ML023400575
| ML023400575 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 01/09/2003 |
| From: | Ernstes M Operator Licensing and Human Performance Branch |
| To: | Sumner H Southern Nuclear Operating Co |
| References | |
| 50-321/02-301, 50-366/02-301 50-321/02-301, 50-366/02-301 | |
| Download: ML023400575 (153) | |
See also: IR 05000321/2002301
Text
CONTENTS
1
2
3
4
5
6
"7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
QUESTIONS REPORT
for Revision4HT2002
2. 204000K5.08 001
Unit 1 is at 100% RTP. The I & C Techs have just completed the quarterly functional
surveillance for the RWCU Area High Temperature isolation instruments. The foreman
is reviewing the paperwork and notes that isolation setpoints for all the areas were set
to 1550F. He immediately notifies the Shift Supervisor.
Which ONE of the following describes the determination the Shift Supervisor should
make? (Provide TS Section 3.3.6.1 and Table 3.3.6.1-1)
A. This is not a problem because the setpoint per Tech Specs is < 1600F.
B! This is a problem and all of the instruments are INOPERABLE. The RWCU system
isolation capability must be restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
C. This is a problem and all of the instruments are INOPERABLE. Each channel must
be placed in the tripped condition within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> of INOPERABILITY.
D. This is not a problem if the I & C Techs can recalibrate the instruments within
tolerance provided the surveillance frequency hasn't expired.
References: Tech Spec section 3.3.6.1
Tech Spec Table 3.3.6.1-1
A. Incorrect since the Tech Spec setpoint is < 150 F.
B. Correct answer since isolation capability is not maintained since all channels are
C. Incorrect since isolation capability is not maintained per Bases definition.
D. Incorrect since the instruments should be declared INOPERABLE immediately.
RO Tier:
SRO Tier:
T2G2
Keyword:
RWCU ISOLATION
Cog Level:
C/A 2.6/2.6
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
2
Friday, October 11, 2002 06:51:25 AM
QUESTIONS REPORT
for Revision2 HT2002
30. 204000K5.08 001
Unit I is at 100% RTP. The I & C Techs have just completed the quarterly functional
surveillance for the RWCU Area High Temperature isolation instruments. The foreman
..
-
-
ý,t-
.--
,
,
oIn+nninfc fnr all the area s. were set
is reviewing the paperwork andu nIotVI
Lild soLi.,
a,
,o, ....
a.
.....
to 1550F. He immediately notifies the Shift Supervisor.
Which ONE of the following describes the determination the Shift Supervisor should
make? (Provide TS Section 3.3.6.1 and Table 3.3.6.1-1)
A. This is not a problem because the setpoint per Tech Specs is < 160 0F.
B.' This is a problem and all of the instruments are INOPERABLE. The RWCU system
isolation capability must be restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
C. This is a problem and all of the instruments are INOPERABLE. Each channel must
be placed in the tripped condition within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of INOPERABILITY.
D. This is not a problem if the I & C Techs can recalibrate the instruments within
tolerance provided the surveillance frequency hasn't expired.
References: Tech Spec section 3.3.6.1
Tech Spec Table 3.3.6.1-1
A. Incorrect since the Tech Spec setpoint is < 150 F.
B. Correct answer since isolation capability is not maintained since all channels are
C. Incorrect since isolation capability is not maintained per Bases definition.
D. Incorrect since the instruments should be declared
RO Tier:
SRO Tier:
Keyword:
RWCU ISOLATION
Cog Level:
Source:
N
Exam:
Test:
S
Misc:
Friday, September 20, 2002 09:23:23 AM
INOPERABLE immediately.
T2G2
C/A 2.6/2.6
HT02301
TCK
33
QUESTIONS REPORT
for HT2002
8. 204000K5.08 001
Unit I is at 100% RTP. The Instrument Maintenance Techs have just completed the
quarterly functional surveillance for the RWCU Area High Temperature isolation
instruments. The foreman is reviewing the paperwork and notes that isolation
setpoints for all the areas were set to 155 0F. He immediately notifies the Shift
Supervisor.
Which ONE of the following describes the determination theShift Supervisor should
make?
A. This is not a problem because the setpoint per Tech Specs is < 160 0F.
Bf This is a problem and all of the instruments are INOPERABLE. The RWCU system
isolation capability must be restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
C. This is a problem and all of the instruments are INOPERABLE. At least one
channel must be placed in the tripped condition witnin 1z hours.
D. This is not a problem if the Instrument Techs can recalibrate the instruments within
tolerance provided the surveillance frequency hasn't expired.
References: Tech Spec section 3.3.6.1
Tech Spec Table 3.3.6.1-1
A. incorrect since the Tech Spec setpoint is < 150 F.
B. Correct answer. Isolation capability is not maintained because no channels are
OPERABLE and none are in trip at this time.
C. Incorrect since Condition A allows 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to place a channel in trip.
D. Incorrect since the instruments should be declared
RO Tier:
SRO Tier:
Keyword:
RWCU ISOLATION
Cog Level:
Source:
N
Exam:
Test:
S
Misc:
INOPERABLE immediately.
T2G2
C/A 2.6/2.6
HT02301
TCK
Monday, June 24, 2002 08:16:46 AM
8
QUESTIONS REPORT
for HT2002
1. 204000K5.08 001
Unit 1 is at 100% RTP. The Instrument Maintenance Techs have just completed the
quarterly functional surveillance for the RWCU Area High Temperature isolation
instruments. The foreman is reviewing the paperwork and notes that isolation
setpoints for all the areas were set to 1551F. He notifies the Shift Supervisor
immediately.
Which ONE of the following describes the determination theShift Supervisor should
make?
A. This is not a problem because the setpoint per Tech Specs is < 1600F.
B.f This is a problem and all of the instruments are INOPERABLE. The RWCU system
isolation capability must be restored within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.
C. This is a problem and all of the instruments are INOPERABLE. At least one
channel must be placed in the tripped condition within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
D. This is not a problem if the Instrument Techs can recalibrate the instruments within
tolerance provided the surveillance frequency hasn't expired.
References: Tech Spec section 3.3.6.1
Tech Spec Table 3.3.6.1-1
A. Incorrect since the Tech Spec setpoint is < 150 F.
B. Correct answer. Isolation capability is not maintained because no channels are
OPERABLE and none are in trip at this time.
C. Incorrect since Condition A allows 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to place a channel in trip.
D. Incorrect since the instruments should be declared INOPERABLE immediately.
1
Friday, May 31, 2002 07:22:22 AM
Primary Containment Isolation Instrumentation
3.3.6.1
Table 3.3.6.1-1 (page 4 of 4)
Primary Containmnent Isolation Instrumrentation
APPLICABLE
CONDITIONS
MODES OR
REQUIRED
REFERENCED
OTHER
CHANNELS
FROM
SPECIFIED
PER TRIP
REQUIRED
SURVEILLANCE
ALLOWABLE
FUNCTION
CONDITIONS
SYSTEM
ACTION C.1
REQUIREMENTS
VALUE
4.
RCIC System Isolation
(continued)
g.
RCIC Suppression Pool
Area Differential
Temperature - High
h.
Emergency Area Cooler
Temperature - High
5.
RWCU System Isolation
a.
Area
Temperature - High
b.
Area Ventilation
Differential
Temperature - High
c.
SLC System Initiation
d.
Reactor Vessel Water
Level - Low Low,
Level 2
6.
System Isolation
a.
Reactor Steam Dome
Pressure - High
b.
Reactor Vessel Water
Level - Low, Level 3
1,2,3
1,2,3
1,2,3
1,2,3
1,2
1,2,3
1,2,3
3,4,5
I
F
F
1 per
area
1 per
area
11(c)
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
F
F
H
2
1
2 (d)
F
SR
SR
SR
SR
F
SR
SR
SR
SR
SR
SR
SR
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
Amendment No. 135
S 420F
S 169OF
5 1500 F
S67*F
NA
> -47 inches
Z 145 psig
Ž 0 inches
(c)
SLC System Initiation only inputs into one of the two trip systems.
(d) Only one trip system required in MODES 4 and 5 when RHR Shutdown Cooling System integrity maintained.
I
3.3-59
HATCH UNIT 2
Primary Containment Isolation Instrumentation
3.3.6.1
3.3
INSTRUMENTATION
3.3.6.1
Primary Containment Isolation Instrumentation
APPLICABILITY:
The primary containment isolation instrumentation
Function in Table 3.3.6.1-1 shall be OPERABLE.
According to Table 3.3.6.1-1.
for each
ACTIONS
-NOTE-
NOTE
Separate Condition entry is allowed for each channel.
CONDITION
REQUIRED ACTION
COMPLETION TIME
A.
One or more required
A.1
Place channel in
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for
channels inoperable,
trip.
Functions 2,a,
2.b, and 6.b
AND
24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for
Functions other
than Functions
2.a, 2.b, and
6.b
B. ---------NOTE --------
8.1
Restore isolation
I hour
Not applicable for
capability.
Function 5.c.
One or more automatic
Functions with
isolation capability
not maintained.
(continued)
4
Amendment No.
135
if
1
3.3-52
HATCH UNIT 2
Primary Containment Isolation Instrumentation
B 3.3.6.1
BASES
ACTIONS
A.1 (continued)
the channel in trip (e.g., as in the case where placing the
inoperable channel in trip would result in an isolation),
Condition C must be entered and its Required Action taken.
B.1
Required Action B.1 is intended to ensure that appropriate
actions are taken if multiple, inoperable, untripped
channels within the same Function result in automatic
isolation capability being lost for the associated
penetration flow path(s).
The MSL Isolation Functions are
considered to be maintaining isolation capability when
sufficient channels are OPERABLE or in trip, such that both
trip systems will generate a trip signal from the given
Function on a valid signal.
The other isolation functions
are considered to be maintaining isolation capability when
sufficient channels are OPERABLE or in trip, such that one
trip system will generate a trip signal from the given
Function on a valid signal.
This ensures that one of the
two PCIVs in the associated penetration flow path can
receive an isolation signal from the given Function.
As
noted, this Condition is not applicable for Function 5.c
(SLC System Initiation), since the loss of the single
channel results in a loss of the Function (one-out-of-one
logic).
This loss was considered during the development of
Reference 5 and considered acceptable for the 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
allowed by Required Action A.1.
The Completion Time is intended to allow the operator time
to evaluate and repair any discovered inoperabilities.
The
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> Completion Time is acceptable because it minimizes
risk while allowing time for restoration or tripping of
channels.
C.I
Required Action C.1 directs entry into the appropriate
Condition referenced in Table 3.3.6.1-1.
The applicable
Condition specified in Table 3.3.6.1-1 is Function and
MODE or other specified condition dependent and may change
as the Required Action of a previous Condition is completed.
(continued)
REVISION I
B 3.3-169
HATCH UNIT 2
QUESTIONS REPORT
for HT2002
9. 205000G2.1.22 001
Unit 2 is shutting down for a maintenance outage due to the failure of the "B" Recirc
pump which is out-of-service electrically. At 0100 on 4/12/02 reactor pressure went
below 145 psig and reactor temperature went below 300 0F. The following conditions
exist at 0400 on 4/12/02:
Reactor pressure
130 psig
Reactor temperature
285°F
Mode Switch position
S/D
At 0415 on 4/12/02 the "A" Recirc pump tripped and cannot be restarted due to bus
Which ONE of the following is required to be taken per Tech Specs?
(Provide copy of Tech Spec sections 3.3.6.1, 3.4.1, 3.4.7)
A. No action is required to be taken since Recirc Pumps are only required to be in
operation in Modes 1 and 2.
B. Initiate action to place Shutdown Cooling in operation within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> AND monitor
reactor coolant temperature and pressure once per hour.
-/
C. Initiate action to restore Shutdown Cooling to OPERABLE status immediately AND
verify reactor coolant circulation by an alternate method within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from
discovery of no reactor coolant circulation AND be in Mode 4 in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
D' No action is required for up 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at which time a Recirc Pump must be running
or Shutdown Cooling must be in operation.
n9
Monday, June 24, LUUt vo: i0,uv inVl
QUESTIONS REPORT
for HT2002
References: Tech Spec section 3.3.6.1, Primary Containment Isol Instrument
Tech Spec section 3.4.1, Recirc Loops Operating
Tech Spec section 3.4.7, RHR Shutdown Cooling
A. Incorrect since Reactor Coolant circulation is required in Mode 3 by Shutdown
Cooling or Recirc Pumps.
B. Incorrect since 3.4.7 requires action to place Shutdown Cooling or a Recirc Pump in
operation IMMEDIATELY provided NOTE 1 of the LCO is not used or expired.
C. Incorrect since these are the actions to take if Shutdown Cooling is INOPERABLE.
At this time Shutdown Cooling is OPERABLE since reactor pressure is below the
Shutdown Cooling low pressure permissive.
D. Correct answer.
RO Tier:
SRO Tier:
T2G2
Keyword:
Cog Level:
C/A 2.8/3.3
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
Monday, June 24, 2002 08:16:46 AM
10
QUESTIONS REPORT
for HT2002
1. 205000G2.1.22 001
Unit 2 is shutting down for a maintenance outage due to the failure of the "B" Recirc
pump which is out-of-service electrically. At 0100 on 4/12/02 reactor pressure went
below 145 psig and reactor temperature went below 300 F. The following conditions
exist at 0400 on 4/12/02:
Reactor pressure
130 psig
Reactor temperature
285 F
Mode Switch position
S/D
At 0415 on 4/12/02 the "A" Recirc pump tripped and cannot be restarted due to bus
overcurrent. What action is required to be taken per Tech Specs?
A. No action is required to be taken since Recirc Pumps are only required to be in
operation in Modes I and 2.
B. Initiate action to place Shutdown Cooling in operation within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> AND monitor
reactor coolant temperature and pressure once per hour.
C. Initiate action to restore Shutdown Cooling to OPERABLE status immediately AND
verify reactor coolant circulation by an alternate method within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from
discovery of no reactor coolant circulation AND be in Mode 4 in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Do No action is required for up 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at which time a Recirc Pump must be running
or Shutdown Cooling must be in operation.
References: Tech Spec section 3.3.6.1, Primary Containment Isol Instrument
Tech Spec section 3.4.1, Recirc Loops Operating
Tech Spec section 3.4.7, RHR Shutdown Cooling
A. Incorrect since Reactor Coolant circulation is required in Mode 3 by Shutdown
Cooling or Recirc Pumps.
B. Incorrect since 3.4.7 requires action to place Shutdown Cooling or a Recirc Pump in
operation IMMEDIATELY provided NOTE 1 of the LCO is not used or expired.
C. Incorrect since these are the actions to take if Shutdown Cooling is INOPERABLE.
At this time Shutdown Cooling is OPERABLE since reactor pressure is below the
Shutdown Cooling low pressure permissive.
D. Correct answer.
Monday, May 06, 2002 07:17:22 AM
Primary Containment Isolation Instrumentation
3.3.6.1
Table 3.3.6.1-1 (page 4 of 4)
Primary Containment Isolation Instrumentation
APPLICABLE
CONDITIONS
MODES OR
REQUIRED
REFERENCED
OTHER
CHANNELS
FROM
SPECIFIED
PER TRIP
REQUIRED
SURVEILLANCE
ALLOWABLE
FUNCTION
CONDITIONS
SYSTEM
ACTION C.1
REQUIREMENTS
VALUE
4.
RCIC System Isolation
(continued)
g.
RCIC Suppression Pool
Area Differential
Temperature - High
h.
Emergency Area Cooker
Temperature - High
5.
RWCU System Isolation
a.
Area
Temperature - High
b.
Area Ventilation
Differential
Temperature - High
c.
SLC System Initiation
d.
Reactor Vessel Water
Level - Low Low,
Level 2
6.
System Isolation
a.
Reactor Steam Dome
Pressure - High
b.
Reactor Vessel Water
Level - Low,
Level 3
F
1,2,3
1,2,3
1,2,3
1,2,3
1,2
1,2,3
1,2,3
3,4,5
1 per
area
1 per
area
1(c)
2
F
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
F
F
H
F
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
SR
SR
SR
SR
F
SR
SR
SR
SR
2(d)
SR
SR
SR
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3,3.6.1.2
3.3.6.1.5
3.3.6.1.6
3.3.6.1.1
3.3.6.1.2
3.3.6.1.5
3.3.6.1.6
Amendment No. 135
S 42°F
S 169*F
5 150°F
S67°F
NA
?:
-47 inches
- 145 psig
ý 0 inches
(c) SEC System Initiation only inputs into one of the two trip systems.
(d) Only one trip system required in MODES 4 and 5 when RHR Shutdown Cooling System integrity maintained.
1
I
3.3-59
HATCH UNIT 2
Recirculation Loops Operating
3.4.1
3.4
3.4.1
Recirculation Loops Operating
Two recirculation loops with matched flows shall be in
operation,
One recirculation loop shall be in operation with the
following limits applied when the associated LCO is
applicable:
a.
LCO 3.2.1, "AVERAGE PLANAR LINEAR HEAT GENERATION
(APLHGR)," single loop operation limits specified
COLR;
b.
LCO 3.2.2, "MINIMUM CRITICAL POWER RATIO (MCPR),"
loop operation limits specified in the COLR; and
RATE
in the
single
c.
LCO 3.3.1.1, "Reactor Protection System (RPS)
Instrumentation," Function 2.b (Average Power Range
Monitor Simulated Thermal Power--High), Allowable Value
of Table 3.3.1.1-1 is reset for single loop operation.
APPLICABILITY:
MODES 1 and 2.
Amendment No.
154
HATCH UNIT 2
I
I
3.4-1
RHR Shutdown Cooling System--Hot Shutdown
3.4.7
3.4
3.4.7 Residual
APPLICABILITY:
Heat Removal
(RHR)
Shutdown Cooling System -
Hot Shutdown
Two RHR shutdown cooling subsystems shall be OPERABLE and,
with no recirculation pump in operation, at least one RHR
shutdown cooling subsystem shall be in operation.
--- -NOTES --------------------------
I.
Both RHR shutdown cooling subsystems and recirculation
pumps may be removed from operation for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
per 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> period.
2.
One RHR shutdown cooling subsystem may be inoperable
for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> for performance of Surveillances.
MODE 3 with reactor steam dome pressure less than the RHR
low pressure permissive pressure.
ACTIONS
6
NOTES -----------------------------------
1.
LCO 3.0.4 is not applicable.
2. Separate Condition entry is allowed for each RHR shutdown cooling
subsystem.
CONDITION
REQUIRED ACTION
COMPLETION TIME
A. One or two RHR
subsystems inoperable.
A._
Initiate action to
restore RHR shutdown
cooling subsystem(s)
to OPERABLE status.
ANDý
Immediately
(continued)
E
Amendment No.
135
HATCH UNIT 2
3.4-16
RHR Shutdown Cooling System--Hot Shutdown
3.4.7
ACTIONS
CONDITION
A. (continued)
B. No RHR shutdown
cooling subsystem in
operation.
AND
No recirculation pump
in operation.
DFAnIIRFfl ACTION
I COMPLETION TIME
A.2
Verify an alternate
method of decay heat
removal is available
for each inoperable
subsystem.
AND
A.3
B.1
Be in MODE 4.
Initiate action to
restore one RHR
subsystem or one
recirculation pump
operation.
AND
B.2
to
Verify reactor
coolant circulation
by an alternate
method.
AND
I hour
24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
immediately
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from
discovery of no
circulation
AND
Once per
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
thereafter
B.3
Monitor reactor
Once per hour
coolant temperature
and pressure.
,^TrU
IIMTT 9
3.4-17
Amendment No.
135
I%6*[V
A l*blJ
.Iv
! ....
nl/ iL~nU*
QUESTIONS REPORT
for Revision4HT2002
3. 206000K5.08 001
Unit I is operating at 100% RTP. The HPCI isolation valves are being stroked and
timed per the Inservice Testing program when MO I E41 -F1 11 HPCI Vacuum Breaker
Isolation Valve failed to close. The Shift Supervisor directed HPCI Vacuum Breaker
Isolation Valve MO 1E41 -F1l04 to be closed and deactivated.
Which ONE of the following describes the time limit for deactivating MO 1 E41 -F1 04 per
Tech Specs and the effect on the HPCI system after the action(s) is/are taken?
(Provide Tech Spec section 3.6.1.3)
A. Actions must be taken within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI should be declared INOP and a 14 day
LCO entered per TS 3.5.1 .C.
B. Actions must be taken within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI should be declared INOP and a 14 day
LCO entered per TS 3.5.1 .C.
C. Actions must be taken within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI system should still be considered
OPERABLE because it can still perform its safety function.
D. Actions must be taken within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI system should still be considered
OPERABLE because it can still perform its safety function.
References: Tech Spec 3.6.1.3 for PCIVs
SI-LP-00501 Rev. 01, LT-00501 Fig. I
SI-LP-00501 Rev. 01, pg 8 of 46
A. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
INOPERABLE. Also, HPCI can still perform its function and should still be considered
B. Incorrect since HPCI can still perform its function and should still be considered
C. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
D. Correct answer.
RO Tier:
SRO Tier:
T2Gl
Keyword:
Cog Level:
C/A 3.0/3.2
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
3
Friday, October 11, 2002 06:51:25 AM
QUESTIONS REPORT
for Revision2 HT2002
31. 206000K5.08 001
Unit 1 is operating at 100% RTP. The HPCI isolation valves are being stroked and
timed per the Inservice Testing program when MO 1 E41-F1 11 HPCI Vacuum Breaker
Isolation Valve failed to close. The Shift Supervisor directed HPCI Vacuum Breaker
Isolation Valve MO 1E41-F104 to be closed and deactivated.
Which ONE of the following describes the time limit for deactivating MO 1 E41-F104 per
Tech Specs and the effect on the HPCI system after the action(s) is/are taken?
(Provide Tech Spec section 3.6.1.3)
A. Actions must be taken within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI should be declared INOP and a 14 day
LCO entered per TS 3.5.1.C.
B. Actions must be taken within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI should be declared INOP and a 14 day
LCO entered per TS 3.5.1.C.
C. Actions must be taken within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI system should still be considered
OPERABLE because it can still perform its design function.
D. Actions must be taken within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI system should still be considered
OPERABLE because it can still perform its design function.
References: Tech Spec 3.6.1.3 for PCIVs
SI-LP-00501 Rev. 01, LT-00501 Fig. 1
SI-LP-00501 Rev. 01, pg 8 of 46
A. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
INOPERABLE. Also, HPCI can still perform its function and should still be considered
B. Incorrect since HPCI can still perform its function and should still be considered
C. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than I PCIV in the penetration flow path and only 1 valve is
D. Correct answer.
RO Tier:
SROTier:
T2G1
Keyword:
Cog Level:
C/A 3.0/3.2
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
r
nAn
o
A
oo
fO
A
34
Friday, September 0,
- :
QUESTIONS REPORT
for HT2002
12. 206000K5.08 001
Unit I is operating at 100% RTP. The HPCI isolation valves are being stroked and
timed per the Inservice Testing program when MO F111 HPCI Vacuum Breaker
Isolation Valve failed to close. The Shift Supervisor directed HPCI Vacuum Breaker
Isolation Valve MO F104 to be closed and deactivated.
Which ONE of the following describes the time limit for deactivating MO F1 04 per Tech
Specs and the effect on the HPCI system after the action(s) is/are taken?
(Provide Tech Spec section 3.6.1.3)
A. Actions must be taken within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI should be declared INOP and a 14 day
LCO entered per TS 3.5.1.C.
B. Actions must be taken within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI should be declared INOP and a 14 day
LCO entered per TS 3.5.1.C.
C. Actions must be taken within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI system should still be considered
OPERABLE because it can still perform its design function.
Df Actions must be taken within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI system should still be considered
OPERABLE because it can still perform its design function.
References: Tech Spec 3.6.1.3 for PCIVs
SI-LP-00501 Rev. 01, LT-00501 Fig. 1
SI-LP-00501 Rev. 01, pg 8 of 46
A. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
INOPERABLE. Also, HPCI can still perform its function and should still be considered
B. Incorrect since HPCI can still perform its function and should still be considered
C. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
D. Correct answer.
RO Tier:
SRO Tier:
T2G0
Keyword:
Cog Level: C/A 3.0/3.2
-
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
Monday, June 24, 2002 08:16:47 AM
13
QUESTIONS REPORT
for HT2002
3. 206000K5.08 001
Unit 1 is operating at 100% RTP. The HPCI isolation valves are being stroked and
timed per the Inservice Testing program when MO F1 11 HPCI Vacuum Breaker
Isolation Valve failed to close. The Shift Supervisor directed HPCI Vacuum Breaker
Isolation Valve MO F104 to be closed and deactivated.
Which ONE of the following describes the time limit for deactivating MO F1 04 per Tech
Specs and the effect on the HPCI system after the action(s) is/are taken?
(Provide Tech Spec section 3.6.1.3)
A. HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI should be declared INOP and a 14 day LCO entered per TS
3.5.1 .C.
B. HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI should be declared INOP and a 14 day LCO entered per TS
C. HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI system should still be considered OPERABLE because it can
still perform its design function.
DW HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI system should still be considered OPERABLE because it can
still perform its design function.
References: Tech Spec 3.6.1.3 for PCIVs
SI-LP-00501 Rev. 01, LT-00501 Fig. 1
SI-LP-00501 Rev. 01, pg 8 of 46
A. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
INOPERABLE. Also, HPCI can still perform its function and should still be considered
B. Incorrect since HPCI can still perform its function and should still be considered
C. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than I PCIV in the penetration flow path and only 1 valve is
D. Correct answer.
4
Friday, May 31, 2002 03:24:45 PM
QUESTIONS REPORT
for HT2002
1. 206000K5.08 001
Unit I is operating at 100% RTP. The HPCI isolation valves are being stroked and
timed per the Inservice Testing program when the HPCI Vacuum Breaker Isolation
Valve MO F1 11 failed to close. SELECT the answer that meets the requirements of
Tech Specs and indicates the effect on the HPCI system after the action(s) is/are
taken?
A. HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI should be declared INOP and a 14 day LCO entered per TS
B. HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI should be declared INOP and a 14 day LCO entered per TS
3.5.1 C.
C. HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. HPCI system should still be considered OPERABLE because it can
still perform its design function.
D.* HPCI Vacuum Breaker Isolation Valve MO F104 must be closed and deactivated
within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. HPCI system should still be considered OPERABLE because it can
still perform its design function.
References: Tech Spec 3.6.1.3 for PCIVs
SI-LP-00501 Rev. 01, LT-00501 Fig. 1
SI-LP-00501 Rev. 01, pg 8 of 46
A. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
INOPERABLE. Also, HPCI can still perform its function and should still be considered
B. Incorrect since HPCI can still perform its function and should still be considered
C. Incorrect since the actions for Tech Spec 3.6.1.3 is 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to isolate the line since
there is more than 1 PCIV in the penetration flow path and only 1 valve is
D. Correct answer.
Wednesday, April 10, 2002 10:59:13 AM
Note:
Minimum recommended speed for Turbine operation is 2000
rpm based on maintaining adequate oil pressure for governor
operation and bearing lubrication. Above this speed there is also
sufficient steam flow through the Turbine to prevent turbine
exhaust valve chatter.
8.
