MONTHYEARWM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) WM 22-0004, Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment2022-07-27027 July 2022 Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment WM 22-0003, Operating Corp. - Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment2022-05-26026 May 2022 Operating Corp. - Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel - Form 405F Amendment WM 21-0005, Supplement to License Amendment Request for Change to Owner Licensee Names2021-05-24024 May 2021 Supplement to License Amendment Request for Change to Owner Licensee Names WM 21-0003, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2021-03-31031 March 2021 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) WM 20-0006, (WCGS) - License Amendment Request for Change to Owner Licensee Names2020-11-0404 November 2020 (WCGS) - License Amendment Request for Change to Owner Licensee Names WM 20-0009, Notification of Readiness for Supplemental Inspection 927222020-09-0808 September 2020 Notification of Readiness for Supplemental Inspection 92722 WM 19-0022, Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel2019-07-17017 July 2019 Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel WM 19-0017, Operating Corp., Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel2019-04-25025 April 2019 Operating Corp., Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel WM 19-0008, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2019-04-10010 April 2019 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) WM 19-0009, Operating Corporation Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors, and Executive Personnel2019-03-25025 March 2019 Operating Corporation Foreign Ownership, Control or Influence Information - Change to Lists of Owners, Officers, Directors, and Executive Personnel WM 19-0006, Operating Corp Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel2019-02-20020 February 2019 Operating Corp Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel WM 19-0003, Notice of Violation and Proposed Imposition of Civil Penalty Statement of Method of Payment2019-01-16016 January 2019 Notice of Violation and Proposed Imposition of Civil Penalty Statement of Method of Payment WM 19-0002, Transmittal of Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel2019-01-10010 January 2019 Transmittal of Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel WM 18-0047, Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel2018-10-0808 October 2018 Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel WM 18-0040, Transmittal of Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel2018-07-25025 July 2018 Transmittal of Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel WM 18-0039, Schedule for the Wolf Creek Nuclear Operating Corporation (WCNOC) Re-Analysis of the LBLOCA and SBLOCA Using the Full Spectrum LOCA (Fsloca) Methodology and the Performance and Analysis Design (PADS) Model, Amendment 213 License Condition2018-07-0303 July 2018 Schedule for the Wolf Creek Nuclear Operating Corporation (WCNOC) Re-Analysis of the LBLOCA and SBLOCA Using the Full Spectrum LOCA (Fsloca) Methodology and the Performance and Analysis Design (PADS) Model, Amendment 213 License Condition t WM 18-0037, Transmittal of Wolf Creek Nuclear Operating Corporation'S(Wcnoc) and Its Owner Companies' Updated Lists of Owners, Officers, Directors and Executive Personnel (Oodep)2018-06-28028 June 2018 Transmittal of Wolf Creek Nuclear Operating Corporation'S(Wcnoc) and Its Owner Companies' Updated Lists of Owners, Officers, Directors and Executive Personnel (Oodep) WM 18-0035, Notice of Receipt of Regulatory Approvals & Closing Date2018-05-29029 May 2018 Notice of Receipt of Regulatory Approvals & Closing Date WM 18-0034, Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel2018-04-26026 April 2018 Foreign Ownership, Control or Influence (FOCI) Information - Change to Lists of Owners, Officers, Directors and Executive Personnel WM 17-0021, Updated Request for Consent to Indirect Transfer of Control2017-09-0505 September 2017 Updated Request for Consent to Indirect Transfer of Control WM 16-0016, Response to Non-Cited Violation 050000482/2016003-012016-12-0808 December 2016 Response to