MONTHYEARJAFP-05-0005, December 2004 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant2005-01-12012 January 2005 December 2004 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant JAFP-04-0186, November 2004 Monthly Operating Report for James A. FitzPatrick2004-12-0707 December 2004 November 2004 Monthly Operating Report for James A. FitzPatrick JAFP-04-0181, October 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-11-10010 November 2004 October 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0166, September 2004 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant2004-10-11011 October 2004 September 2004 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant JAFP-04-0150, August 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-09-14014 September 2004 August 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0122, July 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-08-0606 August 2004 July 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0100, June 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-07-12012 July 2004 June 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0086, May 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-06-14014 June 2004 May 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0066, April 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-05-0707 May 2004 April 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0035, February 2004 Monthly Operating Report for James a FitzPatrick2004-03-10010 March 2004 February 2004 Monthly Operating Report for James a FitzPatrick JAFP-04-0024, January 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-02-12012 February 2004 January 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0004, December 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-01-12012 January 2004 December 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0169, November 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2003-12-0808 December 2003 November 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0154, October 2003 Monthly Operating Report for James a FitzPatrick2003-11-0707 November 2003 October 2003 Monthly Operating Report for James a FitzPatrick JAFP-03-0139, September 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2003-10-14014 October 2003 September 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0130, August 2003 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant2003-09-15015 September 2003 August 2003 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant JAFP-03-0115, July 2003 Monthly Operating Report for James A. FitzPatrick2003-08-12012 August 2003 July 2003 Monthly Operating Report for James A. FitzPatrick JAFP-03-0097, June 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2003-07-0909 July 2003 June 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-03-0083, May 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant2003-06-12012 June 2003 May 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant JAFP-03-0067, April 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant2003-05-15015 May 2003 April 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant JAFP-03-0068, March 2003 Monthly Operating Report for James A. FitzPatrick, Revision 12003-05-14014 May 2003 March 2003 Monthly Operating Report for James A. FitzPatrick, Revision 1 JAFP-03-0050, March 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2003-04-14014 April 2003 March 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-03-0043, February 2003 Monthly Operating Report for James A. FitzPatrick2003-03-17017 March 2003 February 2003 Monthly Operating Report for James A. FitzPatrick JAFP-03-0022, January 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2003-02-14014 February 2003 January 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0004, December 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2003-01-15015 January 2003 December 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-02-0225, October 2002 Monthly Operating Report for FitzPatrick, Rev 12002-12-12012 December 2002 October 2002 Monthly Operating Report for FitzPatrick, Rev 1 JAFP-02-0226, November 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2002-12-12012 December 2002 November 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-02-0211, October 2002 Monthly Operating Report for James A. FitzPatrick2002-11-12012 November 2002 October 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0199, September 2002 Monthly Operating Report for James A. FitzPatrick2002-10-14014 October 2002 September 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0186, August 2002 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant2002-09-13013 September 2002 August 2002 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant JAFP-02-0164, July 2002 Monthly Operating Report for James A. FitzPatrick2002-08-12012 August 2002 July 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0142, June 2002 Monthly Operating Report for James A. FitzPatrick2002-07-15015 July 2002 June 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0126, May 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-06-13013 June 2002 May 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0107, April 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-05-13013 May 2002 April 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0086, March 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-04-15015 April 2002 March 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0064, Revised November 2001 Monthly Operating Report for James A. FitzPatrick2002-03-15015 March 2002 Revised November 2001 Monthly Operating Report for James A. FitzPatrick JAFP-02-0063, February 2002 Monthly Operating Report for FitzPatrick Nuclear Power Plant2002-03-15015 March 2002 February 2002 Monthly Operating Report for FitzPatrick Nuclear Power Plant JAFP-02-0036, January 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-02-14014 February 2002 January 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0008, December 2001 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-01-15015 January 2002 December 2001 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant 2005-01-12
[Table view] |
Text
Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
James A Fitzpatrick NPP PO Box 110
-- ! terngy Lycoming, NY 13093 Tel 315 349 6024 Fax 315 349 6480 T.A. Sullivan Vice President, Operations-JAF January 15, 2003 JAFP-03-0004 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station O-PI-17 Washington, DC 20555
SUBJECT:
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Monthly Operatin2 Report
Dear Sir:
Enclosed is the Monthly Operating Report for the James A. FitzPatrick Nuclear Power Plant for the month of December 2002.
Should you have any questions concerning this report, please direct them to Mr. Mick Baker, Thermal Performance Engineer, at (315) 349-6181.