The Exhaust Line Drain Pot removes condensation from the HPCI Turbine
Exhaust line drain when the HPCI system is in standby. Level in the Drain
Pot is controlled automatically by drain valve F053. F053 is interlocked
closed IF BOTH F001 AND TSV ARE NOT FULLY CLOSED. EITHER
F001 OR the TURBINE STOP VALVE must be closed for F053 to open
(both units). The drain pot discharges to the Barometric Condenser.
9.
The HPCI System Rupture Disks (D003 and D004) located in the Torus
Area protect the HPCI Turbine casing from excessive exhaust pressure. The
two diaphragms are in series and are designed to rupture at 150 psig. The
space between them is vented to the Torus area through an orifice. High
pressure between the diaphragms will cause a HPCI System Isolation at 10
psig.
10.
HPCI Exhaust Line Vacuum Breakers F102 and F103 prevent drawing a
vacuum on the exhaust line by steam condensation following turbine
shutdown. This vacuum would result in siphoning of Suppression Pool
water into the HPCI Exhaust line and could cause exhaust line damage on a
subsequent start.
11.
Vacuum Breaker Isolation Valves F104 and Fll1 are normally open and
will isolate the vacuum breaker piping if conditions indicate a possible
HPCI system leak. F104 and Fl 11 are AC operated MOVs powered from
R24-S01 1 and S012 respectively.
These valves automatically close on a combined signal of High
Drywell Pressure (set at 1.85 psig) and Low HPCI Steam Line
Pressure (set at 128 psig).
B.
Gland Seal Condenser System
The Gland Seal Condenser System prevents steam outliakage from the turbine
shaft seals, turbine stop valve, turbine control valve, and turbine exhaust drain
from entering the HPCI room. This outleakage could cause potential safety (High
temperatures) or airborne radiological hazards. The system automatically starts
on an auto-initiation of HPCL and consists of:
3.6
CONTAINMENT SYSTEMS
3.6.1.3
Primary Containment Isolation Valves (PCIVs)
APPLICABILITY:
Each PCIV, except reactor building-to-suppression chamber
vacuum breakers, shall be OPERABLE.
MODES 1, 2, and 3,
When associated instrumentation is required to be OPERABLE
per LCO 3.3.6.1, "Primary Containment Isolation
Instrumentation."
ACTIONS
---------------- -
NO T ES ----
------ -----
-
1.
Penetration flow paths except for 18 inch purge valve penetration flow
paths may be unisolated intermittently under administrative controls.
2.
Separate Condition entry is allowed for each penetration flow path.
3.
Enter applicable Conditions and Required Actions for systems made
inoperable by PCIVs.
4.
Enter applicable Conditions and Required Actions of LCO 3.6.1.1, "Primary
Containment," when PCIV leakage results in exceeding overall containment
leakage rate acceptance criteria.
-.....-
___-----------------------------------------------
CONDITION
REQUIRED ACTION
COMPLETION TIME
A. - --------
NOTE ---------
A.1
Isolate the affected
4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> except
Only applicable to
penetration flow path
for main steam
penetration flow paths
by use of at least
line
with two PCIVs.
one closed and de
activated automatic
AND
valve, closed manual
One or more
valve, blind flange,
8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> for main
penetration flow paths
or check valve with
steam line
with one PCIV
flow through the
inoperable except due
valve secured.
to leakage not within
limit.
AND
(continued)
Amendment No.
135
HATCH UNIT 2
3.6.1.3
4
4
4
3.6-8
PCIVS
3.6.1.3
ACTIONS
CONDITION
A. (continued)
REQUIRED ACTION
A.2
- --------
NOTE------
Isolation devices in
may be verified by
use of administrative
means.
Verify the affected
penetration flow path
is isolated.
3.6-9
COMPLETION TIME
Once per 31 days
for isolation
devices outside
primary
containment
AND
Prior to
entering MODE 2
or 3 from MODE 4
if primary
containment was
de-inerted while
in MODE 4, if
not performed
within the
previous
92 days, for
isolation
devices inside
primary
containment
(continued)
Amendment No. 135
HATCH UNIT 2
3.6.1.3
6
1/2>_
C. - -------- NOTE------
Only applicable to
penetration flow paths
with only one PCIV.
One or more
penetration flow paths
with one PCIV
inoperable except due
to leakage not within
limits.
_____________________________________________________________i
C.1
AND
C.2
Isolate the affected
penetration flow path
by use of at least
one closed and de
activated automatic
valve, closed manual
valve, or blind
- --------
NOTE------
Valves and blind
flanges in high
radiation areas may
be verified by use of
administrative means.
Verify the affected
penetration flow path
is isolated.
4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> except
for excess flow
(EFCV) line
AND
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for
EFCV line
a
Once per 31 days
(continued)
C
/
Amendment No.
135
HATCH UNIT 2
3.6-10
CONDITION
REQUIRED ACTION
COMPLETION TIME
B. ----------
NOTE ---------
B.1
Isolate the affected
I hour
Only applicable to
penetration flow path
penetration flow paths
by use of at least
with two PCIVs.
one closed and de
activated automatic
valve, closed manual
One or more
valve, or blind
.penetration flow paths
with two PCIVs
inoperable except due
to leakage not within
limit.
ArTIAtIC
f,-nn+in;iprl
Vacuum
Pump
(S022)
HPCI SYSTEM
(
(SIMPLIFIED DIAGRAM)
LT-00501 Fig 1
Page 33 of 4
QUESTIONS REPORT
for HT2002
14. 2090010G2.2.21 001
The "A" Core Spray system on Unit 1 was taken out-of-service to inspect the pump
internals due to high vibration. Foreign material was found inside the pump and no
additional repairs were necessary. The unit is in Day 5 of a 7 day LCO and the system
has been returned to service, filled and vented.
Which ONE of the following indicates the surveillances that are required to be
performed prior to declaring "A" Core Spray operable?
A. SR 3.5.1.1 piping filled from pump disch to injection valve, SR 3.5.1.7 flow rate test,
SR 3.5.1.10 subsystem actuates on initiation signal.
B. SR 3.5.1.1 piping filled from pump disch to injection valve, SR 3.5.1.2 valve position
verification, SR 3.5.1.7 flow rate test, SR 3.5.1.10 subsystem actuates on initiation
signal.
C. SR 3.5.1.2 valve position verification, SR 3.5.1.7 flow rate test, SR 3.5.1.10
subsystem actuates on initiation signal, SR 3.5.1.13 ECCS Response time.
D' SR 3.5.1.1 piping filled from pump disch to injection valve, SR 3.5.1.2 valve position
verification, SR 3.5.1.7 flow rate test.
Reference: Tech Spec Bases SR 3.0.1
A. Incorrect since SR 3.5.1.10 does not need to be performed since no work was done
on the Core Spray Logic and SR 3.5.1.2 does need to be performed since valves in the
system were out of the normal Operable lineup.
B. Incorrect since SR 3.5.1.10 does not need to be performed since no work was done
on the Core Spray Logic.
C. Incorrect since SR 3.5.1.10 and SR 3.5.1.13 do not need to be performed since no
work was done on the Core Spray Logic. Also, SR 3.5.1.1 does need to be performed
since system was drained.
D. Correct answer.
ROTier:
SROTier:
T2G1
Keyword:
TECH SPEC
Cog Level:
C/A 2.3/3.5
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
Monday, June 24, 2002 08:16:47 AM
16
QUESTIONS REPORT
for HT2002
1. 209001G2.2.21 001
The "A" Core Spray system on Unit I was taken out-of-service to inspect the pump
internals due to high vibration. Foreign material was found inside the pump and no
additional repairs were necessary. The unit is in Day 5 of a 7 day LCO and the system
has been returned to service, filled and vented. Which surveillances are required to be
performed prior to declaring A Core Spray operable?
A. SR 3.5.1.1 piping filled from pump disch to injection valve, SR 3.5.1.7 flow rate test,
SR 3.5.1.10 subsystem actuates on initiation signal.
B. SR 3.5.1.1 piping filled from pump disch to injection valve, SR 3.5.1.2 valve position
verification, SR 3.5.1.7 flow rate test, SR 3.5.1.10 subsystem actuates on initiation
signal.
C. SR 3.5.1.2 valve position verification, SR 3.5.1.7 flow rate test, SR 3.5.1.10
subsystem actuates on initiation signal, SR 3.5.1.13 ECCS Response time.
D' SR 3.5.1.1 piping filled from pump disch to injection valve, SR 3.5.1.2 valve position
verification, SR 3.5.1.7 flow rate test.
Reference: Tech Spec Bases SR 3.0.1
A. Incorrect since SR 3.5.1.10 does not need to be performed since no work was done
on the Core Spray Logic and SR 3.5.1.2 does need to be performed since valves in the
system were out of the normal Operable lineup.
B. Incorrect since SR 3.5.1.10 does not need to be performed since no work was done
on the Core Spray Logic.
C. Incorrect since SR 3.5.1.10 and SR 3.5.1.13 do not need to be performed since no
work was done on the Core Spray Logic. Also, SR 3.5.1.1 does need to be performed
since system was drained.
D. Correct answer.
Monday, May 06, 2002 07:42:08 AM
1
SR Applicability
B 3.0
B 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY
BASES
SRs
SR 3.0.1 through SR 3.0.4 establish the general requirements
applicable to all Specifications and apply at all times, unless otherwise
stated.
SR 3.0.1 establishes the requirement that SRs must be met during the
MODES or other specified conditions in the Applicability for which the
requirements of the LCO apply, unless otherwise specified in the
individual SRs. This Specification is to ensure that Surveillances are
performed to verify the OPERABILITY of systems and components,
and that variables are within specified limits. Failure to meet a
Surveillance within the specified Frequency, in accordance with
SR 3.0.2, constitutes a failure to meet an LCO.
Systems and components are assumed to be OPERABLE when the
associated SRs have been met. Nothing in this Specification,
however, is to be construed as implying that systems or components
are OPERABLE when:
a.
The systems or components are known to be inoperable,
although still meeting the SRs; or
b.
The requirements of the Surveillance(s) are known to be not
met between required Surveillance performances.
Surveillances do not have to be performed when the unit is in a
MODE or other specified condition for which the requirements of the
associated LCO are not applicable, unless otherwise specified. The
SRs associated with a Special Operations LCO are only applicable
when the Special Operations LCO is used as an allowable exception
to the requirements of a Specification.
Surveillances, including Surveillances invoked by Required Actions,
do not have to be performed on inoperable equipment because the
ACTIONS define the remedial measures that apply. Surveillances
have to be met and performed in accordance with SR 3.0.2, prior to
returning equipment to OPERABLE status.
Upon completion of maintenance, appropriate post maintenance
testing is required to declare equipment OPERABLE. This includes
ensuring applicable Surveillances are not failed and their most recent
performance is in accordance with SR 3.0.2. Post maintenance
(continued)
HATCH UNIT 1
B 3.0-9
REVISION 0
SR Applicability
B3.0
BASES
testing may not be possible in the current MODE or other specified
(continued)
conditions in the Applicability due to the necessary unit parameters
not having been established. In these situations, the equipment may
be considered OPERABLE provided testing has been satisfactorily
completed to the extent possible and the equipment is not otherwise
believed to be incapable of performing its function. This will allow
operation to proceed to a MODE or other specified condition where
other necessary post maintenance tests can be completed.
Some examples of this process are:
a.
Control Rod Drive maintenance during refueling that requires
scram testing at > 800 psi. However, if other appropriate
testing is satisfactorily completed and the scram time testing of
SR 3.1.4.3 is satisfied, the control rod can be considered
OPERABLE. This allows startup to proceed to reach 800 psi
to perform other necessary testing.
b.
High pressure coolant injection (HPCI) maintenance during
shutdown that requires system functional tests at a specified
pressure. Provided other appropriate testing is satisfactorily
completed, startup can proceed with HPCI considered
OPERABLE. This allows operation to reach the specified
pressure to complete the necessary post maintenance testing.
SR 3.0.2 establishes the requirements for meeting the specified
Frequency for Surveillances and any Required Action with a
Completion Time that requires the periodic performance of the
Required Action on a "once per..." interval.
SR 3.0.2 permits a 25% extension of the interval specified in the
Frequency. This extension facilitates Surveillance scheduling and
considers plant operating conditions that may not be suitable for
conducting the Surveillance (e.g., transient conditions or other
ongoing Surveillance or maintenance activities).
The 25% extension does not significantly degrade the reliability that
results from performing the Surveillance at its specified Frequency.
This is based on the recognition that the most probable result of any
particular Surveillance being performed is the verification of
conformance with the SRs. The exceptions to SR 3.0.2 are those
Surveillances for which the 25% extension of the interval specified in
the Frequency does not apply. These exceptions are stated in the
individual Specifications. The requirements of regulations take
(continued)
HATCH UNIT 1
B 3.0-10
REVISION 0
QUESTIONS REPORT
for HT2002
25. 215004K5.03 001
A startup is in progress on Unit I with all the IRM's on Range 4. The Control Board
Operator is in the process of withdrawing SRM's to keep the rod block cleared when it
is determined that SRM "A" will not retract. All attempts to free the SRM have failed
and Upper Management decides to continue with the startup and to leave the SRM
inserted.
Which ONE of the following states IF and WHEN the SRM should be declared
A. Declare "A" SRM INOPERABLE immediately, since the SRM cannot be moved.
B/ Declare "A" SRM INOPERABLE when it is bypassed to continue with the startup.
C. You don't have to consider the SRM Inoperable since the SRM's are not required
with IRM's on range 3 or above.
D. Declare "A" SRM INOPERABLE when the "A" SRM reading deviates by >200 cps
from the other 3 SRM's.
References: Tech Spec 3.3.1.2, Source Range Monitor (SRM) Instrumentation
Tech Spec 3.3.1.2 Bases
Technical Requirements Manual Table 3.3.2-1
34SV-SUV-019-2S, Surveillance Checks Rev. 32.3 pg 21 of 59
(NOTE) If this question is unacceptable then HATCH99,1NK #96 may be
used in its place.
A. Incorrect since the SRM is currently performing its function and there isn't a
requirement that the detector move.
B. Correct answer. The SRM has to be bypassed prior to continuing with the startup
since there is a rod block inserted when the SRM reaches the high limit of 7 X 10e4.
C. Incorrect since the
on range 8 or above.
D. Incorrect since the
RO Tier:
Keyword:
Source:
N
Test:
S
Rod Block function of the SRM's are required until the IRM's are
deviation is figured as the Max
SRO Tier:
Cog Level:
Exam:
Misc:
divided by Min < 20.
T2G I
C/A 2.8/2.8
HT02301
TCK
27
Monday, June 24, 2002 08:16:48 AM
QUESTIONS REPORT
for HT2002
1. 215004K5.03 001
A startup is in progress on Unit 1 with all the IRM's on Range 4. The Control Board
Operator is in the process of withdrawing SRM's to keep the rod block cleared when it
is determined that SRM "A" will not retract. All attempts to free the SRM have failed
and Upper Management decides to continue with the startup and to leave the SRM
inserted. As Shift Supervisor, determine IF and WHEN the SRM should be declared
A. Declare "A" SRM INOPERABLE immediately, since the SRM cannot be moved.
B! Declare "A" SRM INOPERABLE when it is bypassed to continue with the startup.
C. You don't have to consider the SRM Inoperable since the SRM's are not required
with IRM's on range 2 or above.
D. Declare "A" SRM INOPERABLE when the "A" SRM reading deviates by >200 cps
form the other 3 SRM's.
References: Tech Spec 3.3.1.2, Source Range Monitor (SRM) Instrumentation
Tech Spec 3.3.1.2 Bases
34SV-SUV-019-2S, Surveillance Checks Rev. 32.3 pg 21 of 59
7
(NOTE) If this question is unacceptable then HATCH99.BNK #96 may be
used in its place.
A. Incorrect since the SRM is currently performing its function and there isn't a
requirement that the detector move.
B. Correct answer. The SRM has to be bypassed prior to continuing with the startup
since there is a rod block inserted when the SRM reaches the high limit of 7 X 1 0e4.
C. Incorrect since the SRM's are required until the IRM's are on range 8 or above.
D. Incorrect since the deviation is figured as the Max divided by Min < 20.
Friday, May 03, 2002 07:48:40 AM
Control Rod Block Instrumentation
T 3.3.2
Table T3.3.2-1 (Page 1 of 2)
Control Rod Block Instrumentation
APPLICABLE
MODES OR
REQUIRED
OTHER
CHANNELS
SPECIFIED
PER
SURVEILLANCE
ALLOWABLE
FUNCTION
CONDITIONS
FUNCTION
REQUIREMENTS
VALUE
1.
3
a. Detector Not Full In
5 (e)
2(c)
b.
Upscale
2 (b)
3
5
c. Inoperative
d.
Downscale
2(c)
5
3
2 (b)
3
2 (b)
5
2.
a. Detector Not Full In
b. Upscale
c.
Inoperative
d. Downscale
2,5(e)
2,5
2,5
2(d)
6
6
6
6
TSR 3.3.2.1
TSR 3.3.2.1
TSR 3.3.2.1
TSR 3.3.2.3
TSR 3.3.2.1
TSR 3.3.2.3
TSR 3.3.2.1
TSR 3.3.2.1
TSR 3.3.2.1
TSR 3.3.2.3
TSR 3.3.2.1
TSR 3.3.2.3
TSR 3.3.2.1
TSR 3.3.2.1
TSR 3.3.2.3
TSR 3.3.2.1
TSR 3.3.2.1
TSR 3.3.2.3
NA
NA
_O
105 cps
< 105 cps
NA
NA
Ž 3 cps
> 3 cps
_<
N/A
108/125 of full
scale
NA
> 5/125 of full
scale
(continued)
(a) With IRMs on Range 2 or below.
(b) Only one SRM is required to be OPERABLE during spiral offload or reload when the fueled region
includes only that SRM detector.
(c) With IRMs on Range 7 or below.
(d)
With IRMs on Range 2 or above.
(e) This function is not required if the detector is verified to be in the fully inserted position and the drive
motor is deactivated.
Revision 24
T 3.3-5
HATCH UNIT 2 TRM
2(a)
SOUTHERN NUCLEAR
PAGE 21 OF 59
PLANT E. I. HATCH
DOCUMENT TITLE:
DOCUMENT NUMBER:
REVNER NO:
SURVEILLANCE CHECKS
32.3
PANEL - INSTRUMENT / TECH SPEC.
2H11-P689 - 2011-K621A, W.R. Drywell Radiation
2H1 1-P690 - 2D1 1-K621B. W.R. Drywell Radiation
ConfimI max minus mi < 10 for Items in 7.5.1
(SR 3.3.3.1.1 for 3.3.3.1-1(5.)),
(SR 3.3.6.1.1 for 3.3.6.1-1(2.c.))
N
OPER COND
1,2,3
B
1 1,2,3
a
7.5.3
2D21-P600 - Area Rad Monitors
I Ba
6
I
a
2D21-P600 - 2D211-K601A, Area Rad. Monitor
- 2D21-K601M, Area RMd. Monitor
(TSR 3.3.7.1 for T3.3.7-1 14.))
Confirm Max Divided by
Min <- 5 for Items in 7.5.4.
(TSR 3.3.7.1 for T3.3.7-1
.241)
2H1 1-P606 - 2C51-K600A, SRM A CPS
- 2C51-K600B, SRM B CPS
- 2C51 -K600C, SIRM C CPS
- 2C51-K600D, SRM D CPS
(SR 3.3.1.2.4 for 3.3.1.2-1(1.))
Confirm max divided by min _< 20 for items in 7.5.6
(SR 3.3.1.2.1 AND 3.3.1.2.3 for 3.3.1.2-1 (1 .))
2H1 1-13606 - 2C51-K501 A thru H, IRM Channel
Check
(SR 3.3.1.1.1 for 3.3.1.1-1(1.a.))
2H11-P608 - 2C51-K615A thru D, APRM Channel
Check
(SR 3.3.1.1.1 for 3.3.1.1-1(2.a.)(2.b.)(2.c.)
(2 e Wh'2
f) SR 3.10.8.1)
B
B
B
B,
BB
B,
7.5.10
2H1 1-P608 - 2C51-K617A thru D, APRM 2 of 4 Voter
C,
,Logic
Module
cc
1,2,3,(*)
2(5-),3,4,
5
5
2,5($)
1,2,5(+)
1,2,5(+)
Calculations verified
/
Ninht I Day
FREQ TS - OPER LIM
a
< 138 RIHR
On scale
On scale AND
< 20 mr/hr.
a
> 3 cps
AND detector
full-in
a
a
On scale and
a
difference
between
Highest Range
and Lowest
Range eS 3
SELF-TEST OK
a
NO ERROR
MESSAGES.
All APRMs read
within 3%
power of
each other
Lamp test,
a
All LED's lit
Initials
(*) During movement of irradiated fuel assemblies in the secondary containment, during CORE ALTERATIONS, during OPDRVs.
($) With any control rod withdrawn from a core cell containing one or more fuel assemblies.
(+) During Shutdown Margin Testing.
(**) With IRM's on Range 2 OR below.
G16.30
MGR-0001 Rev 3
7.5.1
7.5.2
7.5.4
7.5.5
7.5.6
7.5.7
7.5.8
7.5.9
I
NIGHTFDAY
1,2,3,(*)
a
Time
Date
SRM Instrumentation
3.3.1.2
Table 3.3.1.2-1 (page 1 of 1)
Source Range Monitor Instrumentation
APPLICABLE
MODES OR OTHER
SPECIFIED
REQUIRED
SURVEILLANCE
FUNCTION
CONDITIONS
CHANNELS
REQUIREMENTS
1.
Source Range Monitor
2(a)
3,4
5
2
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
2(b)(c)
3.3.1.2.1
3.3.1.2.4
3.3.1.2.6
3.3.1.2.7
3.3.1.2.3
3.3.1.2.4
3.3.1.2.6
3.3.1.2.7
3.3.1.2.1
3.3.1.2.2
3.3.1.2.4
3.3.1.2.5
3.3.1.2.7
(a)
With IRMs on Range 2 or below.
(b)
Only one SRM channel is required to be OPERABLE during spiral off load or reload when the fueled region includes
only that SRM detector.
(c)
Special movable detectors may be used in place of SRMs if connected to normal SRM circuits.
4
Amendment No. 195
HATCH UNIT 1
3.3-14
a
3
SRM Instrumentation
B 3.3.1.2
BASES
LCO
(continued)
APPLICABILITY
ACTIONS
indication can be generated. These special detectors provide more
flexibility in monitoring reactivity changes during fuel loading, since
they can be positioned anywhere within the core during refueling.
They must still meet the location requirements of SR 3.3.1.2.2 and all
other required SRs for SRMs.
For an SRM channel to be considered OPERABLE, it must be
providing neutron flux monitoring indication.
The SRMs are required to be OPERABLE in MODES 2, 3, 4, and 5
prior to the IRMs being on scale on Range 3 to provide for neutron
monitoring. In MODE 1, the APRMs provide adequate monitoring of
reactivity changes in the core; therefore, the SRMs are not required.
In MODE 2, with IRMs on Range 3 or above, the IRMs provide
adequate monitoring and the SRMs are not required.
A.1 and B.1
In MODE 2, with the IRMs on Range 2 or below, SRMs provide the
means of monitoring core reactivity and criticality. With any number of
the required SRMs inoperable, the ability to monitor neutron flux is
degraded. Therefore, a limited time is allowed to restore the
inoperable channels to OPERABLE status.
Provided at least one SRM remains OPERABLE, Required Action A.1
allows 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to restore the required SRMs to OPERABLE status.
This time is reasonable because there is adequate capability
remaining to monitor the core, there is limited risk of an event during
this time, and there is sufficient time to take corrective actions to
restore the required SRMs to OPERABLE status or to establish
alternate IRM monitoring capability. During this time, control rod
withdrawal and power increase is not precluded by this Required
Action. Having the ability to monitor the core with at least one SRM,
proceeding to IRM Range 3 or greater (with overlap required by
SR 3.3.1.1.6), and thereby exiting the Applicability of this LCO, is
acceptable for ensuring adequate core monitoring and allowing
continued operation.
With three required SRMs inoperable, Required Action B.1 allows no
positive changes in reactivity (control rod withdrawal must be
immediately suspended) due to inability to monitor the changes.
Required Action A.1 still applies and allows 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to restore
(continued)
HATCH UNIT 1
REVISION 0
B 3.3-35
SRM Instrumentation
B 3.3.1.2
BASES
ACTIONS
A.1 and B.1 (continued)
monitoring capability prior to requiring control rod insertion. This
allowance is based on the limited risk of an event during this time,
provided that no control rod withdrawals are allowed, and the desire to
concentrate efforts on repair, rather than to immediately shut down,
C.1
In MODE 2, if the required number of SRMs is not restored to
OPERABLE status within the allowed Completion Time, the reactor
shall be placed in MODE 3. With all control rods fully inserted, the
core is in its least reactive state with the most margin to criticality.
The allowed Completion Time of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is reasonable, based on
-operating experience, to reach MODE 3 from full power conditions in
an orderly manner and without challenging plant systems.
D.1 and D.2
With one or more required SRMs inoperable in MODE 3 or 4, the
neutron flux monitoring capability is degraded or nonexistent. The
requirement to fully insert all insertable control rods ensures that the
reactor will be at its minimum reactivity level while no neutron
monitoring capability is available. Placing the reactor mode switch in
the shutdown position prevents subsequent control rod withdrawal by
maintaining a control rod block. The allowed Completion Time of
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is sufficient to accomplish the Required Action, and takes into
account the low probability of an event requiring the SRM occurring
during this interval.
E.1 and E.2
With one or more required SRMs inoperable in MODE 5, the ability to
detect local reactivity changes in the core during refueling is
degraded. CORE ALTERATIONS must be immediately suspended
and action must be immediately initiated to fully insert all insertable
control rods in core cells containing one or more fuel assemblies.
Suspending CORE ALTERATIONS prevents the two most probable
causes of reactivity changes, fuel loading and control rod withdrawal,
from occurring. Inserting all insertable control rods ensures that the
reactor will be at its minimum reactivity given that fuel is present in the
(continued)
HATCH UNIT 1
B 3.3-36
REVISION 0
SRM Instrumentation
B 3.3.1.2
BASES
/
ACTIONS
E.1 and E.2 (continued)
core. Suspension of CORE ALTERATIONS shall not preclude
completion of the movement of a component to a safe, conservative
position.
Action (once required to be initiated) to insert control rods must
continue until all insertable rods in core cells containing one or more
fuel assemblies are inserted.
SURVEILLANCE
As Noted at the beginning of the SRs, the SRs for each SRM
REQUIREMENTS
Applicable MODE or other specified conditions are found in the SRs
column of Table 3.3.1.2-1.
The Surveillances are modified by a second Note to indicate that
when a channel is placed in an inoperable status solely for
performance of required Surveillances, entry into associated
Conditions and Required Actions may be delayed for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />,
provided the other required channel (or channels when 3 channels are
required) is OPERABLE. Upon completion of the Surveillance, or
expiration of the 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> allowance, the channel must be returned to
-'
OPERABLE status or the applicable Condition entered and Required
Actions taken. The Note is based upon a NRC Safety Evaluation
Report (Ref. 1) which concluded that the 6 hour6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> testing allowance
does not significantly reduce the probability of detecting power
changes, when necessary.
