FENOC F5501 North State Route 2 FirstEnergyNuclear Operating Company Oak Harbor,Ohio 43449 Barny S. Allen 419-321-7676 Vice President- Nuclear Fax: 419-321-7582 November 10, 2010 L-1 0-326 ATTN: Document Control Desk United States Nuclear Regulatory Commission Washington, D.C. 20555-0001

SUBJECT:

Davis-Besse Nuclear Power Station, Unit 1 Docket Number 50-346, License Number NPF-3 Readiness for 95001 Supplemental Inspection; EA-09-283 On October 29, 2010, the Nuclear Regulatory Commission (NRC) documented the results of a supplemental inspection completed pursuant to NRC Inspection Procedure 95001 at the Davis-Besse Nuclear Power Station (DBNPS). This inspection was conducted because of a White finding previously issued to FirstEnergy Nuclear Operating Company (FENOC) involving the failure to appropriately implement the emergency classification and action level scheme during an event in the switchyard on June 25, 2009, at the DBNPS. This inspe6tion did not close the White finding and required a further inspection to follow completion of the actions to address the identified concerns regarding the extent of cause review and the developed corrective actions.

This letter provides notification that the actions to address the identified concerns have been completed and are ready for NRC follow-up inspection.

There are no regulatory commitments contained in this letter. If there are any questions or if additional information is required, please contact Mr. Patrick J. McCloskey, Site Regulatory Compliance Manager, at (419) 321-7274.

Sincerely, Barry S. Allen JCS cc: Regional Administrator, NRC Region III DB-1 NRC Senior Resident Inspector DB-1 NRC/NRR Project Manager Utility Radiological Safety Board