TAS:BO:SB:SA:tmb Enclosure
cc: Regional Administrator U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Resident Inspector James A. FitzPatrick Nuclear Power Plant U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. Guy Vissing, Project Manager Project Directorate I Division of Licensing Project Management U.S. Nuclear Regulatory Commission Mail stop OWFN 8C2 Washington, DC 20555 Mr. R. Toole ENN BWR SRC Operations Subcommittee Chairman 605 West Homer Street Ebensburg, PA 15931 JENG JAFP Files RMS (JAF)
RMS (WPO)
ENTERGY NUCLEAR NORTHEAST JAMES A. FITZPATRICK NUCLEAR POWER PLANT OPERATING DATA REPORT REPORT MONTH: DECEMBER 2002 Docket No.: 50-333 Unit Name: FitzPatrick Date: January 7, 2003 Completed By: M. Baker Telephone: (315) 349-6181 OPERATING STATUS
- 1. Unit name: FitzPatrick
- 2. Reporting period: 12/01/2002 - 12/31/2002
- 3. Licensed thermal power (MWT): 2536
- 4. Nameplate rating (gross MWE): 883.0
- 5. Design electrical rating (net MWE): 816
- 6. Maximum dependable capacity (gross MWE): 839
- 7. Maximum dependable capacity (net MWE): 813
- 8. If changes occur in capacity ratings (Items 3-7) since last report, give reasons:
- 9. Power level to which restricted, if any (net MWE):
- 10. Reasons for restrictions, if any:
NO. DATA REQUESTED THIS YR-TO-DATE CUMULATIVE MONTH 11 Hours in reporting period: 744 8,760 240,456 12 Number of hours reactor was critical: 744 8,170.4 181,330.5 13 Reactor reserve shutdown hours: 0.00 0.00 0.00 14 Hours generator on-line: 744 8,112.5 176,134.3 15 Unit reserve shutdown hours: 0.00 0.00 0.00 16 Gross thermal energy generated (MWH): 1,881,189.6 20,056,615.3 401,786,124.9 17 Gross electrical energy generated (MWH): 650,357.0 6,814,311.0 135,894,451.0 18 Net electrical energy generated (MWH): 629,316.0 6,595,025.0 130,939,795.0 19 Unit service factor: 100.00 92.61 73.25 20 Unit availability factor: 100.00 92.61 73.25 21 Unit capacity factor (using MDC net): 104.04 92.60 74.86 22 Unit capacity factor (using DER net) 103.66 92.26 66.73 23 Unit forced outage rate: 0.00 0.00 10.84
- 24. Shutdowns scheduled over next 6 months (type, date, and duration of each): None
- 25. If shutdown at end of report period, estimated date of startup: N/A
- 26. Units in test status (prior to commercial operation): FORECAST ACHIEVED Initial Criticality:
Initial Electricity:
Commercial Operation:
ENTERGY NUCLEAR NORTHEAST JAMES A. FITZPATRICK NUCLEAR POWER PLANT OPERATING DATA REPORT REPORT MONTH: DECEMBER 2002 Docket No.: 50-333 Unit Name: FitzPatrick Date: January 7, 2003 Completed By: M. Baker Telephone: (315) 349-6181 DAY NET AVERAGE DAILY DAY NET AVERAGE DAILY POWER LEVEL POWER LEVEL 1 846 17 848 2 828 18 848 3 845 19 812 4 848 20 847 5 848 21 847 6 848 22 847 7 848 23 848 8 848 24 848 9 848 25 847 10 848 26 848 11 848 27 848 12 848 28 848 13 848 29 847 14 848 30 848 15 848 31 848 16 848
REPORT MONTH: DECEMBER 2002 Docket No.: 50-333 Unit Name: FitzPatrick Date: January 7, 2003 Completed By: M. Baker Telephone: (315) 349-6181 NO. DATE TYPE DURATION REASON METHOD OF LICENSEE SYSTEM COMPONENT CAUSE and CORRECTIVE HOURS SHUTTING EVENT CODE CODE ACTION TO PREVENT DOWNTHE REPORT RECURRENCE REACTOR NO.
____ I ______ I _____ J ________ A______ L __________
F: FORCED REASON: METHOD: EXHIBIT G: Instructions for preparation of S: SCHEDULED A. Equipment failure (explain) 1. Manual data entry sheets for Licensee Event Report B. Maintenance or Test 2. Manual Scram (LER) file (NUREG-0161)
C. Refueling 3. Automatic Scram D. Regulatory Restriction 4. Continued E. Operator training and license examination 5. Reduced load F. Administrative 9. Other G. Operational error (explain)
H. Other (explain)
REPORT MONTH: DECEMBER 2002 Dock et No.: 50-333 Uniti Name: FitzPatrick Date: January 7, 2003 Comp leted By: M. Baker Telep hone: (315) 349-6181 OPERATIONAL
SUMMARY
OPERATI L
SUMMARY
The FitzPatrick plant - with the exception of minor derates for rod adjustments - operated at or near rated power for the duration of the month of December 2002 with the exception of the following:
0 December 2, 2002 -0905 Power was reduced to 71.4 % reactor power for an intermediate rod pattern adjustment. Power was returned to 95 % reactor power at 1017 December 19, 2002 - 0828 Power was reduced to 75.9 % reactor power at 0923 and further to 75%
reactor power at 1100 for a sequence exchange. The plant then increased power to 82.8% reactor power at 1215 and back to 97% reactor power at 1235.