Performance of the CHANNEL CHECK ensures that a gross failure of
instrumentation has not occurred. A CHANNEL CHECK is normally a
comparison of the parameter indicated on one channel to a similar
parameter on another channel. It is based on the assumption that
instrument channels monitoring the same parameter should read
approximately the same value. Significant deviations between the
instrument channels could be an indication of excessive instrument
drift in one of the channels or something even more serious. A
CHANNEL CHECK will detect gross channel failure; thus, it is key to
verifying the instrumentation continues to operate properly between
each CHANNEL CALIBRATION.
Agreement criteria are determined by the plant staff based on a
combination of the channel instrument uncertainties, including
-j
(continued)
a ,_REVISION
15
HATCH UNIT 1
U 2.
"0
SRM Instrumentation
B 3.3.1.2
BASES
SURVEILLANCE
SR 3.3.1.2.1 and SR 3.3.1.2.3 (continued)
REQUIREMENTS
indication and readability. If a channel is outside the criteria, it may be
an indication that the instrument has drifted outside its limit.
The Frequency of once every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for SR 3.3.1.2.1 is based on
operating experience that demonstrates channel failure is rare. While
in MODES 3 and 4, reactivity changes are not expected; therefore,
the 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Frequency is relaxed to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for SR 3.3.1.2.3. The
CHANNEL CHECK supplements less formal, but more frequent,
checks of channels during normal operational use of the displays
associated with the channels required by the LCO.
To provide adequate coverage of potential reactivity changes in the
core when the fueled region encompasses more than one SRM, one
SRM is required to be OPERABLE in the quadrant where CORE
ALTERATIONS are being performed, and the other OPERABLE SRM
must be in an adjacent quadrant containing fuel. Note 1 states that
the SR is required to be met only during CORE ALTERATIONS. It is
not required to be met at other times in MODE 5 since core reactivity
changes are not occurring. This Surveillance consists of a review of
plant logs to ensure that SRMs required to be OPERABLE for given
CORE ALTERATIONS are, in fact, OPERABLE. In the event that
only one SRM is required to be OPERABLE (when the fueled region
encompasses only one SRM), per Table 3.3.1.2-1, footnote (b), only
the a. portion of this SR is required. Note 2 clarifies that more than
one of the three requirements can be met by the same OPERABLE
SRM. The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Frequency is based upon operating experience
and supplements operational controls over refueling activities that
include steps to ensure that the SRMs required by the LCO are in the
proper quadrant.
This Surveillance consists of a verification of the SRM instrument
readout to ensure that the SRM reading is greater than a specified
minimum count rate, which ensures that the detectors are indicating
count rates indicative of neutron flux levels within the core. This
surveillance also requires the signal to noise ratio to be verified to be
2 2:1. A signal to noise ratio that meets this requirement ensures the
detectors are inserted to an acceptable operating level. Therefore, to
meet this portion of the surveillance, it is necessary only to verify the
(continued)
HATCH UNIT 1
B 3.3-38
REVISION 15
QUESTIONS REPORT
for HT2002
29. 218000G2.2.22 001
"On 3/2/02 at 0800 Unit 2 is in Mode 1 when RCIC is declared inoperable and day 1 of
a 14 day LCO is entered. On 3/7/02 at 1600 the Instrument Techs start a surveillance
on a Drywell Pressure instrument associated with ADS Trip system A by valving the
instrument out. At 2200 they report to the Shift Supervisor that the instrument cannot
be calibrated and that no other instruments are affected.
Per Tech Specs, which ONE of the following is the latest time the channel shall be
placed in the tripped condition?
(Provide Tech Spec section 3.3.5.1 and 3.5.3)
A.! 2200 on 3/11/02.
B. 1600 on 3/11/02.
C. 2200 on 3/15/02.
D. 1600 on 3/15/02.
Reference: Tech Spec section3.3.5.1 and 3.5.3.
A. Correct answer.
B. Incorrect answer. Can delay the actions for Condition F for 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> due to note 2 for
surveillance requirements even though the instrument is inoperable.
C. Incorrect answer. Completion time in answer is 8 days from required action time.
This is wrong since RCIC is inoperable concurrent with this instrument.
D. Completion time in answer is 8 days from instrument being inoperable. This is wrong
since you can use the surveillance note of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and RCIC is also inoperable.
RO Tier:
SRO Tier:
T2G1
Keyword:
TECH SPEC
Cog Level:
C/A 3.4/4.1
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
31
Monday, June 24, 2002 08:16:49 AM
QUESTIONS REPORT
for HT2002
6. 218000G2.2.22 001
On 3/2/02 at 0800 Unit 2 is in Mode I when RCIC is declared inoperable and day 1 of
a 14 day LCO is entered. On 3/7/02 at 1600 the Instrument Techs start a surveillance
on a Drywell Pressure instrument associated with ADS Trip system A by valving the
instrument out. At 2200 they report to the Shift Supervisor that the instrument cannot
be calibrated and that no other instruments are affected. Per Tech Specs, what is the
latest time the channel shall be placed in the tripped condition?
A.r 2200 on 3/11/02.
B. 1600 on 3/11/0 2 .
C. 2200 on 3/15/02.
D. 1600 on 3/15/02.
Reference: Tech Spec section3.3.5.1 and 3.5.3.
A. Correct answer.
B. Incorrect answer. Can delay the actions for Condition F for 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> due to note 2 for
surveillance requirements even though the instrument is inoperable.
C. Incorrect answer. Completion time in answer is 8 days from required action time.
This is wrong since RCIC is inoperable concurrent with this instrument.
D. Completion time in answer is 8 days from instrument being inoperable. This is wrong
since you can use the surveillance note of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and RCIC is also inoperable.
Thursday, April 04, 2002 11:36:26 AM
6
ECCS Instrumentation
3.3.5.1
3.3 INSTRUMENTATION
3.3.5.1
Emergency Core Cooling System (ECCS) Instrumentation
APPLICABILITY:
The ECCS instrumentation for each Function in Table 3.3.5.1-1 shall be
According to Table 3.3.5.1-1.
---.
.--------..........--------------------------- NOTE ------------------------------------------------------------
Separate Condition entry is allowed for each channel.
CONDITION
REQUIRED ACTION
COMPLETION TIME
A.
One or more channels
B.
As required by Required
Action A.1 and referenced
in Table 3.3.5.1-1.
A.1
Enter the Condition
referenced in
Table 3.3.5.1-1 for the
channel.
B.1 -
NOTES ----------
1.
Only applicable in
MODES 1,2,
and 3.
2.
Only applicable for
Functions 1 .a, 1.b,
2.a, and 2.b.
- --------------------------------
Declare supported
feature(s) inoperable.
Immediately
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from discovery
of loss of initiation
capability for
feature(s) in both
divkinn*
AND
(continued)
3.3-33
Amendment No. 135
HATCH UNIT 2
ACTIONS
ECCS Instrumentation
3.3.5.1
ACTIONS (continued)
CONDITION
F.
As required by Required
Action A.1 and referenced
in Table 3.3.5.1-1.
G.
As required by Required
Action A.1 and referenced
in Table 3.3.5.1-1.
H. Required Action and
associated Completion
-r;m- ,.*f rnndfltinn R fl. fl.
- REQUIRED ACTION
F.1
Declare Automatic
Depressurization
System (ADS) valves
AND
F.2
G.1
Place channel in trip.
Declare ADS valves
AND
G.2
Restore channel to
OPERABLE status.
H.1
Declare associated
supported feature(s)
COMPLETION TIME
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from discovery
of loss of ADS
initiation capability in
both trip systems
96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> from
discovery of
inoperable channel
concurrent with HPCI
or reactor core
isolation cooling
AND
8 days
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from discovery
of loss of ADS
initiation capability in
both trip systems
96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> from
discovery of
inoperable channel
concurrent with HPCI
or RCIC inoperable
AND
8 days
Immediately
E, F, or G not met.
,, ,i,,-r ,
3.3-36
Amendment No. 135
rim I Uil
U1,4l I
I
4
ECCS Instrumentation
3.3.5.1
SURVEILLANCE REQUIREMENTS
.----------..........---------------------.......
NOTES ----------------------------------------------------------
1.
Refer to Table 3.3.5.1-1 to determine which SRs apply for each ECCS Function.
2.
When a channel is placed in an inoperable status solely for performance of required
Surveillances, entry into associated Conditions and Required Actions may be delayed as
follows: (a) for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for Functions 3.c and 3.f; and (b) for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> for
Functions other than 3.c and 3.f provided the associated Function or the redundant
Function maintains initiation capability.
SURVEILLANCE
Perform CHANNEL CHECK.
Perform CHANNEL FUNCTIONAL TEST.
Perform CHANNEL CALIBRATION.
Perform CHANNEL CALIBRATION.
Perform LOGIC SYSTEM FUNCTIONAL TEST.
FREQUENCY
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
92 days
92 days
18 months
18 months
3.3-37
Amendment No. 137
HATCH UNIT 2
I
ECCS Instrumentation
3.3.5.1
Table 3.3.5.1-1 (page 4 of 5)
Emergency Core Cooling System Instrumentation
APPLICABLE
CONDITIONS
MODES
REQUIRED
REFERENCED
OR OTHER
CHANNELS
FROM
SPECIFIED
PER
REQUIRED
SURVEILLANCE
ALLOWABLE
FUNCTION
CONDITIONS
FUNCTION
ACTION A.1
REQUIREMENTS
VALUE
4.
Automatic Depressurization
System (ADS) Trip System A
a.
Reactor Vessel Water
1,
2
F
k-113 inches
Level - Low Low Low,
2 (d), 3(d)
Level 1
b.
Drywell
1,
2
F
s 1.92 psig
Pressure - High
2(d), 3(d)
c.
Automatic
1,
G
5 114 seconds
Depressurization
2(d), 3(d)
System Initiation
Timer
d.
Reactor Vessel Water
1,
F
0 Oinches
Level - Low, Level 3
2(d), 3(d)
94
(Confirmatory)
e.
Core Spray Pump
1,
2
G
>Ž137 psig
Discharge Pressure -
2 (d), 3 (d)
and
High
-< 180 psig
f.
Low Pressure Coolant
1,
4
G
112 psig
Injection Pump
2(d), 3(d)
and
Discharge Pressure -
< 180 psig
High
g.
Automatic
1,
2
G
r 12 minutes
Depressurization
2 (d), 3(d)
18 seconds
System Low Water
Level Actuation Timer
(continued)
(d)
With reactor steam dome pressure> 150 psig.
Amendment No. 135
HATCH UNIT 2
3.3-41
QUESTIONS REPORT
for HT2002
48. 264000K5.06 001
Unit 1 is operating at 75% RTP when the following actions occur:
Reactor Scram
D/G "A" and "B" start and attain proper speed and voltage
D/G "C" fails to start
Reactor Water Level
-15" increasing
Drywell Pressure
4.5 psig
Drywell Temperature
200OF
Startup Transformers 1 C and 1D are De-Energized
Which ONE of the following lists the major loads on the "1 B" D/G and the sequence
that they started?
A. Core Spray "B", LPCI "C", LPCI "D".
B. LPCI "C", LPCI "D", PSW "C".
C. LPCI "B", LPCI "C", LPCI "D".
DO LPCI "C", LPCI "D", PSW "D".
Reference: LT-LP-02801 Rev 3 pg 49 and 50 of 87.
Copy of Electrical Lineup
A. Incorrect since "B" Core Spray pump is powered from DIG "C" only.
B. Incorrect since "C" PSW pump only starts if the "A" PSW pump fails to start.
C. Incorrect since "B" LPCI pump starts from D/G "C" only.
D. Correct answer. PSW pump "D" starts since the "C" D/G has failed to start which
powers the "B" PSW pump.
RO Tier:
SROTier:
T2G1
Keyword:
D/G START SEQUENCE
Cog Level: C/A 3.4/3.5
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
52
Monday, June 24, zuuz u0:16:5
AlVI
QUESTIONS REPORT
for HT2002
7. 264000K5.06 001
In regards to the Diesel Generator Loading Sequence, which ONE of the following
describes why the engineered safety feature (ESF) loads are applied automatically in
approx. 10 second intervals?
A. prevent overloading the DG output breaker and causing it to trip on overcurrent
from starting motor-driven pumps.
B. minimize the initial voltage increase due to starting the motor-driven pumps.
C. prevent a differential lockout due to high starting current from the motor-driven
pumps.
Df minimize the initial voltage drop due to starting the motor-driven pumps.
Reference: FSAR Section 8.3.1.1.3 F Sequential Loading
A. Incorrect since output breaker can handle current from starting all D/G loads at once.
B. Incorrect since starting pumps causes a voltage decrease instead of an increase.
C. Incorrect since the differential lockout is caused by an internal generator fault on
different phases.
D. Correct answer.
(This may be too easy for an SRO Only question)
8
Friday, May 31, 2002 03:24:45 PM
QUESTIONS REPORT
for HT2002
1. 264000K5.06 001
In regards to the Diesel Generator Loading Sequence, the engineered safety feature
(ESF) loads are applied automatically in approx. 10 second intervals to:
A. prevent overloading the DG output breaker and causing it to trip on overcurrent.
B. minimize the initial voltage increase due to starting the motor-driven pumps.
C. prevent a differential lockout due to high starting current from the motor-driven
pumps.
D. minimize the initial voltage drop due to starting the motor-driven pumps.
Reference: FSAR Section 8.3.1.1.3 F Sequential Loading
A. Incorrect since output breaker can handle current from starting all D/G loads at once.
B. Incorrect since starting pumps causes a voltage decrease instead of an increase.
C. Incorrect since the differential lockout is caused by an internal generator fault on
different phases.
D. Correct answer.
(This may be too easy for an SRO Only question)
Friday, May 10, 2002 08:07:23 AM
Page 49 of 87
LT-LP-02801-03
DIESEL GENERATORS
Review Attachment 2 with
NOTE:
Refer to Attachment 2 for detailed
students
sequence.
3.
Diesel Generator Start Failure
a.
If the time delayed (T2A and T2B) relays time
out (7 seconds) before the Low Speed Relay
deenergizes them, the Start Failure Relay (SFR)
is energized (diesel generator has cranked for 7
seconds without firing and has failed to start).
b.
The energized Start Failure Relay energizes the
Shutdown Relay (SDR) which seals in and stops
the diesel generator.
c.
The diesel generator can be returned to a standby
condition after the shutdown relay is manually
reset using the pushbutton on P652. The diesel
generator may now be restarted after a 100
second time delay.
EO 14
5.
Diesel Generator Loading Sequence
Table 02
a.
If the diesel generator started due to a LOSP
signal, it will tie to its respective 4160 VAC
emergency bus and initiate LOSP/LOCA Timers
and Load Shed Relays which will:
1)
Prior to the Diesel tying to the bus, all
loads on the respective 4160 VAC
emergency bus are Loadshed.
NOTE:
Loadshed is a term used to
describe the tripping of power
supply breakers to non-essential
loads. This in conjunction with
time delayed starts prevents
overloading the diesels.
2)
Immediately start both Core Spray Pumps
and LPCI RHR Pump C if a LOCA signal
exists. (T=12 seconds)
Figs 09 & 14
EO 15a
MKV-2(1) Normal fan
MKV-1(2) Backup fans
3)
10 seconds later, LPCI RHR Pumps A, D
and B start if a LOCA exists (T=22
seconds)
4)
8 seconds later, PSW Pumps A and B start
(T=30 seconds)
5)
2 seconds later, PSW Pump C start if PSW
pump A failed to start. (T=32 seconds)
6)
2 seconds later, PSW Pump D start if PSW
pump B failed to start. (T=34 seconds)
b.
This loading sequence prevents overloading the
diesel generator due to motor starting current.
6.
Diesel Generator Shutdown Sequence
NOTE:
Refer to Attachment 2 for detailed
sequence.
B.
Diesel Generator Heating Ventilation System Operation
1 .
Generator Room Heating and Ventilation System
Each generator room contains three 50% heaters.
Each heater is rated at 12 kW. These heaters are
normally automatically controlled by separate wall
mounted thermostats to maintain the area temperature
above 40'F. The operating range of the heaters is 40
43°F.
There are three vents fans located in each generator
room. The MK V-2 fan is controlled by thermostat
X41-N012, and the MK V-I fans are controlled by
thermostat X41-NO11. At 95'F increasing the MK V
2 fan is auto started and at 97°F increasing the MK V
1 primary fan is auto started. The MK V-I fan is
tripped off at 94°F decreasing and the MK V-2 fan at
92°F decreasing.
a.
Interlocks
Ei,_'OR INTERLOCKS
TIM
S WILLTRIPA DIESEL GENERATOR:
SH
,TURE HIGH
9 LOW
I
sOnmNT
21 psig
230 degrees
205 degrees
9 psig
0.5 incses Water
1000 rpm
<250 rpm, 7 seconds after Diesel Start
LICABLE IN THE TEST MODE
ATOR'S TEST RELAYS RESULTS IN THE FOLLOWING:
ESEL GENERATOR EMERGENCY START
)F ASSOCIATED DIESEL GENERATOR OUTPUT BREAKER
iSSOCIATED DIESEL GENERATOR AND EITHER ITS NORMAL OR
IE OF START-UP TRANSFORMER SUPPLY BREAKER TO 4160V
"TO FAST TRANSFER WILL STILL OCCUR)
OF ASSOCIATED EMERGENCY 4160V BUS TO ITS ALTERNATE
- ENERATOR TRIPS
L DEENERGIZE THE DIESEL GENERATOR TEST RELAYS.
0 SEC
12 SEC
22 SEC
30 SEC
32 SEC
34 SEC
DIG/"A"
START
TIE
LPCI A
ING"lB
START
TIE
LPCI C
LPCI D
PSW A
PSW C
IF PSWA FAILED TO START
PSW D
IF PSW B FAILED TO START
UI
4160 VAC "2F"
4160 VAC G
RHRSW PUMP 1B
RHRSW PUMP ID
PSW PUMP 1B
RHR PUMP lB
CORE SPRAY PUMP IB
DRYWELL CHILLER IB
iD
['ION
@,,
ri N.
600 VAC "I'D"
"rs 7-Th
T
Tl
1
- T
-
001
B C
2R 24-S0181
S
(oN
7'> ( K
7 K I
/
.2
_J
)*RBCCW
PUMP IB
UNIT 1 AND 2 REACTOR BLDG CRANES
-STATION SERVICE AIR COMP lB
WATER FROM DIV 11
)
TRASH RAKE IBl
1P41-F313B PSW SIRAINER
[
2B BACKWASH
VENT FANIB
1
i R
TRAVEI.NG WAIER SCREEN I R
DIESEL
GENERATOR
R-E
F
MEDICAL BUILDING FE"I0
I R24-S0
CHEM/HPARICA HVAC
VITAL AC NON-ESS RNI
RFPTA & BOILPUMP,
I NS4C005BIC006B
25-S045
I R24.
f-
MA
GENE]
UN
DIESEL
GENERATOR
1B
)
)UTBD MSIVs
NBD MSIVs
& P924
.Y
Xl
/
HNP-2-FSAR-8
The supply breakers between startup auxiliary transformers 2C and 2D
on the associated essential 4160-V bus are tripped.
When the last condition above is met, the possibility of one diesel generator
operating in parallel with any other diesel generator is precluded.
E.
Load Shedding
When the diesel generator breaker closes, the following load shedding has already
taken place:
The 4160-V loads and most nonessential 600-V loads are tripped, but the feeder
breakers to the 4160-600-V station service transformers supplying the essential
600-V load centers and their associated MCCs remain closed. This ensures
power continuity to vital 600-V auxiliaries such as the generator seal oil pumps and
instrumentation transformers even when a reactor trip does not accompany loss of
normal power.
F.
Sequential Loading
The diesel generator loading sequence is shown in table 8.3-3. Emergency loads
are shown in tables 8.3-4, 8.3-5, and 8.3-6.
Timing devices are provided to sequentially start the motors for each essential
load. The engineered safety feature (ESF) loads are applied automatically in
sequence at - 10-s intervals to minimize the initial voltage drop due to starting the
induction motor-driven pumps. This method of starting motors provides flexibility
in timing adjustment and independence of control. The tabulation of tables 8.3-3
through 8.3-6 assumes three diesel generators are available.
At time t-plus-30 s after a LOCA with all three essential buses available, four
residual heat removal (RHR) and two core spray (CS) pumps would be in
operation. Full flow injection or spray may still be prohibited by flow- or
pressure-sensing ESF interlocks. Failure of any one diesel or diesel battery and
its buses cannot prevent attainment of minimum safe shutdown requirement
regardless of which bus fails. The plant operator can manually drop off any
excess pumping capacity at any time t-plus-30 s but prior to proceeding into the
second phase of accident control. This occurs at approximately time t-plus-10 min
when reactor water level is stabilized and containment cooling begins.
The automatic starting and load sequencing times in the current design are more
restrictive than the timing assumptions made in the SAFER/GESTR-LOCA
analysis. The LOCA analysis supports a 34-s response time for CS and a 64-s
response time for LPCI.
At time t-plus-10 min, all diesel generator loading can be controlled by the plant
operator. The plant operator makes decisions as to which emergency loads may
8.3-8
REV 19 7/01
QUESTIONS REPORT
for HT2002
58. 295002AA2.02 001
Unit 2 is holding load at 25% RTP. The main turbine is on line when the steam seal
regulator fails closed.
Which ONE of the following describes the impact this will have on reactor power with
no operator action?
A. Reactor power will remain constant since seal steam is not required at this power
level.
BY Reactor power will decrease since condenser vacuum will decrease.
C. Reactor power will decrease since less steam is required from the reactor.
D. Reactor power will remain constant since the steam seal bypass valve automatically
opens to maintain seal steam pressure constant.
Reference: SI-LP-02501 Rev. SI-00 pg 6 of 13
A. Incorrect since condenser vacuum will decrease with Rx Power <28%. This will
cause reactor power to decrease.
B. Correct answer since seal steam is required up to 28% RTP or condenser vacuum
will decrease. If condenser vacuum decreases then reactor power will decrease.
C. Incorrect since this amount of steam being drawn off of reactor is negligible..
D. Incorrect since steam seal bypass valve does not automatically open.
RO Tier:
SRO Tier:
TIG2
Keyword:
Cog Level:
MEM 3.2/3.3
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
62
Monday, June 24, 2002 08:16:53 AM
Page 6 of 13
SI-LP-02501-00
D.
Steam Seal System
Fig 2
1.
The Steam Seal System contains one 100% capacity gland seal condenser,
two 100% capacity steam packing exhauster fans, associated piping and
valves.
2.
The Steam Seal System supplies sealing steam to the main turbine, RFPT
and shafts and various turbine valves, (main stop, control, combined
intercept, and bypass valves). Sealing steam can is supplied by the main
steam system.
3.
The excess steam from the steam seals is condensed in the gland seal
condenser and is returned as condensate to the main condenser. The air and
non-condensable gases are removed by the Steam Packing Exhauster and are
discharged via a 1.75 minute holdup volume to the main stack.
4.
At low power (< 30%) sealing steam prevents air from being drawn across
the seals and into the turbine which could result in a loss of condenser
vacuum or damage to the main turbine.
5.
At higher power (> 30%) pressure inside the turbine casing is greater than
sealing steam pressure therefore the internal steam tends to leak into the seal
cavity.
Fig 4
6.
When the steam pressure leaking out past the inner labyrinth exceeds the
seal steam supply pressure the steam seal regulator valve will close.
Pressure is controlled in the seal steam header by two pressure control
valves which dump to the main condenser.
IV. System Interfaces
A.
Power Supplies
Mechanical Vacuum pump is powered from 600V 2A (2R23-S001) [U1 600V IB
(1R23-S002)].
Steam Packing Exhauster fans are powered from 208V MCC2 A2 2R24-S039
(600V MCC IA R24-S005 for Ul).
QUESTIONS REPORT
for HT2002
1. 295002AA2.02 001
According to procedure 34AB-N61-002-1S, Main Condenser Vacuum Low, SELECT
the condition below which would require reducing reactor power to maintain condenser
vacuum > 25".
A. Inlet flow to holdup line is high.
B. Circulating Waterbox dP's are erratic.
C.r Circulating Water dT exceeds > 25 F.
D. Circulating Water Suction Bay has been < 116'.
Reference: Procedure 34AB-N61-002-1S, Rev. 4 pg 3 of 6
A. Incorrect since this requires the operator to check proper SJAE operation.
B. Incorrect since this would require the operator to vent the waterboxes and pumps.
C. Correct answer.
D. Incorrect since this would require the operator to vent the waterboxes and pumps.
Wednesday, April 24, 2002 10:57:46 AM
SOUTHERN NUCLEAR
PAGE
PLANT E. I. HATCH
3 OF 6
DOCUMENT TITLE:
DOCUMENT NUMBER: REVISIONNERSION
MAIN CONDENSER VACUUM LOW
NO:
0.4
4.0
SUBSEQUENT OPERATOR ACTIONS
NOTE
Decreasing Condenser Vacuum may result in saturated conditions within the Condenser and the
flashing of condensate. IF it becomes necessary OR desirable to break Vacuum, THEN refer to
34AB-C71-001-1 S, Scram Procedure, for placing the Condenser Low Vacuum Trip Bypass switches in
IBYPASS.
4.1
IF main condenser vacuum decreasing trend cannot be stopped prior to any automatic action
that could cause a scram OR complicate/prohibit continued operation, enter 34AB-C71-001-1S,
Scram Procedure, AND SCRAM the reactor.
4.2
IF RTP is <5%, attempt to restore main condenser vacuum with the mechanical vacuum pump,
per 34SO-N61-001-1S, Main Condenser Vacuum System and Closeout.
4.3
Confirm proper Circ Water System operation. IF a singlecirculating pump has tripped and
cannot be restarted enter 34AB-N71-001-1S, Loss of Circulating Water System AND
34SO-N71-001-1S, Circulating Water System, AND reduce reactor power per
34GO-OPS-005-1S, Power Changes to maintain a constant vacuum.
-J
4.4
CONFIRM CLOSED 1N22-F058A & B, Condenser Vacuum Breakers at IH11-P650.
4.5
CONFIRM/START all available cooling tower fans per 34SO-W24-001-IN, Cooling Towers.
4.6
CONFIRM normal hotwell level and adjust level as necessary per 34SO-N21-007-1S,
Condensate System.
4.7
IF Circulating Water dT exceeds > 25 OF, maintain condenser vacuum > 25" by reducing
reactor power per 34GO-OPS-005-1S, Power Changes.
,
4.8
IF Circulating Waterbox dP's are erratic ORcirc water suction bay has been <116', vent the
waterboxes and Circ water pumps per 34-SO-N71-001-1S, Circulating Water System. Notify
I&C to vent condenser waterbox dP instrument lines.
4.9
IF inlet flow to holdup line is high, confirm proper operation of the SJAE in accordance with
34SO-N61-001-1 S, Main Condenser Vacuum System and Closeout.
4.10
CONFIRM proper operation of the Steam Packing Exhauster per 34SO-N33-001-IS, Seal
Steam System.
4.11
Verify 1G31-F034 (Disch to Main Cndsr) AND 1G31-F035 (Drain to Waste Coil Tnk) on panel
1H1 1-P602 are not open at the same time, if so, restore to proper lineup per
34SO-G31-003-1 S, Reactor Water Cleanup System.
MGR-0001 Rev 3
QUESTIONS REPORT
for Revision2 HT2002
32. 295006G2.2.22 001
Unit 1 is operating at 100% RTP. The I & C Techs notify you at 0900 that "A" and "B"
APRM's will not generate a scram signal until the reactor is at 122% RTP.
