ML033320398

From kanterella
Jump to navigation Jump to search
IR 05000483-03-007, on 09/22/2003 - 10/21/2003; Callaway Plant. Triennial Fire Protection Inspection
ML033320398
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/28/2003
From: Marschall C
NRC/RGN-IV/DRS/EMB
To: Randolph G
Union Electric Co
References
FOIA/PA-2004-0277 IR-03-007
Download: ML033320398 (27)


See also: IR 05000483/2003007

Text

November 28, 2003

Garry L. Randolph, Senior Vice

President and Chief Nuclear Officer

Union Electric Company

P.O. Box 620

Fulton, MO 65251

SUBJECT: CALLAWAY PLANT - NRC TRIENNIAL FIRE PROTECTION INSPECTION

REPORT 05000483/2003-007

Dear Mr. Randolph:

On October 21, 2003, the Nuclear Regulatory Commission (NRC) completed an inspection at

your Callaway Plant. This included onsite inspection from September 22 through October 2,

2003, as well as, in-office review from October 6-21, 2003. The enclosed report documents the

inspection findings, which were discussed on October 21, 2003, with Mr. R. Affolter and other

members of your staff.

This triennial fire protection inspection examined activities conducted under your license as they

relate to safety and compliance with the Commissions rules and regulations and with the

conditions of your license. Within these areas, the inspection consisted of selected

examination of procedures and representative records, observations of activities, and interviews

with personnel.

Based on the results of this inspection, the NRC has identified two findings that were evaluated

under the risk significance determination process. One finding was determined to have very

low safety significance (Green). The other finding is at least Green, but requires additional

evaluation to determine the safety significance. The latter finding does not present an

immediate safety concern because the procedure was corrected during the inspection. The

NRC has also determined that violations are associated with each of these findings. One

violation is being treated as a noncited violation, consistent with Section VI.A of the

Enforcement Policy. The other violation will be dispositioned once a significance determination

has been completed. These violations are described in the subject inspection report. If you

contest the violation or significance of these noncited violations, you should provide a response

within 30 days of the date of this inspection report, with the basis for your denial, to the

U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC

20555-0001, with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission,

Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington, Texas 76011; the Director, Office of

Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the

NRC Resident Inspector at the Callaway Plant facility.

Union Electric Company -2-

During the inspection, several examples of an apparent violation of 10 CFR Part 50,

Appendix R,Section III.G.2 were identified. These circuit vulnerabilities could, under certain

postulated fire scenarios, adversely affect the ability to achieve and maintain a safe shutdown

of the facility. It is the NRCs understanding that you do not consider these vulnerabilities to be

violations of NRC requirements. In order to allow the industry to develop an acceptable

approach to resolving this issue that the NRC can endorse, the NRC will defer any enforcement

action relative to these matters while the staff evaluates NEIs proposed resolution methodology

and you have time to implement the resolution methodology, once approved, provided you take

adequate compensatory measures for the identified vulnerabilities.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/ RPM for

Charles S. Marschall, Chief

Engineering and Maintenance Branch

Division of Reactor Safety

Docket: 50-483

License: NPF-30

Enclosure:

NRC Inspection Report 05000483/2003-007

cc w/enclosure:

Professional Nuclear Consulting, Inc.

19041 Raines Drive

Derwood, MD 20855

John ONeill, Esq.

Shaw, Pittman, Potts & Trowbridge

2300 N. Street, N.W.

Washington, DC 20037

Mark A. Reidmeyer, Regional

Regulatory Affairs Supervisor

Regulatory Affairs

AmerenUE

P.O. Box 620

Fulton, MO 65251

Union Electric Company -3-

Manager - Electric Department

Missouri Public Service Commission

301 W. High

P.O. Box 360

Jefferson City, MO 65102

Ronald A. Kucera, Deputy Director

for Public Policy

Department of Natural Resources

P.O. Box 176

Jefferson City, MO 65102

Rick A. Muench, President and

Chief Executive Officer

Wolf Creek Nuclear Operating Corporation

P.O. Box 411

Burlington, KS 66839

Dan I. Bolef, President

Kay Drey, Representative

Board of Directors Coalition

for the Environment

6267 Delmar Boulevard

University City, MO 63130

Chris R. Younie, Manager

Quality Assurance

AmerenUE

P.O. Box 620

Fulton, MO 65251

Jerry Uhlmann, Director

State Emergency Management Agency

P.O. Box 116

Jefferson City, MO 65102-0116

Scott Clardy, Director

Section for Environmental Public Health

P.O. Box 570

Jefferson City, MO 65102-0570

Keith D. Young, Manager

Regulatory Affairs

AmerenUE

P.O. Box 620

Fulton, MO 65251

Union Electric Company -4-

David E. Shafer

Superintendent, Licensing

Regulatory Affairs

AmerenUE

P.O. Box 66149, MC 470

St. Louis, MO 63166-6149

Union Electric Company -5-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

Senior Resident Inspector (MSP)

Branch Chief, DRP/B (DNG)

Senior Project Engineer, DRP/B (RAK1)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

J. Clark (JAC), OEDO RIV Coordinator

CWY Site Secretary (DVY)

ADAMS: * Yes * No Initials: ______

  • Publicly Available * Non-Publicly Available * Sensitive * Non-Sensitive

SRI:EMB TL:EMB RI:EMB C:EMB C:PBB C: EMB

NFOKeefe/lmb RLNease TAMcConnell CSMarschall DNGraves CSMarschall

/RA/ /RA/ /RA/ NA /RA/ /RA/by RPM

11/25/03 11/25/03 11/25/03 11/26/03 11/28/03

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 50-483

License: NPF-30

Report No.: 50-483/2003-007

Licensee: Union Electric Company

Facility: Callaway Plant

Location: Junction Highway CC and Highway O

Fulton, Missouri

Dates: September 22 - October 21, 2003

Inspectors: N. OKeefe, Senior Reactor Inspector, Engineering and Maintenance Branch

