ML022330024
ML022330024 | |
Person / Time | |
---|---|
Site: | Braidwood |
Issue date: | 08/13/2002 |
From: | Vonsuskil J Exelon Generation Co, Exelon Nuclear |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
BW020088 | |
Download: ML022330024 (25) | |
Text
Exelon.
Exelon Generation Company, LLC www.exeloncorp.com Nuclear Braidwood Station 35100 South Rt 53, Suite 84 Braceville, IL 60407-9619 Tel. 815-417-2000 August 13, 2002 BW020088 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and 50-457
Subject:
Supplemental Startup Report for Braidwood Station, Unit 2 - Full Power Uprate Power Ascension
Reference:
Letter from James D. von Suskil (Exelon Generation Company, LLC) to U.S.
NRC, "Startup Report for Braidwood Station, Units 1 and 2 - Mid-Cycle Power Uprate" dated August 15, 2001 In the referenced letter we submitted a mid-cycle startup report in accordance with the requirements of the Braidwood Station, Technical Requirements Manual, Section 5.0, "Administrative Controls," Section 5.3.a, "Startup Report." Section 5.3.a requires the submittal of a startup report within 90 days following resumption of commercial power operations after an amendment to the license involving a planned increase in power level.
The Unit 2 mid-cycle power ascension started May 24, 2001 and was completed May 28, 2001. Power was raised until Governor Valve #4 indicated Valve Wide Open (VWO). This interim mid-cycle uprated power level was approximately 3436 megawatts thermal (MWt).
The remainder of the Full Power Uprate power ascension to 3586.6 MWt was recently performed following the modifications to the High Pressure (HP) Turbine in the Spring 2002 refueling outage.
The Supplemental Startup Report for Braidwood Station Unit 2 Full Power Uprate Power Ascension (i.e., Attachment 1) summarizes the startup test program and results. The Full Power Uprate Power Ascension Test Program was successfully completed with all acceptance criteria being satisfied.
Also enclosed for information are the Braidwood Unit 2 Cycle 10 Startup and Power Ascension Test Results (i.e., Attachment 2).
August 13, 2002 U.S. Nuclear Regulatory Commission Page 2 If you have any questions or require additional information concerning this report, please contact Ms. Amy Ferko, Regulatory Assurance Manager, at (815) 417-2699.
Respectfully, D. von Suskil
-p)nes Tite Vice President Braidwood Station Attachments: 1. Braidwood Station Unit 2 Full Power Uprate Ascension Supplemental Startup Report
- 2. Braidwood Unit 2 Cycle 10 Startup and Power Ascension Test Results cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Braidwood Station
ATTACHMENT I BRAIDWOOD STATION UNIT 2 FULL POWER UPRATE ASCENSION SUPPLEMENTAL STARTUP REPORT
Braidwood Station Unit 2 Full Power Uprate Ascension Supplemental Startup Report INDEX Section Description Page Executive Summary -ii 1.0 Purpose 1 2.0 Full Power Uprate Power Ascension Program Scope 1 2.1 Program Development 1 2.2 Prerequisites for Full Power Uprate Power Ascension 2 Testing 2.3 Full Power Uprate Power Ascension Testing 2 2.4 Test Acceptance Criteria 3 3.0 Unit 2 - Summary of Testing and Equipment Performance 5 Results 3.1 Unit 2 Power Ascension Chronological Sequence of Events 5 3.2 Unit 2- Control Systems Performance Results 5 3.3 Unit 2 - System and Equipment Performance Results 6 3.4 Unit 2 - Review and Approval of Testing at the Full Power 7 Uprate Plateau 4.0 Application of the UFSAR Initial Startup Test Program to 8 the Braidwood Full Power Uprate Power Ascension Test Program 4.1 General Discussion 8 4.1.1 Preoperational Tests 9 4.1.2 Initial Startup Tests 9 4.1.3 Comparison of UFSAR Startup Tests to Power Ascension 9 Tests 5.0 Electrical Output Tests 10 5.1 Unit 1 11 5.2 Unit 2 12 6.0 Additional Testing 12 7.0 Full Power Capability 12 1-i
Executive Summary In a letter from James D. von Suskil (Exelon Generation Company, LLC) to the U.S.
NRC, "Startup Report for Braidwood Station, Units 1 and 2 - Mid-Cycle Power Uprate,"
dated August 15, 2001, we submitted a mid-cycle startup report in accordance with the requirements of the Braidwood Station, Technical Requirements Manual, Section 5.0, "Administrative Controls," Section 5.3.a. Section 5.3.a requires the submittal of a startup report within 90 days following resumption of commercial power operations after an amendment to the license involving a planned increase in power level.
