All undergrowth is to be cut within six (6) inches of the ground. All vines on poles and brush around poles in fields are to be cut and removed out of cropped areas. Cut all leaning trees that have been pulled into the right-of-way by winter ice storms or hurricanes. All brush cut from stream banks or drainage ditches must be removed from streams and ditches so as not to impede the flow of water.
When run ways are cut through existing canals, the canal must be restored to original condition allowing drainage to continue as it did before our operation. The vista' screens and trimmed trees are not to be cut without specific instructions from Company representative.
If an area of brush grows tall enough to threaten the line before the scheduled time of cutting, a move to cut the area will be required upon specific instructions from the Company representative.
Make daily production sheets of clearing completed between adjoining line structures and send in weekly to David L. Smith, Jr., 8645 Trade Street, Leland, NC 28451.
The work may be started within seven (7) days of endorsement of the contract and must be completed by December 1, 2005.
Rev. 10/22/04
I-EXHIBIT B WILMINGTON AREA 2005 PAYMENT DISTRIBUTION After completion and approval of each line, invoices may be submitted for payment according to the following percentages of the accepted contract price:
Brunswick - Castle Hayne East 230kV Line Brunswick - Cumberland 230kV Line
- From Structure # 34 to Structure #216
- From Structure #216 to Structure #382
- From Structure #382 to Structure #685 Brunswick - Jacksonville 230kV Line
- From Structure #208 to Structure #316
- From Structure #316 to Structure #450
- From Structure #450 to Structure #567 Sutton - Castle Hayne 230kV Line Sutton - Castle Hayne North 115kV Line 6%
13%
13%
13%
-7%
7%
7%
6%
4%
Sutton - Wallace 230kV Line
- From Structure # 1 to Structure #138
- From Structure #138 to Structure #255 12%
12%
TOTAL 100%
- Where payment is requested for a section of line completed, all taps and lines as designated on "Exhibit A" for that section of line will be completed before payment will be made.
Rev. 10/22/04
BRUNSWICK - CASTLE HAYNE EAST 230KV LINE Extends from Structure #1 at the Castle Hayne 230kV Substation, located at the intersection of NCSR 1318 and NCSR 1336, north of Wilmington, NC, to Structure
- 111 at the Barnard Creek 230kV Substation, located east of NCSR 1100 south of Wilmington, NC. (See attached map.)
Only the taps and sections of lines listed in ROW widths are to be recleared.
The right-of-way widths are as follows:
Castle Havne - Wrightsville Beach Section Structure #17 through Structure #68, 100 feet; 50 feet each side of centerline of line.
Wrightsville Beach - Barnard Creek Section Structure #1 through Structure #3, 50 feet; 25 feet each side of centerline of line.
Structure #5 through Structure #7, 50 feet; 25 feet each side of centerline of line.
Structure #37 through Structure #40, 70 feet; 35 feet each side of centerline of line.
Structure #45 through Structure #48, 70 feet; 35 feet each side of centerline of line.
Structure #74 through Structure #81, 50 feet; 25 feet each side of centerline of line.
Structure #83 through Structure #102, 170 feet; 50 feet outside of centerline of lines; 70 feet between centerlines of lines.
Structure #102 through Structure #111, 220 feet; 35 feet outside of centerline of 115kV line; 50 feet outside of centerline of outside 230kV line; 65 feet between centerline of 11 5kV line and centerline of 230kV line; 70 feet between 230kV centerlines of lines.
Structure #95 through Structure #97, (Echo Farms) Do not cut ROW clean to yards - leave a strip of trees to be trimmed as a screen.
Structure #126 through Structure #128, 170 feet; 50 feet outside of centerline of lines; 70 feet between the centerlines of lines.
Barnard Creek - Carolina Beach 115kV Structure #10 through #37, 70 feet; 35 feet each side of centerline of line.
Barnard Creek - Sunset Park 11 5kV Structuie #1 through Structure #5, 70 feet; 35 feet each side of centerline of line.
Structure #5 through Structure #9, 50 feet; 25 feet each side of centerline of line.
Estimated acres of brush to be cut are as follows:
Hand -
18 acres Mow - 125 acres Total - 143 acres Rev. 10/22/04
BRUNSWICK - CUMBERLAND 230KV LINE Extends from Structure #34, located west of Highway 87 north of Southport, NC, to Structure #685 at the Cumberland 500kV Substation, located approximately 6 miles south of Cedar Creek, NC on NCSR 2023. (See attached map.)
All sections of line listed in ROW widths are to be recleared.
The right-of-way widths are as follows:
Brunswick - Cumberland 230kV Structure #34 through #685, 100 feet; 50 feet each side of centerline of line.
From Structure #468 through Structure #473, do not mow wildlife food plots of bicolor lespedeza.
Estimated acres of brush to be cut are as follows:
Hand 33 acres Mow
- 854 acres Total 887 acres Rev. 10/22/04
BRUNSWICK - JACKSONVILLE 230KV LINE Extends from Structure #208, located west of intersection of NCSR 1109 and Highway 421 north of Wilmington, NC, to structure #567 near the Jacksonville 230kV Substation, located on NCSR 1308 west of Jacksonville, NC. (See attached map.)
From Structure #355 through Structure #365, Structure #444 through Structure
- 445, and Structure #450 through Structure #451, the right-of-way is not to be recleared until specific directions are given on when and how to cut. These are rare plant sites and no disturbance can be made to the plants during their reproductive stages The right-of-way widths are as follows:
Brunswick - Jacksonville 230kV Structure #208 through Structure #567, 100 feet; 50 feet each side of centerline of line.