R. Nease, Team Leader, Engineering and Maintenance Branch

T. McConnell, Reactor Inspector, Engineering and Maintenance Branch

Contractor: R. Deem, Brookhaven National Laboratory

Approved By: Charles S. Marschall, Chief

Engineering and Maintenance Branch

-2-

SUMMARY OF FINDINGS

IR 05000483-007; 09/22/2003 - 10/21/2003; Callaway Plant. Triennial Fire Protection

Inspection

The inspection was conducted by three region-based engineering and maintenance inspectors

and one contractor. One Green noncited violation and one violation with a potential safety

significance greater than Green were identified. The significance of findings is indicated by

their color (green, white, yellow, red) using Inspection Manual Chapter 0609, Significance

Determination Process." The NRCs program for overseeing the safe operation of commercial

nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 3,

dated July 2000.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

  • Green. The licensee did not recognize that the halon system protecting both

engineered safety feature switchgear rooms was rendered inoperable and,

therefore, failed to take the required compensatory action when the control room

emergency ventilation and isolation system was in operation. Two ventilation

dampers in parallel through the common fire wall between these rooms open

when this system starts. The team identified that these dampers do not

automatically shut when the halon system actuates. The halon system would not

be capable of reaching the required concentration to suppress a fire because

halon would be allowed to escape under these conditions. License Condition

2.C.(5)(c) requires that the licensee implement and maintain in effect all

provisions of the approved fire protection program as described in the

Standardized Nuclear Unit Power Plant System Final Safety Analysis Report.

Updated Final Safety Analysis Report, Table 9.5.1-2, "Halon Systems," requires

that when this halon system is inoperable, the licensee shall establish a

continuous fire watch with backup fire suppression capability in the affected

area. Contrary to this, on numerous occasions throughout the operating life of

the plant, the team found that the licensee had failed to post a continuous fire

watch whenever the vital switchgear room halon system was rendered

inoperable due to testing of the control room ventilation system. This violation of

License Condition 2.C.(5)(c) will be treated as a noncited violation, consistent

with Section VI.A of the Enforcement Policy. This issue was in the licensees

corrective action program under Callaway Action Request 200307189.

This finding was greater than minor because it involved the potential degradation

of a fire protection feature protecting the electrical distribution equipment

powering both trains of mitigating systems. This finding is of very low safety

significance because the fire ignition frequency in the rooms affected is low, the

remaining fire detection and suppression capability are unaffected, and sufficient

accident mitigation equipment was available. (Section 1R05.9)

-3-

  • TBD. The alarm response procedure for responding to smoke in the control

room outside supply duct was inadequate because it did not direct operators to

isolate outside air makeup upon receipt of the alarm. This alarm does not cause

an automatic isolation of the control room, so operators must recognize the

condition and take manual action to prevent losing control room habitability.

Failure to have a procedure, required by Technical Specification 5.4.1.a and

Regulatory Guide 1.33, that provided appropriate response actions for abnormal

or alarm conditions was a violation. This issue was entered into the licensees

corrective action program under Callaway Action Request 200306977.

This finding is unresolved pending completion of a significance determination.

This issue was more than minor because failure to isolate the control room

ventilation could lead to unnecessary evacuation, which would result in a plant

transient and disabling much of the mitigation equipment that would otherwise be

available. This issue is being treated as an unresolved item pending completion

of a significance determination. (Section 1R05.9)

B. Licensee-Identified Violations

Violations of very low safety significance, which were identified by the licensee have

been reviewed by the inspectors. Corrective actions taken or planned by the licensee

have been entered into the licensees corrective action program. These violations and

corrective actions are listed in Section 4OA7 of this report.

Report Details

1. REACTOR SAFETY

1R05 Fire Protection

The purpose of this inspection was to review the Callaway Plant fire protection program

for selected risk-significant fire areas. Emphasis was placed on verification of the

licensees post-fire safe shutdown capability. The inspection was performed in

accordance with the NRC regulatory oversight process using a risk-informed approach

for selecting the fire areas and attributes to be inspected. The team leader and a

Region IV senior reactor analyst used the Callaway Individual Plant Examination for

External Events to choose several risk-significant areas for detailed inspection and

review. Inspection Procedure 71111.05 requires selecting three to five fire areas for

review. The three fire areas reviewed during this inspection were:

  • C-9, Train A engineered safety feature switchgear room
  • A-21, north control room ventilation equipment room

For each of these fire areas, the inspection was focused on the fire protection features,

the systems and equipment necessary to achieve and maintain safe shutdown

conditions, determination of license commitments, and changes to the fire protection

program.

Documents reviewed by the team are listed in the attachment.

.1 Systems Required to Achieve and Maintain Post-Fire Safe Shutdown

a. Inspection Scope

The team reviewed the functional requirements identified by the licensee as necessary

for achieving and maintaining hot shutdown conditions to ensure that at least one post-

fire safe shutdown success path was available in the event of a fire in each of the

selected areas. The team reviewed piping and instrumentation diagrams of systems

credited in accomplishing safe shutdown functions to independently verify whether the

licensee's shutdown methodology had properly identified the required components. The

team focused on the following functions that must be available to achieve and maintain

post-fire safe shutdown conditions:

  • Reactivity control capable of achieving and maintaining cold shutdown reactivity

conditions,

and

-2-

  • Supporting systems capable of providing all other services necessary to permit

extended operation of equipment necessary to achieve and maintain hot

shutdown conditions.