On May 4, 2001, the NRC issued License Amendment 113 for Braidwood Station, Units 1 and 2, which allowed an increase in the maximum reactor power level from 3411 megawatts thermal (MWt) to 3586.6 MWt. Power ascension on both Braidwood Station units was initiated during mid-cycle operations to an interim level, prior to performing modifications necessary to attain full power uprate.
Unit 2 Power was increased from 3431 MWt to the Full Power Uprate power level of 3586.6 MWt during two separate ramps. The first ramp was completed on May 14, 2002 when the Unit reached 3548 MWt with the Feedwater Flow Calibration Multiplier set at 1.0000. The second ramp was completed on May 15, 2002 when the Unit reached 99.9% calorimetric power with the average Feedwater Flow Calibration Multiplier set at 0.98915. The Full Power Uprate Power Ascension load ramp was successfully completed with all acceptance criteria being satisfied.
1-ii
Braidwood Station, Unit 2 Full Power Uprate Power Ascension Supplemental Startup Report 1.0 Purpose This Supplemental Startup Report is submitted to the NRC to satisfy the reporting requirements of the Braidwood Station's Technical Requirements Manual, Section 5.3.a, "Startup Report," which requires this report to address the following items:
- 1. Address each of the tests identified in the Updated Final Safety Analysis Report.
- 2. Include a description of the measured values of the operating conditions or characteristics obtained during the test program and a comparison of these values with design predictions and specifications.
- 3. Describe corrective actions required to obtain satisfactory operation.
- 4. Include any additional specific details required in license conditions based on other commitments.
2.0 Full Power Uprate Power Ascension Program Scope 2.1 Program Development The development of the power uprate test recommendations and acceptance criteria was based on the review of similar power uprate test programs performed at other nuclear plants, and the generic guidelines provided in WCAP-1 0263, "A Review Plan for Uprating the License Power of a PWR Power Plant," dated 1983.
The full power uprate Power Ascension Test Program verified the following items:
"* Automatic control systems and equipment affected by the Full Power Uprate Power Ascension are maintained within selected operating limits.
"* Chemistry parameters are below the "Action" levels.
"* Steam Generator feedwater flow and water level are satisfactorily maintained in automatic control.
"* The feedwater heater level control system is stable.
"* Selected Area Radiation Surveys have been updated and found acceptable.
"* Condensate / Condensate Booster and Heater Drain pump swaps do not cause any divergent oscillations.
1
2.2 Prerequisites for Full Power Uprate Power Ascension Testing Prior to the commencement of full power uprate power ascension testing, a special test procedure required the completion of numerous activities. These activities included the following items.
" The applicable plant instrumentation setpoint changes or recalibrations were completed as determined by the Power Uprate Master Design Change Package (DCP).
"* Plant modifications required to support operation at the full uprate power level were closed out.
"* The Clearance Order Log and the Operation Configuration Change log were reviewed to assure there was no effect on uprate testing.
"* Baseline data was taken at 3431 MWt.
2.3 Full Power Uprate Power Ascension Testing Full power uprate power ascension was performed in accordance with a Braidwood Station Special Procedure (SPP). A Heightened Level of Awareness (HLA) briefing was completed with operations and other appropriate plant personnel prior to power ascension.
Power was increased from 3431 MWt to the Full Power Uprate power level of 3586.6 MWt during two separate ramps. The first ramp was completed on May 14, 2002 when the Unit reached 3548 MWt with the Feedwater Flow Calibration Multiplier set at 1.0000. The second ramp was completed on May 15, 2002 when the Unit reached 99.9% calorimetric power with the average Feedwater Flow Calibration Multiplier set at 0.98915. Following the power increase, control system and equipment performance data was collected and evaluated in accordance established acceptance criteria. At the 99.9% full power plateau, the following activities were performed:
"* Reactor fuels parameters were evaluated.
"* Automatic control systems were evaluated.
" Chemistry evaluations were conducted.
" Feedwater and main steam parameters for turbine driven main feedwater pump speed, feedwater control valve position, feedwater pump, condensate pump and condensate booster pump suction pressure net positive suction head (NPSH) requirements, and steam generator water level control were evaluated.
"* Feedwater heater level control performance data were evaluated.
2
"* Main generator stator internal temperature data were collected and evaluated.
"* Radiation surveys were performed and evaluated at key points in the power ascension sequence.
"* Secondary plant and turbine/generator system performance were evaluated.
"* Condensate / Condensate Booster system performance was evaluated.
"* A selected set of equipment performance data (e.g., plant process computer points, control room readings, and local readings) was collected and evaluated.
