Information Notice 1982-53, Main Transformer Failures at North Anna Nuclear Power Station

From kanterella
Jump to navigation Jump to search
Main Transformer Failures at North Anna Nuclear Power Station
ML070220268
Person / Time
Site: Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Three Mile Island, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Haddam Neck, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Sterling, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Yankee Rowe, Maine Yankee, Quad Cities, Humboldt Bay, La Crosse, Big Rock Point, Rancho Seco, Zion, Midland, Bellefonte, Fort Calhoun, FitzPatrick, McGuire, LaSalle, 05000514, 05000000, 05000515, 05000355, Zimmer, Fort Saint Vrain, Washington Public Power Supply System, Shoreham, Satsop, Trojan, Allens Creek, Atlantic Nuclear Power Plant, Perkins, Cherokee, Clinch River, Skagit, Marble Hill, Black Fox, Hartsville, Phipps Bend, Yellow Creek
Issue date: 12/22/1982
From:
NRC/IE
To:
References
IN-82-053, NUDOCS 8212060350
Download: ML070220268 (12)


SSINS NO. 6835 IN 82-53ý

UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

WASHINGTON, D. C. 20555 December 22, 1982 IE INFORMATION NOTICE NO. 82-53: MAIN TRANSFORMER FAILURES AT THE NORTH ANNA

NUCLEAR POWER STATION

Addressees

All nuclear power reactor facilities holding an operating license (OL) or

construction permit (CP).

Purpose

The purpose of this information notice is to describe seven main transformer

failurk's, including one that resulted in a fire and one that caused extensive

damage to thi main generator, at the North Anna Nuclear Power Station, to

alert other nuclear power facilities to the causes.

Description of Circumstances

The North Anna main transformers consist of three 330MVA single-phase Westing- house transformers for each unit' which are cooled by a forced oil/forced air

cooling system. The 22kv low-voltage windings of these transformers are

supplied from the main unit generator by an isolated phase bus system. The

500kv voltage windings supply power to the transmission system by an overhead

line to the station switchyard.

The North Anna main transformers have experienced seven failures in the past

two years, the first five of which involved the Unit 2 transformers and the

last two involved the Unit I transformers. Of these, the third and seventh

caused the most damage and also posed the greatest threat to the health and

safety of plant personnel. The third failure generated sufficient forces and

heat to rupture the transformer's casing and an oil line. The oil that erupted

from these two breaks ignited and the resulting fire engulfed and shorted out

an overhead three-phase bus system that supplies offsite power to the normal

and emergency buses of the North Anna facility from a reserve station trans- former. The seventh failure also generated sufficient forces to rupture the

transformer's casing; however, the rupturr was at the upper portion of the

transformer such that the total oil discharged was significantly less than

that of the third failure. Although no fire ensued in the immediate vicinity

of the transformer, the total damage and risk to personnel posed by the

seventh failure were greater than those of'any of the previous events. For

example, the effects of the fault were propagated to the main generator where

significant damage was done to the main generator and its appendages (e.g. , the

neutral grounding transformer and its feeder cable and enclosure were destroyed, the neutral enclosure was severely damaged with the north side being blown out,

0212060350

IN 82-53 December 22, 1982 Page. Z of 7 a fire was created in the neutral enclosure but little damage ensued, the

hydrogen lines to the generator around the nuetral enclosure were badly damaged

but no leaks occurred).

It has been determined that three of the failures involved both the high-voltage

and low-Voltage windings. In addition, it was found that the failures were

either winding to ground faults, as experienced in the first and fourth

failures, or high-voltage bushing to ground failures, as experienced in the

second and third failures. The investigation also suggests that the following

circumstances contributed to the failures:

1. Exposure to Other Faulted Units: At least once before their respective

failures, the transformers involved in the second, third, foufth., fifth

and seventh failures had been used in a bank of transformers where one

of the companion units had failed.