A review was also conducted to ensure that all required electrical components in the

selected systems were included in the licensees safe shutdown analysis. The team

identified the systems required for each of the primary safety functions necessary to

shut down the reactor. These systems were then evaluated to identify the systems that

interfaced with the fire areas inspected and were the most risk significant systems

required for reaching both hot and cold shutdown conditions. The systems selected for

review were the chemical and volume control, reactor coolant, and the safety injection.

b. Findings

No findings of significance were identified.

.2 Fire Protection of Safe Shutdown Capability and Post-fire Safe Shutdown Circuit

Analysis

a. Inspection Scope

The team reviewed licensee documentation to verify that at least one post-fire safe

shutdown success path was free of fire damage in the event of a fire in the selected fire

areas. Specifically, the team examined the separation of safe shutdown cables,

equipment, and components within the same fire areas. The team reviewed, on a

sample basis, the analysis of electrical protective devices (e.g., circuit breakers, fuses,

relays), coordination, and adequacy of electrical protection provided for nonessential

cables, which share a common enclosure (e.g., cable trays) with cables of equipment

required to achieve and maintain safe shutdown conditions. Additionally, the team

reviewed the protection of diagnostic instrumentation required for safe shutdown for

fires in the selected areas. The team reviewed the licensee's methodology for meeting

the requirements of 10 CFR 50.48, and the bases for the NRC's acceptance of this

methodology as documented in NRC safety evaluation reports. In addition, the team

reviewed license documentation, such as, the Updated Final Safety Evaluation Report,

submittals made to the NRC by the licensee in support of the NRC's review of their fire

protection program, and deviations from NRC regulations to verify that the licensee met

license commitments.

b. Findings

Introduction. The scope of Inspection Procedure 71111.05 has been temporarily

reduced to stop requiring inspectors to address fire-induced circuit failure of associated

circuits as a direct line of inquiry, nor to require developing associated circuit inspection

findings. This was being done in order to allow the industry to develop an approach

acceptable to the NRC for resolving this issue. However, during the course of this

inspection, a number of associated circuit vulnerabilities were incidentally identified.

These circuit vulnerabilities could, under certain postulated fire scenarios, adversely

affect the ability to achieve and maintain safe shutdown of the facility.

-3-

Description. Appendix R,Section III.G.1 of 10 CFR Part 50, requires that one train of

systems needed to achieve and maintain hot shutdown conditions must be free of fire

damage.Section III.G.2 states that cables or equipment, including associated non-

safety-related circuits that could prevent operation or cause mal-operation due to fire

damage of redundant trains of systems necessary to achieve and maintain hot

shutdown conditions, must be protected. The Callaway Updated Final Safety Analysis

Report allows either free of fire damage, or a diverse means will be provided. The

team identified some associated circuit issues that are neither protected from fire

damage nor provided with a diverse means of providing the function. Specific examples

of equipment or associated cables located within the fire areas reviewed by the team

that could affect the safe shutdown process included:

Fire Area A-21 - possible loss-of-seal water injection capability to any one of the

four reactor coolant pumps, which could lead to seal failure; and inability to

isolate any one of the four main steam isolation valves or main feedwater

isolation valves, which cool lead to overcooling of the reactor coolant system.

Fire Area A-18 - loss of thermal barrier cooling to any one of four reactor coolant

pumps, which could lead to seal failure; spurious opening of a pressurizer spray

valve or the pressurizer auxiliary spray valve, which could lead to uncontrolled

depressurization and overfilling the reactor coolant system; spurious opening of

a containment emergency recirculation sump isolation valve that could divert

water from the refueling water storage tank to the containment sump and make it

unavailable for coolant inventory control; spurious opening of a reactor head vent

flow path, causing a loss-of-coolant and uncontrolled depressurization; and

spurious closing of either steam admission valves to the turbine driven auxiliary

feedwater pump, making it unavailable for decay heat removal.

Fire Area C-9 - spurious closure of a volume control tank outlet valve, causing a

loss of charging, affecting reactor coolant inventory control and reactor coolant

pump seal cooling.

Analysis. This finding is unresolved pending additional action by the NRC. See below.

Enforcement. Failure to either protect these associated circuits from spurious operation

or otherwise prevent them from affecting safe shutdown is an apparent violation of

Appendix R,Section III.G.2. In accordance with the NRC Enforcement Manual,

Section 8.1.7.1.a, this apparent violation will be treated as an unresolved item pending

development of an industry method to resolve these types of issues; Unresolved

Item 05000483/2003007-01, Failure to Protect Associated Circuits. The determination

of the safety significance and disposition of this apparent violation will be performed

after the NRC develops additional guidance for addressing associated circuit issues.

This issue is in the licensees corrective action program under Callaway Action

Request 200307232. This Callaway action request included an action to evaluate

whether any specific compensatory actions were needed.

-4-

.3 Alternative Safe Shutdown Capability

a. Inspection Scope

The team reviewed the licensees alternative shutdown methodology to determine if the

licensee properly identified the components and systems necessary to achieve and

maintain safe shutdown conditions from the remote shutdown panel and alternative

shutdown locations for a fire in the units control room. The team focused on the

adequacy of the systems selected for reactivity control, reactor coolant makeup, reactor

heat removal, process monitoring and support system functions. The team verified that

hot and cold shutdown from outside the control room can be achieved and maintained

with off-site power available or not available. The team verified that the transfer of

control from the control room to the alternative locations has been demonstrated and not

affected by fire-induced circuit faults by reviewing the provision of separate fuses for

alternative shutdown control circuits.

b. Findings

Findings from this review are discussed in Section 1R05.4. No additional findings of

significance were identified.