Adjustments to the APRM's cannot be made for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Which ONE of the following describes the condition of the plant after the 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> has
expired? (Provide copy of Tech Spec 3.3.1.1 conditions and SR's)
A. The Unit is in Mode 2 as required by Required Action F.1.
B. The Unit is in Mode 3 as required by Required Action G.1.
C. The Unit is <28% RTP as required by Required Action E.I.
D. The Unit is at 100% RTP with one APRM bypassed and the other APRM channel in
trip.
Reference: Tech Spec section 3.3.1.1
Tech Spec table 3.3.1.1-1
A. Incorrect since this action would only be required if you cannot meet the Required
Action of Condition A. This can be met by bypassing one APRM and placing the other
APRM in trip.
B. Incorrect since Condition G would be entered if the APRM were INOPERABLE for
the Inop function. They are Inop for the Neutron Flux-High function.
C. Incorrect since you would only go below 28% RTP if the problem was turbine
related.
D. Correct answer. Bypass one APRM and then you can meet Condition A by placing
the other APRM in trip. This maintains the unit at the current power level as long as
you want.
RO Tier:
SROTier:
T1GI
Keyword:
Cog Level:
C/A 3.4/4.1
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
35
Friday, September 20, 2002 09:23:23 AM
QUESTIONS REPORT
for HT2002
64. 295006G2.2.22 001
Unit I is operating at 100% RTP. The Instrument Maintenace Techs notify you at 0900
that "A" and "B" APRM's will not generate a scram signal until the reactor is at 122%
RTP. Adjustments to the APRM's cannot be made for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Which ONE of the following describes the condition of the plant after the 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> has
expired?
A. The Unit is in Mode 2 as required by Required Action F.1.
B. The Unit is in Mode 3 as required by Required Action G.1.
C. The Unit is <28% RTP as required by Required Action E.1.
Df The Unit is at 100% RTP with one APRM bypassed and the other APRM channel in
trip.
Reference: Tech Spec section 3.3.1.1
Tech Spec table 3.3.1.1-1
A. Incorrect since this action would only be required if you cannot meet the Required
Action of Condition A. This can be met by bypassing one APRM and placing the other
APRM in trip.
B. Incorrect since Condition G would be entered if the APRM were INOPERABLE for
the Inop function. They are Inop for the Neutron Flux-High function.
C. Incorrect since you would only go below 28% RTP if the problem was turbine
related.
D. Correct answer. Bypass one APRM and then you can meet Condition A by placing
the other APRM in trip. This maintains the unit at the current power level as long as
you want.
RO Tier:
SROTier:
TIG1
Keyword:
Cog Level:
C/A 3.4/4.1
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
69
Monday, June 24, 2002 U0:I:54 M
QUESTIONS REPORT
for HT2002
1. 295006G2.2.22 001
Unit 1 is operating at 100% RTP. The Instrument Maintenace Techs notify you at 0900
that "A" and "B" APRM's will not generate a scram signal until the reactor is at 122%
RTP. Adjustments to the APRM's cannot be made for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
Which ONE of the following describes the condition of the plant after the 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> has
expired?
A. The Unit is in Mode 2 as required by Required Action F.1.
B. The Unit is in Mode 3 as required by Required Action G.1.
C. The Unit is <28% RTP as required by Required Action E.1.
Do The Unit is at 100% RTP with one APRM bypassed and the other APRM channel in
trip.
Reference: Tech Spec section 3.3.1.1
Tech Spec table 3.3.1.1-1
A. Incorrect since this action would only be required if you cannot meet the Required
Action of Condition A. This can be met by bypassing one APRM and placing the other
APRM in trip.
B. Incorrect since Condition G would be entered if the APRM were INOPERABLE for
the Inop function. They are Inop for the Neutron Flux-High function.
C. Incorrect since you would only go below 28% RTP if the problem was turbine
related.
D. Correct answer. Bypass one APRM and then you can meet Condition A by placing
the other APRM in trip. This maintains the unit at the current power level as long as
you want.
Friday, May 31,2002 11:21:37 AM
RPS Instrumentation
3.3.1.1
3.3 INSTRUMENTATION
3.3.1.1
Reactor Protection System (RPS) Instrumentation
APPLICABILITY:
The FPS instrumentation for each Function in Table 3.3.1.1-1 shall be
According to Table 3.3.1.1 -1.
ACTIONS
S--------------------------------------------------- NOTE -------.-------..............................................
Separate Condition entry is allowed for each channel.
CONDITION
A.
One or more required
channels inoperable.
B. --------
---
---
NOTE ------------
Not applicable for
Functions 2.a, 2.b, 2.c,
2.d, and 2.f.
One or more Functions with
one or more reqluired
channels inoperable in both
trip systems.
REQUIRED ACTION
I COMPLETION TIME
A.1
A.2
B.1
B.2
Place channel in trip.
.
NOTE
Not 'applicable for
Functions 2.a, 2.b, 2.c,
2.d, and 2.f.
Place associated trip
system in trip.
Place channel in one
trip system in trip.
Place
trip.
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
6 hours
one trip system in
6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
(continued)
Amendment No. 213
HATCH UNIT 1
3.3-1
RPS Instrumentation
3.3.1.1
ACTIONS (continued)
CONDITION
REQUIRED ACTION
COMPLETION TIME
C.
One or more Functions with
C.1
Restore RPS trip
1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />
RPS trip capability not
capability.
maintained.
D.
Required Action and
D.1
Enter the Condition
Immediately
associated Completion
referenced in
Time of Condition A, B,
Table 3.3.1.1-1 for the
or C not met.
channel.
E.
As required by Required
E.1
Reduce THERMAL
4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />
Action D.1 and referenced
POWER to < 28% RTP.
in Table 3.3.1.1-1.
F.
As required by Required
F.1
Be in MODE 2.
6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
Action D.1 and referenced
in Table 3.3.1.1-1.
G.
As required by Required
GA
Be in MODE 3.
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
Action D.1 and referenced
in Table 3.3.1.1-1.
H.
As required by Required
H.1
Initiate action to fully
Immediately
Action D.1 and referenced
insert all insertable
in Table 3.3.1.1-1.
control rods in core
cells containing one or
more fuel assemblies.
(continued)
6
6
4
Amendment No. 214
HATCH UNIT 1
3.3-2
RPS Instrumentation
3.3.1.1
.
ACTIONS (continued)
CONDITION
1.
As required by Required
Action D.1 and referenced
in Table 3.3.1.1-1.
J.
Required Action and
associated Completion
Time of Condition I not met.
REQUIRED ACTION
1.1
Initiate alternate method
to detect and suppress
thermal-hydraulic
instability oscillations.
AND
1.2
Restore required
channels to OPERABLE.
J.1
Be in MODE 2.
COMPLETION TIME
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
120 days
4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />
SURVEILLANCE REQUIREMENTS
- ---------------------------------------------------------
NOTES ----------------------------------------------------------
1.
Refer to Table 3.3.1.1-1 to determine which SRs apply for each RPS Function.
2.
When a channel is placed in an inoperable status solely for performance of required
Surveillances, entry into associated Conditions and Required Actions may be delayed
for up to 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> provided the associated Function maintains RPS trip capability.
SURVEILLANCE
FREQUENCY
Perform CHANNEL CHECK.
NOTE ---------------------------
Not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after
THERMAL POWER >:25% RTP.
-
-
-
-
-
Verify the absolute difference between the
average power range monitor (APRM) channels
and the calculated power is S 2% RTP while
operating at a 25% RTP.
7 days
(continued)
3.3-3
Amendment No. 213
<-
HATCH UNIT 1
If-- ggUl *)
RPS Instrumentation
3.3.1.1
SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE
SIR 3.3.1.1.3
(Not used.)
NOTE -------------------
Not required to be performed when entering
MODE 2 from MODE 1 until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after
entering MODE 2.
- --------------------------------------------------
Perform CHANNEL FUNCTIONAL TEST.
SIR 3.3.1.1.5
Perform CHANNEL FUNCTIONAL TEST.
Verify the source range monitor (SRM) and
intermediate range monitor (IRM) channels
overlap.
NOTE
-
Only required to be met during entry into MODE 2
from MODE 1.
- --------------------------------------------------
Verify the IRM and APRM channels overlap.
Calibrate the local power range monitors.
Perform CHANNEL FUNCTIONAL TEST.
SR 3.3.1.1.10
NOTE -------------
.....----------
For Function 2.a, not required to be performed
when entering MODE 2 from MODE 1 until
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after entering MODE 2.
- -
eT---------------------------
Perform CHANNEL FUNCTIONAL TEST.
6
FREQUENCY
7 days
7 days
Prior to
withdrawing SRMs
from the fully
inserted position
a
7 days
1000 effective full
power hours
92 days
184 days
(continued)
Amendment No. 213
"->
HATCH UNIT 1
4
3.3-4
RPS Instrumentation
3.3.1.1
SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE
SR 3.3.1.1.11
Verify Turbine Stop Valve - Closure and
Turbine Control Valve Fast Closure, Trip Oil
Pressure - Low Functions are not bypassed
when THERMAL POWER is; *28% RTP.
SR 3.3.1.1.12
Perform CHANNEL FUNCTIONAL TEST.
SR 3.3.1.1.13
NOTES ---------------------------
1.
Neutron detectors are excluded.
2.
For Function 1, not required to be
performed when entering MODE 2 from
MODE 1 until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after entering
MODE 2.
-- --------------------------------------------------
Perform CHANNEL CALIBRATION.
SR 3.3.1.1.14
(Not used.)
SR 3.3.1.1.15
Perform LOGIC SYSTEM FUNCTIONAL TEST.
SR 3.3.1.1.16 -
- ------------- NOTE ---------------------------
Neutron detectors are excluded.
Verify
Verify the RPS RESPONSE TIME is within limits.
FREQUENCY
184 days
18 months
18 months
18 months
18 months on a
STAGGERED
TEST BASIS
(continued)
Amendment No. 214
HATCH UNIT 1
I
3.3-5
RPS Instrumentation
3.3.1.1
MiIM~~I I ANhlF; REQUIIREMENTS (continued)
SURVEILLANCE
SR 3.3.1.1.17
t
Verify OPRM is not bypassed when APRM
Simulated Thermal Power is 2 25% and
recirculation drive flow is < 60% of rated
recirculation drive flow.
FREQUENCY
18 months
I
I
Amendment No. 213
-
HATCH UNIT 1
6
3.3-6
RPS Instrumentation
3.3.1.1
Table 3.3.1.1-1 (page 1 of 3)
Reactor Protection System Instrumentation
APPLICABLE
CONDITIONS
MODES OR
REQUIRED
REFERENCED
OTHER
CHANNELS
FROM
SPECIFIED
PER TRIP
REQUIRED
SURVEILLANCE
ALLOWABLE
FUNCTION
CONDITIONS
SYSTEM
ACTION D.1
REQUIREMENTS
VALUE
1.
a.
Neutron Flux- High
2
3
G
5120/125
divisions of full
scale
SR 3.3.1.1.13
SR 3.3.1.1.15
5(a)
3
H
%1201125
divisions of full
SR 3.3.1.1.13
scale
SR 3.3.1.1.15
b.
Inop
2
3
G
NA
SR 3.3.1.1.15
5 (a)
3
H
NA
SR 3.3.1.1.15
2.
Average Power Range
Monitor
a.
Neutron Flux - High
2
3(c)
G
- s 20% RTP
(Setdown)
SR 3.3.1.1.10
SR 3.3.1.1.13
b. Simulated Thermal
1
3(c)
F
- 0.58W +
Power-High
58% RTP
and
SR 3.3.1.1.10
- 5115.5%
SR 3.3.1.1.13
RTP(b)
c.
Neutron Flux -High
1
3()
F
!5 120% RTP
SR 3.3.1.1.10
SR 3.3.1.1.13
d.
Inop
1,2
S(i)
G
SR 3.3.1.1.10
NA
(continued)
(a)
With any control rod withdrawn from a core cell containing one or more fuel assemblies.
(b)
0.58 W + 58% -0.58 AW RTP when reset for single loop operation per LCO 3.4.1, "Recirculation Loops Operating."
(c)
Each APRM channel provides inputs to both trip systems.
Amendment No. 214
HATCH UNIT 1
3.3-7
RPS Instrumentation
3.3.1.1
Table 3.3.1.1-1 (page 2 of 3)
Reactor Protection System Instrumentation
E
APPLICABLE
CONDITIONS
MODES OR
REQUIRED
REFERENCED
OTHER
CHANNELS
FROM
SPECIFIED
PER TRIP
REQUIRED
SURVEILLANCE
ALLOWABLE
FUNCTION
CONDITIONS
SYSTEM
ACTION D.1
REQUIREMENTS
VALUE
2.
Average Power Range Monitor
(continued)
e.
Two-out-of-Four Voter
f.
OPRM Upscale
3.
Reactor Vessel Steam Dome
Pressure - High
4.
Low, Level 3
5.
Closure
6.
DryWenl Pressure - High
7.
Water Level - High
a.
Resistance Temperature
Detector
b.
Float Switch
1,2
1
1,2
1,2
1
1,2
1,2
5 (a)
1,2
5(a)
G
2
3(c)
2
G
G
2
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
SR
F
8
2
2
2
2
2
G
G
H
G
H
SR
SR
SR
SR
SR
3.3.1.1.10
3.3A.1.15
3.3.1.1.13
3.3.1.1.1
33.1.1.18
3.3.1.1.10
3.3.1.1.13
3.3.1.1.17
3.3.1.1.1
3.3.1.1.9
3.3.1.1.13
3.3.1.1.15
3.3.1.1.1
3.3.1.1.9
3.3.1.1.13
3.3.1.1.15
3.3.1.1.9
3.3.1.1.13
3.3.1.1.15
3.3.1.1.1
3.3.1.1.9
3.3.1.1.13
3.3.1.1.15
3.3.1.1.9
3.3.1.1.13
3.3.1.1.15
3.3.1.1.9
3.3.1.1.13
3.3.1.1.15
SR 3.3.1.1.13
SR 3.3.1.1.15
SR 3.3.1.1.13
SR 3.3.1.1.15
NA
NA
< 1085 psig
2: 0 inches
a
- 10% closed
- 1.92 psig
- 71 gallons
S 71 gallons
s 71 gallons
< 71 gallons
(continued)
(a)
With any control rod withdrawn from a core cell containing one or more fuel assemblies.
(c)
Each APRM channel provides inputs to both trip systems.
4
Amendment No. 213
'w.
HATCH UNIT 1
3.3-8
RPS Instrumentation
3.3.1.1
Table 3.3.1.1-1 (page 3 of 3)
Reactor Protection System Instrumentation
APPLICABLE
CONDITIONS
MODES OR
REQUIRED
REFERENCED
OTHER
CHANNELS
FROM
SPECIFIED
PER TRIP
REQUIRED
SURVEILLANCE
ALLOWABLE
FUNCTION
CONDITIONS
SYSTEM
ACTION D.1
REQUIREMENTS
VALUE
8.
Turbine Stop Valve - Closure
a 28% RTP
4
E
- s 10% closed
SR 3.3.1.1.11
SR 3.3.1.1.13
SR 3.3.1.1.15
9.
Turbine Control Valve Fast
2:28% RTP
2
E
Ž600 psig
Closure, Trip Oil Pressure-
SR 3.3.1.111
SR 3.3.1.1.13
SR 3.3.1.1.15
SR 3.3.1.1.16
10.
Reactor Mode Switch -
1,2
1
G
SR 3.3.1.1.12
NA
Shutdown Position
SR 3.3.1.1.15
5(a)
1
H
SR 3.3.1.1.12
NA
SR 3.3.1.1.15
11.
Manual Scram
1,2
1
G
NA
SR 3.3.1.1.15
5 (a)
1
H
NA
SR 3.3.1.1.15
a
(a)
With any control rod withdrawn from a core cell containing one or more fuel assemblies.
Amendment No. 214
<"->
HATCH UNIT 1
3.3-9
QUESTIONS REPORT
for HT2002
70. 295010AA2.06 001
A DBA LOCA has occurred on Unit 2 and the following conditions exist:
Drywell Pressure
51 psig and increasing at 2 psig/min
Reactor Water Level
-230 inches and increasing at 10"/min with RHR pumps
Bulk Drywell Temp
280°F
Torus Water Level
218" and increasing slowly
Which ONE of the following should be ordered by the Shift Supervisor?
A. Vent the Drywell IRRESPECTIVE of offsite radioligical release rates.
B!. Vent the Torus IRRESPECTIVE of offsite radioligical release rates.
C. Spray the Drywell after verifying within Drywell Spray Initiation Limit.
D. Enter the Severe Accident Guidelines (SAG's).
Reference: PC-1 Primary Containment Control
Drywell Spray Initiation Limit (Graph 8)
(Consider providing PC-1 and Graph 8)
A. Incorrect since Torus water level is below 300".
B. Correct answer.
C. Incorrect since spraying the Drywell is not allowed since RWL is below Top of Active
Fuel and RHR pumps are required to maintain adequate core cooling.
D. Incorrect since EOP's have direction to cover this situation.
Need to verify these answers with drawings.
RO Tier:
SROTier:
TIGI
Keyword:
DRYWELL PRESSURE
Cog Level: C/A 3.6/3.6
Source:
B
Exam:
HT02301
Test:
S
Misc:
TCK
Monday, June 24, 2002 08:16:55 AM
76
QUESTIONS REPORT
for HT2002
10. 295010AA2.06 001
A DBA LOCA has occurred on Unit 2 and the following conditions exist:
Drywell Pressure
51 psig and increasing at 2 psig/min
Reactor Water Level
-230 inches and increasing at 10"/min with RHR pumps
Bulk Drywell Temp
280 F
Torus Water Level
218" and increasing slowly
The Shift Supervisor SHOULD DIRECT:
A. Venting the Drywell IRRESPECTIVE of offsite radioligical release rate.
B.e Venting the Torus IRRESPECTIVE of offsite radioligical release rate.
C. Spray the Drywell after verifying within Drywell Spray Initiation Limit (Graph 8).
D. Entering the Severe Accident Guidelines (SAG's).
Reference: PC-1 Primary Containment Control
Drywell Spray Initiation Limit (Graph 8)
A. Incorrect since Torus water level is below 300".
B. Correct answer.
C. Incorrect since spraying the Drywell is not allowed since RWL is below Top of Active
Fuel and RHR pumps are required to maintain adequate core cooling.
D. Incorrect since EOP's have direction to cover this situation.
Need to verify these answers with drawings.
Thursday, April 04, 2002 11:36:27 AM
10
QUESTIONS REPORT
for HT2002
77. 295017G2.3.4 001
An event has occurred on Unit I that resulted in an individual getting injured. The
individual is disabled and is in a 100 R/Hr field. An individual is standing by to save the
disabled individuals life (He has NOT volunteered). The job will require being in the
radiation field for 13 minutes. After conferring with HP Supervision the
has determined that
is the maximum amount of dose allowed per
73EP-EIP-017-OS, Emergency Exposure Control, for this lifesaving attempt.
(CHOOSE the answer that correctly fills in the blanks.)
A. Shift Supervisor, 10 Rem
B. Emergency Director, 10 Rem
C. Shift Supervisor, 25 Rem
DO Emergency Director, 25 Rem
References: Procedure 73EP-EIP-017-OS, Emergency Exposure Control pg 4 & 6 of
13.
A. Incorrect since the Emergency Director has the responsibility to make these
decisions.
B. Incorrect since the maximum dose allowed without volunteering is 25 Rem.
C. Incorrect since the Emergency Director has the responsibility to
decisions.
D. Correct answer.
RO Tier:
Keyword:
EMERGENCY EXPOSURE
Source:
N
Test:
S
SRO Tier:
Cog Level:
Exam:
Misc:
make these
TIG1
C/A 2.5/3.1
HT02301
TCK
Monday, June 24, 2002 08:16:56 AM
83
QUESTIONS REPORT
for HT2002
1. 295017G2.3.4 001
An event has occurred on Unit 1 that resulted in an individual getting hurt. The
individual is disabled and is in a 100 R/Hr field. An individual is standing by to save the
disabled individuals life (He has NOT volunteered). The job will require being in the
radiation field for 13 minutes. After conferring with HP Supervision the
has determined that
is the maximum amount of dose allowed per
73EP-EIP-017-OS, Emergency Exposure Control, for this lifesaving attempt.
(CHOOSE the answer that correctly fills in the blanks.)
A. Shift Supervisor, 10 Rem
B. Emergency Director, 10 Rem
C. Shift Supervisor, 25 Rem
D., Emergency Director, 25 Rem
References: Procedure 73EP-EIP-017-OS, Emergency Exposure Control pg 4 & 6 of
13.
A. Incorrect since the
decisions.
Emergency Director has the responsibility to make these
B. Incorrect since the maximum dose allowed without volunteering is 25 Rem.
C. Incorrect since the
decisions.
D. Correct answer.
Monday, April 29, 2002 01:35:39 PM
Emergency Director has the responsibility to make these
1
GEORGIA POWER COMPANY
PAGE
4
OF 13
PLANT E.I.
HATCH
_
DOCUMENT TITLE:
DOCUMENT NUMBER:
REVISION
NO:
EMERGENCY EXPOSURE CONTROL
2 ED 1
REFERENCE
7.0
PROCEDURE
Emergency response personnel may receive exposure under a variety of
circumstances in order to assure protection of others and of valuable property.
These exposures will be justified if the risks permitted to the workers are
acceptably low, AND the costs to others that are avoided by their actions
outweigh the risks to which workers are subjected.
7.1
SAVING OF HUMAN LIFE
Where the potential risk of radiation hazard following the nuclear incident
is
such that life would be in jeopardy, or that there would be severe effects
on the public health or loss of property detrimental to the public safety,
the following criteria for saving of human life shall apply:
7.1.1
In consultation with HP supervision, the Emergency Director will evaluate
the risks involved versus the benefits to be gained by considering the
following:
7.1.1.1
The reliability of the prediction of radiation injury.
Consideration
must be given to limits of error associated with specific instruments
AND techniques used to estimate the dose rate.
This is especially
crucial when the estimated dose approximates 100 REM or more.
7.1.1.2
Assessment of the capability of reducing inherent risks from the
hazard through the use of appropriate mechanisms such as protective
equipment, remote manipulation equipment or similar means.
7.1.1.3
The probable effects of acute exposure that may be incurred AND
numerical estimates of the delayed effects.
These effects are listed
in Attachment 3,
Emergency Worker Risks and Delayed Health Effects
Associated With Large Doses of Radiation.
7.1.1.4
The probability of success of the emergency action.
7.1.2
Make exposure authorizations in accordance with subsection 7.4 Emergency
Exposure Guidelines.
7.2
PROTECTION OF HEALTH AND PROPERTY
7.2.1
When the Emergency Director in consultation with HP supervision, deems-it
necessary to reduce a hazard OR potential hazard to acceptable levels to
prevent a substantial loss of property, an exposure of up to, but not to
exceed,
10 REM may be received by individuals participating in
the
operation.
MGR-0001 Rev.
1
GEORGIA POWER COMPANY
PLANT E.I.
HATCH
DOCUMENT TITLE:
EMERGENCY EXPOSURE CONTROL
DOCUMENT NUMBER:
PAGE
6
OF 13
REVISION
NO:
REVISION
NO:
2 ED I
7.4
EMERGENCY EXPOSURE GUIDELINES
7.4.1
The Emergency Director will establish the exposure limits for the
emergency response personnel based on the following Emergency Response
Personnel Exposure Guides:
NOTE
These guidelines do not establish a rigid upper
limit of exposure.
The Emergency Director may use
his/her judgment in establishing the appropriate
limit.
NOTE
No thyroid limit is specified for lifesaving action
since the complete loss of the thyroid may be
considered an acceptable risk for saving a life;
however, thyroid exposure must be minimized through
the use of respiratory protection and/or KI
tablets.
C
EMERGENCY RESPONSE PERSONNEL EXPOSURE GUIDES
Dose Limit*
Activity
Condition
(REM)
5
all
n/a
10
protecting valuable
lower dose not practicable
property
25
life saving or protection
lower dose not practicable
of large populations
1
>25
life saving or protection
only on a voluntary basis to
of large populations
persons fully aware of the
risks involved
This limit is expressed as the sum of the effective dose equivalent (EDE) and the
committed effective dose equivalent (CEDE)
I
M
R/
MGR-000l Rev.
1
K->
-
6
I
QUESTIONS REPORT
for Revision4HT2002
10. 295025EA2.04 001
Unit 2 Scrammed from High Drywell pressure due to a small leak in the Recirc piping.
The following conditions currently exist:
Drywell pressure
3.5 psig (decreasing)
Drywell temperature
245OF (decreasing)
Torus level
185 inches (increasing)
Torus temperature
160OF (decreasing)
Reactor pressure
600 psig (decreasing)
Torus sprays and cooling
running
Based upon the above conditions the Shift Supervisor has determined that injection
into the RPV from sources external to primary containment must be terminated.
Which ONE of the following identifies the systems that are EXEMPTED from
termination?
A. Systems needed for adequate core cooling, boron injection and CRD.
B. Systems needed to shutdown the reactor, boron injection and CRD.
C. Systems needed for boron injection, CRD and RCIC.
D. Systems needed for adequate core cooling, fire fighting and boron injection.
References: PC-1 Primary Containment Control
Suppression Pool Level High
SRV Tail Pipe Level Limit (Graph 6)
A. Correct answer due to torus water level CANNOT be maintained below SRV Tail
Pipe Level Limit (graph 6).
B. Incorrect since systems needed to shutdown the reactor are not exempted.
C. Incorrect since these systems are excepted when preventing all injection during an
ATWS.
D. Incorrect since fire fighting systems are only excepted during SC Secondary
Containment Control.
RO Tier:
SRO Tier:
TIGI
Keyword:
TORUS LEVEL
Cog Level:
C/A 3.9/3.9
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
11
Friday, October 11, 2002 06:51:26 AM
QUESTIONS REPORT
for HT2002
85. 295025EA2.04 001
Unit 2 Scrammed from High Drywell pressure due to a small leak in the Recirc piping.
The following conditions currently exist:
Drywell pressure
3.5 psig (decreasing)
Drywell temperature
245OF (decreasing)
Torus level
185 inches (increasing)
Torus temperature
160°F (decreasing)
Reactor pressure
600 psig (decreasing)
Torus sprays and cooling
running
Based upon the above conditions the Shift Supervisor has determined that injection
into the RPV from sources external to primary containment must be terminated.
Which ONE of the following identifies the systems that are EXEMPTED from
termination?
A! Systems needed for adequate core cooling, boron injection and CRD.
B. Systems needed for boron injection and CRD.
C. Systems needed for boron injection, CRD and RCIC.
D. Systems needed for adequate core cooling, fire fighting and boron injection.
References: PC-I Primary Containment Control
Suppression Pool Level High
SRV Tail Pipe Level Limit (Graph 6)
A. Correct answer due to torus water level CANNOT be maintained below SRV Tail
Pipe Level Limit (graph 6).
B. Incorrect since these systems are excepted per CP-2 RPV Flooding.
C. Incorrect since these systems are excepted when preventing all injection during an
ATWS.
D. Incorrect since fire fighting systems are only excepted during SC Secondary
Containment Control.
RO Tier:
SRO Tier:
TIGI
Keyword:
TORUS LEVEL
Cog Level:
C/A 3.9/3.9
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
Monday, June 24, 2002 08:16:57 AM
92
QUESTIONS REPORT
for HT2002
1. 295025EA2.04 001
Unit 2 Scrammed from High Drywell pressure due to a small leak in the Recirc piping.