2. Improper Storage: The high-voltage bushings for these transformers were

improperly stored (i.e., in a near-horizontal position). This improper

storage, coupled with subsequent over-voltage conditions, is believed to

be a major contributor to the second and third failures.

3. Overvoltage: Before the first, second, and third failures, the North Anna

Unit . main transformer bank had been subjected to several documented over- voltage conditions. In addition, as a consequence of the third transformer

failure, the transformer associated with the fourth failure was subjected

'to an overvoltage condition of unknown magnitude for a short period of

time.

Discussion of Failures and Postulated Causes:

Th6 paragraphs that follow address each failure and highlight factors believed

to have had a bearing on the failure.

1. First Failure: On November 29, 1980, the Phase A transformer of the North

Anna Unit 2 main transformer bank experienced a winding to ground failure.

Although the transformer was operating at 100 percent load, the hot oil

temperature, hot spot temperature, and nitrogen system trouble annunciators

were inoperable. Had these annunciators been operating, the failure may

have been averted. This transformer had previously failed while on loan

to Georgia Power Company. The following factors contributed to this

failure:

0 On January 31, 1979 and October 19, 1980, the transformer was subjected

to overvoltage conditions of 31kV and 25kV, respectively.

0 Approximately 61/2 hours before the transformer failed, its mechanical

relief device .MRD) operated. Although the station electricians

detected no oil, they found only two coolers running; therefore, they

reset a tripped circuit breaker to start three other coolers. In

addition, the indicated temperature of the oil on the top of the tank

and of the windings were found to be 90%C and O°C, respectively. The

IN 82- December 22, 1982 windinq temperature indication was obviously in error and may have

been the reason for some coolers not operating. Further examination

of the transformer verified MRO operation and detected oil on the

cover of the transformer. Operation of the additonal oil coolers

reduced the temperature to 500 C at the time of failure.

The oil expansion calculations performed by Westinghouse indicated the oil

level was approximately 21/2 inches below the top of the tank at the time the

MRD operated. Since the inert gas system was isolated, this oil expansion

would produce a gas pressure of about 19 psig in the absence of MRD operation;

however, the MRD apparently opened at approximately 10 psig and relieved the

pressure. Soon after the reseal, the inerting gas cylinder was isolated in an

effort to silence the MRO alarm, and three additional coolers wcre started

manually, thereby increasing the cooling units by 150 percent. As a consequence

the temperatuy, of the oil on the top of the tank dropped about 18*C in the

first 2h hours and an additional 22*C in the next 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. This reduction in

oil temperature caused the oil level to drop approximately 31/2 inches, and since

the inert gas pressure system was inoperable, a partial vacuum was created.

It is postulated by Westinghouse that the vacuum condition resulted in the

release of previously dissolved nitrogen gas from the oil, and that this released

gas rose as bubbles. It is also postulated that these gas bubbles entered the

cylindrical insulation structure around the high-voltage bushing and distorted

the electrostatic field surrounding the high-voltage lead. The distorted

electrostatic field, coupled with the reduced dielectric strength caused by the

gas within the high-voltage bushing, allowed electrical arcing which resulted

In the low-and high-voltage windings being shorted to ground.

2. Second and Third Failures: On June 19 and July 3, 1981 respectively, the

Phase C and Phase B transformers of the North Anna Unit 2 main transformer

bank experienced high-voltage bushing to ground failures. Before these

failures, these two units had been exposed to overvoltage stresses of 31kV

on one occasion and 25kV on four other occasions. Other factors that may

have contributed to these failures include:

0 These units and their companion unit were initially installed at

North Anna on July, 1974. On April of 1976 they were shipped to a

Georgia Power Co. facility where, on May 6, 1976, they were exposed

to the aforementioned failure of the companion unit. After the

failure of the companion unit, they were shipped to the Westinghouse

factory in Muncie, Indiana for inspection and test before being

returned to the North Anna facility. While at North Anna, these units

were again exposed to the failure of their companion unit described

above in Item 1.