.4 Operational Implementation of Alternate Shutdown Capability

a. Inspection Scope

The team performed walkdowns of the actions defined in Procedure OTO-ZZ-00001,

Control Room Inaccesibility, Revision 19, with licensed and non-licensed operators.

Procedure OTO-ZZ-00001 provided instructions for performing an alternative shutdown

from the remote shutdown panel and for manipulating equipment locally in the plant.

The team verified that the number of available operators could reasonably be expected

to perform the procedure actions within the applicable plant shutdown time

requirements, and that equipment labeling was consistent with the procedure. Also, the

team verified that the licensee had adequate tools and equipment to successfully

perform the procedure as intended. The team also reviewed records for training

conducted on this procedure.

b. Findings

Introduction. An unresolved item was identified to assess the safety significance of the

licensee not completing some manual actions for shutting down the plant from outside

the control room within the times required in the Callaway Safety Evaulation Report

during a timed walk-through.

Discussion. The team conducted a walk-through of Procedure OTO-ZZ-00001 with

qualified licensed and non-licensed operators. Each operator performed the actions of a

specific watchstation to which the individuals were typically assigned. Procedure steps

were simulated, and completion times were noted. The team noted that the operators

were familiar with the procedure and the actions assigned, and were able to perform the

-5-

required actions smoothly. However, some of the required actions intended to assure a

safe shutdown condition was achieved took longer than the time required in the safety

evaluation report.

The team attempted to determine whether the performance goals of 10 CFR Part 50,

Appendix R, III.L.2, for a fire safe shutdown were being met based on the actual

performance times. However, the licensee was unable to provide documentation, which

demonstrated that the alternate shutdown actions and required times satisfied these

performance goals. Therefore, the team requested information on several important

thermal hydraulic parameters. This information was used to construct a rough thermal

hydraulic time line to evaluate performance criteria in the shutdown procedures. There

were six instances where one or both criteria were exceeded, as shown below:

Required Action Safety Evaluation Report Calculation Measured

Time Required Minimum Time Completion Time

Establish auxiliary 5 min 17 min 9:06 min

feedwater flow

Open two steam 5 min 9:30 min

generator power

operated relief valves

Isolate letdown 5 min 61 min 8:05 min

Isolate pressurizer 5 min 7 min 8:05 and 9:00 min

power operated relief

valves

Isolate auxiliary 20 min not in procedure

pressurizer spray

As an example, the safety evaluation report required that operators establish auxiliary

feedwater flow to two steam generators and begin bleeding steam through two steam

generator power-operated relief valves within 5 minutes of initiating a control room

evacuation in order to establish a method of core decay heat removal. During the walk-

through conducted by the team, these actions took over 9 minutes to complete.

However, preliminary calculations performed at the teams request indicated that as

many as 17 minutes were available before the steam generators would boil dry. The

technical basis for the time requirements listed could not be determined during the

inspection. Therefore, additional information is required to establish the significance of

the actual time needed to complete the above actions. The other actions above either

establish similar required states or prevent conditions that could cause the licensee to

fail to meet the required performance goals.

Analysis. This finding is unresolved pending review of additional information to be

provided by the licensee. See below.

Enforcement. Failure to meet the required action times from the safety evaluation report

was an apparent violation of License Condition 2.C. Failure to meet the other

(calculated) times needs to be further evaluated for possible failure to meet the

acceptance criteria of Appendix R,Section III.L.2. The licensee stated that they would

-6-

perform a formal timing and validation of the procedure in accordance with station

procedures, using several operations crews, to precisely determine how long it takes to

complete each critical action. This issue was not an immediate safety concern because

the times to complete the actions were reasonable compared to the reference times

discussed above. In the case of isolation the auxiliary pressurizer spray, indications

were available to allow diagnosis of a problem and corrective actions.

The significance of not meeting the times required in the safety evaluation report could

not be determined based on the information available. Additional analysis by the

licensee was needed to evaluate the significance, as well as, to verify the calculated

times, in order to place this issue into context for safety significance and enforcement.

Additionally, the inspectors will consider the licensees timing and validation

methodology, and compare the results with the results of the teams walkthrough. This

finding is identified as Unresolved Item 05000483/2003007-02, Failure to Perform

Alternative Shutdown Manual Actions Within Required Times, pending this additional

information from the licensee. This issue was being tracked in the licensees corrective

action program under Callaway Action Request 200307160.

.5 Communications

a. Inspection Scope

The team reviewed the communications required to implement the alternative shutdown

Procedure OTO-ZZ-00001, Control Room Inaccessibility, Revision 19. The plant radio

system was to be used by operations personnel to perform an alternative shutdown

outside of the control room. The team reviewed the design of the radio system to

(1) ensure the radio system was sufficient to support alternative shutdown operator

actions, and (2) ensure that damage from a control room fire will not impact the

performance of the rest of the system.

b. Findings

No findings of significance were identified.

.6 Emergency Lighting

a. Inspection Scope

The team reviewed the adequacy of emergency lighting for performing actions required

in Procedure OTO-ZZ-00001, Control Room Inaccessibility, Revision 19, which

included access and egress routes. The team reviewed test procedures and test data to

verify that the individual battery operated units were able to supply light for the required

8-hour period. The following specific documents were reviewed:

Callaway Plant Procedure OTS-QD-00001,Emergency Light Tests, Revision 11

Callaway Preventive Maintenance Procedure PM-17,Annual Service of Fire

Protection Emergency Lighting, dated 7/22/03

-7-

Union Electric Company, Callaway Plant Fire Protection Emergency Battery

Lights White Paper dated 04/30/96

b. Findings

No findings of significance were identified.