2.4 Test Acceptance Criteria General Discussion The development of the power uprate test recommendations and acceptance criteria was based on the review of similar power uprate test programs performed at other plants and the power uprate master DCP.
Following the load increase in power level to 99.9% calorimetric power, test data recorded during the power ascension were evaluated and compared to performance acceptance criteria (i.e., design predictions or limits). Ifthe test data satisfied the acceptance criteria, then system and component performance were determined to comply with their design requirements.
Plant parameters during full power uprate power ascension were evaluated using two levels of acceptance criteria. The criteria associated with plant safety were classified as Level 1. The criteria associated with design expectations were classified as Level 2. The following paragraphs describe the actions required to be taken if an individual criterion was not satisfied.
Level 1 Acceptance Criteria Level 1 acceptance criteria normally relate to the values of process variables for components and systems determined during the design of the plant. If a level 1 test criterion is not satisfied, the plant must be placed in a safe "hold" condition.
Plant operating or test procedures or the Technical Specifications may guide the decision on the appropriate actions to be taken. Resolution of the problem must be immediately pursued by equipment adjustments or through engineering evaluation, as appropriate. Following resolution, the applicable test steps must be repeated to verify that the Level 1 acceptance criterion is satisfied. A description of the problem must be included in the test report documenting successful completion of the test.
For the Braidwood Station full power uprate power ascension, the following specific Level 1 acceptance criteria were established:
3
"* The chemical and volume control system can maintain RCS volume and a steady RCS boron concentration during steady state power level and routine power changes without excessive operator intervention.
"* Steam generator feedwater flow and steam generator water level are satisfactorily maintained in automatic control.
"* The turbine driven main feedwater pump speed during steady state conditions does not exceed 5500 RPM.
All the above Level 1 criteria were met for Unit 2 following the full power uprate power ascension.
Level 2 Acceptance Criteria If a Level 2 acceptance criteria limit is not satisfied, then startup testing may proceed after an investigation by testing, engineering, and operations personnel.
The limits stated in this category are usually associated with expectations of system performance whose characteristics can be improved by equipment adjustments.
For the Braidwood full power uprate power ascension, the following specific Level 2 acceptance criteria were established.
System and Equipment Performance
- System and Equipment Level 2 acceptance limits are identified in various attachments of the appropriate SPP. Any limits that were exceeded required a documented evaluation in the SPP Test Report.
Turbine Generator Temperature Monitoring System (TGTMS)
"* TGTMS Data are within Acceptance Limits.
"* Turbine Supervisory Vibration Data are within Acceptance Limits.
"* Turbine End Turn Vibration Limits are within guidelines.
Plant Instrumentation
"* RCS delta temperature power and calorimetric power are within plus or minus 2% of the plant process computer (PPC) indication.
"* Nuclear Instrumentation and calorimetric power are within plus or minus 2%.
"* RCS pressure remains stable with no unexpected operation of backup heaters during steady state power levels.
"* RCS flow between pre-uprate PPC points and post- uprate PPC points are within plus or minus 2%.
4
" Steam Flow / Feed Flow Mismatch are less than 2% between pre-uprate PPC points and post-uprate PPC points.
" Pre-heater flow is less than or equal to 3.672 x 106 Ibm/hr for steam generators 2A, 2B, 2C, and 2D.
3.0 Unit 2 - Summary of Testing and Equipment Performance Results 3.1 Unit 2 Power Ascension Chronological Sequence of Events No. Event Description Date @ Time 1 Completed Heighten Level of Awareness (HLA) Brief 5/13/02 @ 1100 2 Obtained Baseline Data at the 3431 MWt Plateau 5/14/02 @ 0630 3 Commenced first ramp to 3548 MWt 5/14/02 @ 0847 4 Secured ramp at 3548 MWt 5/14/02 @ 1300 5 Completed data collection in accordance with SPP at 3548 MWt 5/14/02 @ 1530 6 Completed Pre Job Brief for ramp to 100% power with average 5/15/02 @ 0830 Feedwater Flow Calibration Multiplier set at 0.98915 7 Commenced ramp to 3586.6 Mwt 5/15/02 @ 0916 8 Secured ramp at 3586.6 MWt 5/15/02 @ 1056 9 Completed review and signoff of testing for the full power uprate 6/10/02 @ 1100 I power ascension plateau 3.2 Unit 2 - Control Systems Performance Results Control Systems most affected by the full power uprate power ascension were monitored to assure acceptable performance and compliance with their specific Level 1 and 2 acceptance criteria. The following table summarizes these control systems.