From September 25 to October, 1976, the Phase B and C transformers

were stored out of the oil at North Anna for 5 and 6 months, respec- tively. During this time, their bushings were stored in shipping

crates at an 80 to 90 angle, but they should have been stored at a

minimum angle of 200.

IN 82-53 December 22, 1982 Initial inspections of the failed transformers disclosed internal failures of

the high-voltage bushings; burning was more severe on the bushing of Phase B

transformer. Although no other causes for failure were evident, examination

of Phase B transformer revealed secondary flashover points and a ruptured cover

that raised the high-voltage bushing and lead. Phase C transformer on the

other hand, evidenced no tank distortion.

Factory inspections of these bushings (see attached Figure 1) disclosed burning

of the tap and ground foils on the straight portion of the condenser where the

flange and ground sleeve are attached (Region A of Figure 1). The insulating

paper between these foils was wrinkled and burned on the edges in'this region

and across the surface of the condenser from Region A to the bottom end of the

condenser taper. Arc marks were found on the lower bushing corona end shield

and the ground sleeve of Phase C transformer, and on the HV lead tank wall of

Phase B transformer. Based on the factory inspections, it was concluded that

the failures originated as arcs between the ground and tap foils in the straight

portion of the condenser (Region A). These arcs then propagated across the

surface of the tapered portion of the condenser (Region 8). On Phase C trans- former, the gas generated by this burning disintegrated the lower portion of

the bushing and established an arc path from the lower corona shield to the

steel ground sleeve. The arc path on the Phase B transformer included the

high voltage lead connected to the bottom of the bushing, the tank wall, and

windings.

Since the bushings were improperly positioned (i.e., in the near-horizontal

position) during their transportation and storage periods, portions of the

condenser were not completely covered by oil. The absence of oil allowid the

gas in the expansion cap to permeate the exposed paper layers. Once gas

permeates the paper region the busings are degraded electrically and long time

periods are required to completely reimpregnate the paper with oil. Such

degraded bushings are susceptible to corona discharges on overvoltage Londi- tions such as those experienced by these bushings before their ultimate failures.

Corona discharges are usually extinguished when the voltage returns to normal;

however, the dielectric quality of the bushing is reduced each time a corona

discharge occurs. As a result, new corona discharges will occur at lower

voltage levels than those of the previous discharges. This process is cumula- tive and can continue until the corona extinction voltage level is less than

the normal operating level, in which case disruptive failures will occur.

Unlike previous disruptive events at North Anna, the transformer failure of

July 3 generated such great internal forces that the transformer box and one

oil pump discharge pipe ruptured. The oil that erupted from these two breaks

ignited, and the resultant fire shorted out the overhead bus bars from a

three-phase reserve station service (RSS) transformer. The affected RSS

transformer is one of three transformers that supply Unit 1 and 2 with offsite

power(startup power) whenever a unit generater is not available. These trans- formers are also the preferred sources of power for the Class 1E loads whenever

a unit generator is not available. Underground cables serve the 4160-V emer- gency buses from these RSS transformers, and the overhead bus bars and cables

serve the normal service station buses; however, there are no isolation breakers

near the RSS transformer for the overhead bus bars.

IN 82-53 December 22, 1982 '

3. Fourth Failure: On July 25, 1981, while being backfed from the 500-kV

switchyard for preoperational testing, Phase C transformer of the North

Anna Unit 2 main transformer bank failed. The failure was a high voltage

to ground fault which ruptured the tank and resulted in the loss Of

cooling oil. No fire ensued. Factors which contributed to this failure

include:

o This transformer was purchased by another utility in 1968 and placed

in service in 1970; its two companion transformers failed in 1976.

It was then shipped to the Westinghouse factory in Muncie for retest, where it was subjected to its basic insulation level test. The unit

was shipped from Muncie to the other utility and in June of 1981 it

was shipped to North Anna.

0 On July 3, 1981 it was exposed to the failure experienced by Phase B

transformer.