.7 Cold Shutdown Repairs

a. Inspection Scope

The team reviewed equipment operations and capability to determine if any repairs were

required in order to achieve cold shutdown. The team noted that the licensee did not

require the repair of equipment to reach cold shutdown based on the safe shutdown

methodology implemented.

b. Findings

No findings of significance were identified.

.8 Compensatory Measures

a. Inspection Scope

The team verified, by sampling, that adequate compensatory measures were put in

place by the licensee for out-of-service, degraded, or inoperable fire protection features

and post-fire safe shutdown equipment, and systems.

b. Findings

Introduction. A Green noncited violation was identified for failure to take required

compensatory actions when operation of the control room emergency ventilation and

isolation system (CREVIS) rendered the engineered safety features switchgear room

halon inoperable.

Description. The team identified that the licensee failed to recognize that the halon

system protecting both engineered safety feature switchgear rooms was rendered

inoperable when the CREVIS was in operation. Two ventilation dampers in parallel

through the common fire wall separating these rooms open when CREVIS starts. The

team identified that these dampers do not automatically shut when the halon system

actuates. The halon system would not be capable of reaching the required

concentration to suppress a fire in either switchgear room under these conditions

because halon would be allowed to escape. The team determined that CREVIS was

required by a technical specification surveillance to be run for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> on a monthly

periodicity.

-8-

Updated Final Safety Analysis Report, Table 9.5.1-2, "Halon Systems," requires that

when this halon system was inoperable, the licensee shall establish a continuous fire

watch with backup fire suppression capability in the affected area within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This

requirement should have been implemented during each monthly CREVIS surveillance,

as well as any other time the system was run for longer than 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. However, the

licensee stated that, since this issue was not recognized, it was not their practice to

implement this compensatory measure during CREVIS operation. This issue was in the

licensees corrective action program under Callaway Action Request 200307189.

Analysis. This finding is of very low safety significance because the fire ignition

frequency in the rooms affected was low, the remaining fire detection and suppression

capability were unaffected, and sufficient accident mitigation equipment remained

available. This finding affected only the fixed fire suppression equipment, and did not

impact the manual firefighting capability. Despite the open dampers in the 3-hour fire

barrier, the team concluded that the integrity of the fire barrier would be maintained

because the separate fire dampers in these ducts remained unaffected by this findings,

and should function normally. Therefore, the redundant train of engineered safety

feature switchgear would remain available. This finding was more than minor because it

involved the potential degradation of a fire protection feature protecting the electrical

distribution equipment powering both trains of mitigating systems, affecting the

Mitigating System Cornerstone.

Enforcement. The team found that testing of the control room ventilation system

rendered the halon system in both of the vital switchgear rooms inoperable. Union

Electric Company, Docket No. Stn 50-483, Callaway Plant, Unit 1, Facility Operating

License, Condition 2.C.(5)(c), states, "The licensee shall implement and maintain in

effect all provisions of the approved fire protection program as described in the

Standardized Nuclear Unit Power Plant System (SNUPPS) Final Safety Analysis Report

for the facility through Revision 15, the Callaway Plant site addendum through

Revision 8, and as approved in the Safety Evaluation Report through Supplement 4,

subject to provision "d" below." Final Safety Analysis Report, Table 9.5.1-2, (Sheet 4),

System 4, "Halon Systems," required that when in Condition "a" where one or more

halon systems was inoperable in areas containing redundant systems or components,

the licensee was required by Action "a" to "Establish a continuous fire watch with backup

fire suppression capability in the affected area." Contrary to this requirement, on

numerous occasions throughout the operating life of the plant, the team found that

licensee had failed to post a continuous fire watch whenever the vital switchgear rooms

halon system was rendered inoperable due to testing of the control room ventilation

system. This is a violation of License Condition 2.C.(5)(c); Noncited

Violation 50-483/0307-03, Failure to Take Required Compensatory Actions.

.9 Fire Protection Systems, Features and Equipment

a. Inspection Scope

For the selected fire areas, the team evaluated the adequacy of fire protection features

(e.g., detection and suppression systems, or passive fire barrier features), such as, fire

suppression and detection systems, fire area barriers, penetration seals, and fire doors.

-9-

The team observed the material condition and configuration of the installed fire detection

and suppression systems, fire barriers, and construction details and supporting fire tests

for the installed fire barriers. In addition, the team reviewed license documentation,

such as, NRC safety evaluation reports and deviations from NRC regulations and the

National Fire Protection Association codes to verify that fire protection features met

license commitments.

The team walked down the areas to verify that the detection and suppression system

location drawings agreed with the as-installed configurations. The team reviewed the

original suppression systems specifications, the hydraulic calculations for the pre-action

water systems, and the carbon dioxide system design calculations. The team reviewed

the periodic testing performed on the automatic halon total flooding system including the

interfacing fire detection systems and ventilation system dampers. The team also

reviewed the original testing performed to confirm that the design concentration of halon

was sufficient.

b. Findings

Introduction. An apparent violation was identified for an inadequate smoke alarm

response procedure. This issue was being tracked as an unresolved item pending

significance determination.