The following conditions currently exist:
Drywell pressure
3.5 psig (decreasing)
Drywell temperature
245 F (decreasing)
Torus level
185 inches (increasing)
Torus temperature
160 F (decreasing)
Reactor pressure
600 psig (decreasing)
Torus sprays and cooling
running
Based upon the above conditions the Shift Supervisor has determined that injection
into the RPV from sources external to primary containment must be terminated. Which
systems are EXCEPTED from termination?
A.r Systems needed for adequate core cooling, boron injection and CRD.
B. Systems needed for boron injection and CRD.
C. Systems needed for boron injection, CRD and RCIC.
D. Systems needed for adequate core cooling, fire fighting and boron injection.
References: PC-1 Primary Containment Control
Suppression Pool Level High
A. Correct answer due to torus water level CANNOT be maintained below SRV Tail
Pipe Level Limit (graph 6).
B. Incorrect since these systems are excepted per CP-2 RPV Flooding.
C. Incorrect since these systems are excepted when preventing all injection during an
ATWS.
D. Incorrect since fire fighting systems are only excepted during SC Secondary
Containment Control.
Tuesday, April 09, 2002 10:51:43 AM
defeat high torus water level
suction transfer logic per
31 EO-EOP-1 00-2S
PERFORM CONCURRENTLY
I Maintain torus water level below
SRV Tail Pipe Level Umit(Graph 6) per
3480-Ell-0 10-2S or 34GO-OPS-087-2S
SMWAIT UNTIL
Maintain torus water level
below 215 in. per 34SO-Ell-010-2S or
WAIT UNTIL
torus water level
CANNOT be maintained
below SRV Tail Pipe Level Limitf
(Graph 6)
RCAPERFORMon ACONCURRENTLY
SWAIT LINT L
/
~torus water level
S~ANDI
/
~reactor pressure/
o usANDNOT
be maintand
J
below SRV Tail Pipe Level Umit
T(Graph 6)
torus water level
CANNOT be maintained
C
below 215 in.
-
ýWAIT UNTIL
torus water level
QCANNOT
be maintained
below 300 in.
Determine primary containmentwater level
per 31EO-EOP-105-2S
IF primary contal
and torus prea
I
maintainedb
Pressure Umi
E LF drell sprat
BEFORE d
ýWAIT UNTIL.
torus water level
AND
reactor pressure
CANNOT be restored and maintained
below SRV Tail Pipe Level Uimit
(Graph 6)
-. , (EMERGENCY
DEPRESS IS REQUIRED
MflTF 9
Terminate drywell sprays
AND
Terminate injection into RPV from sources
external to primary containment EXCEPT
systems required for:
"o adequate core cooling
"C boron injection
o CRD
Terminate injection into RPV from sources
external to primary containment EXCEPT
systems required for.
o adequate core cooling
o boron injection
o CRD
SGRAPH 6
180
174
S
U)
C
168
162
156
UNIT -1
SRV TAIL PIPE LEVEL LIMIT
150
0
200
400
600
NOTE: M,
SPDS Emergency Displays in place of this Graph.
bv
800
RPV PRESSURE (psig)
1000
1200
Q
QUESTIONS REPORT
for Revision2 HT2002
33. 295030EA2.01 001
Unit 2 has developed a leak in the Torus and the Shift Supervisor has entered PC-1
Primary Containment Control. Mechanical Maintenance and Health Physics have been
dispatched to investigate and repair the leak. Mechanical Maintenance has reported
that the leak should be stopped in approximately 30 minutes. Torus level is currently at
120" and is dropping at a rate of 1" per minute.
Which ONE of the following should be directed by the Shift Supervisor?
A. wait until Torus level drops to 110" and order HPCI tripped.
B. wait until Torus level drops to 98" and order Emergency Depressurization per CP-1.
C' order HPCI tripped and depressurize reactor through the Main Turbine Bypass
Valves irrespective of cooldown rate.
D. order HPCI tripped and depressurize reactor through the Main Turbine Bypass
valves without exceeding a 100OF/hr cooldown rate.
References: LR-LP-20310 Rev. 05 pg. 20 - 23 of 96
RC RPV CONTROL (NON-ATWS)
PC-1 PRIMARY CONTAINMENT CONTROL
A. Incorrect since actions should be taken before they are hit if the trend indicates that
the limit will be met.
B. Incorrect since actions should be taken before they are hit if the trend indicates that
the limit will be met.
C. Correct answer.
D. Incorrect since it is acceptable to exceed the 100 F/hr cooldown rate when you
anticipate blowdown per overide in PC RPV Control (Non-ATWS).
RO Tier:
SROTier:
TIGI
Keyword:
TORUS LEVEL
Cog Level: C/A 4.1/4.2
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
...
36
Friday, September 20, ZuUL u0:23:23 AMl
QUESTIONS REPORT
for HT2002
89. 295030EA2.01 001
Unit 2 has developed a leak in the Torus and the Shift Supervisor has entered PC-1
Primary Containment Control. Mechanical Maintenance and Rad Protection have been
dispatched to investigate and repair the leak. Mechanical Maintenance has reported
that the leak should be stopped in approximately 30 minutes. Torus level is currently at
120" and is dropping at a rate of 1" per minute.
Which ONE of the following should be directed by the Shift Supervisor?.
A. wait until Torus level drops to 110" and order HPCI tripped.
B. wait until Torus level drops to 98" and order Emergency Depressurization per CP-1.
C' order HPCI tripped and depressurize reactor through the Main Turbine Bypass
Valves irrespective of cooldown rate.
D. order HPCI tripped and depressurize reactor through the Main Turbine Bypass
valves without exceeding a 1 00OF/hr cooldown rate.
References: LR-LP-20310 Rev. 05 pg. 20 - 23 of 96
RC RPV CONTROL (NON-ATWS)
PC-1 PRIMARY CONTAINMENT CONTROL
A. Incorrect since actions should be taken before they are hit if the trend indicates that
the limit will be met.
B. Incorrect since actions should be taken before they are hit if the trend indicates that
the limit will be met.
C. Correct answer.
D. Incorrect since it is acceptable to exceed the 100 F/hr cooldown rate when you
anticipate blowdown per overide in PC RPV Control (Non-ATWS).
ROTier:
SROTier:
TIGI
Keyword:
TORUS LEVEL
Cog Level:
C/A 4.1/4.2
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
96
Monday, June 24, 2002 08:16:57 AM
QUESTIONS REPORT
for HT2002
1. 295030EA2.01 001
Unit 2 has developed a leak in the Torus and the Shift Supervisor has entered PC-1
Primary Containment Control. Mechanical Maintenance and Rad Protection have been
dispatched to investigate and repair the leak. Mechanical Maintenance has reported
that the leak should be stopped in approximately 30 minutes. Torus level is currently at
120" and is dropping at a rate of 1" per minute. The Shift Supervisor should:
A. wait until Torus level drops to 110" and order HPCI tripped.
B. wait until Torus level drops to 98" and order Emergency Depressurization per CP-1.
C. order HPCI tripped and depressurize reactor through the Main Turbine Bypass
Valves irrespective of cooldown rate.
D. order HPCI tripped and depressurize reactor through the Main Turbine Bypass
valves without exceeding a 100 F/hr cooldown rate.
References: LR-LP-20310 Rev. 05 pg. 20 - 23 of 96
RC RPV CONTROL (NON-ATWS)
PC-1 PRIMARY CONTAINMENT CONTROL
A. Incorrect since actions should be taken before they are hit if the trend indicates that
the limit will be met.
B. Incorrect since actions should be taken before they are hit if the trend indicates that
the limit will be met.
C. Correct answer.
D. Incorrect since it is acceptable to exceed the 100 F/hr cooldown rate when you
anticipate blowdown per overide in PC RPV Control (Non-ATWS).
Tuesday, April 09, 2002 02:14:15 PM
Page 20 of 96
LR-LP-20310-05
PRIMARY CONTAINMENT CONTROL (PC-1 & 2)
Q: Why are these paths
concurrent and not in series?
A: As level decreases, HPCI
would need to be secured,
however, the plant would not
necessarily need to be
depressurized.
PERFORM CONCURRENTLY
I
Maintain torus water level
above 98 in. per 34SO-E21-001-2S
or 34GO-OPS-087-2S
I
Maintain torus water level
above 110 in. per 34SO-E21-001-2S
or 34G0-OPS-087-2S
The two paths for the low level condition direct control of torus water
level relative to the elevation of the downcomer openings and the
elevation of the top of the HPCI exhaust line, respectively.
Therefore, these two paths must be executed in parallel since the
actions required in one path may or may not have to be accomplished at
the same time as the actions in the other path.
HPCI PATH WILL BE DISCUSSED LATER
98" is the elevation of the
downcomer openings
PRIOR to tows level dropping
below 98", the RPV should be
depressurized.
The RPV is not permitted to remain at pressure if suppression of steam
discharged from the RPV into the drywell cannot be assured. When the
downcomer vent openings are not adequately submerged, any steam
discharged from the RPV into the drywell may not condense in the
torus before tows pressure reaches unacceptable levels.
Emergency RPV depressurization will be required at or before the point
at which this low water level condition occurs (98in.).
I
4
WAIT UNTIL
torus water level
CANNOT be maintained
above 98in.
4
Page 21 of 96
LR-LP-20310-05
PRIMARY CONTAINMENT CONTROL (PC-1 & 2)
At this point, if the torus level is
above 98", there is no need for
emerg depressurization.
NOTE: Results of the Bodega Bay Mark I containment tests
indicate 95% steam condensation may be achieved from a
vertical downcomer vent that discharges at a level six inches
above the torus surface.
As long as torus water level remains at or above the elevation of the
downcomer vent openings, the need to emergency depressurize the
RPV due to torus heatup is dictated by the Heat Capacity Temperature
Limit. Actions associated with the Heat Capacity Temperature will be
discussed in the SP/F path.
PERFORM CONCURRENTLY
RC[A] point A
Stress that if torus level cannot be
prevented from decreasing to 98
inches, enter the RC flowchart.
EO 9
ASK
What does entering
RC flowchart accomplish ?
EO 10
ASK How is the Emergency
Depressurization Flowchart CP-l
reached ?
The determination that torus level cannot be maintained above 98
inches should be made BEFORE reaching the actual limit based on
level trend or other plant conditions.
In other words, the operator should ANTICIPATE the need to
perform RC[A] and enter the correct chart.
Entering either RC or RCA at point "A" assures that, if possible, the
reactor is scrammed and shutdown by control rod insertion before RPV
depressurization is initiated.
Directing that the RPV Control EOP be entered, rather than explicitly
stating here "Initiate a reactor scram," coordinates actions currently
being executed if the RPV Control has already been entered. (Note that
the RPV Control requires initiating a reactor scram only if one has not
previously been initiated.)
In addition, entry into RC or RCA must be made
because it is through these flowcharts that the transfer
to the "Emergency RPV Depressurization"
contingency is effected.
j
I
EMERGENCY DEPRESS IS REQUIRED
EO 11
Discuss reason for Emerg RPV
Depressurization if unable to
maintain above 98inches.
Depressurizing the RPV ensures
steam can be condensed while
adequate water level exists.
<S
EO 12
Depressurizing the RPV when torus water level cannot be maintained
above 98 inches is done to prevent failure of the containment or
equipment necessary for the safe shutdown of the plant.
The RPV is not permitted to remain at pressure if suppression of steam
discharged from the RPV cannot be assured.
Therefore the vessel is depressurized while the tows can still support a
blow down and places the RPV in the lowest possible energy state.
This precludes the possibility of a primary containment failure and the
resultant uncontrolled radioactivity release,
- This override flag DOES NOT direct the operator to leave the
SP/L flow path.
- The override flag DOES direct the operator to exercise the
EMERGENCY DEPRESSURIZATION IS REQUIRED
overrides in all other flow paths that are currently being
performed, especially the override on the RC[A] pressure
path that directs the operator to the Emergency
Depressurization path on CP-1.
HPCI PATH WILL NOW BE DISCUSSED
1
PERFORM CONCURRENTLY
I
Maintain torus water level
above 110 in per 34SO-E21-001-2S or
I
EO 13
If level decreases < 110 inches,
the torus air space will be directly
pressurized with HPCI running.
EO 14
HPCI is secured and prevented
from operating (PTL) even if
needed to maintain RWL
The torus level needs to be maintained above the discharge of the HPCI
steam turbine exhaust line to ensure adequate steam condensing. This
precludes possible primary containment failure due to over
pressurization caused by HPCI steam exhaust discharging directly into
the torus air space.
The determination that the torus level cannot be maintained above 110
inches CAN BE MADE BEFORE reaching the actual limit based on
trend or other plant conditions. As soon as this determination is made,
the operator proceeds to the next step and secures HPCI.
I
PTL.
Aux Oil Pump is placed in
ASK Why must HPCI be tripped
at 110" "?
ASK
Why is RCIC operation is
allowed ?
HPCI exhaust press trip approx
140 psig where as RCIC is about
40 psig.
Trip and prevent operation of HPCI
irrespective of adequate core cooling
Operation of the HPCI System with its exhaust discharge line (located
at 110 in.) not submerged will directly pressurize the torus air space.
HPCI operation is therefore secured, and prevented from restarting, to
preclude the occurrence of this condition.
The consequences of not doing so may extend to failure of the primary
containment from over pressurization, and thus HPCI must be secured
irrespective of adequate core cooling concerns.
No instruction regarding RCIC operation is included in this step (or in
an equivalent step) for two reasons:
1.
The exhaust flow rate of RCIC is approximately equal to
that of decay heat, and is thus consistent with the basis used
for determining the Primary Containment Pressure Limit.
2.
Elevated torus pressure will cause the RCIC turbine to trip
much sooner than the HPCI turbine.
WAIT UNTIL
torus water level
CANNOT be maintained
above 110 in.
I
4*
C
RWL below + 3 in.
A condition which requires reactors
and reactor power is above 5%
)
C
IF ALL control roc
or beyond posi
control rods ar
shutdown rod
I
[
I
S
WHILE PERFORMING THE FOLLOWING
IF Emergency Depress is anticipated,
biTEN rapidly depress with
EXCEPT for low RWLtI
main turbine bypass valves,
I
irrespective of the resulting
cooldown rate.
LF EMERGENCY DEPRESS IS,
THEN perform Emergency Depress
OR HAS BEEN, REQUIRED
I
I
IF RWL CANNOT be determined
THEN perform RPV Flooding
IF drywell pressure is above 1.85 psig
THEN prevent injection from CS and LPCI
pumps per 31EO-EOP-114-2S
C_
A
B
C
C $
I
1
0
I I
I
I
V
SP/
NOTE2
If fuel failure is suspected consult with
I
Plant Chemistry prior to discharging water 1
GO TO ANY entry condition
on PC-2
B
PERFORM CONCURRENTLY
I
Maintain torus water level
above 98 in. per 34$0-E21-001-2S or
I
ýWAIT U`NTILý
trswtr
level
CANNOT be maintained
above 98 in.
PERFORM CONCURRENTLY
RC[A] point A
Maintain torus water level
above 110 in. per 34SO-E21-001-2S or
,-ý WAIT UNTIL
" ~
~torus
water level
'
CANNOT be maintained
above 110 in.
Trip and prevent operation of HPCI
irrespective of adequate core cooling
EMERGENCY DEPRESS IS REQUIRED'
I
ir PRIMP
I%*Ss+/-Ig
7
"torus water level
NNOT
146b main* a
in.
BELOW 146
IsABOVE
15
toruswaterleve
Monitor and control torus water level
between 146 in. and 150 in. using:
"o CS for low water levels per
3480-E21-001-28
"o RHR for high water levels per
3480-Ell-010-2I
D
I
-
-
/
WAI T UN T I L
U
QUESTIONS REPORT
for Revision2 HT2002
34. 29503 1G2.4.4 001
Unit 1 is operating at 100% power when a leak in the Drywell develops. Reactor water
level is trending down and Drywell pressure, temperature and level are trending
upward. The SRO orders a reactor SCRAM with the following conditions occuring:
RWL initially reaches +2" and stabilizes at +15"
Drywell pressure reaches 1.83 psig and stabilizes
Drywell temperature currently at 147 0F and rising slowly
Torus level currently at 148" and rising slowly
Reactor pressure at 920 psig and steady
6 control rods stuck at position 02 and all others fully inserted
Which ONE of the following actions are required by the Shift Supervisor under these
conditions?
A. Enter RCA RPV Control (ATWS) and take actions to ensure reactor stays shutdown
under all conditions.
B. Enter PC-1 and PC-2 and take actions to prevent reaching entry conditions.
C" Enter RC RPV Control (Non-ATWS) and take actions to stabilize plant.
D. Entry into EOP's not required since an entry condition does not exist at this time.
S~34AB-C71-OO1-2S,
Scram Procedure is entered.
References: LR-20308 Entry Conditions
LR-20310 Entry Conditions
LR-20328 ATWS Conditions
A. Incorrect answer. Does not meet conditions for ATWS. All rods are at position 02 or
beyond.
B. Incorrect answer. Does not meet entry conditions yet. Not appropriate to take
actions to prevent meeting entry conditions.
C. Correct answer.
D. Incorrect answer. EOP entry is required since conditions were previously met. RWL
<+3".
-
-.
-
-
-.-
~.
-,~a
an
AftA37
Friday, September 2u, 2UU2 U0:2J3: 3wVI
RO Tier:
Keyword:
Source:
N
Test:
S
QUESTIONS REPORT
for Revision2 HT2002
SRO Tier:
Cog Level:
Exam:
Misc:
Friday, September 20, 2002 09:23:23 AM
T1GI
C/A 4.0/4.3
HT02301
TCK
38
QUESTIONS REPORT
for HT2002
91. 295031G2.4.4 001
Unit I is operating at 100% power when a leak in the Drywell develops. Reactor water
level is trending down and Drywell pressure, temperature and level are trending
upward. The SRO orders a reactor SCRAM with the following conditions occuring:
RWL innitially reaches +2" and stabilizes at +15"
Drywell pressure reaches 1.83 psig and stabilizes
Drywell temperature currently at 147 0F and rising slowly
Torus level currently at 148" and rising slowly
Reactor pressure at 920 psig and steady
6 control rods stuck at position 02 and all others fully inserted
Which ONE of the following actions are required by the Shift Supervisor under these
conditions?
A. Enter RCA RPV Control (ATWS) and take actions to ensure reactor stays shutdown
under all conditions.
B. Enter PC-1 and PC-2 and take actions to prevent reaching entry conditions.
C. Enter RC RPV Control (Non-ATWS) and take actions to stabilize plant.
D. Entry into EOP's not required since an entry condition does not exist at this time.
34AB-C71-001-2S, Scram Procedure is entered.
References: LR-20308 Entry Conditions
LR-20310 Entry Conditions
LR-20328 ATWS Conditions
A. Incorrect answer. Does not meet conditions for ATWS. All rods are at position 02 or
beyond.
B. Incorrect answer. Does not meet entry conditions yet. Not appropriate to take
actions to prevent meeting entry conditions.
C. Correct answer.
D. Incorrect answer. EOP entry is required since conditions were previously met. RWL
<+3".
98
Monday, June 24, 2002 08:16:57 AM
RO Tier:
Keyword:
Source:
N
Test:
S
Monday, June 24, 2002 08:16:57 AM
QUESTIONS REPORT
for HT2002
SRO Tier:
TIGI
Cog Level:
C/A 4.0/4.3
Exam:
HT02301
Misc:
TCK
99
QUESTIONS REPORT
for HT2002
14. 29503 1G2.4.4 001
Unit 1 is operating at 100% power when a leak in the Drywell develops. Reactor water
level is trending down and Drywell pressure, temperature and level are trending
upward. The SRO orders a reactor SCRAM with the following conditions occuring:
RWL innitially reaches +2" and stabilizes at +15"
Drywell pressure reaches 1.83# and stabilizes
Drywell temperature currently at 147 F and rising slowly
Torus level currently at 148" and rising slowly
Reactor pressure at 920# and steady
6 control rods stuck at position 02 and all others fully inserted
What actions are required by the Shift Supervisor under these conditions?
A. Enter RCA RPV Control (ATWS) and take actions to ensure reactor stays shutdown
under all conditions.
B. Enter PC-1 and PC-2 and take actions to prevent reaching entry conditions.
C. Enter RC RPV Control (Non-ATWS) and take actions to stabilize plant.
D. Entry into EOP's not required since an entry condition does not exist at this time.
References: LR-20308 Entry Conditions
LR-20310 Entry Conditions
LR-20328 ATWS Conditions
A. Incorrect answer. Does not meet conditions for ATWS. All rods are at position 02 or
beyond.
B. Incorrect answer. Does not meet entry conditions yet. Not appropriate to take
actions to prevent meeting CorrectnLamer.entry conditions. *
C. Correct answer.
D. Incorrect answer. EOP entry is required since conditions were previously met. RWL
<+3".
Thursday, April 04, 2002 11:36:28 AM
14
QUESTIONS REPORT
for Revision2 HT2002
35. 295033G2.3.10 001
Unit 1 is operating at 100% RTP. The Fuel Movement Team is moving fuel bundles in
the Unit 1 Fuel Pool to get ready for an upcoming outage. There is a malfunction
associated with the mast and a fuel bundle is dropped in the pool. This caused some
fuel pins to break and radiation levels are increasing on the Refuel Floor and around
the Fuel Pool pumps. The following radiation levels exist on Unit 1:
Refuel Floor
1500 mR/hr
Spent Fuel Pool Demin Equip
2000 mR/hr
Fuel Pool Demin Panel
75 mR/hr
Which ONE of the following actions should the Shift Supervisor order?
(Provide copy of Unit 1 SC-Secondary Containment Control)
A. Scram the reactor and evacuate the Reactor Building per 73EP-RAD-O01-OS,
Radiological Event.
B.' Commence a Normal Unit Shutdown and evacuate the associated High Rad areas.
C. Scram the reactor and commence a Reactor Blowdown per the EOP's.
D. Announce the High Rad condition over the public address system and evacuate the
affected areas. Reactor operation should not be affected.
References: 73EP-RAD-001-OS, Radiological Event Rev. 1.1 pg 4 of 7
SC - SECONDARY CONTAINMENT CONTROL
A. Incorrect since a reactor scram is not required by the EOP's.
B. Correct answer.
C. Incorrect, a reactor blowdown is not required since there is not a primary system
discharging into secondary containment.
D. Incorrect since the reactor should be shutdown per the EOP's.
RO Tier:
SROTier:
T1G2
Keyword:
EOP PC CONTROL
Cog Level: C/A 2.9/3.3
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
flfl
q,ýo
ll.O
A"A
39
Friday, S)eptembrn[ 20, 2004 09.:.*
,v
QUESTIONS REPORT
for HT2002
93. 295033G2.3.10 001
Unit 1 is operating at 100% RTP. The Fuel Handlers are moving fuel bundles in the
Unit 1 Fuel Pool to get ready for an upcoming outage. There is a malfunction
associated with the mast and a fuel bundle is dropped in the pool. This caused some
fuel pins to break and radiation levels are increasing on the Refuel Floor and around
the Fuel Pool pumps. The following radiation levels exist on Unit 1:
Refuel Floor
Spent Fuel Pool Demins
Fuel Pool Demin Panel
1500
2000
75
mR/hr (Max Safe Operating value = 1000
mR/hr (Max Safe Operating value = 1000
mR/hr (Max Normal Operating value = 50
Which ONE of the following actions should the Shift Supervisor order?
A. Scram the reactor and evacuate the Reactor Building per 73EP-RAD-O01-OS,
Radiological Event.
B! Commence a Normal Unit Shutdown and evacuate the associated High Rad areas.
C. Scram the reactor and commence a Reactor Blowdown per the EOP's.
D. Announce the High Rad condition over the public address system and evacuate the
affected areas. Reactor operation should not be affected.
73EP-RAD-001-0S, Radiological Event Rev. 1.1 pg 4 of 7
SC - SECONDARY CONTAINMENT CONTROL
A. Incorrect since a reactor scram is not required by the EOP's.
B. Correct answer.
C. Incorrect, a reactor blowdown is not required since there is not
discharging into secondary containment.
D. Incorrect since the reactor should be shutdown per
RO Tier:
SRO Tier:
Keyword:
EOP PC CONTROL
Cog Level:
Source:
N
Exam:
Test:
S
Misc:
a primary system
the EOP's.
TIG2
C/A 2.9/3.3
HT02301
TCK
101
Monday, June 24, 2002 08:16:58 AM
mR/hr))
mR/hr)
mR/hr)
References:
QUESTIONS REPORT
for HT2002
1. 295033G2.3.10 001
Unit 1 is operating at 100% RTP. The Fuel Handlers are moving fuel bundles in the
Unit 1 Fuel Pool to get ready for an upcoming outage. There is a malfunction
associated with the mast and a fuel bundle is dropped in the pool. This causes some
fuel pins to break and radiation levels are going up on the Refuel Floor and around the
Fuel Pool pumps. The following radiation levels exist on Unit 1:
Refuel Floor
1500 mR/hr (Max Safe Operating value = 1000 mR/hr))
Spent Fuel Pool Demins
2000 mRPhr (Max Safe Operating value = 1000 mR/hr)
Fuel Pool Demin Panel
75 mRlhr (Max Normal Operating value = 50 mR/hr)
The Shift Supervisor should:
A. Order the Control Board Operator to Scram the reactor and evacuate the Reactor
Building per 73EP-RAD-001-OS, Radiological Event.
B!. Order the Control Board Operator to commence a Normal Unit Shutdown and
evacuate the associated High Rad areas.
C. Order the Control Board Operator to Scram the reactor and commence a Reactor
Blowdown per the EOP's.
D. Have the Control Board Operator announce the High Rad condition over the public
address system and evacuate the affected areas. Reactor operation should not be
affected.
References: 73EP-RAD-001-0S, Radiological Event Rev. 1.1 pg 4 of 7
SC - SECONDARY CONTAINMENT CONTROL
A. Incorrect since a reactor scram is not required by the EOP's.
B. Correct answer.
C. Incorrect, a reactor blowdown is not required since there is not a primary system
discharging into secondary containment.
D. Incorrect since the reactor should be shutdown per the EOP's.
Tuesday, April 30, 2002 01:41:50 PM
GEORGIA POWER COMPANY
PAGE
4 OF
7
PLANT E.I.
HATCH
I
DOCUMENT TITLE:
DOCUMENT NUMBER:
REVISION NO:
RADIOLOGICAL EVENT
1 ED 1
4
I
REFERENCE
7.0
PROCEDURE
7.1
INVOLVED PERSONNEL
CAUTION
PERSONNEL MUST NOT BE SENT INTO AN AREA OF
UNKNOWN RADIATION CONDITIONS WITHOUT HP COVERAGE,
DOSIMETRY AND APPROPRIATE PROTECTIVE EQUIPMENT.
i
7.1.1
Control RoomPersonnel
Upon determining that a Radiological Event has occurred, the Shift
Supervisor will perform the following actions:
7.1.1.1
Direct the Control Room Operator to make the following announcement
over the public address system:
A RADIOLOGICAL EVENT IS OCCURRING.
ABOVE NORMAL RADIATION
(OR
AIRBORNE RADIOACTIVITY)
EXISTS IN THE
(location)
AREA.
