Unit, 1 and 2 - License Amendments 259 & 142 Elimination of Requirements for Hydrogen Recombiners and Hydrogen Monitors
ML040930130
Person / Time
Site: Beaver Valley
Issue date: 05/19/2004
From: Colburn T
NRC/NRR/DLPM/LPD1
To: Pearce L
FirstEnergy Nuclear Operating Co
Colburn T, NRR/DLPM, 415-1402
Shared Package
ML040930138 List:
References
TAC MC1869, TAC MC1870
Download: ML040930130 (15)


Text

May 19, 2004 Mr. L. William Pearce Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 - ISSUANCE OF AMENDMENTS RE: ELIMINATION OF HYDROGEN RECOMBINERS AND HYDROGEN MONITORS (TAC NOS. MC1869 AND MC1870)

Dear Mr. Pearce:

The Commission has issued the enclosed Amendment No. 259 to Facility Operating License No. DPR-66 and Amendment No. 142 to Facility Operating License No. NPF-73 for the Beaver Valley Power Station, Unit Nos. 1 and 2. These amendments consist of changes to the Technical Specifications (TSs) in response to your application dated January 28, 2004, as supplemented by letter dated May 3, 2004.

These amendments eliminate the requirements in TSs associated with hydrogen recombiners and relocate the requirements for hydrogen monitors to the Licensing Requirements Manuals.

A notice of availability for this TS improvement using the consolidated line item improvement process was published in the Federal Register on September 25, 2003 (68 FR 55416).

A copy of our Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commissions biweekly Federal Register notice.

Sincerely,

/RA/

Timothy G. Colburn, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosures:

1. Amendment No. 259 to DPR-66
2. Amendment No. 142 to NPF-73
3. Safety Evaluation cc w/encls: See next page

May 19, 2004 Mr. L. William Pearce Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077

SUBJECT:

BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 - ISSUANCE OF AMENDMENTS RE: ELIMINATION OF HYDROGEN RECOMBINERS AND HYDROGEN MONITORS (TAC NOS. MC1869 AND MC1870)

Dear Mr. Pearce:

The Commission has issued the enclosed Amendment No. 259 to Facility Operating License No. DPR-66 and Amendment No. 142 to Facility Operating License No. NPF-73 for the Beaver Valley Power Station, Unit Nos. 1 and 2. These amendments consist of changes to the Technical Specifications (TSs) in response to your application dated January 28, 2004, as supplemented by letter dated May 3, 2004.

These amendments eliminate the requirements in TSs associated with hydrogen recombiners and relocate the requirements for hydrogen monitors to the Licensing Requirements Manuals.

A notice of availability for this TS improvement using the consolidated line item improvement process was published in the Federal Register on September 25, 2003 (68 FR 55416).

A copy of our Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commissions biweekly Federal Register notice.

Sincerely,

/RA/

Timothy G. Colburn, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosures:

1. Amendment No. 259 to DPR-66
2. Amendment No. 142 to NPF-73
3. Safety Evaluation cc w/encls: See next page DISTRIBUTION:

PUBLIC MOBrien ACRS PDI-1 R/F TColburn CBixler, RGN-I OGC RLaufer GHill (4) TBoyce WReckley ADAMS Accession Numbers: Letter - ML040930130; TS - ML Package - ML040930138 *see previous concurrence OFFICE CLIIP LPM PDI-1/PM PDI-2/LA PDI-1/SC OGC NAME WReckley* TColburn CRaynor for MOBrien RLaufer GMLongo(NLO)

DATE 3/29/04 5/5/04 04/08/04 5/11/04 5/7/04 OFFICIAL RECORD COPY

Beaver Valley Power Station, Unit Nos. 1 and 2 cc:

Mary OReilly, Attorney Rich Janati, Chief FirstEnergy Nuclear Operating Company Division of Nuclear Safety FirstEnergy Corporation Bureau of Radiation Protection 76 South Main Street Deparment of Environmental Protection Akron, OH 44308 Rachel Carson State Office Building P.O. Box 8469 FirstEnergy Nuclear Operating Company Harrisburg, PA 17105-8469 Regulatory Affairs/Performance Improvement Mayor of the Borough of Shippingport Larry R. Freeland, Manager P O Box 3 Beaver Valley Power Station Shippingport, PA 15077 Post Office Box 4, BV-A Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission Commissioner James R. Lewis 475 Allendale Road West Virginia Division of Labor King of Prussia, PA 19406 749-B, Building No. 6 Capitol Complex Resident Inspector Charleston, WV 25305 U.S. Nuclear Regulatory Commission Post Office Box 298 Director, Utilities Department Shippingport, PA 15077 Public Utilities Commission 180 East Broad Street FirstEnergy Nuclear Operating Company Columbus, OH 43266-0573 Beaver Valley Power Station ATTN: R. G. Mende, Director Director, Pennsylvania Emergency Work Management (BV-IPAB)

Management Agency Post Office Box 4 2605 Interstate Dr. Shippingport, PA 15077 Harrisburg, PA 17110-9364 FirstEnergy Nuclear Operating Company Ohio EPA-DERR Beaver Valley Power Station ATTN: Zack A. Clayton Mr. B. F. Sepelak Post Office Box 1049 Post Office Box 4, BV-A Columbus, OH 43266-0149 Shippingport, PA 15077 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 J. H. Lash, Plant Manager (BV-IPAB)

FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077

PENNSYLVANIA POWER COMPANY OHIO EDISON COMPANY FIRSTENERGY NUCLEAR OPERATING COMPANY DOCKET NO. 50-334 BEAVER VALLEY POWER STATION, UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.259 License No. DPR-66

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by FirstEnergy Nuclear Operating Company, et al. (the licensee), dated January 28, 2004, as supplemented May 3, 2004, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-66 is hereby amended to read as follows:

(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 259, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.

3. This license amendment is effective as of the date of its issuance and shall be implemented within 120 days.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Richard J. Laufer, Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

Attachment:

Changes to the Technical Specifications Date of Issuance: May 19, 2004

ATTACHMENT TO LICENSE AMENDMENT NO. 259 FACILITY OPERATING LICENSE NO. DPR-66 DOCKET NO. 50-334 Replace the following pages of Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Insert VI VI 3/4 6-18 3/4 6-18 3/4 6-20 -

3/4 6-21 -

3/4 6-22 -

PENNSYLVANIA POWER COMPANY OHIO EDISON COMPANY THE CLEVELAND ELECTRIC ILLUMINATING COMPANY THE TOLEDO EDISON COMPANY FIRSTENERGY NUCLEAR OPERATING COMPANY DOCKET NO. 50-412 BEAVER VALLEY POWER STATION, UNIT NO. 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.142 License No. NPF-73

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by FirstEnergy Nuclear Operating Company, et al. (the licensee), dated January 28, 2004, as supplemented May 3, 2004, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-73 is hereby amended to read as follows:

(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 142, and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto are hereby incorporated in the license. FENOC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

3. This license amendment is effective as of the date of its issuance and shall be implemented within 120 days.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Richard J. Laufer, Chief, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

Attachment:

Changes to the Technical Specifications Date of Issuance: May 19, 2004

ATTACHMENT TO LICENSE AMENDMENT NO. 142 FACILITY OPERATING LICENSE NO. NPF-73 DOCKET NO. 50-412 Replace the following pages of Appendix A Technical Specifications with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Insert VII VII 3/4 6-16 3/4 6-16 3/4 6-31 -

3/4 6-32 -

3/4 6-32a -

3/4 6-33 -

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NOS. 259 AND 142 TO FACILITY OPERATING LICENSE NOS. DPR-66 AND NPF-73 PENNSYLVANIA POWER COMPANY OHIO EDISON COMPANY THE CLEVELAND ELECTRIC ILLUMINATING COMPANY THE TOLEDO EDISON COMPANY FIRSTENERGY NUCLEAR OPERATING COMPANY BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 (BVPS-1 and 2)