Description. The alarm response procedure for responding to smoke in the control

room outside supply duct was inadequate because it did not direct isolating outside air

makeup upon receipt of the alarm. The team determined that this alarm does not cause

an automatic isolation of the control room, so operators must recognize the condition

and take manual action to prevent losing control room habitability. However, the alarm

response procedure directed that operators search the control building for a source of

the fire, which would be misleading if the smoke were coming from outside the building.

This misdirected search for the source of the smoke could allow smoke to build up to

the point where control room habitability would be jeopardized. This issue was entered

into the licensees corrective action program under Callaway Action

Request 200306977.

Analysis. Loss of control room habitability could cause operators to evacuate the control

room. This action would necessitate manually tripping the plant, establishing control of

the plant at the alternate shutdown panel, and manually operating the plant with limited

control and indication equipment. This represented an inappropriate response to a fire

outside the plant. A Phase 1 significance determination process required that a Phase 3

significance determination process be performed by senior reactor analysts. However,

this analysis was not complete at the time of this report. This issue is unresolved

pending completion of a significance determination process. This issue was more than

minor because failure to isolate the control room ventilation could lead to unnecessary

evacuation, which would result in a plant transient and disabling much of the mitigation

equipment that would otherwise be available, affecting the Initiating Events and

Mitigating Systems Cornerstones.

-10-

Enforcement. Alarm Response Procedure OTA-KC-00008, window 119/157, Auxiliary

Building Control Building Supply Air Supply Alarm, Revision 9, a procedure required by

Technical Specification 5.4.1.a and Regulatory Guide 1.33, was determined to be

inadequate because it did not contain steps to secure outside makeup to ensure control

room habitability when smoke was detected in this duct. This violation existed since the

plant began operation. This apparent violation will be treated as Unresolved

Item 5000483/2003007-04, Inadequate Smoke Alarm Response Procedure for Control

Room Supply, pending determination by the NRC of the significance of the finding. This

finding did not present an immediate safety concern because the licensee corrected the

procedure promptly during the inspection.

4. OTHER ACTIVITIES (OA)

4OA5 Other

(Closed) Unresolved Item 05000483/2001007-01: Control Room Halon Bank

Operability Questions

An unresolved item was identified in NRC Inspection Report 50-483/2001-07, dated

May 1, 2002, for further evaluation of the licensing basis of the control room halon

system. Specifically, inspectors questioned the acceptance criteria for determining the

operability of the control room halon system in Administrative Procedure APA-ZZ-00703

(95 percent of the full charge weight of 110 pounds).

The team reviewed NRC Inspection Reports 50-483/84-41 (dated September 7, 1984)

and 50-483/84-49 (dated October 16, 1984). In Inspection Report 50-483/84-41, the

NRC documented that the licensee's halon pre-operational test in the control room

resulted in a halon concentration in the upper 5 feet that did not meet National Fire

Protection Association Code 12A-1975. A fully charged 110 pound halon bottle was

discharged during this test. At that time, the NRC agreed that the licensee would add a

second bottle of halon which would discharge immediately following the first bottle, and

that no further halon testing was necessary. This open item was closed in NRC

Inspection Report 50-483/84-49, with no further discussion of the control room halon

system.

In October 18, 1984, the NRC issued the Callaway Facility Operating License NPF-30

together with the Callaway Technical Specifications (Revision 1 of NUREG-1058,

"Technical Specifications, Callaway Plant, Unit 1, Appendix 'A' to License No. NFP-30").

The technical specifications included operability requirements for the control room halon

system. Technical Specification Surveillance Requirement 4.7.10.3, stated that halon

systems shall be demonstrated operable every 6 months by verifying the halon tanks to

be at least 95 percent of full charge weight. In 1989, the NRC, at the licensee's request,

removed this specification from the technical specifications, and placed this requirement

(95 percent of full charge weight) in Administrative Procedure APA-ZZ-00703.

The team concluded that the NRC was aware that the concentration of halon in the

upper 5 feet of the control room halon trench did not meet the National Fire Protection

Association Code 12A. In addition, in issuing the technical specifications, the NRC

-11-

approved the acceptance criteria for operability of the control room halon system as

95 percent of the full charge weight of 110 pounds. Therefore Unresolved

Item 50-483/0107-01 is closed.

4OA6 Exit Meeting

On October 21, 2003, the team presented the inspection results to Mr. R. Affolter and

other members of his staff, who acknowledged the findings. The team confirmed that

proprietary information was not provided or examined during the inspection.

4OA7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by the

licensee and is a violation of NRC requirements, which meet the criteria of Section VI of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an noncited

violation.

  • Union Electric Company, Docket No. Stn 50-483, Callaway Plant, Unit 1, Facility

Operating License, Condition 2.C.(5)(c), requires that the licensee shall

implement and maintain in effect all provisions of the approved fire protection

program as described in the SNUPPS Final Safety Analysis Report, the Callaway

Plant site addendum, and as approved in the Safety Evaluation Report.

Callaway Plant Final Safety Analysis Report, Site Addendum, Appendix 9.5A,

Section C.8, requires that non-conformances, which affect fire protection are

controlled by the Operating Quality Assurance Manual. The Operating Quality

Assurance Manual, Section 16.1, states, "Measures shall be established to

assure that conditions adverse to quality are promptly identified, reported, and

corrected." Contrary to this, in 1994, the licensee failed to correct a condition

adverse to quality. Specifically, the licensee failed to revise the fire hazards

analysis and the fire pre-plans to address the potential failure of the condensate

storage tank level transmitters because of fire damage, potentially preventing

automatic swap-over of auxiliary feedwater pump suction from the condensate

storage tank to emergency service water. This is a violation of License

Condition 2.C.(5)(c). The licensee identified this failure to correct a condition

adverse to quality in SA01-NE-008, "Self-Assessment Report, Post-Fire Safe

Shutdown, Electrical Fire Hazards Analysis," and in Callaway Action

Requests 200107132 and 20017174. This finding is of very low safety

significance because alarms in the control room would alert the operators to the

low condensate storage tank level in time to manually switch auxiliary feedwater

pump suction from the condensate storage tank to emergency service water.