EVACUATE AND STAY CLEAR OF THE
(location)
AREA(S).
7.1.1.2
Direct the Control Room Operator to repeat the announcement a second
time.
7.1.1.3
Contact the Health Physics Office to assist in investigating the
condition.
Inform HP of the indicated dose rate of the area, IF the
event was initiated due to an alarming ARM,
and any other pertinent
information, e.g., dropped fuel bundle, indication of leak, etc..
7.1.1.4
Attempt to confirm accuracy of alarmed ARMs and effluent monitors by
directing that the status of ARMs and effluent monitors near or
associated with incident area be checked for recent or sudden change.
7.1.1.5
Check habitability of Control Room by observing radiation monitors OR
possible automatic isolation of control room ventilation.
7.1.1.6
Ensure that START HIST (history) light on the SPDS keyboard is
ILLUMINATED;
if
not, simultaneously DEPRESS the CTRL and START HIST
keys.
Cancel or continue history as directed by the SOS.
7.1.1.7
Observe Control Room instrumentation and controls.
Implement
corrective action to eliminate cause of this abnormal condition, IF
possible, from the Control Room.
MGR-0001 Rev.
1
HVAC Isolation
"o
Unit 1 and Unit 2 Refuel Floor
HVAC isolation
"o Unit 1 and Unit 2 SBGT initiation
per 34AB-T22-O03-1 S
TH~FN restart Refuel Floor HVAC per
If necessary defeat high dqywell pressure
'/L isolation interlocks
EO-EOP-100-1S
THEN 'reseetd Reactor Building HVAC per
If necessary defeat high drywell pressure
ANDl
low RWL isolation Interlocks
per31EO-EOP-100-1S
3NCURRENTLY
SIC'
WAIT UNTIL
area radiation level
is above
Maximum Normal Operating Radiation Level
(Table 6)
INTIL
ollowing
ye
crating Water Level
) 5):
n sump water level
iter level
ump
Pumps to restore
level below Maximum
Vater Level (Table 5)
tg CANNOT be
alned below Maximum
Nater Level (Table 5):
in sump water level
Iar level
aems disc&,ning water
ua EXC
-tems
luate &,.Ang
)actor
nary containment
Isolate ALL systems discharging into area
EXCEPT systems required to:
"o assure adequate core cooling
"o shut down reactor
"o suppress fire
"o maintain primary containment
integrity
PERFORM CONCURRENTLY
I
primary system
(Tdi
arg bgleac o cooan
Shut down reactor per 34GO-OPS-013-IS
or34GO-OPS-f14-1S
I
I ANY area radiation level reaches
Maximum Safe Operating Radiation Level
(Table 6)
PERFORM CONCURRENTLY
RC(A) pantA
WAIT UNTIL
area radiation level
F0Is
above
Maximum Safe Operating Radiation Level
In more than one area
(TableS6)
EMERGENC
DEPRESS IS REQUIRIED
RR - RADIOACTIVITY RELEASE CONTROL
C
rr
Offslte radioactivity release rate
above 0.57 mR/hr
WHII F= PFRFORMIWG TIHI FOLLOWING
'I
IF
PR IM AR Y
tfN
TA INM FM TFV 1 fl
rlf
lM f
TR FN prit
f
lPq n
Hta
ntor
Thn
B
C
D
E
F
I
WHL
PE F RMN
THE* FOUL
ING.....
.
.....
area radiation level
is above
Maximum Safe OperatingRaitoLel
in more than one area
(Table 6)
I
QUESTIONS REPORT
for Revision2 HT2002
36. 295034EA2.02 001
Which ONE of the following conditions would most likely cause a Secondary
Containment Ventilation High Radiation isolation?
A. A leak has developed on the RHRSW side of the RHR Heat Exchanger and the
water level in the room is approximately 1/2" deep.
B. A Recirc Pump seal failure which causes Drywell Pressure to exceed 1.85 psig.
C. The packing is blown on a Startup Level Control Valve (SULCV) and the area is
blanketed in steam.
Df A leak has developed upstream of the HPCI Stop Valve but it is not large enough to
cause a high temperature isolation of HPCI.
References: SI-LP-01303 Rev. Sl-00, Figures 10.
A. Incorrect since the RHRSW side of the HX is not highly radioactive.
B. Incorrect since the drywell will contain the Recirc Pump seal leakage.
C. Incorrect since the feedwater reg valve is in the turbine building.
D. Correct answer since this steam leak is directly off of main steam and has the
potential of being highly radioactive.
RO Tier:
SROTier:
TIG2
Keyword:
SECONDARY CONTAIN
Cog Level:
C/A 3.7/4.2
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
Friday, September 20, 2002 09:23:23 AM
40
QUESTIONS REPORT
for HT2002
94. 295034EA2.02 001
Which ONE of the following conditions would most likely cause a Secondary
Containment Ventilation High Radiation isolation?
A. A leak has developed on the RHRSW side of the RHR Heat Exchanger and the
water level in the room is approximately 1/2" deep.
B. A Recirc Pump seal failure which causes Drywell Pressure to exceed 1.85 psig.
C. The packing is blown on a Feedwater Reg Valve and the area is blanketed in
steam.
D. A leak has developed upstream of the HPCI Stop Valve but it is not large enough to
cause a high temperature isolation of HPCI.
References: SI-LP-01303 Rev. SI-00, Figures 10.
A. Incorrect since the RHRSW side of the HX is not highly radioactive.
B. Incorrect since the drywell will contain the Recirc Pump seal leakage.
"-*~
C. Incorrect since the feedwater reg valve is in the turbine building.
D. Correct answer since this steam leak is directly off of main steam and has the
potential of being highly radioactive.
RO Tier:
SRO Tier:
T1G2
Keyword:
SECONDARY CONTAIN
Cog Level:
C/A 3.7/4.2
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
102
Monday, June z4, zuuz u0:16:58 AM
QUESTIONS REPORT
for HT2002
1. 295034EA2.02 001
SELECT the condition that would most likely cause a Secondary Containment
"Ventilation High Radiation isolation.
A. A leak has developed on the RHRSW side of the RHR Heat Exchanger and the
water level in the room is approximately 1/2" deep.
B. A firemain leak has developed in the CRD repair area on Unit 1 and is draining into
the floor drains.
C. The packing is blown on a Feedwater Reg Valve and the area is blanketed in
steam.
D.r A leak has developed upstream of the HPCI Stop Valve but it is not large enough to
cause a high temperature isolation of HPCI.
References: SI-LP-01303 Rev. SI-00, Figures 6, 10, 11 and 12.
A. Incorrect since the RHRSW side of the HX is not highly radioactive.
B. Incorrect since firemain is not highly radioactive and whatever is getting wet should
not go airborne until it is isolated and dries.
C. Incorrect since the feedwater reg valve is in the turbine building.
D. Correct answer since this steam leak is directly off of main steam and has the
potential of being highly radioactive.
Thursday, April 11, 2002 02:31:54 PM
C
-4
0
w
0 w
-L
0
c
Xh
x
ca
FL
to m
x4
-D
CD
C
ah
QUESTIONS REPORT
for Revision5HT2002
1. 295035G2.1.7 001
A tornado was observed moving toward the plant 15 minutes ago. Meteorological
instruments have detected wind speeds in excess of 100 mph. The annunciator for
"RB INSIDE TO OUTSIDE AIR DIFF PRESS LOW" has just alarmed and the Inside
Rounds SO reports air rushing in and then out through a crack in the Reactor Bldg wall
on the 158' EL. The following conditions exist for Secondary Containment:
Reactor Power
Both Units at 100% RTP
Rx Bldg Dp
fluctuating between 0" and +.25" Hg
Rx Bldg Vent System
system isolated
Rx Bldg Vent Rad level
I mR/hr
Area water levels
normal
Which ONE of the following describes the appropriate actions the Shift Supervisor
should take?
(Provide copy of 73EP-EIP-001-OS)
A. Declare an ALERT. Initiate actions for Secondary Containment System being
B! Declare a SITE AREA EMERGENCY. Initiate actions for Secondary Containment
System being Inoperable.
C. Declare an ALERT. No actions required for Secondary Containment System.
D. Declare a SITE AREA EMERGENCY. No actions required for Secondary
Containment System.
References: 73EP-EIP-001-0S Rev. 14.2 pg 16 & 22 of 47
SC - Secondary Containment Control
A. Incorrect since should declare a Site Area Emergency due to tornado damage.
B. Correct answer.
C. Incorrect since should declare a Site Area Emergency due to tornado damage.
D. Incorrect since actions are required by Tech Specs since the Containment is
RO Tier:
SRO Tier:
T1G2
Keyword:
SECONDARY CONTAIN
Cog Level:
C/A 3.7/4.4
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
I
Monday, October 28, 2002 08:02:11 AM
QUESTIONS REPORT
for Revision2 HT2002
37. 295035G2.1.7 001
A tornado was observed moving toward the plant 15 minutes ago. Meteorological
instruments have detected wind speeds in excess of 100 mph. The annunciator for
"RB INSIDE TO OUTSIDE AIR DIFF PRESS LOW" has just alarmed and the Inside
Rounds SO reports air rushing in and then out through a crack in the Reactor Bldg wall
on the 158' EL. The following conditions exist for Secondary Containment:
Reactor Power
Rx Bldg Dp
Rx Bldg Vent System
Rx Bldg Vent Rad level
Area water levels
Both Units at 100% RTP
fluctuating between 0" and +.25" Hg
system isolated
I mR/hr
normal
Which ONE of the following describes the appropriate actions the Shift Supervisor
should take?
(Provide copy of 73EP-EIP-001-OS)
A. Declare an ALERT due to loss of containment. Restart Reactor Bldg Vent System,
commence a shutdown on both units and be in Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
B! Declare a SITE EMERGENCY due to damage caused by the tornado. Restart
Reactor Bldg Vent System, restore containment to OPERABLE status within 4
nlnrn hnth ,nite
in M*,,n4
q within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
SVerify or Start the SBGT S stem reduce reactor power on both units t
within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, declare an UNUSUAL EVENT f power reduction not
D. Declare an ALERT due to damage caused by the tornado. Restart Re
Vent System and SBGT System, maintain reactor power at Shift Supe
discretion.
References: 73EP-EIP-001-0S Rev. 14.2 pg 16 & 22 of 47
SC - Secondary Containment Control
A. Incorrect since declare a Site Emergency due to tornado damage. 4
B. Correct answer.
o < 15% RTP
completed on
actor Bldg
rvisors
C. Incorrect since there is no direction to start SBGT and no direction to lower power to
<15%. The 15% is the power level where primary containment is not required.
D. Incorrect since no direction to start SBGT and reactor power should be lower due to
Friday, September 20, 2002 09:23:24 AM
41
RO Tier:
Keyword:
SECONDARY CONTA1
Source:
N
Test:
S
QUESTIONS REPORT
for Revision2 HT2002
SRO Tier:
N
Cog Level:
Exam:
Misc:
Friday, September 20, 2002 09:23:24 AM
TIG2
C/A 3.7/4.4
HT02301
TCK
42
QUESTIONS REPORT
for HT2002
95. 295035G2.1.7 001
A tornado was observed moving toward the plant 15 minutes ago. Meteorological
instruments have detected wind speeds in excess of 100 mph. The annunciator for
"RB INSIDE TO OUTSIDE AIR DIFF PRESS LOW" has just alarmed and the outside
operator reports that it looks like part of the Reactor Bldg siding is loose. The following
conditions exist for Secondary Containment:
Reactor Power
Both Units at 100% RTP
Rx Bldg Dp
fluctuating between 0" and +.25" Hg
Rx Bldg Vent System
system isolated
Rx Bldg Vent Rad level
1 mR/hr
Area water levels
normal
Which ONE of the following describes the appropriate actions the Shift Supervisor
should take?
A. Restart Reactor Bldg Vent System, commence a shutdown on both units and be in
Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, declare ALERT due to loss of containment.
B.! Restart Reactor Bldg Vent System, restore containment to OPERABLE status
within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or place both units in Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, declare a SITE
EMERGENCY due to damage caused by the tornado.
C. Verify or Start the SBGT System, reduce reactor power on both units to < 15% RTP
within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, declare an UNUSUAL EVENT if power reduction not completed on
time.
D. Restart Reactor Bldg Vent System and SBGT System, maintain reactor power at
Shift Supervisors discretion, declare ALERT due to damage caused by tornado.
References: 73EP-EIP-001-0S Rev. 14.2 pg 16 & 22 of 47
SC - Secondary Containment Control
A. Incorrect since declare a Site Emergency due to tornado damage.
B. Correct answer.
C. Incorrect since there is no direction to start SBGT and no direction to lower power to
<15%. The 15% is the power level where primary containment is not required.
D. Incorrect since no direction to start SBGT and reactor power should be lower due to
loss of containment and Site Emergency should be declared.
103
Monday, June 24, 2UU2 ub:16:b8 AM
RO Tier:
Keyword:
Source:
Test:
SECONDARY CONTAIN
N
S
UESTIONS REPORT
for HT2002
SRO Tier:
Cog Level:
Exam:
Misc:
Monday, June 24, 2002 08:16:58 AM
TIG2
C/A 3.7/4.4
HT02301
TCK
104
QUESTIONS REPORT
for HT2002
1. 295035G2.1.7 001
A tornado was observed moving toward the plant 15 minutes ago. The annunciator for
"RB INSIDE TO OUTSIDE AIR DIFF PRESS LOW" has just alarmed and the outside
operator reports that it looks like part of the Reactor Bldg siding is loose. The following
conditions exist for Secondary Containment:
Reactor Power
Both Units at 100% RTP
Rx Bldg Dp
fluctuating between -.1" and +.25" Hg
Rx Bldg Vent System
system isolated
Rx Bldg Vent Rad level
1 mR/hr
Area water levels
normal
The Shift Supervisor actions should be:
A. Restart Reactor Bldg Vent System, commence a shutdown on both units and be in
Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, declare ALERT due to loss of containment.
B! Restart Reactor Bldg Vent System, restore containment to OPERABLE status
within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or place both units in Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, declare a SITE
EMERGENCY due to damage caused by the tornado.
C. Verify or Start the SBGT System, reduce reactor power on both units to < 15% RTP
within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, declare an UNUSUAL EVENT if power reduction not completed on
time.
D. Restart Reactor Bldg Vent System and SBGT System, maintain reactor power at
Shift Supervisors discretion, declare ALERT due to damage caused by tornado.
References: 73EP-EIP-001-0S Rev. 14.2 pg 16 & 22 of 47
SC - Secondary Containment Control
A. Incorrect since declare a Site Emergency due to tornado damage.
B. Correct answer.
C. Incorrect since there is no direction to start SBGT and no direction to lower power to
<15%. The 15% is the power level where primary containment is not required.
D. Incorrect since no direction to start SBGT and reactor power should be lower due to
loss of containment and Site Emergency should be declared.
Wednesday, May 08, 2002 04:26:53 PM
1
SOUTHERN NUCLEAR
PLANT E.I. HATCH
DOCUMENT TITLE:
EMERGENCY CLASSIFICATION AND INITIAL ACTIONS
PAGE 22 OF 47
DOCUMENT NUMBER:
REVISIONNERSIONT
NO:
14.2
6s
10.0 - NATURAL PHENOMENON, (continued)
I
Emergency conditions exist WHEN:
HIGH WINDS EXIST:
HIGH WINDS are indicated by:
Any tornado observed onsite
Any hurricane force winds projected onsite with windspeed > 75 mph
SAny tornado observed striking the operating facility (areas within the protected
area and the 230 Kv and 500 Kv switchyards)
Any hurricane observed. onsite with sustained windspeeds at design level
L> 94.5 mph)
SOS/ED judgment
The observation of damage from an onsite tornado with windspeed in excess of
meteorological instruments range (>100 mph)
Sustained windspeeds in excess of meteorological
mph)
instruments range (>100
AND
Either unit NOT in Cold Shutdown
END - HIGH WINDS
->
[NATURAL PHENOMENON - CONTINUED TO NEXT PAGE]->
MGR-0001 Rev. 3
CAUTION
The value of any emergency actions, which may require movement of
plant personnel, must be judged against the danger to personnel or
nuclear safety.
S
A
E
i--
G
E
N
N A
U L
E E
R
T
4
I
I
SOUTHERN NUCLEAR
PLANT E.I. HATCHI
DOCUMENT TITLE:
DOCUMENT NUMBER:
EMERGENCY CLASSIFICATION AND INITIAL ACTIONS
PAGE 16 OF 47
REVISIONNERSION
NO:
14.2
Is_
7.0 - LOSS OF CONTAINMENT
Emergency conditions exist WHEN:
NOTE
NUE is to be declared upon commencing Load Reduction.
A LOSS OF PRIMARY OR SECONDARY CONTAINMENT INTEGRITY OCCURS as indicated by the
inability to meet any one of the requirements WITHIN the time limit established by the
applicable unit's TS.
See Section 11.0, Hazards to Plant Operation, for determination of Alert Classification.
See Section 11.0, Hazards to Plant Operation for determination of Site Area Emergency
Classification.
-See Section 22.0, Multiple Symptoms and Other Conditions, for determination of General
Emergency Classification.
7-
LOSS OF
END
CONTAINMENT
E
MGR-0001 Rev. 3
SOUTHERN
NUC
PLANT
. .
C
I
I
I
STPLANT E
SC - SECONDARY CONTAINMENT CONTROL
to:Nucxhr
C
Areaorfloor dmiaiu
tv a rn s levell eove
Tube Maximums Nomna, Dapmersau Water Level]
ken or NAC
ieaest redleton Wlee Mabo.e
lTulfbte 6 Maximum NMusl Operftan Fraatio
ee
D0feantiat iressre
wateorebo.
in o' . watera
T
SPRIMARYCONTAINMENTFLOODING
THE
erdnhellOpsand
IS OR HAS BEEN REQUIRED
enter the Severe Atcideut Guidlines
Gs
PERFORM CONCURRENTLY
I
eus*iluble area coolers
ad areas,
sacondary conalinment radnation
niion does NOT ealst
W
.............
...
arate
tititowig:
Rental Fluor HYAC
per 34S0-T41 -1W-S
Reactor
rteding
HVAD
per 54SO-T41"0t-IS
WAIT UN"TIL
'blent E- dsltrenliat tsmeatelre
It abtove
oINorma Oprefin Tmpretroiar
(Table 4)
7LL a,
c9n10 into ares
T.s,
I to:
ire a1
cooling
stain ptimay cornamemantre
Idly
I
.RFORM CON C UINTLy
atur
SCIL
WAIT UNTIL
ONE of the flloiine
Is shone
Maximum No"rn Opeationg Water tenv
(Table 6):
O A oor dranlnamp etatertenl
Operelt alilable aump pumps to retore
and maintaln mter tevne below MEourrm
Normal Oueatno Water Level (Tubla 5)
I
IF ONE orf t
foloomig CANNOT be
rent oed and maintained below Maximum
Natinal Operating Water Level (Table 5):
o My floor drain somp maret levl
o ANy areawater leel
THENISOte ALL
Uystems dbPmcharging
muter
Into strmp or area EXCEPT syStears
reluired to:
O0 catureaderurate core colln,
O shut down reacor
O .upprfss fire
O maintain pdmrry containment
Intagrity
PERPORMCONCURRENTLy
WAIT UNTIL
ia flacurein
reacor co~olan
rtutusecondary containment
I-'
BFORE
ANY area esther level reaches
,.Mo.ma Sate Domitno, Water Level
(Tablet5)
PERFORM CONCURRENTLY
ROIA poNtA
WAIT UNTIL
area wother level
Masinahm SaeOero~at'ingWter Level
in morellaren ometae
(Teble 0)
(EMERGENCY DEPRESS IS REQUIRED)
WAIT UNTIL
eree water level
is ubove
Maximum Sate Operutna Water Level
in mare then ore area
(TableS)
Shot down reactor per3400OPS0fl45
or 3400OFS.014.1S
lENT
"URES
aF Nomuaw as Sare
SIC'
" WAIT Tul
ra
rem radat_
leveo
tint
No thl~
.a NO .
Isttm
sh
vel
Matniuam Nortnut Operetin Radiautio
(Table S)
toailst ALLsyttnmt ditchurat
into
EXCEPT sYstemsrlresmoa to:
0 assuraxeeeuatoe cmcaniog
o supress fire
o
enslnaIn pri*naXcnainment
PERFORM O*NCURRENTLY
WAIT UNTIL
pitmaty syttern
isdiec~arguiimug
racor oon
into econdorycontainmentm
(Table 7)
BEFORE
kYnareardan
NOW
vel. reaches
Maximumn Sore Operebu Rodlaton Level
(Table 6)
PERFORM CONCURRENTLY
RC(A) pointA
WAIT UNTIL
area
raiamnlee
PMasinvm Sama
Opeatming Radiation Level
in mare Soon ove arear
(EMERGENCY.F DERES ISREOUIRED
RR -RADIOACTIVITY RELEAS
SOtter. redsOact~vty rleat
aret
shove 0 S7 ruPlhr
i t
LE PRIMARY CONTAINMENT FLOODING IM
saxt the tOPic
IS OR HAS ShEN REOLIIRPED
I
Ser
Acl*,d,
C Ez
i[
WHMpTHFORM'GTEGOLLOWINO
L
T TurbieeBulkifitnHVACioshuldOWn
HE r.a Trarurm
roiurel Per 34
isolate ALL Primary systoem discharogng
Nomanc coolant into ares outsie pnmsry
aMd secondary ronanarrnts (Tuse 7)
EXCEPT systems raruired to:
o asreadesutne cor coling
o shut dow reantor
o nalnottin tmarycntttelmrnent
ruintnfd
WtHILE PERFORMHING
THE FOLLOWING
4,5
IE MOYUniitI orUn 2 secondary
co'.
a'rent ':
conS
2t,
tVAC eahsaus radationtlevetexcsadsee
0 Unt 1 and Unit 2 Readclorul~ding
isolation serpoint (Table 14)
I
WAC Iscoalo
"0
Unit I ntd Unit2 RatedaFloor
HVAC isecation
"I o Unit 1 n
Unit 2 SBGT initiation
I per 34A,0.Tfl-0O)-1S
fRefetl Floor WAD isolates
'T
n restar Reruel Floor (aAD per
8 Unit1 I orUnit 2 secondary conainment
i
If ,eceasetay deot h*l dt
dell
pressure
radiation conditiondoes NOT exist
R
low
F
soruonUintadncts
I
per 31EO.EOP.I00-1S
if Reactor Buei* HVAC Isolates
If
restart Reodor sBilding HVAC per
I
a Unit 1 or U=R 2
rec
arsconlainnment
If nocestay defeuthta
llt
d"
pressrue
mrdabon
Boaditon
does NOT avast
I
.
i
RWL holatimon intedos
I
per 31ECEOP-100-iS
r M--- an
Shut unnon a
or 34GO-O
J
T1
QUESTIONS REPORT
for HT2002
107. G2.1.22 001
Unit 2 has been shutdown for a refueling outage. After 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> the following
conditions exist:
Reactor Mode Switch:
Refuel
Reactor Temperature:
1650F and steady
Reactor Pressure:
0 psig
All reactor vessel head closure bolts are fully tensioned.
All rods are IN.
Which ONE of the following is correct Mode of Operation for Unit 2?
A! Mode 2
B. Mode 3
C. Mode 4
D. Mode 5
References: Tech Spec section 1.1, Table 1.1-1
Modified from question #84 on 1995 SRO exam
A. Correct answer.
B,C,D Incorrect (See table 1.1-1) Unless a Special Operations Tech Spec is invoked
then the reactor changes modes when moving the mode switch to refuel.
RO Tier:
SRO Tier:
T3
Keyword:
MODE
Cog Level: C/A 2.8/3.3
Source:
M
Exam:
HT02301
Test:
S
Misc:
TCK
116
Monday, June 24, 2002 08:16:59 AM
Definitions
1.1
6
Table 1.1-1 (page 1 of 1)
MODES
AVERAGE REACTOR
COOLANT
REACTOR MODE
TEMPERATURE
MODE
TITLE
SWITCH POSITION
(OF)
1
Power Operation
Run
NA
Dfa
nr .trrti n/Hnt
NA
StartupL
Hot Shutdown(a)
Cold Shutdown(a)
Refueling(b)
Standby
Shutdown
Shutdown
Shutdown or Refuel
> 212
S 212
NA
(a)
<-'
(b)
E
All reactor vessel head closure bolts fully tensioned.
One or more reactor vessel head closure bolts less than fully tensioned.
4
Amendment No. 195
HATCH UNIT 1
3
4
5
2
1.1-6
84.
Preparations are presently being made to startup the Unit One reactor. The following conditions
exist:
Reactor Mode Switch:
Shutdown
Reactor Pressure:
125 psig
All reactor vessel head closure bolts are fully tensioned
All rods are IN.
The reactor is in:
a.
Mode 2
b.
Mode 3
c.
Mode 4
d.
Mode 5
ANS:
b
a,c,d incorrect, see table 1.1-1 (pg 1.1-8) in Unit 1 Tech Specs.
NEW
KA#
Generic 2.1.22
OBJ# 400.067.a.05
REF LR-LP-30005
COGNITIVE LVL 3
5.
During a valve lineup, an operator needs to check a valve open. It is noted that the valve has a
locking device on it. To check the valve position the operator should:
a.
unlock the valve, turn it in the closed direction no more than 1/4 turn, place it full
open, and replace the locking device
b.
unlock the valve, turn it in the open direction, verify that the hand wheel moves less than
1/4 turn, and replace the locking device
c.
leave the locking device installed, try to move the hand wheel to ensure locking device
integrity, and verify stem position
d.
leave the locking device installed, verify stem position, and verify administratively that
the valve has not been repositioned.
ANS:
a
b incorrect, check it in the closed direction
c,d incorrect, the locking device needs to be remove to check actual valve position.
NEW
IKA#
Generic 2.1.29
OBJ# 300.022.a.06 i
REF LT-LP-30004
[COGNITIVE LVL 1
1[
49
QUESTIONS REPORT
for HT2002
110. G2.1.4 001
Fuel movement is on progress on Unit 2 with the following plant conditions:
Mode Switch
Coolant
Reactor
Position
Temperature
Power
Unit I
Run
5450F
80%
Unit 2
Refuel
128 0F
0%
Which ONE of the following is the minimum on-site shift staffing required by the Unit 2
Technical Specifications?
(Provide Tech Spec section 5.2.2)
A. SRO
I + I for Fuel Handling
2
2
1
B!3 SRO
1 + 1 for Fuel Handling
2
3
1
C. SRO
2 + 1 for Fuel Handling
2
3
0
D. SRO
2 + 1 for Fuel Handling
3
3
0
119
Monday, June 24, LuuL u0:1t 7uu ,0lv
QUESTIONS REPORT
for HT2002
References: Tech Spec Section 5.2.2
-
99 exam Question #6
LT-ST-30003-05, p.7 & 8
Modified answer A as follows: PEO from 3 to 2.
A. Incorrect since 3 PEO's are required at all times.
B. Correct answer.
C. Incorrect since Unit 2 does not need an SRO since it is in Mode 5.
D. Incorrect since only 2 RO's are required (one for each unit that has fuel).
RO Tier:
Keyword:
STAFFING
Source:
B
Test:
S
Monday, June 24, 2002 08:17:00 AM
SRO Tier:
T3
Cog Level: MEM 2.3/3.4
Exam:
HT02301
Misc:
TCK
120
QUESTIONS REPORT
for HT2002
18. G2.1.4 001
Fuel movement is on progress on Unit 2 with the following plant conditions:
Mode Switch
Position
Run
Refuel
Coolant
Temperature
545 F
128 F
Which one of the following is the minimum on-site shift staffing required by the Unit 2
Technical Specifications?