DOCKET NOS. 50-334 AND 50-412

1.0 INTRODUCTION

By application dated January 28, 2004, as supplemented May 3, 2004, the FirstEnergy Nuclear Operating Company (FENOC, the licensee), requested changes to the Technical Specifications (TSs) for BVPS-1 and 2. The proposed amendments eliminate the requirements in TSs associated with hydrogen recombiners and relocate the requirements for hydrogen monitors to the Licensing Requirements Manuals. A notice of availability for this TS improvement using the Consolidated Line Item Improvement Process (CLIIP) was published in the Federal Register on September 25, 2003 (68 FR 55416). The supplement dated May 3, 2004, provided additional information that clarified the application, did not expand the scope of the application as originally noticed, and did not change the staffs original proposed no significant hazards consideration determination as published in the Federal Register.

The Nuclear Regulatory Commission (NRC or the Commission) has revised Title 10 of the Code of Federal Regulations (10 CFR), Section 50.44, Combustible gas control for nuclear power reactors. The amended standards eliminated the requirements for hydrogen recombiners and relaxed the requirements for hydrogen and oxygen monitoring. In letters dated December 17, 2002, and May 12, 2003, the Nuclear Energy Institute (NEI) Technical Specification Task Force (TSTF) proposed to remove requirements for hydrogen recombiners and hydrogen and oxygen monitors from the standard technical specifications (STS) (NUREGs 1430 - 1434) on behalf of the industry to incorporate the amended standards. This proposed change is designated TSTF-447.

The NRC staff prepared a model safety evaluation (SE) for the elimination of requirements regarding containment hydrogen recombiners and the removal of requirements from TSs for containment hydrogen and oxygen monitors and solicited public comment (67 FR 50374,

published August 2, 2002) in accordance with the CLIIP. The use of the CLIIP in this matter is intended to help the NRC to efficiently process amendments that propose to remove the hydrogen recombiner and hydrogen and oxygen monitor requirements from TSs. Licensees of nuclear power reactors to which the model SE applies were informed (68 FR 55416, published September 25, 2003) that they could request amendments conforming to the model and, in such requests, should confirm the applicability of the SE to their facilities and provide the requested plant-specific verifications and commitments.

2.0 BACKGROUND

Regulatory Issue Summary 2000-06, Consolidated Line Item Improvement Process for Adopting Standard Technical Specification Changes for Power Reactors, was issued on March 20, 2000. The CLIIP is intended to improve the efficiency of the NRCs licensing processes. This is accomplished by processing proposed changes to the STS in a manner that supports subsequent license amendment applications. The CLIIP includes an opportunity for the public to comment on proposed changes to the STS following a preliminary assessment by the NRC staff and finding that the change will likely be offered for adoption by licensees. The NRC staff evaluates any comments received for a proposed change to the STS and either reconsiders the change or proceeds with announcing the availability of the change for proposed adoption by licensees. Those licensees opting to apply for the subject change to TSs are responsible for reviewing the NRC staff's evaluation, referencing the applicable TSs, and providing any necessary plant-specific information. Each amendment application made in response to the notice of availability would be processed and noticed in accordance with applicable rules and NRC procedures.

The Commissions regulatory requirements related to the content of TSs are set forth in 10 CFR 50.36. This regulation requires that the TSs include items in five specific categories.

These categories include: 1) safety limits, limiting safety system settings and limiting control settings; 2) limiting conditions for operation (LCOs); 3) surveillance requirements; 4) design features; and, 5) administrative controls. However, the regulation does not specify the particular TSs to be included in a plants license.

Additionally, 10 CFR 50.36(c)(2)(ii) sets forth four criteria to be used in determining whether an LCO is required to be included in the TSs. These criteria are as follows:

(A) Criterion 1. Installed instrumentation that is used to detect, and indicate in the control room, a significant abnormal degradation of the reactor coolant pressure boundary.

(B) Criterion 2. A process variable, design feature, or operating restriction that is an initial condition of a design basis accident or transient analysis that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.

(C) Criterion 3. A structure, system, or component that is part of the primary success path and which functions or actuates to mitigate a design basis accident or transient that either assumes the failure of or presents a challenge to the integrity of a fission product barrier.