5
Level 1 Level 2 Tuning No. Control System Description Acceptance Acceptance Adjustments Criteria Criteria Required 1 RCS (Pressurizer) Pressure Satisfied Satisfied None 2 Pressurizer Level Control Satisfied Satisfied None 3 Rod Control Satisfied Satisfied None 4 Steam Generator Level Control Satisfied Satisfied None System 5 Feedwater Pump Speed Control Satisfied Satisfied None 6 Steam Flow / Feed Flow Mismatch Satisfied Satisfied None 7 Feedwater Heater Level Control Satisfied Satisfied None System 8 DEHC Control System Satisfied Satisfied None 3.3 Unit 2 - System and Equipment Performance Results The following systems and selected equipment within the plant most affected by full power uprate power ascension were closely monitored to assure that equipment performed as predicted and that they operated within their design requirements.
Level I Level 2 Equipment No. System Description Operating Operating Performance Limits Limits 1 Condensate System Satisfied Satisfied (4) Acceptable 2 Condenser Satisfied Satisfied Acceptable 3 Condensate Booster System Satisfied Satisfied Acceptable 4 Feedwater System Satisfied Satisfied Acceptable (1)(2)(3) 5 Heater Drain System Satisfied Satisfied (5) Acceptable 6 Reactor Satisfied Satisfied Acceptable 7 Reactor Coolant System Satisfied Satisfied Acceptable 8 Main Steam System Satisfied Satisfied Acceptable 9 Main Turbine Satisfied Satisfied Acceptable 10 Main Transformer Satisfied Satisfied Acceptable 11 Auxiliary Transformers Satisfied Satisfied Acceptable 12 Generator Cooling System Satisfied Satisfied Acceptable 13 Generator Condition Monitoring Satisfied Satisfied Acceptable 14 Main Generator and Exciter Field Satisfied Satisfied Acceptable 15 Isophase Bus Cooling Satisfied Satisfied Acceptable 16 Reheater Systems Satisfied Satisfied Acceptable 6
(1) Feedwater Regulating Valves 2FW530 and 2FW540 were adjusted within limits following a troubleshooting activity after testing at the 100% power plateau was completed. The Test Director along with Engineering and Operations personnel reviewed the final positions of the Feedwater Regulating Valve position and concluded that all valves were within the optimum range of 60% to 85% open at full feedwater flow conditions.
(2) The 2B steam generator Feedwater Nozzle Flow High Alarm toggled in / out during the final ramp to 100% power and was addressed by Power Uprate Project Contingency Plan # 6. Data was taken for Feedwater Pressure, Temperature, Flow Delta Pressure, and Pre-heater bypass flow for the 2FW-520 Feedwater Loop. Surveillance 2BwVP 800-3, "Unit 2 Steam Generator Main Feedwater Nozzle Flow Surveillance," verified that the pre-heater flow was under the alarm setpoint of 3.672 KBH/hr. This surveillance determined the pre-heater flow by calculating the loop feedwater flow using the current Feedwater Flow Calibration Multiplier and making adjustments for loop uncertainties.
(3) The 2A steam generator Feedwater Isolation Valve (FWIV) outlet temperature reading was greater than the level 2 operating limit of 4550 F. The Plant Process Computer Point, T2385, used to obtain the 2A steam generator FWIV outlet temperature status had a high high alarm indicating a bad input condition. Plant Process Computer Point T0408 for "STM GEN 2A Feedwater Inlet Temperature" upstream of T2385 was indicating 440.18 0 F with a good status and was consistent with the other steam generator FWIV outlet temperatures. Work Request 51157 was written to correct the bad input condition for Plant Process Computer Point T2385.
(4) Local Pressure Indicator 2PI-CDO1 1 for Condensate Pump 2A Discharge Pressure was indicating - 30 psig above the other Condensate Pump Discharge Pressure indicators which read - 132 psig. This implied that Local Pressure Indicator 2PI-CD01 1 was out of tolerance. Work Request WR 448413 was active and the Pressure Indicator has been corrected.
(5) The 2C Flash Tank Emergency Drain Valves was positioned at 50% open by operations to maintain level in the flash tank while maintenance activities were performed to return the flash tank back to normal level control. This abnormal lineup had a minimal impact on thermal megawatts as both return flow paths return to the Condenser Hotwell. The normal lineup was restored prior to the Unit 2 Post Megawatt Electrical Verification Test.
3.4 Unit 2 - Review and Approval of Testing at the Full Power Uprate Plateau
- 1. Reactor Fuel Parameters: Fuel thermal margins were found acceptable for continued operation at the full power uprate power ascension plateau as demonstrated by power ascension testing performed in accordance with surveillance procedure BwVS TRM 3.1.h.1 following reload.