A. SRO
B.r SRO
C. SRO
D. SRO
1 + 1 for Fuel Handling
2
2
1
1 + 1 for Fuel Handling
2
3
1
2 + 1 for Fuel Handling
2
3
1
2 + 1 for Fuel Handling
3
3
1
References: Tech Spec Section 5.2.2
A. Incorrect since 3 PEO's are required at all times.
B. Correct answer.
C. Incorrect since Unit 2 does not need an SRO since it is in Mode 5.
D. Incorrect since only 2 RO's are required (one for each unit that has fuel).
18
Thursday, April 04, 2002 11:36:29 AM
Unit 1
Unit 2
Reactor
Power
80%
0%
QUESTIONS REPORT
for HT2002
SRO Only
99 exam Question #6
LT-ST-30003-05, p. 8
Modified answer A as follows:
Thursday, April 04, 2002 11:36:29 AM
STA from 0 to 1, PEO from 3 to 2.
19
Organization
5.2
5.0
ADMINISTRATIVE CONTROLS
5.2 Organization
5.2.1
Onsite and Offsite Organizations
Onsite and offsite organizations shall be established for unit operation and
corporate management, respectively. The onsite and offsite organizations shall
include the positions for activities affecting safety of the nuclear power plant.
a.
Lines of authority, responsibility, and communication shall be defined and
established throughout highest management levels, intermediate levels,
and all operating organization positions. These relationships shall be
documented and updated, as appropriate, in organization charts,
functional descriptions of departmental responsibilities and relationships,
and job descriptions for key personnel positions, or in equivalent forms of
documentation. These requirements, including plant specific titles of
those personnel fulfilling the responsibilities of the positions delineated in
these Technical Specifications, shall be documented in the Plant Hatch
Unit 2 FSAR;
b.
An assistant plant manager shall be responsible for overall safe operation
of the plant and shall have control over those onsite activities necessary
for safe operation and maintenance of the plant;
c.
The corporate executive responsible for Plant Hatch shall take any
measures needed to ensure acceptable performance of the staff in
operating, maintaining, and providing technical support to the plant to
ensure nuclear safety; and
d.
The individuals who train the operating staff, carry out health physics, or
perform quality assurance functions may report to the appropriate onsite
manager; however, these individuals shall have sufficient organizational
freedom to ensure their independence from operating pressures.
5.2.2
Unit Staff
The unit staff organization shall include the following:
a.
A total of three plant equipment operators (PEOs) for the two units is
required in all conditions. At least one of the required PEOs shall be
assigned to each reactor containing fuel.
(continued)
Amendment No. 135
HATCH UNIT 2
5.0-2
Organization
5.2
5.2 Organization
5.2.2
Unit Staff (continued)
b.
At least one licensed Reactor Operator (RO) shall be present in the
control room for each unit that contains fuel in the reactor. In addition,
while the unit is in MODE 1, 2, or 3, at least one licensed Senior Reactor
Operator (SRO) shall be present in the control room.
c.
The minimum shift crew composition shall be in accordance with
10 CFR 50.54(m)(2)(i). Shift crew composition may be less than the
minimum requirement of 10 CFR 50.54(m)(2)(i) and 5.2.2.a for a period of
time not to exceed 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> in order to accommodate unexpected absence
of on duty shift crew members provided immediate action is taken to
restore the shift crew composition to within the minimum requirements.
d.
An individual qualified to implement radiation protection procedures shall
be on site when fuel is in the reactor. The position may be vacant for not
more than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, in order to provide for unexpected absence, provided
immediate action is taken to fill the required position.
e.
Administrative procedures shall be developed and implemented to limit
the working hours of unit staff who perform safety related functions (e.g.,
licensed and non-licensed operations personnel, health physics
technicians, key maintenance personnel, etc.).
Adequate shift coverage shall be maintained without routine heavy use of
overtime. The objective shall be to have operating personnel work a
nominal 40 hour4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> week while the unit is operating. However, in the event
that unforeseen problems require substantial amounts of overtime to be
used, or during extended periods of shutdown for refueling, major
maintenance, or major plant modification, on a temporary basis the
following guidelines shall be followed:
1.
An individual should not be permitted to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />
straight, excluding shift turnover time;
2.
An individual should not be permitted to work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />
in any 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period, nor more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in any 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />
period, nor more than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in any 7 day period, all excluding
shift turnover time;
3.
A break of at least 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> should be allowed between work
periods, including shift turnover time;
4.
Except during extended shutdown periods, the use of overtime
should be considered on an individual basis and not for the entire
staff on a shift.
(continued)
Amendment No. 135
HATCH UNIT 2
5.0-3
Page 7 of 28
LT-LP-30003-05
C,
I.
Tech Spec Administrative Controls
Cover Tech Spec section 5.1,
Responsibility
A.
Responsibility
- 1.
The Plant Manager provides direct executive oversight
over all aspects of Plant Hatch.
2.
The assistant plant manager is responsible for overall
unit operation.
3.
The Plant Manager, or his designee, is responsible for
the Radiological Environmental Monitoring Program.
4.
The Superintendent of Shift (SOS) is responsible for
the control room command function. During his
absence an active Senior Reactor Operator (SRO), OR
Licensed Reactor Operator (RO) if both units are in
Mode 4 or 5, shall be designated to assume the control
room command function.
L02
EO la,b
B.
Unit Staff
- fEN 91-024 (CO 9100131)
I.
A total of three Plant Equipment Operators (PEOs) for
the two units is required at all times. At least one of
the required PEOs shall be assigned to the reactor
containing fuel.
2.
At least one Licensed RO shall be in the Main Control
Room (MCR) for each reactor containing fuel. Also at
least one SRO shall be present in the MCR while the
unit is in MODE 1, 2, or 3.
3.
Minimum shift crew composition
The MCR shall be manned as a minimum per
1OCFR50.54(m)(2)(i). The chart below outlines the
requirements. Shift crew composition may be less
than the minimum requirements for short periods, not
to exceed 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, to accommodate unexpected
absences provided immediate action is taken to
restore shift crew composition.
TECH SPECS / ADMINISTRATIVE CONTROLS
Page 7 of 28
Minimum # Required
Units in Cold'Shutdown
,
2
0
4.
Overtime
Question:
If employee came to work on night
shift at 7:00 p.m. Friday and worked
night shifts for 4 days, then came in
at 7:00 a.m. Wednesday and worked
day shift for 3 days; would employee
violate overtime limits?
a.
Section 5.2.2.e limits the working hours of Unit
staff who perform safety-related functions (e.g.,
SROs, ROs, Plant Equipment Operators, HPs,
and key maintenance personnel, etc.).
b.
In the event that unforeseen problems require
substantial amounts of overtime to be used or
during periods of shutdown for refueling, major
maintenance, or major plant modifications, the
following guidelines shall be followed on a
temporary basis:
1)
An individual should not be permitted to
work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> straight,
excluding shift turnover time.
2)
An individual should not be permitted to
work more than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> in any 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
period, nor more than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in any 48
hour period, nor more than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in any
7 day period, all excluding shift turnover
time.
4
Both
Position
QUESTIONS REPORT
for Revision2 HT2002
38. G2.2.27 001
Unit 1 is in Mode 5 with a core shuffle in progress. The bridge operator has just
inserted a fuel bundle into the core when he notices that the adjacent fuel bundle is
mis-oriented.
Which ONE of the following actions are required to be performed by the fuel handling
crew with regards to the fuel shuffle?
A/ The bridge operator stops fuel movements and informs SRO of condition. The SRO
contacts Reactor Engineering to prepare a Fuel Movement Sheet change. The
crew reviews the approved change sheet, corrects the orientation error and
continues with fuel movements with SRO approval.
B. The SRO allows the crew to continue with fuel movements after correcting the
orientation error and notifies Reactor Engineering for documentation on the Core
Loading Verification sheet.
C. The SRO stops fuel movements and the crew determines the proper orientation of
the adjacent fuel bundle. The SRO approves the actions to re-orient the fuel bundle
and the bridge operator notifies the control room when move is complete.
D. The SRO allows fuel movements to continue and contacts Reactor Engineering to
prepare a Fuel Movement Sheet change. At the next appropriate opportunity the
crew will correct the orientation error per the Movement Sheet as long as it is done
on their shift.
References: 42FH-ERP-014-OS Rev. 15.2, pg 10 of 28
34FH-OPS-001-OS Rev. 21.1, pg 6 and 7 of 42
A. Correct answer.
B. Incorrect since ALL fuel movements must be stopped when an error is found.
C. Incorrect since the SRO cannot approve a movement without proper authorization.
D. Incorrect since the Fuel Movement Change sheet must be approved prior to any
further fuel movements.
RO Tier:
SRO Tier:
T3
Keyword:
FUEL MOVEMENTS
Cog Level:
C/A 2.6/3.5
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
o OnlflO'23:2 AM
43
Fida~i:y, Septt*ll~ em
U
e
-r
,¢
I
- 't'~,"
- v
QUESTIONS REPORT
for HT2002
113. G2.2.27 001
Unit 1 is in Mode 5 with a core shuffle in progress. The bridge operator has just
inserted a fuel bundle into the core when he notices that the adjacent fuel bundle is
mis-oriented.
Which ONE of the following actions are required to be performed by the fuel handling
crew with regards to the fuel shuffle?
Af The bridge operator stops fuel movements and informs SRO of condition. The SRO
contacts Reactor Engineering to prepare a Fuel Movement Sheet change. The
crew reviews the approved change sheet and continues with fuel movements with
SRO approval.
B. The SRO allows the crew to continue with fuel movements and notifies Reactor
Engineering for documentation on the Core Loading Verification sheet.
C. The SRO stops fuel movements and the crew determines the proper orientation of
the adjacent fuel bundle. The SRO approves the actions to re-orient the fuel bundle
and the bridge operator notifies the control room when move is complete.
D. The SRO allows fuel movements to continue and contacts Reactor Engineering to
prepare a Fuel Movement Sheet change. At the next appropriate opportunity the
crew will complete the new movement as long as it is done on their shift.
References: 42FH-ERP-014-OS Rev. 15.2, pg 10 of 28
34FH-OPS-001-OS Rev. 21.1, pg 6 and 7 of 42
A. Correct answer.
B. Incorrect since ALL fuel movements must be stopped when an error is found.
C. Incorrect since the SRO cannot approve a movement without proper authorization.
D. Incorrect since the Fuel Movement Change sheet must be approved prior to any
further fuel movements.
RO Tier:
SRO Tier:
T3
Keyword:
FUEL MOVEMENTS
Cog Level: C/A 2.6/3.5
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
0
....
,,O
.o
.7.nn
AhA
123
IVIUIIay, "JUIn
I-' U {
O II.v,*v
QUESTIONS REPORT
for HT2002
1. G2.2.27 001
Unit I is in Mode 5 with a core shuffle in progress. The bridge operator has just
inserted a fuel bundle into the core when he notices that the adjacent fuel bundle is
mis-oriented. SELECT the actions required to be performed by the fuel handling crew
with regards to the fuel shuffle?
A. The bridge operator stops fuel movements and informs SRO of condition. SRO
allows bridge operator to correct orientation after verifying that the orientation was
not correct.
B. The SRO allows the crew to continue with fuel movements and notifies Reactor
Engineering for documentation on the Core Loading Verification sheet.
C. The SRO stops fuel movements and contacts Reactor Engineering to prepare a
Fuel Movement Sheet change. The crew reviews the approved change sheet and
continues with fuel movements with SRO approval.
D. The SRO allows fuel movements to continue and contacts Reactor Engineering to
prepare a Fuel Movement Sheet change. At the next appropriate opportunity the
crew will complete the new movement as long as it is done on their shift.
References: 42FH-ERP-014-0S Rev. 15.2, pg 10 of 28
34FH-OPS-001-0S Rev. 21.1, pg 6 and 7 of 42
A. Incorrect since all moves must be controlled by a Fuel Movement Sheet.
B. Incorrect since ALL fuel movements must be stopped when an error is found.
C. Correct answer.
D. Incorrect since the Fuel Movement Change sheet must be approved prior to any
further fuel movements.
Friday, May 03, 2002 02:07:34 PM
PAGE
10 OF 28
PL
T
E
I-
HATCH..-.---
DOCUMENT TITLE:
FUEL MOVEMENT
7.1.4.1.9
7.1.4.1.10
7.1.4.1.11
7. 1.4 .1.12
DOCUMENT NUMBER:
R1V5SEDN
15 ED 2
Present the change request, original marked-up move sheet(s),
any additional sheets to another Reactor Engineer/designated
alternate, OR a Shift Supervisor/SRO for review.
Present the reviewed change request, original marked-up move
sheet(s),
AND any additional sheets to the Reactor Engineering
Supervisor, Manager of Engineering Support,
OR the SOS for
approval.
Upon approval, the Reactor Engineering Supervisor,
Manager of Engineering Support,
OR the SOS will sign the change
request and any additional sheets and initial
the changes on the
original move sheet(s).
Make a copy of the completed Change Request AND forward to the
Reactor Engineering Supervisor for review and possible Computer
Database Update.
Attach the completed change request to the original move sheet.
7.1.4.2
IF major changes to the move sheet are needed AND these changes are
such that they cannot be adequately handled by the above rules for
changes,
THEN all fuel movements must stop UNTIL a new move sheet can
be prepared incorporating the new moves.
The Reactor
Engineer/designated alternate and the SRO on the refueling
floor/Shift Supervisor decide IF a new move sheet is required.
IF a
new move sheet is required, make a copy of the approved move sheet
and forward to the Reactor Engineering Supervisor.
4
MGR-0001 Rev.
2
SOUTHERN NUCLEAR
6
NOTE
In the special case of fuel movements that only
involve the Spent Fuel Pool or a Spent Fuel Pool
location, a Reactor Engineer may serve as the
approval authority for the Reactor Engineering
Supervisor.
The Reactor Engineering Supervisor or
superior must approve changes to move sheets being
used to load an MPC-68.
<-V
C
NO:
SOUTHERN NUCLEAR
PAGE
PLANT E. I. HATCH
6 OF 42
DOCUMENT TITLE:
DOCUMENT NUMBER: REVISIONNERSIK
FUEL MOVEMENT OPERATION
NO:
21.1
5.2.7
Irradiated fuel must NOT be ungrappled in any Fuel Preparation Machine (FPM) UNLESS
the FPM is in the full down position.
5.2.8
Fuel must NOT be ungrappled in the core, fuel storage canister OR in the fuel storage
racks UNLESS proper depth and seating are verified.
5.2.9
IF, during fuel movement, it is found that conditions have changed such that any of the
requirements of this procedure are no longer satisfied, any member of the refueling
bridge team has the authority to halt fuel movement. Prior to halting fuel movement, the
bundle will be loaded in a safe Fuel Pool location or returned to its proper In-Core
location, if possible, UNTIL all requirements are again satisfied.
5.2.10
The Fuel Grapple must be in the full up position prior to moving the bridge OR trolley,
except WHEN:
"* making small adjustments of the bridge OR trolley position to allow alignment for
latching OR discharging a fuel bundle, blade guide,or weight.
"
transporting a blade guide/fuel bundle from one core location to another core location
provided the "BUNDLE CLEAR OF CORE" light is illuminated. WHILE moving the
bridge/trolley, the travel must be slow enough such that the mast does not contact the
trolley.
"* performing refueling interlock checks.
"* core load OR fuel pool verification as long as the bridge is not moved at a high rate of
speed and no load other than the camera and bracket are attached.
"
after discharging a load in the fuel pool/core, THEN raise the grapple several feet OR
as high as necessary to clear any obstruction. WHILE moving the bridge/trolley to a
new location for the purpose of grappling onto another load, the travel must be slow
enough such that the mast does not contact the trolley.
5.2.11
The trolley (operator's cab) must be aligned to allow passage through the transfer canal
prior to moving the bridge forward OR backward WHEN transferring fuel OR blade guides
from the Spent Fuel Pool to the Reactor Cavity, OR vice versa, OR WHEN transferring
fuel OR blade guides from one spent Fuel Pool to another.
MGR-0001 Rev 3
SOUTHERN NUCLEAR _-
PAGE
PLANT E. I. HATCH
7 OF 42
DOCUMENT TITLE:
DOCUMENT NUMBER: REVISIONNERSIOIT
FUEL MOVEMENT OPERATION
NO:
21.1
5.2.12
The Refueling Bridge Operator will NOT engage in any other activities WHILE moving the
Refueling Bridge OR manipulating any Refueling Bridge controls that will divert full
attention from being devoted to the operation of the Refueling Bridge. Any movement of
the Refueling Bridge OR Hoists must be terminated IF full attention cannot be devoted to
the Refueling activity in progress.
5.2.12.1
The Refueling Bridge Operator will be fully cognizant of all procedural requirements
for fuel movement and must immediately inform the SRO of any problems, whether
with equipment or procedures, which could prevent compliance with these procedural
requirements.
5.2.12.2
The Refueling Bridge Operator must remain aware of the critical nature of his task,
utilize STAR techniques to preclude any errors, and maintain a questioning attitude.
5.2.12.3
The Refueling Bridge Operator is expected to ask the SRO to verify or clarify any
movement which appears unusual.
5.2.13
A Senior Reactor Operator (SRO) shall be on the Refueling Bridge during all core
alterations, and other fuel movements as directed by the Operations Manager. His
responsibilities will be as follows:
5.2.13.1
The SRO will not allow any fuel movement unless the Refuel crew is able to devote
100% attention to the task. The crew, as a minimum, will consist of an SRO, a bridge
operator, and a second verifier. The SRO must ensure that each member is fully
qualified and capable of performing their task, and that each is aware of their
responsibilities.
5.2.13.2
The SRO must ensure compliance with all applicable procedures at all times, and
must ensure that procedural & equipment problems are properly documented.
Procedure problems, or conditions which preclude compliance, must be corrected
before proceeding.
5.2.13.3
The SRO will not allow any crew member to conduct a turnover or be relieved when
the bridge or grapple is moving, or when the grapple is loaded.
5.2.13.4
The SRO must ensure that the control room is aware of conditions on the refueling
floor. Constant communications will be maintained with a licensed individual in the
control room when core alterations are in progress.
5.2.13.5
The SRO will ensure that the crew has all the material necessary (i.e., procedures,
core maps, movement sheets, etc.) to conduct fuel movement promptly and correctly.
One required item will be a core map with the cell removal sequence for upcoming
cells already marked and verified (not required for fuel shuffle). Laptop computer
displays of the core may be used instead of paper copies of core maps.
5.2.13.6
The SRO will ensure that the work pace is comfortable to all members, and that no
one feels any urgency in completing the task.
MGR-0001 Rev 3
-- V
QUESTIONS REPORT
for HT2002
115. G2.2.32 001
Unit 2 is in a refueling outage with a fuel shuffle in progress. A fuel bundle is being
transfered from the core to the fuel pool when the Control Board Operator reports that
reactor cavity water level is decreasing.
Per 34AB-G41-002-2S, Decreasing Rx Well/Fuel Pool Water Level, which ONE of the
following actions should the refueling SRO direct the bridge operator to perform?
A. Return the fuel bundle to the closest in-core location as possible.
B. Stop all movement and evacuate the refueling floor immediately.
C. Continue with movement to the fuel pool and lower it as deep into the pool as
possible.
Df Return the fuel bundle to its proper in-core location.
References: 34AB-G41-002-2S Rev. 2 pg 2 of 5.
1999 Hatch Exam Question 21
Modified answers slightly to make different answer correct.
A. Incorrect since the direction should be to move the fuel bundle to its proper in-core
location.
B. Incorrect since direction should be to lower the bundle and you only have to
evacuate the refueling floor if there are radiation alarms.
C. Incorrect since direction should be to place the fuel bundle in any fuel pool rack.
D. Correct answer.
RO Tier:
SRO Tier:
T3
Keyword:
FUEL POOL
Cog Level:
MEM 2.3/3.3
Source:
B
Exam:
HT02301
Test:
S
Misc:
TCK
125
Monday, June 24, 2002 08:1 t:uu AM
QUESTIONS REPORT
for HT2002
1. G2.2.32 001
Unit 2 is in a refueling outage with a fuel shuffle in progress. A fuel bundle is being
transfered from the core to the fuel pool when the Control Board Operator reports that
reactor cavity water level is decreasing. Per 34AB-G41-002-2S, Decreasing Rx
Well/Fuel Pool Water Level, which one of the following actions should the refueling
SRO direct the bridge operator to perform?
A. Return the fuel bundle to the closest in-core location as possible.
B. Stop all movement and evacuate the refueling floor immediately.
C. Continue with movement to the fuel pool and lower it as deep into the pool as
possible.
D. Return the fuel bundle to its proper in-core location.
References: 34AB-G41-002-2S Rev. 2 pg 2 of 5.
1999 Hatch Exam Question 21
Ro
Aro'o:rli
1
_
I2a
tiferari -.
a :..
A. Incorrect since the direction should be to move the fuel bundle to its properin-core ..
S...
l-
ocation. -
.- ncorrect-since-dtirectioflhOU-oýowerh-bInllC
ad you oly ....
t.....
evacuate the refueling floor if there are radiation alarms.
C. Incorrect since direction should be to place the fuel bundle in any fuel pool rack.
D. Correct answer.
Friday, May 03, 2002 06:58:19 AM
SOUTHERN NUCLEAR
DI AKlT M
I WATW.
S......PAGE 2OF 5
DOCUMENT TITLE:
DOCUMENT NUMBER:
REVISION NO:
DECREASING RX WELL/FUEL POOL WATER LEVEL
j_-_----2
4.0
SUBSEQUENT OPERATOR ACTIONS
N>
4.1
Dispatch personnel to investigate the alarm.
4.2
IF a refueling floor radiation monitor alarms due to decreasing reactor well OR fuel pool water
level:
4.2.1
Evacuate the refueling floor immediately.
4.2.2
Have Health Physics assess the Radiological conditions on the Refueling Floor AND
establish a manned access control point to the Refueling Floor. IF fuel OR highly
irradiated components are actuallyý-ncovered - exposure rates may b&
evere
additional entries may NOT- be possible.
......
, ....
-- --
4.3
F
Wfuelmvment-is-in-progressr-pIth4U
Jt-)bundI
the following:
4.3.1
Return fuel bundle to its proper incore location, OR
-.
i-ti~f~flfl~
Tift
.4 MTN7MF1'W thdIMP151, Y_7
4.3.3
4.4
4.4.1
4.4.2
4.5
Lower fuel bundle as deep into the vessel as possible.
IF movement of other highly radioactive materials (irradiated control rods, fuel channels,
LPRM's, etc.) is in progress, PLACE the item in a safe condition by performing one of the
following:
Lower item as deep into vessel as possible
Lower item as deep into fuel pool, cask storage area, OR transfer canal, as possible
Contact Health Physics to provide continuous coverage WHILE personnel are on the refueling
floor.
E
MGR-0001 Rev 3
CAUTION
CONTROL ROD BLADES AND FUEL IN THE FUEL PREP MACHINE MAY BECOME UNCOVERED
ALONG WITH IRRADIATED MATERIAtýSýrýTH
IRFTHE PRO-tESSflFB
.
....
EXTREME RADIATION LEVELS COULD RESULT IF THESE ITEMS ARE EXPOSED ABOVE
WATER.
'riday, October 01, 1999 @ 06:18 PM
HATCH99.BNK
Page: 21
21. Unit 2 is in a refueling outage with a full core off load in progress. A fuel bundle is
being transfered from the core to the fuel pool when the control room operator reports
that reactor cavity water level is decreasing. Per 34AB-G41-002-2S, "Decreasing Rx
Well/Fuel Pool Water Level," which one of the following actions should the refueling
SRO direct the bridge operator to perform?
a. Return the fuel bundle to any in-core location that is available.
,1b Move the fuel bundle to any fue storage rack in the fuelpool.
c. Move the fuel bundle to the fuel pool and lower it as deep into the pool as possible.
d. Do not move the fuel bundle any further and lower it as deep as possible where it is.
Bank question (modified slightly)
LT-LP-04502-03, p. 36
KEY WORDS:
System
K/A No.
KA/Value
Difficulty
SampiePian
VendorL-
LiceAsee
Last used
GENERICS
.2.32
(2.3/33)
_1
IER3CAT2
HATCH
BANK
QUESTIONS REPORT
for HT2002
116. G2.2.6 001
While reviewing a procedure that is required to be completed before the end of the
current shift, the SS notices a step that requires the use of a gauge which is broken.
Another gauge is available in the system and the SS has confirmed it will operationally
function as a substitute.
At a minimum, which ONE of the following actions must be done to perform the
procedure? The SS should:
A. Make a pen and ink change to the procedure.
B. Make a SRO change to the procedure.
C. Make a pen and ink change to the procedure with SOS concurrence.
D. Make a permanent change to the procedure obtaining manager approval prior to
use.
Reference: LT-LP-30004-04, Pg. 15-17
99 exam question #19
EO 300.002.a.02
A. Incorrect since this process is used for editorial changes. This change is not
editorial.
B. Correct answer.
C. Incorrect since this process is used for editorial changes. This change is not
editorial.
D. Incorrect since this is the normal process that is used if the procedure is not needed
now. Since this procedure change is needed prior to the end of the shift then an SRO
change is appropriate.
RO Tier:
Keyword:
Source:
Test:
PROCEDURE CHANGE
B
S
SRO Tier:
Cog Level:
Exam:
Misc:
T3
MEM 2.3/3.3
HT02301
TCK
126
Monday, June 24, 2002 08:17:01 AM
QUESTIONS REPORT
for HT2002
22. G2.2.6 001
While reviewing a procedure that is required to be completed before the end of the
current shift, the SS notices a step requireing the use of a gauge which is broken.
Another gauge is available in the system and the SS has confirmed it will operationally
function as a substitute. At a minimum, which one of the following actions must be
done to perform the procedure? The SS should:
A. Make a pen and ink change to the procedure.
B.r Make a SRO change to the procedure.
C. Make a pen and ink change to the procedure with SOS concurrence.
D. Make a permanent change to the procedure obtaining manager approval prior to
use.
Reference: LT-LP-30004-04, Pg. 15-17
99 exam question #19
A. Incorrect since this process is used for editorial changes. This change is not
editorial.
B. Correct answer.
C. Incorrect since this process is used for editorial changes. This change is not
editorial.
D. Incorrect since this is the normal process that is used if the procedure is not needed
now. Since this procedure change is needed prior to the end of the shift then an SRO
change is appropriate.
Thursday, April 04, 2002 11:36:30 AM
23
5.
Controlling equipment status, with special emphasis
on Technical Specifications Limiting Conditions for
Operation and for worker protection.
6.
Controlling the position/condition of all plant
components and systems except as allowed by other
approved procedures.
7.
Ensuring operations personnel are trained and
qualified.
8.
Ensuring that operations activities are governed by
effective administration controls.
9.
Being responsible for the operation of the Radwaste
facility.
E04
B.
The order to startup or to shutdown the reactor for planned
maintenance or refueling is issued by the General Manager
Nuclear Plant or his designated alternate.
E Q
C.