(D) Criterion 4. A structure, system, or component which operating experience or probabilistic risk assessment has shown to be significant to public health and safety.

Existing LCOs and related surveillances included as TS requirements which satisfy any of the criteria stated above must be retained in the TSs. Those TS requirements which do not satisfy these criteria may be relocated to other licensee-controlled documents.

As part of the rulemaking that revised 10 CFR 50.44, the Commission retained requirements for ensuring a mixed atmosphere, inerting Mark I and II containments, and providing hydrogen control systems capable of accommodating an amount of hydrogen generated from a metal-water reaction involving 75 percent of the fuel cladding surrounding the active fuel region in Mark III and ice condenser containments. The Commission eliminated the design-basis loss-of-coolant accident (LOCA) hydrogen release from 10 CFR 50.44, and consolidated the requirements for hydrogen and oxygen monitoring to 10 CFR 50.44 while relaxing safety classifications and licensee commitments to certain design and qualification criteria. The Commission also relocated, without change, the hydrogen control requirements from 10 CFR 50.34(f) to 10 CFR 50.44 and the high point vent requirements from 10 CFR 50.44 to 10 CFR 50.46a.

3.0 EVALUATION The ways in which the requirements and recommendations for combustible gas control were incorporated into the licensing bases of commercial nuclear power plants varied as a function of when plants were licensed. Plants that were operating at the time of the Three Mile Island (TMI), Unit 2 accident are likely to have been the subject of confirmatory orders that imposed the combustible gas control functions described in NUREG-0737, Clarification of TMI Action Plan Requirements, as obligations. The issuance of plant-specific amendments to adopt these changes, which would remove hydrogen recombiner and hydrogen monitoring controls from TSs, supersede the combustible gas control specific requirements imposed by post-TMI confirmatory orders.

3.1 Hydrogen Recombiners The revised 10 CFR 50.44 no longer defines a design-basis LOCA hydrogen release, and eliminates requirements for hydrogen control systems to mitigate such a release. The installation of hydrogen recombiners and/or vent and purge systems formerly required by 10 CFR 50.44(b)(3) was intended to address the limited quantity and rate of hydrogen generation that was postulated from a design-basis LOCA. The Commission has found that this hydrogen release is not risk-significant because the design-basis LOCA hydrogen release does not contribute to the conditional probability of a large release up to approximately 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the onset of core damage. In addition, these systems were ineffective at mitigating hydrogen releases from risk-significant beyond design-basis accidents (BDBAs). Therefore, the Commission eliminated the hydrogen release associated with a design-basis LOCA from 10 CFR 50.44 and the associated requirements that necessitated the need for the hydrogen recombiners and the backup hydrogen vent and purge systems. As a result, the NRC staff finds that requirements related to hydrogen recombiners no longer meet any of the four criteria in 10 CFR 50.36(c)(2)(ii) for retention in TSs and the existing TS requirements may, therefore, be eliminated for all plants.

3.2 Hydrogen Monitoring Equipment Section 50.44(b)(1), the STS, and plant-specific TSs currently contain requirements for monitoring hydrogen. Licensees have also made commitments to design and qualification criteria for hydrogen monitors in Item II.F.1, Attachment 6 of NUREG-0737 and Regulatory Guide (RG) 1.97, Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess Plant and Environs Conditions During and Following an Accident. The hydrogen monitors (referred to as hydrogen analyzers in BVPS-1 and 2 TS 3/4.6.4, Combustible Gas Control) are required to assess the degree of core damage during a BDBA and confirm that random or deliberate ignition has taken place. If an explosive mixture that could threaten containment integrity exists during a BDBA, then other severe accident management strategies, such as purging and/or venting, would need to be considered. The hydrogen monitors are needed to implement these severe accident management strategies.