- 2. Automatic Control Systems: All automatic control systems were acceptable for continued operation at the full power uprate power ascension plateau.
7
- 3. Chemistry Approval: RCS, Condensate and Feedwater chemistry did not reach Chemistry Action Levels.
- 4. Feedwater and Main Steam Parameters: The turbine driven main feedwater pump speed, feedwater control valve position, and steam generator water level met Level 2 acceptance criteria. Feedwater pump, condensate pump and condensate booster pump suction pressures exceeded NPSH requirements. Feedwater Heater Level Control performance data was taken and evaluated to be acceptable.
- 5. Main Generator Parameters: Generator stator temperatures and bus bar temperatures satisfied their Level 2 acceptance limits. Generator conditions were also satisfactory for continued operation at the full power uprate plateau.
- 6. Radiation Protection Approval: Surveys were performed and all radiological conditions were found acceptable for operation at the full power uprate plateau.
- 7. Secondary Plant And Turbine/Generator Systems Approval: System and Equipment data obtained by System Engineering were reviewed and performance found acceptable at the full power uprate plateau.
- 8. Condensate (CD) / Condensate Booster (CB) System Approval: CD Pump and CB Pump pressures, flows, temperatures, and motor amps were found acceptable. Current computer alarm setpoints and scaling changes made as part of the power uprate were found acceptable.
- 9. Main Control Room Instrumentation: Zone banding was reviewed and the necessary changes were provided to the Procedure Group.
4.0 Application of the UFSAR Initial Startup Test Program to the Braidwood Full Power Ascension Test Program 4.1 General Discussion The development of the power uprate test recommendations and acceptance criteria is based on the review of similar test programs performed at other nuclear plants; Westinghouse Topical Report, WCAP-1 0263, "A Review Plan for Uprating the License Power of a PWR Power Plant," dated 1983; and Section 7, "Output Determination," of the Westinghouse "Revised Proposal for Power Uprate," dated August 23, 1999. WCAP-10263 recommends that a test program be developed on a plant specific basis addressing the significance of hardware modifications and the magnitude of the power uprate. The Braidwood Station hardware upgrades were limited to the replacement of the HP turbine, instrument setpoint scaling changes, and minor equipment modifications that were completed as part of the plant modification process.
The Updated Final Safety Analysis Report (UFSAR) Chapter 14, "Initial Test Program," addresses the Braidwood initial test program. The initial test program 8
included both preoperational and initial startup testing. Each of these programs is discussed in the following paragraphs:
4.1.1 Preoperational Tests Preoperational testing consisted of system performance tests performed prior to core load on completed systems prior to final acceptance. These tests demonstrated the capability of structures, systems and components to meet safety related performance requirements.
This category of tests is now conducted as part of the post modification testing process. The full power uprate modification tests (setpoint and scaling changes) were successfully completed as part of the modification process and work control process.
4.1.2 Initial Startup Tests Initial startup testing consisted of those single and multi-system tests that occurred during or after fuel loading and which demonstrated overall plant performance. This included such activities as precritical tests, low-power tests (i.e., including criticality tests), and power ascension tests. This testing confirmed the design bases and demonstrated, where possible, that the plant is capable of withstanding the anticipated transients and postulated accidents.
This category of tests was reviewed for applicability in developing the Braidwood Station Full Power Uprate Test Program.
4.1.3 Comparison of UFSAR Startup Tests to Power Ascension Tests The following table addresses each of the initial power ascension tests and their applicability to the Braidwood Station Full Power Uprate Power Ascension Test Program. Tests identified with a 'Yes' were incorporated into the Braidwood Station Full Power Uprate Power Ascension Test Program.
9
Required in Full Acceptance Test No. Startup Test Title Power Uprate Criteria Same as (1) Test Procedure UFSAR 14.2-62 Initial Core Load No NA 14.2-63 Control Rod Drives No NA 14.2-64 Rod Position Indicators No NA 14.2-65 Reactor Trip Circuit No NA 14.2-66 Rod Drop Measurements No NA 14.2-67 Incore Flux Monitor System No NA 14.2-68 Nuclear Instrumentation No NA 14.2-69 Reactor Coolant System Pressure No NA 14.2-70 Reactor Coolant System Flow No NA 14.2-71 Pressurizer Effectiveness No NA 14.2-72 Water Chemistry Yes (2) Yes 14.2-73 Radiation Surveys Yes (3) Yes 14.2-74 Effluent Radiation Monitors No NA 14.2-75 Initial Criticality No NA 14.2-76 Power Ascension Yes (4) Yes 14.2-77 Moderator Temperature Reactivity Coefficient Measurement No NA 14.2-78 Control Rod Reactivity Worth Measurement No NA 14.2-79 Boron Reactivity Worth Measurement No NA 14.2-80 Flux Distribution Measurement No NA 14.2-81 Pseudo Rod Ejection No NA 14.2-82 Power Reactivity Coefficient Measurement No NA 14.2-83 Core Performance Evaluation No NA 14.2-84 Flux Asymmetry Evaluation No NA 14.2-85 Full-Power Plant Trip No NA 14.2-86 Shutdown from Outside the Control Room No NA 14.2-87 Loss of Offsite Power No NA 14.2-88 10% Load Swing No NA 14.2-89 50% Load Reduction No NA 14.2-90 RTD Cross-Calibration No NA 14.2-91 Turbine Trip from 25% Power No NA Notes: (1) UFSAR Chapter 14 table numbers.