It appears that the low-voltage coil edge of the transformer experienced an

,incipient failure as a result of the high-voltage to low-voltage failure of

Phase B transformer on July 3, 1981. Evidence leading to the assumption

includes:

The inside of the tank top above the end frames was coated with carbon.

The corner nearest the failed points was darker than other walls.

The original oil level was clearly defined by a dark carbon ring en- circling the inside of the tank, indicating that the carbon ring was

probably generated during the July 3 failure of Phase 2 transformer (e.g.,

the ruptured tank associated with the July 25 failure depleted the oil too

quickly for a carbon ring to form).

4. Fifth Failure: On August 22, 1982, Phase B transformer of the North Anna

Unit 2 main transformer bank experienced an electrical insulator bushing

failure. This failure caused a turbine trip and reactor trip from 30

percent power; as a result hot transformer oil was sprayed around the

failed unit and the fire protection water deluge systemwas activated.

Although no fire ensued, the oil emanating from the bushing also sprayed

the bus bars of RSS Transformer C. After the plant was brought to a

static cond'tkr and to ensure that no fire would occur from the sprayed

oil, RSS Transformer C was taken out of service until the oil was removed.

Offsite power to most of the plant auxiliary loads remained available via

RSS Transforme.rs A and B; however, the Class 1E buses normally served from

RSS Transformer C required the running of the. onsite emergency diesel

generator dedicated to said buses. While in the process of restoring RSS

Transformer C to service, an unrelated event occurred. Load on the diesel

generator was being increased while syschronizing the generator with the

grid in order to restore RSS Transformer C to service. During this period

oil leaked on tho hot exhaust system of the diesel generator and a fire

ensued. The fire was quickly extinguished and no damage was done .to the

diesel generator.

IN 82-53 December 22, 1982 5. Sixth Failure: On November 16, 1982, while Unit 1 was being heated up

following a refueling outage, the Phase C Transformer of the main trans- former failed. Since the Unit was not generating power at the time~of the

failure, the main transformer was being used to provide power to the

auxiliary loads from the grid. Although this is the sixth main transr

former failure experienced at the North Anna nuclear facility, it is the

first failure of a Unit 1 main transformer.

As a result of this failure, a small hole was blown in the transformer's

case, causing oil to be sprayed into the adjacent area. The oil Was

contained in the concrete basin surrounding the transformer and no fire

ensued.

Subsequent to this failure, Westinghouse recommended that the North Anna

Unit transformers be modified. Shortly thereafter the licensee modified

the Unit 1 transformers as recommended by Westinghouse. The recommen- dations included incorporating a constant oil pressure system (COPS)-that

separates the nitrogen gas from the transformer oil by use of a diaphragm.

The intent of this modification was to eliminate the previously described

adverse affect of dissolved nitrogen gas in the oil.

6. Seventh Failure: On December 5, 1982, with Unit 1 operating at 30 percent

power, its Phase B main transformer failed. The transformer failure

caused an automatic trip of the turbine and the reactor. Prior to the

trip, but not related to the transformer failure, two steam flow instru- ments had been tripped because of erratic indications. Subsequent to the

trip, the reactor coolant temperature (Tave) reached a low setpoint which

initiated emergency safeguards functions, including safety injection

which was terminated after seven minutes.

The forces associated with this failure caused the transformer's case to

rupture; however, since the rupture occurred in the upper part of the

transformer, the oil discharged was limited to approximately 1,500 gallons.

ihe oil was contained within the transformer's concrete basin.

The effects of the failure were not confined to the immediate area of the

transformer. Rather, the effects were propagated to the main unit genera- tor and its accessories which suffered significant damages. The damage

due to this event included:

0 Phase B Transformer: Tank ruptured in several places; COPS remained

intact, but the connection line from the tank to top of the trans- former ruptured. Cooling fans and enclosures were blown off and fell

against the fire lines breaking the lower ring of the deluge system;

low-voltage bushings were both broken; low-voltage connection box

split; high-voltage flexible cable to the bushing had failed and had

gone to ground and to the secondary winding.