With the elimination of the design-basis LOCA hydrogen release, hydrogen monitors are no longer required to mitigate DBAs; and, therefore, the hydrogen monitors do not meet the definition of a safety-related component as defined in 10 CFR 50.2. The recommendation in RG 1.97 is to classify the hydrogen monitors as Category 1. Category 1 in RG 1.97, is intended for key variables that most directly indicate the accomplishment of a safety function for DBA events and, therefore, are items usually addressed within TSs. As part of the rulemaking to revise 10 CFR 50.44, the Commission found that the hydrogen monitors no longer meet the definition of Category 1 in RG 1.97. The Commission concluded that Category 3, as defined in RG 1.97, is an appropriate categorization for the hydrogen monitors because the monitors are required to diagnose the course of BDBAs. Hydrogen monitoring is not the primary means of indicating a significant abnormal degradation of the reactor coolant pressure boundary. Section 4 of Attachment 2 to SECY-00-0198, Status Report on Study of Risk-Informed Changes to the Technical Requirements of 10 CFR Part 50 (Option 3) and Recommendations on Risk-Informed Changes to 10 CFR 50.44 (Combustible Gas Control), found that the hydrogen monitors were not risk-significant. Therefore, the NRC staff finds that hydrogen monitoring equipment requirements no longer meet any of the four criteria in 10 CFR 50.36(c)(2)(ii) for retention in TSs and, therefore, may be relocated to other licensee-controlled documents.

However, because the monitors are required to diagnose the course of BDBAs, each licensee should verify that it has, and make a regulatory commitment to maintain, a hydrogen monitoring system capable of diagnosing BDBAs.

The elimination of Post-Accident Sampling System requirements from some plant-specific TSs (and associated CLIIP notices) indicated that during the early phases of an accident, safety grade hydrogen monitors provide an adequate capability for monitoring containment hydrogen concentration. The NRC staff has subsequently concluded that Category 3 hydrogen monitors also provide an adequate capability for monitoring containment hydrogen concentration during the early phases of an accident.

4.0 VERIFICATIONS AND COMMITMENTS As requested by the NRC staff in the notice of availability for this TS improvement, the licensee has addressed the following plant-specific verification and commitment:

Each licensee should verify that it has, and make a regulatory commitment to maintain, a hydrogen monitoring system capable of diagnosing BDBAs.

The licensee has verified that it has a hydrogen monitoring system capable of diagnosing BDBAs. The licensee has committed to maintain the hydrogen monitors within its Licensing Requirements Manuals. The licensee will implement this commitment as part of the implementation of these amendments.

The NRC staff finds that reasonable controls for the implementation and for subsequent evaluation of proposed changes pertaining to the above regulatory commitments are provided by the licensees administrative processes, including its commitment management program.

Should the licensee choose to incorporate a regulatory commitment into the emergency plan, final safety analysis report, or other document with established regulatory controls, the associated regulations would define the appropriate change-control and reporting requirements. The NRC staff has determined that the commitments do not warrant the creation of regulatory requirements which would require prior NRC approval of subsequent changes. The NRC staff has agreed that NEI 99-04, Revision 0, Guidelines for Managing NRC Commitment Changes, provides reasonable guidance for the control of regulatory commitments made to the NRC staff. (See Regulatory Issue Summary 2000-17, "Managing Regulatory Commitments Made by Power Reactor Licensees to the NRC Staff," dated September 21, 2000.) The commitments should be controlled in accordance with the industry guidance or comparable criteria employed by the licensee. The NRC staff may choose to verify the implementation and maintenance of these commitments in a future inspection or audit.

5.0 STATE CONSULTATION

In accordance with the Commission's regulations, the Pennsylvania State official was notified of the proposed issuance of the amendments. The State official had no comments.

6.0 ENVIRONMENTAL CONSIDERATION

The amendments change a requirement with respect to installation or use of a facility component located within the restricted area as defined in 10 CFR Part 20 and change surveillance requirements. The NRC staff has determined that the amendments involve no significant increase in the amounts, and no significant change in the types, of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendments involve no significant hazards consideration, and there has been no public comment on such finding (69 FR 12370, March 16, 2004). Accordingly, the amendments meet the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendments.

7.0 CONCLUSION

The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.

Principal Contributor: W. Reckley Date: May 19, 2004