(2) Water Chemistry at uprate power in accordance with Chemistry Action Levels.
(3) Radiation Surveys done in certain specified areas.
(4) Special Test Procedure at full uprate power was implemented.
5.0 ELECTRICAL OUTPUT TESTS The objective of the Braidwood Station Power Uprate initiative was to optimize electrical power production by implementing an approximate 5% increase in reactor power. In conjunction with the reactor power uprate, turbine hardware changes were made to increase each unit's turbine-generator output. Four 10
electrical output tests were performed to collect plant data to calculate the electrical output of each unit. A "Pre-Uprate Electrical Output Test" and a "Post Uprate Electrical Output Test" were conducted on each unit in order to determine the change in electrical output of each unit's turbine generator. Testing was performed in accordance with BwVP 850-22, "Braidwood Power Uprate Project Pre and Post Installation Electrical Output Test.
Seasonal variations and plant operating conditions affect electrical power output.
As a result, electrical output may be higher or lower than the value indicated on heat balance drawings. To account for variations in conditions, calculations were performed to normalize electrical output consistent with the conditions noted on the baseline heat rate drawings. These calculations were performed by the turbine vendor and reviewed by Exelon Nuclear.
Test Obiective Collect data for determining the corrected electrical output at the baseline heat rate conditions at pre-uprate and at post-uprate power levels.
Plant Conditions or Prerequisites The reactor and turbine power levels were stable. Operation was near full power with the RCS temperature within 1OF of the programmed reference temperature.
Steam generator blowdown and main condenser hotwell makeup systems were isolated. The main generator reactive load was adjusted between 300 and 350 Mega-Volt-Amps Reactive (MVARS). Test equipment was installed for data collection.
Test Summary The test method was based on the American National Standards Institute (ANSI)
/ American Society of Mechanical Engineers (ASME), "Steam Turbines, Performance Test Code, PTC-6, Alternate Method." The plant configuration was controlled by the test procedure. Each test collected two data sets with the plant at steady state conditions.
ASME Test Criterion The corrected heat rate for the two data sets was within 0.25% satisfying the ASME Test criteria. If the heat rate difference were greater than 0.25%, an additional data collection would have been required.
5.1 Unit I Electrical Output Test Results Using test data, the electrical output was corrected to pre-uprate and post-uprate heat rate conditions. Results are presented in the table below.
11
Pre-Uprate 1
I I
- Post-Uprate I I Corrected Corrected Gain in Electrical Data Set 1
Electrical Output (MWe) 1157.770 Data Set Electrical Output (MWe) 1241.836 Output (MWe) I 2 j 1158.381 2 1241.312 I Avg. 1161.076- Avg. 1241.574 Average includes adjustment for Main Turbine Driven Feedwater Pumps being supplied by Main Steam as opposed to Extraction Steam.
5.2 Unit 2 Electrical Output Test Results Using test data, the electrical output was corrected to pre-uprate and post-uprate heat rate conditions. Results are presented in the table below.
Pre-Uprate Post-Uprate Corrected Corrected Gain in Data Electrical Output Electrical Output Electrical Output (MWe) (MWe) MWe 1 1175.705 1 1213.389 2 1175.563 2 1212.896 Avg. 1178.634- Avg. 1213.142 34.508 Average includes adjustment for Main Turbine Driven Feedwater Pumps being supplied by Main Steam as opposed to Extraction Steam.
6.0 Additional Testing Additional testing including a Moisture Carryover Test for both Unit 1 and Unit 2 will be performed later in the Fall of 2002. The review of results for these tests will be performed and approved in accordance with a special procedure and can be reviewed by the NRC using the normal special test review process.
7.0 Full Power Capability Braidwood Station, Units I and 2 were able to achieve the uprated full license power level of 3586.6 MWt. The results of the startup test program have indicated that the plant can safely operate at the current uprated power levels.