Isolated Phase Bus and Oucting: Oil found on the B Phase duct;

breaker G-12 was coated with aluminum dust and its access cover on

Phase A was bowed out; Phase A and B duct and bus work at the elbow

on the generator side of Breaker G-12 and six standoff insulators

for the bus were damaged sufficiently to require replacement.

IN 82-53 December 22, 1982 Main Unit Generator: Neutral grounding transformer, feeder cable

and enclosure destroyed; generator neutral enclosure was damaged

and the north side was blown out (a fire was created in the

enclosure but only minimal damage resulted); hydrogen lines to the

generator around the neutral enclosure were badly damaged, but no

leaks occurred (had a leak occurred or had the line ruptured, the

health and safety of plant personnel could have been endangered);

Phase C in the neutral enclosure bushing was cracked and others

received splatter; stator damaged and copper found in the lead box;

air haidler ducting damaged.

The licensee estimates that repair or replacement of the damaged parts will

be completed by April of 1983.

The licensee is inivestigating the main transformer failures at the North Anna

nuclear facility. The licensee plans to replace the Unit 1 transformers prior

to restart and the Unit 2 transformers during the next refueling outage with

different make transformers.

We have been informed that about 300 similar transformers were placed in

service between 1965 and 1976. To date, twenty-one failures have been experi- enced by these transformers, seven of which have occurred at the North Anna

facility and six at a Georgia Power Company fossil fuel plant. These failures

have been characterized as being winding or bushing failures similar to those

described in this Notice.

If you have any questions regarding this matter, please contact the Regional

Administrator of the appropriate NRC Regional Office or this office.

v-J

Edward L. Jordan, Director

Division of Engineering' and

Quality Assurance

Office of Inspection and Enforcement

Technical Contact:

I. Villalva, IE

(301) 492-9635 Attachments:

1. Figure 1, "Outline - High Voltage Bushing"

2. List of Recently Issued IE Information Notices

ASEE PREVIOUS CONCURRENCES

WPU:JD *EAB:DEQA:IE *C:DEQA:IE *D:DEQA:IE

12/17/82 I VILLALVA WR MILLS EL JORDAN

5520 12/ /82 12/ /82 12/ /82

IN 82- December , 1982 Page 7 of

The licensee is investigating the main transformer failures at the North

Anna nuclear facility. Thent i p tor, a,,d sptcli13sts-4om

tnc Rcgizn II1 10ffiee are monit3l 1 -re3-is f the illce Iiiv's-mt-

-twtt-reiv

arJj ekotiyth 0ll-.

the tfUz-unLvThe

Ldq~c

licensee plans to replace the Unit I transformers prior to restart and

the Unit 2 transformers during the next refueling outage with different

make transformers.

We have been informed that about 300 similar transformers were placed in

service between 1965 and 1976. Todate, twenty-one failures have been

experienced by these transformers, seven of which have occurred at the

North Anna facility and six at a Georgii Power Company fossil fuel plant.

These failures have been characterized as being winding or bushing

failures similar to those described in this Notice.

t/

S'Edward L. Jordan, Director

Division of Engineering and

Quality Assurance

Office of Inspection and Enforcement

Technical Contact:

I. Villalva, IE

(301) 492-9635 Attachments:

1. Figure 1 "Outline - High Voltage Bushing"

2. List of Recently Issued IE Information Notices

EAB:DEQA:IE C:DEQA:IE 4ý.1E

I VILLALVA WR MILLS EL JORDAN

12/ /82 12/ /82 12//*//82

iN 82- December , 1982 Page 7 of

The licensee is investigating the main transformer failures at the North

Anna nuclear facility. The NRC resident inspector and specialists from

the Region 11 Office are monitoring the progress of the licensee's

investigation and will review the adequacy of the corrective actions. The

licensee plans to replace the Unit I transformers with different make

prior to restart.