In an emergency or when it is judged that continued
operation would jeopardize plant or personnel safety, any
member of the plant staff holding an operator license has the
authority to order the reactor shutdown or to shut it down
himself.
Review 10AC-MGR-003-0S
IV.
1OAC-MGR-003-OS, "Preparation and Control of
Procedures"
Procedure is now a flowchart.
A.
This procedure shows how to process:
Review Attachment 3 of LP
30004.
Review lOAC-MGR-003-OS,
1.
Changes to existing procedures,
2.
New procedures,
3.
Special purpose procedures and,
4.
Vendor procedures controlled under the Plant Hatch
Quality Assurance Program
(10AC-MGR-003, Attachment 1)
EO 6
Question: May a SRO
change be made to a
procedure that addresses core
alteration?
Ans: No (IOAC-MGR-003,
Attachment 2)
B.
Editorial Changes must fit one of the examples listed in
Attachment 1. The Editorial Change process is restricted to
those examples and no other changes can be made using this
process.
C.
SRO Changes may be made provided the change is not
Editorial and the intent of the original procedure is not
altered. Intent of a procedure is what the procedure does
and how it does it.
1.
General Examples of Changes of Intent:
a.
Change in the method of performing a step or
the sequence of steps in such a way that it would
affect the results.
b.
Achieving the same result with different steps or
a different sequence of steps which have not
been previously evaluated.
2.
Specific Examples of Changes of Intent:
4
a.
Change in sequence of performing Core
Alterations.
b.
Changes to Limits/Setpoints/Acceptance Criteria
NOT previously evaluated (by 10 CFR 50.59
Evaluation).
c.
Changes that reduce control or design features
for ALARA.
d.
Changes to initial conditions.
e.
Deleting or reducing verifications or
requirements.
f.
Deleting or relocating Hold Points.
g.
Changes to authority or responsibility for review
or approval.
h.
Changes to SSC alignment not previously
evaluated.
3.
SRO Changes to procedures must be approved by two
members of management:
EO 7
a.
Any Supervisor familiar with the work and
knowledgeable of the procedure change process.
b.
Any licensed SRO whose license is active or
inactive. This does not have to be an individual
actually on shift. The role of the SRO here is to
ensure that there is no adverse impact on plant
operation.
4.
SRO Changes must be reviewed by the PRB or
Qualified Reviewer (QR) and approved by the
applicable manager within 14 days of becoming
effective.
V.
10AC-MGR-004-OS, "Deficiency Control System"
A.
Correction of Deficiencies
The normal methods for affecting change to improve
reliability or to correct defects that reduce reliability are the
various administrative controls that have been established to
identify and either correct or improve these conditions. The
administrative processes for correcting defects or causing
improvements are identified as follows:
1.
A Maintenance Work Order (MWO) is used to control
the correction of defects in plant equipment.
2.
A Request for Engineering Review (RER) is used to
initiate and control modifications to plant equipment.
3.
A Procedure Processing Form, or an Instruction
Request/ Development Form is used to control the
development of or revision to Plant Hatch Procedures
and Instructions.
Page 3 of 64
LT-LP-30004-04
ADMINISTRATIVE PROCEDURES
300.041.C
MAINTAIN key control per the guidelines outlined in 80AC-SEC-002-OS, "Key and
Annunciator Door Control."
400.059.A
Given a plant transient and/or accident has occurred, collect and analyze the required data to,
DETERMINE the root cause per 10AC-MGR-012-OS "Plant Event Analysis and Resolution
Program."
ENABLING OBJECTIVES
1.
Given procedure OOAC-REG-001-OS, IDENTIFY the events that require a report to be made to the
NRC within one hour. (SRO ONLY) (300.004.b.01)
2.
Given procedure OOAC-REG-00l-OS, IDENTIFY the reporting requirements to the NRC on the
actuation and injection of an Emergency Core Cooling System. (SRO ONLY) (300.004.b.03)
3.
Given procedure OOAC-REG-001 -OS, IDENTIFY those events that require a report to be made to the
NRC within four hours. (SRO ONLY) (300.004.b.02)
4.
LIST the personnel having the authority to order a startup or shutdown of the Reactor for planned
maintenance or refueling per 10AC-MGR-001-0S. (300.032.a.02)
5.
STATE who has the authority to shutdown the Reactor in an emergency condition per 1OAC-MGR
001-OS. (300.032.a.03)
6.
Given the applicable procedure, IDENTIFY the conditions in which a SRO change to a procedure is
allowed to be made. (SRO ONLY) (300.002.a.02)
7.
Given the applicable administrative procedure, IDENTIFY the approval requirements for an SRO
change to a procedure. (SRO ONLY) (300.002.a.03)
8.
Given a scenario, STATE whether the conditions given require the initiation of a Deficiency Card.
(300.023.a.01)
9.
Given a list of statements, SELECT the statement which best describes the purpose of analyzing
unusual plant events per 10AC-MGR-012-0S, "Plant Event Analysis and Resolution Program."
(400.059.a.01)
10.
Given a list of evolutions, SELECT the evolution that satisfies the procedure requirements for
independent verification. (300.016.a.02)
(2
11.
Given plant\\system status and a copy of 30AC-OPS-001-0S, DETERMINE if an equipment
clearance is being processed correctly. (300.016.a.01)
QUESTIONS REPORT
for Revision2 HT2002
39. G2.3.3 001
Unit 1 is at 75% RTP. At 1400 on 8/12/02, after performing scram time testing, the
Control Board Operator notes that the Offgas Flow has increased from the steady state
level as follows:
Offgas Inlet Flow to Stack prior to scram time testing
100 scfm
Offgas Inlet Flow to Stack after scram time testing
175 scfm
Which ONE of the following actions is/are required by Tech Specs for this condition?
(Provide copy of TS Section 3.7.6 along with SR's)
A. Notify Chemistry to sample the offgas system by 1900 to verify gross gamma
activity is < 240 mCi/second. If greater than 240 mCi/second then isolate SJAE
within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OR BE in Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
B! Notify Chemistry to sample the offgas system by 1800 to verify gross gamma
activity is < 240 mCi/second. If greater than 240 mCi/second then enter 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />
LCO to restore within limits.
C. Notify Chemistry to sample the offgas system by 0200 on 8/13/02 to verify gross
gamma activity is < 240 mCi/second. If greater than 240 mCi/second then enter 72
hour LCO to restore within limits.
ID. Notify Chemistry to sample the offgas system by 0400 on 8/13/02 to verify gross
gamma activity is < 240 mCi/second. If greater than 240 mCi/second then enter 24
hour LCO to restore within limits.
References: Tech Spec section 3.7.6 (SR 3.7.6.1)
LT-LP-03101 Rev. 3 pg 29 of 44
A. Incorrect since the sample time does not allow for 25% grace period and if exceed
the LCO limit then have 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore.
B. Correct answer.
C. Incorrect since the sample time is based on 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> instead of the required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
D. Incorrect since the sample time is based on 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> plus 25% instead of the
required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Also, if exceed the LCO limit then have 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore.
RO Tier:
SRO Tier:
T3
Keyword:
OFF-GAS
Cog Level:
C/A 1.8/2.9
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
-
k
A
ýý
ý023:2
AM44
Friday,
e~ptllU
I
m
U
e
-r U-
I
- /O*-
~¥
QUESTIONS REPORT
for HT2002
119. G2.3.3 001
Unit 1 is at 75% RTP. At 1400 on 8/12/02, after performing scram time testing, the
Control Board Operator notes that the Offgas Flow has increased from the steady state
level as follows:
Offgas Inlet Flow to Stack prior to scram time testing
100 scfm
Offgas Inlet Flow to Stack after scram time testing
175 scfm
Which ONE of the following actions is/are required by Tech Specs for this condition?
A. Notify Chemistry to sample the offgas system by 1800 at the latest to verify gross
gamma activity is < 240 mCi/second. If greater than 240 mCi/second then enter 24
hour LCO to restore within limits.
B! Notify Chemistry to sample the offgas system by 1900 at the latest to verify gross
gamma activity is < 240 mCi/second. If greater than 240 mCi/second then enter 72
hour LCO to restore within limits.
C. Notify Chemistry to sample the offgas system by 0200 on 8/13/02 at the latest to
verify gross gamma activity is < 240 mCi/second. If greater than 240 mCi/second
then enter 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> LCO to restore within limits.
D . Notify Chemistry to sample the offgas system by 0400 on 8/13/02 at the latest to
verify gross gamma activity is < 240 mCi/second. If greater than 240 mCi/second
then enter 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> LCO to restore within limits.
References: Tech Spec section 3.7.6 (SR 3.7.6.1)
LT-LP-03101 Rev. 3 pg 29 of 44
A. Incorrect since the sample time does not allow for 25% grace period and if exceed
the LCO limit then have 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore.
B. Correct answer.
C. Incorrect since the sample time is based on 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> instead of the required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
D. Incorrect since the sample time is based on 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> plus 25% instead of the
required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Also, if exceed the LCO limit then have 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore.
RO Tier:
SRO Tier:
T3
Keyword:
OFF-GAS
Cog Level: C/A 1.8/2.9
Source:
N
Exam:
HT02301
>
Test:
S
Misc:
TCK
,
n.
A
Ann
O
A.O*7t
AnA
129
IVloually, Julle
Z,r'pfU
,r..It.JI/*
QUESTIONS REPORT
for HT2002
1. G2.3.3 001
/
Unit 1 is at 75% RTP. At 1400 on 8/12/02, after performing scram time testing, the
Control Board Operator notes that the Offgas Flow has increased from the steady state
level as follows:
Offgas Inlet Flow to Stack prior to scram time testing
100 scfm
Offgas Inlet Flow to Stack after scram time testing
175 scfm
SELECT the action(s) that is/are required by Tech Specs for this condition.
A. Notify Chemistry to sample the offgas system by 1800 at the latest to verify gross
gamma activity is < 240 mCi/second. If greater than 240 mCi/second then enter 24
hour LCO to restore within limits.
B/ Notify Chemistry to sample the offgas system by 1900 at the latest to verify gross
gamma activity is < 240 mCi/second. If greater than 240 mCi/second then enter 72
hour LCO to restore within limits.
C. Notify Chemistry to sample the offgas system by 0200 on 8/13/02 at the latest to
verify gross gamma activity is < 240 mCi/second. If greater than 240 mCi/second
then enter 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> LCO to restore within limits.
D. Notify Chemistry to sample the offgas system by 0400 on 8/13/02 at the latest to
verify gross gamma activity is < 240 mCi/second. If greater than 240 mCi/second
then enter 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> LCO to restore within limits.
References: Tech Spec section 3.7.6 (SR 3.7.6.1)
LT-LP-03101 Rev. 3 pg 29 of 44
A. Incorrect since the sample time does not allow for 25% grace period and if exceed
the LCO limit then have 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore.
B. Correct answer.
C. Incorrect since the sample time is based on 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> instead of the required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />.
D. Incorrect since the sample time is based on 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> plus 25% instead of the
required 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Also, if exceed the LCO limit then have 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore.
Friday, May 03, 2002 03:16:34 PM
Main Condenser Offgas
3.7.6
SURVEILLANCE REQUIREMENTS
SURVEILLANCE
NOTE -----------------------------
Not required to be performed until 31 days after
any main steam line not isolated and SJAE in
operation.
Verify the gross gamma activity rate of the noble
gases is s 240 mCi/second.
FREQUENCY
31 days
AND
Once within
4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> after a
t 50% increase in
the nominal steady
state fission gas
release after
factoring out
increases due to
changes in
THERMAL
POWER level
Amendment No. 195
HATCH UNIT 1
3.7-17
Main Condenser Offgas
3.7.6
3.7 PLANT SYSTEMS
3.7.6
Main Condenser Offgas
APPLICABILITY:
The gross gamma activity rate of the noble gases measured at the main
condenser evacuation system pretreatment monitor station shall be
< 240 mCi/second.
MODE 1,
MODES 2 and 3 with any main steam line not isolated and steam jet air
ejector (SJAE) in operation.
ACTIONS
CONDITION
REQUIRED ACTION
COMPLETION TIME
A.
Gross gamma activity rate
A.1
Restore gross gamma
72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />
of the noble gases not
activity rate of the noble
within limit,
gases to within limit.
B.
Required Action and
B.1
Isolate all main steam
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
associated Completion
lines.
Time not met.
B.2
Isolate SJAE.
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
B.3.1
Be in MODE 3.
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
AND
B.3.2
Be in MODE 4.
36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />
C
Amendment No. 195
C
C
3.7-16
HATCH UNIT 1
Page 29 of 44
LT-LP-03101-03
OFF GAS SYSTEM
,'
I
LT-03101 Table 1
N62-P600 METER AND RECORDER INDICATIONS
METERS
Glycol Pump Disch
O/G To Preheater
Recomb Inlet A
Recomb Inlet B
BOO 1A Temp (Preheater Inlet)
BOO1 B Temp (Preheater Inlet)
Prefilter Diff Press
Adsorber Train Inlet/Outlet Press
After Fltr Diff Press
0-50 psi
0-15 psi
0-600°F
0-600°F
O-4000F
0-4000 F
0-12"H20
0-3.5 psid
0-12" H20
RECORDERS
Inlet Temp (Reheater)
Outlet Dewpoint
Storage Tk Temp (Glycol)
Inlet Flow To Stack RED
BLK
- High
- Low
Adsorber Vault Temp
H2 Analyzers
RED - A
GRN - B(BLK on Ul)
Recombiner Temperatures (Multipoint)
Adsorber Vessel Temperatures (Multipoint)
O-lOO0F
0-1OO°F
0-100°F
3-256 SCFM
3-24 SCFM
O-100°F
0-5%
0-5%
O-1000°F
O-150°F
I 1N .
I
I
R605
R600
R601A
R601B
R607A
R607B
R611
R612
R616
4
R608
R609
R606
R604
R615
R603
R602
R613
4
QUESTIONS REPORT
for HT2002
120. G2.3.4 001
The Emergency Director decides that is is necessary to send someone into the
Reactor Building (with Health Physics) to isolate a leak before the Core Spray and
RHR pumps are flooded. (No releases are underway and RPV level is being
maintained at 60 inches with the Condensate System)
Which ONE of the following is the maximum allowable dose limit that the Emergency
Director may authorize?
A. 5 REM
Bf 10 REM
C. 25 REM
D. > 25 REM
References: 73EP-EIP-017-OS Rev 2.1 pg 6 of 13.
SRO exam 95-01 question # 94.
B. Correct answer.
K'-
A,C and
RO Tier:
Keyword:
Source:
Test:
D. Incorrect. See reference above on page
SRO Tier:
DOSE RATE LIMITS
Cog Level:
B
Exam:
S
Mise:
6.
T3
MEM 2.5/3.1
HT02301
TCK
Monday, June 24, 2002 08:17:01 AM
130
QUESTIONS REPORT
for HT2002
2. 02.3.4 001
The Emergency Director decides that is is necessary to send someone into the
Reactor Building (with Health Physics) to isolate a leak before Core Spray and RHR
pumps are flooded. (No releases are underway and RPV level is being maintained at
60 inches with the Condensate System)
SELECT the
authorize:
maximum allowable dose limit that the Emergency Director may
A. 5 REM
Bf 10 REM
C. 25 REM
D. > 25 REM
References: 73EP-EIP-017-0S Rev 2.1 pg 6 of 13.
SRO exam 95-01 question # 94.
B. Correct answer.
A,C and D. Incorrect. See reference above on page 6.
Thursday, May 02, 2002 04:51:44 PM
2
GEORGIA POWER COMPANY
PLANT E.I.
HATCH
DOCUMENT TITLE:
EMERGENCY EXPOSURE CONTROL
DOCUMENT NUMBER:
PAGE
6
OF 13
REVISIUN
P1(9:
2 ED 1
7.4
EMERGENCY EXPOSURE GUIDELINES
7.4.1
The Emergency Director will establish the exposure limits for the
emergency response personnel based on the following Emergency Response
Personnel Exposure Guides:
NOTE
These guidelines do not establish a rigid upper
limit of exposure.
The Emergency Director may use
his/her judgment in establishing the appropriate
limit.
NOTE
No thyroid limit is
specified for lifesaving action
since the complete loss of the thyroid may be
considered an acceptable risk
for saving a life;
however, thyroid exposure must be minimized through
the use of respiratory protection and/or KI
tablets.
E
EMERGENCY RESPONSE PERSONNEL EXPOSURE GUIDES
This limit is expressed as the sum of the effective dose equivalent
(EDE)
committed effective dose equivalent (CEDE)
and the
4
MGR-0001 Rev.
1
6
Dose Limit*
Activity
Condition
(REM)
5
all
n/a
protecting valuable
10
25
life saving or protection
lower dose not practicable
of large populations
>25
life saving or protection
only on a voluntary basis to
of large populations
persons fully aware of the
risks involved
i
.
.
...
i
lower dose not practicable
94.
KA#
Generic 2.3.4
OBJ# LT-30008.002
REF LT-LP-30008
COGNITIVE LVL 1
95.
An Alert Emergency has been declared and the OSC has been manned. A fire in the Service
Building breakroom kitchen requires that the OSC be evacuated due to excessive smoke. When
the evacuation is ordered, the OSC workers should go to the:
a.
East Wing of the Simulator Building
b.
Classroom 172 in the Simulator Building
C.
Simulator Building Cafeteria
d.
Technical Support Center conference room.
ANS:
c
a incorrect, normal for EOF
b incorrect, OSC supervision goes here
d incorrect, TSC is not an alternate
NEW
KA# Generic 2.4.42
OBJ# 200.052.h.01
REF EP-LP-30200
COGNITIVE LVL 1
54
The Emergency Director decides that it is necessary to send someone into the Reactor Building
(with Health Physics) to isolate a leak before Core Spray and RHR pumps are flooded. (No
releases are underway and RPV level is being maintained at 60 inches with the Condensate
System)
SELECT the maximum allowable dose limit that the Emergency Director may authorize:
a.
5 REM
b.
10 REM
C.
25 REM
d.
> 25 REM
ANS:
b
a,c,d incorrect, see 73EP-EIP-017-OS pg 6 of 13
NEW
QUESTIONS REPORT
for Revision2 HT2002
40. G2.4.48 001
Unit 1 is in an ATWS condition with Reactor Power oscillating between 15 and 45%
RTP. The following indications exist at this time:
SBLC Pump Select Switch in Start Sys A position.
SBLC Squib Vlv Ready lights are LIT.
Rx Water Cleanup VIv, 2G31-F004,Rx Wtr Cleanup Suction Vlv, is CLOSED.
SBLC Discharge Pressure is greater than reactor pressure.
Which ONE of the following describes the appropriate actions the Shift Supervisor
should order?
A. Inhibit ADS and bypass RWCU filter/demineralizers per 34SO-G31-003-1S.
B. Continue to monitor SBLC and secure when the Cold Shutdown Boron Weight has
been added.
C. Inhibit ADS, continue to monitor SBLC, and exit RC/Q when the reactor is
subcritical.
D' Initiate SBLC per 34SO-C41-003-1S using the manual-local initiation method.
References: RCA RPV CONTROL (ATWS) Rev. 6
LR-20328 Rev. 6 pg 44-45 of 58.
A. Incorrect since 2G31-F004 is closed.
B. Incorrect since boron is not injecting.
C. Incorrect since boron is not being injected and RC/A exit requires subcritical with no
boron injection.
D. Correct answer.
RO Tier:
SRO Tier:
T3
Keyword:
EOP PC CONTROL
Cog Level: C/A 3.5/3.8
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
Friday, September 20, 2002 09:23:24 AM
45
QUESTIONS REPORT
for HT2002
125. G2.4.48 001
Unit I is in an ATWS condition with Reactor Power oscillating between 15 and 35%
RTP. The following indications exist at this time:
SBLC Pump Select Switch in Start Sys A position.
SBLC Squib VIv Ready lights are LIT.
SBLC LOSS OF CONTINUITY TO SQUIB VALVE is ALARMED.
Rx Water Cleanup VIv, 2G31-F004,Rx Wtr Cleanup Suction VIv, is CLOSED.
SBLC Discharge Pressure is greater than reactor pressure.
Which ONE of the following describes the appropriate actions the Shift Supervisor
should order?
A. Inhibit ADS and bypass RWCU filter/demineralizers per 34SO-G31-003-1S.
B. Continue to monitor SBLC and secure when the Cold Shutdown Boron Weight has
been added.
C. Inhibit ADS and inject boron using HPCI, RCIC or CRD to shutdown the reactor.
Df Reset ARI and continue to insert control rods per 31 EO-EOP-103-1S to shutdown
the reactor.
References: RCA RPV CONTROL (ATWS) Rev. 6
LR-20328 Rev. 6 pg 44-45 of 58.
A. Incorrect since reactor power oscillations are less than 25% and these actions are
not yet directed by the ATWS procedure. Also, you don't isolate the RWCU demins
unless there is a failure to isolate the system.
B. Incorrect since the squib valves did not fire and boron is not going into the reactor.
C. Incorrect since reactor power oscillations are less than 25% and these actions are
not yet directed by the ATWS procedure.
D. Correct answer.
RO Tier:
SRO Tier:
T3
Keyword:
EOP PC CONTROL
Cog Level:
C/A 3.5/3.8
Source:
N
Exam:
HT02301
Test:
S
Misc:
TCK
.
.
...
...........
.
135
Monday, June 24, 2uu0 08: I1
A
Mvi
QUESTIONS REPORT
for HT2002
1. G2.4.48 001
Unit 1 is in an ATWS condition with Reactor Power oscillating between 15 and 35%
RTP. The following indications exist at this time:
SBLC Pump Select Switch in Start Sys A position.
SBLC Squib VIv Ready lights are LIT.
SBLC LOSS OF CONTINUITY TO SQUIB VALVE is ALARMED.
Rx Water Cleanup VIv, 2G31-F004,Rx Wtr Cleanup Suction VIv, is CLOSED.
SBLC Discharge Pressure is greater than reactor pressure.
Which ONE of the following describes the appropriate actions the Shift Supervisor
should order?
A. Inhibit ADS and bypass RWCU filter/demineralizers per 34SO-G31-003-1 S.
B. Continue to monitor SBLC and secure when the Cold Shutdown Boron Weight has
been added.
C. Inhibit ADS and inject boron using HPCI, RCIC or CRD to shutdown the reactor.
D. Reset ARI and continue to insert control rods per 31 EO-EOP-103-1S to shutdown
the reactor.
References: RCA RPV CONTROL (ATWS) Rev. 6
LR-20328 Rev. 6 pg 44-45 of 58.
A. Incorrect since reactor power oscillations are less than 25% and these actions are
not yet directed by the ATWS procedure. Also, you don't isolate the RWCU demins
unless there is a failure to isolate the system.
B. Incorrect since the squib valves did not fire and boron is not going into the reactor.
C. Incorrect since reactor power oscillations are less than 25% and these actions are
not yet directed by the ATWS procedure.
D. Correct answer.
Friday, May 31, 2002 03:35:56 PM
I
Page 45 of 58
LR-LP-20328-06
Define Large
Threshold.
Oscillation
if > 25% (above LOT) Boron
injection is required.
Boron injected ONLY if
oscillation persist.
P if cannot maintain below HCTL,
depressurization is required.
5. Higher clad temperatures increase the surface heat flux,
generating steam and a pressure increase in the channel.
6. Moderator is discharged from both the top and bottom of the
bundle with void generation rapidly decreasing power.
7. Inlet flow is restored by the lower plenum pressure/flow
boundary conditions, and the process begins again.
To provide reasonable assurance that any rapidly growing oscillations
are mitigated in a timely manner, boron is injected when neutron flux
oscillations in excess of the Large Oscillation Threshold (LOT)
commence and continue. The LOT is a peak-to-peak neutron flux
oscillation amplitude equal to or less than 25% yet sufficiently large to
be distinguishable from the flux perturbations expected of a stable
thermal-hydraulic system. Flux oscillations at or below the LOT during
a failure-to-scam event are not expected to threaten fuel clad integrity.
Initiation of boron iniection is required for oscillations in excess of the
LOT only if they "commence and continue." This wording clarifies
that boron need not be injected in response to a single flux pulse which
subsequently subsides.
For conditions susceptible to oscillations, the oscillation growth is
directly related to core inlet subcooling. Since the length of time
required to raise in-core boron concentration is longer than the time
required to reduce core inlet subcooling, boron injection alone may not
prevent large irregular neutron flux oscillations from occurring.
However, the magnitude of the oscillations is reduced as the
concentration of boron in the core increases.
If Torus temperature and RPV pressure cannot be maintained below the
Heat Capacity Temperature Limit, rapid depressurization of the RPV
will be required.
BEFORE
Torus water temperature reaches
BUT curve limit
(graph 5)
I-
Efforts to insert rods and inject
boron occur simultaneously.
The initiation and growth of these
oscillations is principally
dependent upon the subcooling at
the core inlet.
Concurrent execution of boron initiation and control rod insertion is
needed to optimize efforts to achieve reactor shutdown.
The symptomatic approach to emergency response precludes
assignment of priorities to these actions since the time at which boron
must be injected into the RPV is dependent on the magnitude of the
failure to scram event.
Instabilities are manifested by oscillations in reactor power which, if
the reactor cannot be shutdown, may increase in magnitude. If the
oscillations remain small or moderately sized, they tend to repeat on
approximately a two second period. Under certain circumstances,
however, the oscillations may continue to grow and become
sufficiently large and irregular to cause localized fuel damage. The
initiation and growth of these oscillations is principally dependent upon
the subcooling at the core inlet, the greater the subcooling, the more
likely that oscillations will commence and increase in magnitude.
Although unlikely, it is possible for such oscillations to develop before
corrective actions can be taken. The process by which large irregular
neutron flux oscillations can develop within a fuel bundle assembly
occurs as follows:
1. Subcooled water enters the fuel bundle.
2. The resulting positive reactivity addition causes a rapid increase
in bundle power.
3. The increased energy deposition in the fuel increases the fuel
and clad temperature.
4. Doppler (fuel temperature) feedback terminates the power
increase.
WAIT UNTIL
Reactor power oscillations
exceed 25% peak to peak
IG THE FOLLOWING
THEN tominate boron injection
perform RPV Control (Non-ATWS)
GO TOR R
point A
OW
N*
LY
0@
ctions:
,er34AB-C71-001IS
V DIESEL GENERATO
-CP
TE_
ad =-
'.-g
/
Goto 34AB-C71-001-1S
I-
r
I
WHILE PERFORMING THE FOLLOWING
.LE reactor is shutdown (subcrifical with
THEN perform scram procedure
IRMs below range 6)
NO boron has been Injected into RPV
I
Confirm reactor mode
switch In SHUTDOWN
I
Confirm ARI initiation
'I
AN>
Confirm reciro flow runback
to minimum
IF reactor power is above 5%
OdR
CANNOT be determined
THEN trip reciro pumps
InhibitADS
Evaluate override on CP-3 Chart
at coordinate C-2
WHILE PERFORMING THE FOLLOWING
IF SBLCtankleveldropsto8%
THEN tip the SBLC pumps
JE RWCU is NOT isolated
TIEN bypass RWCU filterdomlnerolizers
per 34S0-G31-003-1S
CodShutdown Boo
eight
(Table 3) has beeWniJectdI
IF
boron CANNOT be injected with SBLC
THEN Inject boron using one ormore of the
following per 31 EO-EOP-109-1 S:
"o CRD
"O
0 RCIC
'ý7