Non-Cited Violation 050000482/2016003-01 WM 16-0013, Operating Corp., Request for Consent to Indirect Transfer of Control2016-07-22022 July 2016 Operating Corp., Request for Consent to Indirect Transfer of Control WM 16-0006, Reply to Notice of Violation EA-16-0182016-03-10010 March 2016 Reply to Notice of Violation EA-16-018 WM 16-0005, Submittal of Updated Safety Analysis Report (Usar), Revision 292016-03-10010 March 2016 Submittal of Updated Safety Analysis Report (Usar), Revision 29 WM 15-0017, Commitment to Maintain Severe Accident Management Guidelines2015-12-14014 December 2015 Commitment to Maintain Severe Accident Management Guidelines WM 14-0026, 30-Day Response on Planned Actions to Restore Compliance Regarding Essential Service Water Design Issues2014-12-16016 December 2014 30-Day Response on Planned Actions to Restore Compliance Regarding Essential Service Water Design Issues WM 14-0024, Cel Inspection Readiness Letter 11-13-142014-11-13013 November 2014 Cel Inspection Readiness Letter 11-13-14 WM 14-0017, Reply to a Notice of Violation; EA-14-0242014-07-29029 July 2014 Reply to a Notice of Violation; EA-14-024 WM 14-0016, Notification of Readiness for Supplemental Inspection2014-07-0808 July 2014 Notification of Readiness for Supplemental Inspection WM 14-0011, Change to an Essential Service Water System Water Hammer Mitigation Commitment2014-05-0808 May 2014 Change to an Essential Service Water System Water Hammer Mitigation Commitment WM 14-0013, Voluntary Commitment Regarding Containment Coolers at Wolf Creek Generating Station2014-05-0808 May 2014 Voluntary Commitment Regarding Containment Coolers at Wolf Creek Generating Station WM 14-0008, Request for Regulatory Conference (EA-14-024)2014-04-0909 April 2014 Request for Regulatory Conference (EA-14-024) WM 13-0021, Response to NRC Letter Regarding Work Environment Issues at Wolf Creek Generating Station2013-09-18018 September 2013 Response to NRC Letter Regarding Work Environment Issues at Wolf Creek Generating Station WM 13-0014, Commitment to NRC Regarding Actions Necessary to Increase Safety Margins Through Ongoing Actions to Resolve Substantive Cross-Cutting Issues (Sccis)2013-06-27027 June 2013 Commitment to NRC Regarding Actions Necessary to Increase Safety Margins Through Ongoing Actions to Resolve Substantive Cross-Cutting Issues (Sccis) WM 13-0008, Notification of Readiness for Inspection Procedure 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area2013-04-30030 April 2013 Notification of Readiness for Inspection Procedure 95002, Supplemental Inspection for One Degraded Cornerstone or Any Three White Inputs in a Strategic Performance Area WM 13-0002, Operating Corporation - Response to NRC Follow-Up Letter on Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.32013-02-26026 February 2013 Operating Corporation - Response to NRC Follow-Up Letter on Technical Issues for Resolution Regarding Licensee Communication Submittals Associated with Near-Term Task Force Recommendation 9.3 WM 12-0041, Operating Corporation - Submittal of Emergency Preparedness Communications Assessment Results in Response to Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 9.3.2012-10-31031 October 2012 Operating Corporation - Submittal of Emergency Preparedness Communications Assessment Results in Response to Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendation 9.3. WM 12-0039, Reply to Notice of Violation EA-12-1522012-10-18018 October 2012 Reply to Notice of Violation EA-12-152 WM 12-0029, Response to NRC Augmented Inspection Team Follow-up Report 05000482/2012009; Preliminary Yellow Finding2012-08-15015 August 2012 Response to NRC Augmented Inspection Team Follow-up Report 05000482/2012009; Preliminary Yellow Finding WM 12-0023, Reply to Notice of Violation EA-12-1352012-08-0202 August 2012 Reply to Notice of Violation EA-12-135 WM 12-0013, Notification of Readiness for Inspection of Human Performance and Problem Identification and Resolution Safety Culture Themes2012-05-0707 May 2012 Notification of Readiness for Inspection of Human Performance and Problem Identification and Resolution Safety Culture Themes WM 12-0008, Operating Corporation'S Answer to March 12, 2012 Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Event (Order Number EA-12-049)2012-04-0202 April 2012 Operating Corporation'S Answer to March 12, 2012 Commission Order Modifying License with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Event (Order Number EA-12-049) WM 12-0010, Receipt Confirmation for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident2012-04-0202 April 2012 Receipt Confirmation for Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident WM 12-0009, Operating Corporation'S Answer to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2012-04-0202 April 2012 Operating Corporation'S Answer to March 12, 2012 Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) WM 12-0003, Response to NRC Request for Additional Information Regarding 60-day Response to NRC Bulletin 2011-01,Mitigating Strategies2012-01-15015 January 2012 Response to NRC Request for Additional Information Regarding 60-day Response to NRC Bulletin 2011-01,Mitigating Strategies WM 11-0011, 30 Day Response to Mid-Cycle Performance Review and Inspection Plan - Wolf Creek Generating Station2011-09-30030 September 2011 30 Day Response to Mid-Cycle Performance Review and Inspection Plan - Wolf Creek Generating Station WM 11-0009, Reply to Notice of Violation EA-11-1492011-09-0909 September 2011 Reply to Notice of Violation EA-11-149 WM 10-0029, Reply to Notice of Violation EA-10-1602010-10-11011 October 2010 Reply to Notice of Violation EA-10-160 WM 10-0024, Day Response to Mid-Cycle Performance Review and Inspection Plan2010-09-30030 September 2010 Day Response to Mid-Cycle Performance Review and Inspection Plan 2023-05-10
[Table view] |
Text
J-.
WLF- CREEK- 'NUCLEAR OPERATING CORPORATION Richard A. Muench President and Chief Executive Officer JAN 222104 WM 04-0001 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
Subject:
Docket No. 50-482: 60-Day Report for NRC Order EA-03-009,
'Issuance of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors" Gentlemen:
The attachment contains the Wolf Creek Nuclear Operating Corporation (WCNOC) report for the 60-day requirement of U.S. Nuclear Regulatory Commission (NRC) Order EA-03-009, Issuance of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors," dated February 11, 2003. Paragraph IV.E of the order requires, within 60 days after returning the plant to operation, the submittal of a report detailing the results of inspections of the reactor pressure vessel head surface and penetrations. Wolf Creek Generating Station returned to operation following Refuel 13 on December 2, 2003.
No commitments are identified in this submittal. If you have any questions concerning this matter, please contact me at (620) 364-4000, or Mr. Kevin Moles at (620) 364-4126.
Very truly yours, Richa Muench RAM/rIg Attachment cc: J. N. Donohew (NRC), w/a D. N. Graves (NRC), w/a B. S. Mallett (NRC), w/a Senior Resident Inspector (NRC), w/a P.O. Box 411/ Burlington, KS 66839 / Phone: (620) 364-8831 An Equal Opportunity Employer MIF/HCVET
STATE OF KANSAS )
-SS COUNTY OF COFFEY )
Richard A. Muench, of lawful age, being first duly sworn upon oath says that he is President and Chief Executive Officer of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.
-Richard A. Muen6h President and Chief Executive Officer SUBSCRIBED and sworn to before me thisdA day of;So' , 2004.
l,*o^^tt CINDY NOVINGER Notary Publ
-T~tT~KMSS
-Expiration Date - Go y '
Attachment to WM 04-0001 Page 1 of 2 60-Day Report for NRC Order EA-03-009 "Issuance of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors" Below is the Wolf Creek Nuclear Operating Corporation (WCNOC) report for the 60-day requirement of paragraph IV.E of U.S. Nuclear Regulatory Commission (NRC) Order EA-03-009, 'Issuance of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors," dated February 11, 2003. The order's "Required Information" is shown in bold.
Required Information IV.C. (Excerpts)
All Licensees shall perform inspections of the RPV head using the following techniques and frequencies:
(3) For those plants in the Low category, RPV head and head penetration nozzle inspections shall be performed as follows. An inspection meeting the requirements of 3(a) must be completed at least every third refueling outage or every five (5) years, whichever occurs first.