Edward L. Jordan, Director

Division of Engineering and

Quality Assurance

Office of Inspection and Enforcement

Technical Contact:

I. Villalva, IE

(301) 492-9635 Attachments:

1. Figure 1 "Outline - High Voltage Bushing"

2. List of Recently Issued IE Information Notices

EAB:DEQA: IE D: DEQA: IE

I VILLALVA WR MILLS EL JORDAN

12/1q /82 12//6/82 12/ /82

Attachment

IN 82-53 1 December 22, 1983 Expansion cap -2. Z- llormal Bushtfl9 Oil Level

Porcelainf Wall

J

flots: Oil in expanSiOfl C39v

between po-cegaiil and

condenser, and impre- ated

in candensar paper.

I

1

~-Funge

lank{

Top

Nlormial TranSforMl,

-~ -- Oil Level

>

V~~

I,

01 Co

41

0

-FrGURE. t

Attachment 2 IN 82-53 December 22, 1982 LIST OF RECENTLY ISSUED

IE INFORMATION NOTICES

Information- Date of

Notice No. Subject Issue Issued to

82-52 Equipment Environmental 12/21/82 All power reactor

Qualification Testing Experi- facilities holding

ence ` Updating of Test an OL or CP

Summaries Previously Published

in IN 81-29

82-51 Overexposure in PWR Cavities 12/21/82 All holders of a

Senior Reactor Operator

license; all power

reactor facilities

holding an OL or CP

82-50 Modification of Solid State 12/20/82 A!' pcwer reactor

AC Undervoltage ReWays Type ITE-27 facilities holding

an OL or CP

82-49 Correction for Sample Condi- 12/16/82 All power reactor

tions for Air and Gas facilities holding

Monitoring an OL or CP; research

and test reactors;

fuel facilities;

Priority I materials

82-43 Failures of Agastat CR 0095 12/3/82 All power reactor

Relay Sockets facilities holding

an OL or CP

82-47 Transporation of Type A 11/30/82 All NRC licensees

Quantities of Non-Fissile

Radioactive Material

82-46 Defective and Obsolete Com- 11/26/82 All facilities

bination padlocks pursuant to 10 CFR

Parts 50 and 70

and Part 95 appli- cable facilities

82-45 PWR Low Temperature Over- 11/19/82 All PWR facilities

pressure Protection holding an OL or CP

82-44 Clarification of Emergency 11/18/82 All power reactor

Plan Exercise Requirements facilities holding

an OL or CP

DL = Operating License

CP = Construction Permit

'; I

I

Pt

I _

a

-..

a

Olaf 0!

~Xk 1ýb c co

T~Lq -

SI

0 0

0

A^AA&AJAAA"AAA&&"5ZXAZEEZZZZZZ

$ZLICI'NZIZZZ--IZZZZXO 5*Z$ -- 3

  • GSO04JP

JLXJXXJXiXXJXlXXI

4 LABELS - 3

- Tv IX/./XXXlXXXYX IX SILECTION - 60000 SETS - 61 2n08 004596 WO "It -- OI5"3

0

XXmzzXuuaXzzXX 1x~xlxxzixxxlNx AzRAx:xxAzzaAxazzzzza~axxAxA"

6SUP 8 01 TIYP : LALS - 3 SLICIlGN, - 000000 ISIS - 01 bOe 0465% 0a DAEi - 010343 LP

i00000*00 0OQ00004 di~ei~~1 0,Lý he -Jm

XZZXXAXIXX XAZZ) *ZXXX IIZ IiA IX

  • iZJZIAJLAS JZA3833*R3 CROUP 1 0 '

T*PEr LAELS - 3 SELECT ION - 000000 MIS5 - at bOa 0065)9 14 DATE - N30am)

Ea

VAjC0410ýa. it

cJ.AoWIE160 - 4"h2$ UA

' v!. :

GjOUP 0 01 TYP LAI.LS - 3 SELECTION - 000000 SETS - 01 bOf 00&5%l bO BAIR - 010353

9,9'1 a AB*OAS0 .