No additional supplemental startup test reports are required for either of the Braidwood Station Units.
12
ATTACHMENT 2 BRAIDWOOD STATION UNIT 2 CYCLE 10 STARTUP AND POWER ASCENSION TEST RESULTS
Braidwood Station Unit 2 Cycle 10 Startup and Power Ascension Test Results INDEX Section Description Page 1.0 Introduction 1 Table 1.1 Braidwood Unit 2 Cycle 10 Core Design Data 1 2.0 Core Testing 2 2.1 Low Power Physics Testing 2 2.2 Power Escalation 2 2.3 Core Power Distribution 2 2.4 Full Power Loop Delta -T Measurements 2 2.5 Reactor Coolant System Flow Measurement 2 Table 2.1 A2R09 Startup Physics Test Results 3 Table 2.2 Core Power Distribution Results - < 50% Power 4 Plant Data 4 Fluxmap Results 4 Table 2.3 Core Power Distribution Results - Full Power 5 Plant Data 5 Fluxmap Results 5 Table 2.4 Full Power Loop Delta - T 6 Table 2.5 RCS Flow vs. Acceptance Criteria 6 2-i
Braidwood Station Unit 2 Cycle 10 Startup and Power Ascension Test Results 1.0 Introduction Braidwood Station conducted a comprehensive test program following reload. The test program outlined in this report summarizes events and testing performed during the first heatup and power ascension to 100%.
The Braidwood Unit 2 Cycle 10 (U2C1 0) core includes a feed batch of 85 fuel assemblies manufactured by Westinghouse. The new fuel region incorporates Integral Fuel Burnable Absorber (IFBA) rods with a B-1 0 loading of 1.6X and a 100 psig backfill pressure. Thirty-two twice burned Unit 2 assemblies were reinserted with refurbished top nozzles. Table 1.1 contains characteristics of the Braidwood Unit 2 Cycle 10 core design.
The Cycle 10 reactor core achieved initial criticality on May 10, 2002 at 1623 hours0.0188 days <br />0.451 hours <br />0.00268 weeks <br />6.175515e-4 months <br />.
The Unit 2 Main Generator was synchronized to the grid on May 12, 2002 at 0602 hours0.00697 days <br />0.167 hours <br />9.953704e-4 weeks <br />2.29061e-4 months <br />.
Power escalation testing, including testing at full power, was completed on May 16, 2002.
Table 1.1 Braidwood Unit 2 Cycle 10 Core Design Data 0 Unit 2 Cycle 9 Burnup: 505 EFPD Unit 2 Cycle 10 design length: 522 EFPD Region Fuel Type Number of Enrichment Cycles Burned Assemblies w/o U-235 8A VANTAGE+ 4 4.605 2 9A VANTAGE+ 8 4.600 2 9B VANTAGE + 4 4.406 2 10B VANTAGE + 16 3.797 2 11A VANTAGE+ 64 4.950 1 11B VANTAGE+ 12 4.750 1 12A VANTAGE + 60 4.950 0 12B VANTAGE + 25 4.600 0 1
2.0 Core Testing 2.1 Low Power Physics Testing Low Power Physics Testing (LPPT) is performed at the beginning of each cycle and a summary of the Startup Physics Test results from U2C10 is contained in Table 2.1. All test results were determined to be acceptable.
2.2 Power Escalation Testing Power Escalation Testing is performed during the initial power ascension to full power for each cycle and is controlled by surveillance procedure BwVS TRM 3.1 .h. 1. Tests are performed from 0% through 100% with major testing plateaus at approximately 30%,
and 100% power. Significant tests included:
- Core Power Distribution measurements.
- Reactor Coolant System Delta-T Measurements.
- Hot Full Power Critical Boron Concentration Measurement.
- Reactor Coolant System Flow Measurements.
2.3 Core Power Distribution Core power distribution measurements were performed during power escalation at intermediate power (i.e., less than 30%) and full power. Measurements are made to verify flux symmetry and to verify core peaking factors are within limits. Data obtained during these tests are used to check calibration of Power Range Nuclear Instrumentation System (NIS) channels and to calibrate them if required. Measurements are made using the Moveable Incore Detector System and analyzed using the BEACON computer code.
Results of the core power distribution measurements at <30%, and full power are shown in Tables 2.2 and 2.3, respectively.
2.4 Full Power Loop Delta-T Determination The purpose of this test is to determine the full power Delta-T for each Reactor Coolant loop in order to recalibrate any loop with significant change. This procedure is applicable in MODE 1 and is performed above 95% Rated Thermal Power (RTP) after each refueling outage. Results are contained in Table 2.4.