ATTACHMENT

KEY POINTS OF CONTACT

Licensee

R. Affolter, Vice President, Nuclear

K. Barbour, System Engineer

K. Bruckerhoff, Fire Marschall/Emergency Preparedness Supervisor

L. Eitel, Fire Protection Engineer

M. Evans, Manager, Nuclear Engineering

E. Goss, System Engineer

L. Kanuckel, Superintendent, Quality Assurrance

J. Little, Safety Analysis Engineer

R. McCann, System Engineer

G. Olmstead, Assistant Operations Superintendent

S. Petzel, Regional Regulatory Affairs Engineer

R, Pohlman, System Engineer

M. Reidmeyer, Regional Regulatory Affairs Supervisor

K. Young, Manager, Regulatory Affairs

NRC

D. Loveless, Senior Reactor Analyst

P. Qualls, Office Nuclear Reactor Regulation

M. Salley, Office Nuclear Reactor Regulation

ITEMS OPENED AND CLOSED

Opened

05000483/2003007-01 URI Failure to protect associated circuits from fire

damage or provide diverse means to achieve safe

shutdown (Section 1R05.2)05000483/2003007-02 URI Failure to perform alternate shutdown manual

actions within the required times (Section 1R05.4)05000483/2003007-04 URI Alarm response procedure for smoke in control

room outside makeup duct was an inadequate

procedure (Section 1R05.9)

Opened and Closed

05000483/2003007-03 NCV Failure to take required compensatory actions

when CREVIS operation rendered the engineered

safety feature switchgear halon system inoperable

(Section 1R05.8)

-2-

Closed

05000483/2001007-01 URI Inoperable Control Room Halon Bank

DOCUMENTS REVIEWED

The following documents were selected and reviewed by the team to accomplish the objectives

and scope of the inspection and to support any findings:

Corrective Action Documents

Callaway Action Request 200107132, "SA01-NE-008 Finding - Fire Hazards Analysis

Inconsistency," dated 11/16/2001

Callaway Action Request 200107134, "SA01-NE-008 Finding - Fire Hazards Analysis on AFP

Pressure Transmitters," dated 11/16/2001

Callaway Action Request 200201889, Control Room Halon Bank Has Depressurized," dated

3/20/02

Union Electric Company Request for Resolution 16516, "Material Equivalency for Teledyne Big

Beam Module Emergency Light, Revision A, dated 08/09/99

Union Electric Company Request for Resolution 16731, Teledyne Emergency Battery Lights

with Three Lamps, Revision A, dated 06/03/96

Union Electric Company Request for Resolution 19214, Approve Use of Chairman Battery in

EBLs, Revision A, dated 11/02/98

Union Electric Company Request for Resolution 19638, "Change to Charging on Hot Area

Emergency Lights, Revision A, dated 03/15/99

Union Electric Company Request for Resolution 20817, Evaluate Fire Detector Spacing

Requirements," Revision A, dated 12/20/00

Union Electric Company Request for Resolution 21138, Evaluate Fire Rating of TCAFP

Blowout Panel," Revision A, dated 04/08/02

Union Electric Company Request for Resolution 22678, Design Basis of Control Room Cable

Trench Halon," Revision A, dated 09/23/03

Procedures

8.1.4.3, Callaway Design Criteria, Regulatory Guides and IEEE Standards, 05/03 OL-13

APA-ZZ-00701, Callaway Plant Nuclear Engineering, "Control of Fire Protection Impairments,"

06/12/02, Revision 9

-3-

APA-ZZ-00703, Callaway Plant Administrative Procedure Fire Protection Operability Criteria

and Surveillance Requirements, 08/21/01, Revision 13

APA-ZZ-00050, Halon Discharge Test for North Electrical Penetration Room Supplemental

Record to Pre-op Test Package CS-04KC02, 2/7/85

CS-04KC02, Union Electric Company Preoperational Test Procedure Fire Protection System

(Halon) Preoperational Test, 08/02/03, Revision 0

EE-002 Electrical Separation Criteria, 11/8/00, Revision 2

MSM-ZZ-FG002, Callaway Plant Maintenance Surveillance Procedure

Fire Damper Inspection and Drop Test, 08/15/03, Revision 3

MSM-KC-FW009, Callaway Plant Mechanical Surveillance Procedure, "Fire Hose Station

Inspection Outside RCA," 1/13/00, Revision 3

OSP-GK-0001A, Callaway Plant Operations Surveillance Procedure A Train Control Room

Filtration and Pressurization System Monthly Operability Verification, 02/26/03, Revision 3

OTN-GK-00001, Callaway Plant Normal Operating Procedure Control Building HVAC System,

02/19/03, Revision 11

OTS-QD-00001, Callaway Plant Procedure Emergency Light Tests, Revision 11

PM-17, Callaway Preventive Maintenance Procedure Annual Service of Fire Protection

Emergency Lighting, 07/22/03

SDP-KC-00001, "Requirements for and Duties of Compensatory Fire Watches," Revision 5

Calculations and Analyses

800 MHz Mobile Propagation Survey Log for Callaway Plant Power Block 4/18/96

Union Electric Company Callaway Plant Fire Protection Emergency Battery Lights White Paper

dated 04/30/96

CMP 91-1060, Formal Safety Evaluation - Permanent Removal of Halon Systems in Six