Estimated acres of brush to be cut are as follows:
Hand -
57 acres Mow - 433 acres Total - 490 acres Note: Acres sprayed in swamp are not included in above acreage and do not need to be cut.
Rev. 10/22/04
SUTTON - CASTLE HAYNE 230KV LINE Extends from Structure #1 at the Castle Haynie 230kV Substation, located at the intersection of NCSR 1318 and NCSR 1336, north of Wilmington, NC, to Structure
- 110 at the Sutton 230kV Substation', located west of Highway 421, north of Wilmington, NC. (See attached map.)
All taps and sections of lines listed in ROW widths are to be recleared.
The right-of-way widths are as follows:
Sutton - Castle Hayne 230kV Structure #1 through #17, 240 feet; 50 outside of centerlines; 70 feet between the centerlines of lines.
Structure #17 through #43, 170 feet; 50 feet outside of centerline of lines; 70 feet between the centerlines of lines.
Structure #43 through #85, 70 feet; 35 feet each side of centerline of line.
structure #85 through #94, 100 feet; 50 feet each side of centerline of line.
Structure #94 through #98, 70 feet; 35 feet each side of centerline of line.
Structure #98 through #105, 130 feet; 35 feet outside of centerlines of lines; 60 feet between the centerlines of lines.
Structure #105 through #110, 70 feet; 35 feet each side of centerline of line.
Sutton - Eaale Island 115kV Structure #1 through #4, 70 feet; 35 feet each side of centerline of line.
Structure #4 through #11, 130 feet; 35 feet outside of centerlines of lines; 60 feet between the centerlines of lines.
Structure #11 through #18, 70 feet; 35 feet each side of centerline of line.
Wilmington Ninth & Orange 230kV Tap Structure #1 through #7, 100 feet; 50 feet each side of centerline of line.
East Wilmincton - Winter Park 230kV Structure #43 through #48, 70 feet; 35 feet each side of centerline of line.
Coming 230kV Tan?
Structure #1 through #3, 100 feet; 50 feet each side of centerline of line.
Structure #3 through #1 1, 70 feet; 35 feet each side of centerline of line.
Structure #11 through #13, 100 feet; 50 feet each side of centerline of line.
Estimated acres of brush to be cut are as follows:
Hand -
18 acres Mow - 122 acres Total -
140 acres Rev. 10/22104
SUTTON - CASTLE HAYNE NORTH 115KV LINE Extends from Structure #1 at the Suttori115kV Siubstatio6;, located west of Highway 421, north of Wilmington, NC, to Structure #63 at the Castle Hayne 115kV Substation, located at the intersection of NCSR 1318 and NCSR 1336, north of Wilmington, NC.
(See attached map.)
All sections of lines listed in ROW widths are to be recleared.
The right-of-way widths are as follows:
Sutton - Castle Hayne North 115kV Structure #1 through #5,130 feet; 35 feet outside of centerline of lines; 60 feet between the centerlines of lines.
Structure #5 through #24, 190 feet; 35 feet outside of outside centerlines of lines; 60 feet between the centerlines of lines.
Structure #24 through #63, 130 feet; 35 feet outside of centerline of lines; 60 feet between the centerlines of lines.
Sutton - General Electric 115kV Structure #1 through #4, 70 feet; 35 feet each side of centerline of line.
Structure #23 through #40, 70 feet; 35 feet each side of centerline of line.
Structure #1 through #8, 70 feet; 35 feet each side of centerline of line.
DO NOT MOW or HAND CUT any brush from last structure to river on:
Sutton - Castle Hayne North 115kV From river through Structure #28.
Sutton - Castle Hayne South 115kV From river through Structure #31.
This brush can only be topped when it tall enough to threaten the lines.
Estimated acres of brush to be cut are as follows:
Hand -
5 acres.
Mow
- 113 acres Total - 118 acres Rev. 10/22/04
SUTTON -WALLACE 230KV LINE
-Extends from Structure #1 at the Sutton 230kV Substation, located west of Highway 421, north of Wilmington, NC, to Structure #255 at the Wallace 230kV Substation, located south of NCSR 1940 east of Wallace, NC. (See attached map.)
From Structure #213 through Structure #216, the right-of-way is not to be recleared until specific field directions are given own how and when to clear. This is a rare plant site and no disturbance can be made to the plants during their reproductive stages All taps and sections of lines listed in ROW widths are to be recleared.
The right-of-way widths are as follows:
Sutton - Delco 115kV Structure #1 through #6, 70 feet; 35 feet each side of centerline of line.
Structure #36 through #42, 70 feet; 35 feet each side of centerline of line.
Sutton - Wallace 230kV Structure #1 through #6,100 feet; 50 feet each side of centerline of line.
Structure #6 through #33,150 feet; 35 feet outside of centerline of 11 5kV line; 50 feet outside of centerline of 230kV line; 65 feet between the centerlines of lines.
Structure #33 through #38,100 feet; 50 feet each side of centerline of line.
Structure #38 through #40, 240 feet; 50 feet outside of centerlines of lines; 70 feet between the centerlines of lines.
Structure #40 through #255, 170 feet; 50 feet outside of centerline of lines; 70 feet between centerlines of lines.
Hercofina 230kV Tap Structure #1 through #7, 100 feet; 50 feet each side of centerline of line.
Union Carbide 230kV Tap Structure #1 through #7, 100 feet; 50 feet each side of centerline of line.
Estimated acres of brush to be cut are as follows:
Hand -
70 acres Mow 481 acres Total -
551 acres Rev. 10/22/04