(a) Bare metal visual examination of 100% of the RPV head surface (including 360° around each RPV head penetration nozzle).
IV.D. During each refueling outage, visual inspections shall be performed to identify potential boric acid leaks from pressure-retaining components above the RPV head. For any plant with boron deposits on the surface of the RPV head or related insulation, discovered either during the inspections required by this Order or otherwise and regardless of the source of the deposit, before returning the plant to operation the Licensee shall perform inspections of the affected RPV head surface and penetrations appropriate to the conditions found to verify the integrity of the affected area and penetrations.
IV.E. For each inspection required in Paragraph C, the Licensee shall submit a report detailing the inspection results within sixty (60) days after returning the plant to operation. For each Inspection required in Paragraph D, the Licensee shall submit a report detailing the inspection results within sixty (60) days after returning the plant to operation if a leak or boron deposit was found during the inspection.
Response
An inspection meeting the requirements of paragraph IV.C.(3)(a) of the order was conducted in March 2002, in response to NRC Bulletin 2002-01. The inspection results were submitted in Reference 1 in response to Item 2.A of Bulletin 2002-01. In Reference 2, the NRC acknowledged that the Reference 1 submittal also satisfies the
Attachment to WM 04-0001 Page 2 of 2 report requested in Item (2) of Bulletin 2002-02. Reference 1 satisfies the report required by Item IV.E of Order EA-03-009 for paragraph IV.C.(3)(a).
During Refuel 13 in October 2003, WCNOC performed a partial visual examination of the reactor pressure vessel (RPV) head and penetrations, as required by Order EA-03-009,Section IV.D. During a scheduled modification of the Control Rod Drive Mechanism (CRDM) cooling shroud, the presence of boron residue was discovered on the upper surface of the insulation in the vicinity of three CRDMs. The insulation in the affected area was removed and the vessel head and penetrations were visually examined.
The examination was performed using a procedure specifically developed for RPV head bare metal inspections. The procedure includes requirements for personnel certification, examination and acceptance criteria, and recording of inspection results. Examination personnel were certified to a minimum of Level II in the VT-2 method. Examination personnel also received specific training on examination of RPV heads based on industry guidance documentation (Reference 3).
The examination was performed by a certified WCNOC Level IlIl examiner, and results recorded in accordance with the procedure. No evidence of boric acid leakage was detected. The annulus area of the potentially affected penetrations was verified free of boric acid. Small accumulations of loose debris were found on the upper side of some penetrations. Loose boric acid crystals were observed on the head surface and transparent boric acid film was observed on both the penetration sleeves and the head surface. The amount and configuration of the debris and film was compared to as-left conditions from a RPV head bare metal inspection performed in Refuel 12. Amounts and configuration were comparable. The debris was removed and the boric acid film was cleaned.
There were no material deficiencies identified on the RPV head or penetration pressure boundaries. There were also no indications of leakage or potential leakage through the CRDM penetrations. The boron residue on the head insulation that initiated the examination in accordance with NRC Order EA-30-0009 was determined to be residue that originated from head vent valve leakage during Operating Cycle 12. The results of the examination performed during Refuel 12 are documented in Reference 1.
References
- 1. Letter CT 02-0029 from Mark S. Larson, WCNOC, to USNRC, "30-Day Response for NRC Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity," dated May 24, 2002.
- 2. Letter from USNRC to Otto L. Maynard, WCNOC, 'Wolf Creek Generating Station - Response to NRC Bulletin 2002-02, "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs (TAC NO. MB5938),"
dated May 24, 2002.
- 3. Visual Examination for Leakage of PWR Reactor Head Penetrations: Revision 2 of 1006296, Includes 2002 Inspection Results and MRP Inspection Guidance, EPRI, Palo Alto, CA: 2003. 1007842