2.5 Reactor Coolant System Flow Measurement The purpose of this test is to verify by precision heat balance that RCS total flow rate is
_>380,900 gpm and within the limits specified in the COLR (Ž_380,900). Results are contained in Table 2.5.
2
Table 2.1 A2R09 Startup Physics Test Results Review Acceptance Parameter Predicted Measured Difference Criteria Criteria ARO Critical 1440 ppm 1418 ppm 22 ppm _ 50 ppm _ 1000 pcm Boron ARO ITC -3.978 -5.01 1.032 _ 2 pcm/°F of N/A pcm/°F pcm/°F pcm/0 F design value ARO MTC -2.571 -2.86 0.289 N/A Within Tech pcm/OF pcm/OF pcm/0F Spec 3.1.1.3 Control 379.7 pcm 387.8 pcm 2.1% 8.1 *15% or *100 N/A Bank A pcm pcm of design Worth Control 497.7 pcm 488.1 pcm 1.9% 9.6 *-15% or _100 N/A Bank B pcm pcm of design Worth Control 938.3 pcm 955.4 pcm 1.8% 17.1 *15% or *100 N/A Bank C pcm pcm of design Worth Control 562.8 pcm 587.1 pcm 4.3% 24.3 *<15% or *100 N/A Bank D pcm pcm of design Worth Shutdown 185.7 pcm 180.9 pcm 2.6% 4.8 *15% or *100 N/A Bank A pcm pcm of design Worth Shutdown 892.7 pcm 898.0 pcm 0.6% 5.3 *15% or *100 N/A Bank B pcm pcm of design Worth Shutdown 339.2 pcm 339.5 pcm 0.1% 0.3 *15% or *100 N/A Bank C pcm pcm of design Worth Shutdown 343.1 pcm 340.0 pcm 0.9% 3.1 _!_15% or *<100 N/A Bank D pcm pcm of design Worth Shutdown 484.7 pcm 482.6 pcm 0.4% 2.1 -<15%or _100 N/A Bank E pcm pcm of design Worth Total Rod 4623.9 pcm 4659.4 pcm 0.8% 35.5 -< 5.6% between _ 93% of the Worth pcm measured & sum of the predicted predicted worths 3
Table 2.2 Core Power Distribution Results - <30% Power Plant Data Map ID: BW21001 Date of Map: 5/12/2002 Cycle Bumup: 0.1 EFPD Power Level: 26.6%
Control Bank D Position: 177 steps Fluxmap Results Core Average Axial Offset -0.27%
Quadrant Power Tilt Ratios:
Quadrant (N41): 0.980 Quadrant (N42): 1.008 Quadrant (N43): 0.996 Quadrant (N44): 1.017 Max. Nuclear Enthalpy Rise Hot Channel Factor 1.6434 Nuclear Enthalpy Rise Hot Channel Factor Limit 2.0743 Max. Steady State Heat Flux Channel Factor 2.0211 Steady State Heat Flux Channel Factor Limit 5.2000 Max. Transient Heat Flux Channel Factor 2.0332 Transient Heat Flux Channel Factor Limit 4.5274 4
Table 2.3 Core Power Distribution Results - Full Power Plant Data Map ID: BW21002 Date of Map: 5/16/2002 Cycle Bumup: 3.3 EFPD Power Level: 99.9%
Control Rod Position: 220 steps Fluxmap Results Core Average Axial Offset -9.810%
Quadrant Power Tilt Ratios:
Quadrant (N41): 0.989 Quadrant (N42): 0.999 Quadrant (N43): 1.004 Quadrant (N44): 1.007 Max. Nuclear Enthalpy Rise Hot Channel Factor 1.575 Nuclear Enthalpy Rise Hot Channel Factor Limit 1.7005 Max. Steady State Heat Flux Channel Factor 2.0761 Steady State Heat Flux Channel Factor Limit 2.6026 Max. Transient Heat Flux Channel Factor 2.0062 Transient Heat Flux Channel Factor Limit 2.1904 5
Table 2.4 Full Power Loop Delta-T Loop Tave (IF) Full Power Delta-T (°F)
A 579.9 60.9 B 581.3 61.6 C 581.7 62.7 D 580.6 60.5 Table 2.5 RCS Flow vs. Acceptance Criteria RCS loop Measured Minimum Flow Flow (gpm) Requirement (gpm) 2A 98,705 2B 100,850 2C 97,697 2D 101,359 Total 398,611 >380,900 Above data taken from Appendix B-M of 2BwVSR 3.4.1.4 RCS Flow Measurement 6