Switchgear Rooms in Control Building, Revision B

Callaway License Condition Letter to NRR, North Electrical Penetration Room Halon System,

dated 02/21/85

Plant Drawings

A-2803, Bechtel Standardized Nuclear Unit Power Plant System (SNUPPS) Architectural

Drawing Fire Delineation Floor Plan, El 2026', Revision 7

-4-

E-2F3301, Bechtel SNUPPS Drawing Fire Detection/Protection System Control Building,

El-2000' and El 2016', Revision 11

E-2F3101, Bechtel SNUPPS Drawing Fire Detection/Protection System Control Building,

El-1974' and El 1984', Revision 4

A-2804, Bechtel SNUPPS Architectural Drawing Fire Delineation Floor Plan, El 2047',

Revision 20

A-2801, Bechtel SNUPPS Architectural Drawing Fire Delineation Floor Plan, El 1974',

Revision 1

A-2802, Bechtel SNUPPS Architectural Drawing Fire Delineation Floor Plan, El 2000',

Revision 10

E-23RP13, Callaway Plant Electrical Schematic Drawing Lock-Out Relay Contact Development

Sep. Grp. 6, Revision 2

E-2L9903, Bechtel SNUPPS Public Address System Riser Diagram, Revision 49

J-24001, Bechtel SNUPPS Control Room Equipment Arrangement, Revision 11

E-2R3321, Bechtel SNUPPS Raceway Plan Communication Corridor EL 2000', Revision 2

E-2R3212(Q), Bechtel SNUPPS Exposed Conduit Control Building EL 1984', Revision 19

E-2R3211(Q), Bechtel SNUPPS Raceway Plan Control Building EL 1984', Revision 4

E-21001(Q), Callaway Plant Main Single Line Diagram Electrical, Revision 10

E-0R3211(Q), Bechtel SNUPPS Raceway Plan Control Building EL 1974', Revision 8

E-23BB24, Callaway Plant Schematic Diagram Pressurizer Heater Backup Group B, Revision

1

E-23RP15(Q), Callaway Plant Electrical Schematic Drawing Lock-Out Relay Control Circuits

RP334/RP335, Revision 2

E-23RP11(Q), Callaway Plant Electrical Schematic Drawing Lock-Out Relay Contact

Development Sep. Grp. 2, Revision 1

E-23RP12(Q), Callaway Plant Electrical Schematic Drawing Lock-Out Relay Contact

Development Sep. Grp. 4, Revision 3

Miscellaneous Documents

NUREG 0830, Safety Evaluation Report related to the operation of Callaway Plant, Unit No. 1,

dated October 1981

-5-

NUREG 0830, Supplement No. 3, Safety Evaluation Report related to the operation of

Callaway Plant, Unit No. 1, dated October 1983

NUREG 0830, Supplement No. 4, Safety Evaluation Report related to the operation of

Callaway Plant, Unit No. 1, dated October 1984

NUREG-1058, "Technical Specifications, Callaway Plant, Unit No. 1, Appendix 'A' to License

No. NFP-30", Revision 1

Callaway Plant Individual Plant Examination of External Events

Letter to Mr. Harold R. Denton, Director, Office of Nuclear Reactor Regulation, USNRC from

Nicholas A. Petrick, Executive Director, Standardized Nuclear Unit Power Plant System, dated

February 1, 1984 (SLNRC 84-0013)

Letter to Mr. Harold R. Denton, Director, Office of Nuclear Reactor Regulation, USNRC from

Nicholas A. Petrick, Executive Director, Standardized Nuclear Unit Power Plant System, dated

February 1, 1984 (SLNRC 84-0014)

Letter to Mr. Harold R. Denton, Director, Office of Nuclear Reactor Regulation, USNRC from

Nicholas A. Petrick, Executive Director, Standardized Nuclear Unit Power Plant System, dated

February 24, 1984 (SLNRC 84-0037)

Letter to Mr. Harold R. Denton, Director, Office of Nuclear Reactor Regulation, USNRC from

Nicholas A. Petrick, Executive Director, Standardized Nuclear Unit Power Plant System, dated

August 23, 1984 (SLNRC 84-0109)

Letter to Mr. James G. Keppler, Regional Administrator, Region III, USNRC, from Donald R.

Schnell, Vice President, Union Electric Company, "Acceptability of Test Results for Control

Room Halon System (SKC07)," dated June 29, 1984 (ULNRC 857)

Letter to Mr. James G. Keppler, Regional Administrator, Region III, USNRC, from Donald R.

Schnell, Vice President, Union Electric Company, dated July 31, 1984 (ULNRC 893)

Memorandum to Harold R. Denton, Director, Office of Nuclear Reactor Regulation, USNRC

from James G. Keppler, Regional Administrator, Region III, USNRC, dated October 16, 1984

Minutes of August 22, 1984, Meeting with Kansas Gas and Electric and Union Electric

Company, issued by the USNRC on August 31, 1984

SA01-NE-008, "Self-Assessment Report, Post-Fire Safe Shutdown, Electrical Fire Hazards

Analysis," dated November 19, 2001

NRC Inspection Report No. 50-483/84-49(DRP), dated October 16, 1985

NRC Inspection Report No. 50-483/84-41(DRS), dated September 7, 1985

Callaway Plant Final Safety Analysis Report, Revision OL-13, dated May 23, 2003

-6-

Callaway Plant Final Safety Analysis Report, Site Addendum, Revision OL-13

Operating Quality Assurance Manual, Revision 23