MONTHYEARIR 05000458/20240102024-10-31031 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2024010 IR 05000458/20240032024-10-31031 October 2024 Integrated Inspection Report 05000458/2024003 IR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) IR 05000458/20240022024-07-30030 July 2024 Integrated Inspection Report 05000458/2024002 and Notice of Violation ML24164A0862024-06-12012 June 2024 Notification of Commercial Grade Dedication Inspection (05000458/2024010) and Request for Information IR 05000458/20240012024-05-14014 May 2024 Integrated Inspection Report 05000458/2024001 IR 05000458/20244022024-04-15015 April 2024 Security Baseline Inspection Report 05000458/2024402 (Full Report) IR 05000458/20243012024-04-0202 April 2024 Notification of NRC Initial Operator Licensing Examination 05000458/2024301 IR 05000458/20240402024-03-15015 March 2024 – 95001 Supplemental Inspection Report 05000458/2024040 and Follow-Up Assessment IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 IR 05000458/20230042024-01-30030 January 2024 Integrated Inspection Report 05000458/2023004 IR 05000458/20230402024-01-18018 January 2024 – 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter IR 05000458/20230102023-12-12012 December 2023 Biennial Problem Identification and Resolution Inspection Report 05000458/2023010 IR 05000458/20230032023-11-13013 November 2023 Integrated Inspection Report 05000458/2023003 IR 05000458/20234012023-09-26026 September 2023 Cyber Security Inspection Report 05000458/2023401 IR 05000458/20234032023-09-21021 September 2023 NRC Security Inspection Report 05000458/2023403 (Cover Letter) IR 05000458/20230012023-09-21021 September 2023 NRC Inspection Report 05000458/2023001, Disputed Non-Cited Violation Rescinded IR 05000458/20230122023-09-0101 September 2023 – Comprehensive Engineering Team Inspection Report 05000458/2023012 IR 05000458/20230052023-08-21021 August 2023 Updated Inspection Plan for River Bend Station (Report 05000458/2023005) - Mid Cycle Letter IR 05000458/20230922023-08-15015 August 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023092 IR 05000458/20230022023-08-0909 August 2023 Integrated Inspection Report 05000458/2023002 IR 05000458/20230912023-07-20020 July 2023 Final Significance Determination of a White Finding, Notice of Violation, and Follow-Up Assessment Letter; NRC Inspection Report 05000458/2023091 IR 05000458/20234042023-07-11011 July 2023 NRC Security Inspection Report 05000458/2023404 (Cover Letter Only) IR 05000458/20230902023-06-26026 June 2023 NRC Inspection Report 05000458/2023090 and Preliminary White Finding ML23116A2352023-05-0101 May 2023 Integrated Inspection Report 05000458/2023001 IR 05000458/20230112023-04-12012 April 2023 NRC License Renewal Phase 1 Inspection Report 05000458/2023011 IR 05000458/20220062023-03-0101 March 2023 Annual Assessment Letter for River Bend Station Report 05000458/2022006 IR 05000458/20220042023-02-0101 February 2023 Integrated Inspection Report 05000458/2022004 IR 05000458/20220102022-12-12012 December 2022 Triennial Fire Protection Inspection Report 05000458/2022010 IR 05000458/20220032022-11-0303 November 2022 And Independent Spent Fuel Storage Installation Integrated Inspection Report 05000458/2022003 and 07200049/2022001 IR 05000458/20224022022-09-12012 September 2022 NRC Security Inspection Report 05000458/2022402 (Full Report) IR 05000458/20220022022-08-0909 August 2022 Integrated Inspection Report 05000458/2022002 IR 05000458/20220112022-06-0202 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2022011 IR 05000458/20220012022-04-27027 April 2022 Integrated Inspection Report 05000458/2022001 IR 05000458/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000458/2021006) IR 05000458/20210042022-01-25025 January 2022 Integrated Inspection Report 05000458/2021004 ML22011A0992022-01-14014 January 2022 IR 2021012 EOI CO3 IR 05000458/20214022021-12-15015 December 2021 Security Baseline Inspection Report 05000458/2021402 IR 05000458/20214042021-12-0707 December 2021 Material Control and Accounting Program Inspection Report 05000458/2021404, Publicly Available IR 05000458/20214012021-12-0303 December 2021 Security Baseline Inspection Report 05000458/2021401 IR 05000458/20223012021-11-30030 November 2021 Notification of NRC Initial Operator Licensing Examination 05000458/2022301 IR 05000458/20210032021-11-0404 November 2021 Integrated Inspection Report 05000458/2021003 IR 05000458/20210912021-09-30030 September 2021 Notice of Violation and Proposed Imposition of $150,000 Civil Penalty, NRC Inspection Report 05000458/2021091 and Investigation Reports 4-2020-008, 4-2020-009, and 4-2020-019 IR 05000458/20210022021-08-11011 August 2021 Integrated Inspection Report 05000458/2021002 IR 05000458/20210902021-07-0101 July 2021 NRC Inspection Report 05000458/2021090 and Investigation Reports 4-2020-008, 4-2020-009, and 4-2020-019 IR 05000458/20210132021-05-25025 May 2021 Rriver Bend Station - NRC Baseline Inspection Report 05000458/2021013 IR 05000458/20214032021-05-24024 May 2021 Security Baseline Inspection Report 05000458/2021403 IR 05000458/20210012021-05-0505 May 2021 RBS2021001-RP-RJK, River Bend Station - Integrated Inspection Report 05000458/2021001 IR 05000458/20210102021-03-18018 March 2021 2021 River Bend Station - Biennial Problem Identification and Resolution Inspection Report 05000458/2021010 and Notice of Violation IR 05000458/20200042021-02-11011 February 2021 RBS2020004-RP-RJK, River Bend Station - Integrated Inspection Report 05000458/2020004 2024-08-22
[Table view] Category:Letter
MONTHYEARIR 05000458/20240102024-10-31031 October 2024 Design Basis Assurance Inspection (Programs) Inspection Report 05000458/2024010 IR 05000458/20240032024-10-31031 October 2024 Integrated Inspection Report 05000458/2024003 RBG-48315, Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement2024-09-24024 September 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2023003 Supplement RBG-48306, Report of Changes and Errors to 10CFR50.462024-09-24024 September 2024 Report of Changes and Errors to 10CFR50.46 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24255A1192024-09-16016 September 2024 Notification of NRC Follow Up Inspection for One Severity Level (SL) III and Two SL IV or Three or More SL IV Violations and Request for Additional Information RBG-48311, Reply to a Notice of Violation, NRC Inspection Report 05000458/20240022024-08-28028 August 2024 Reply to a Notice of Violation, NRC Inspection Report 05000458/2024002 IR 05000458/20240052024-08-22022 August 2024 Updated Inspection Plan for River Bend Station (Report 05000458/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24214A2752024-08-0202 August 2024 Acknowledgement of Readiness for Supplemental Inspection RBG-48308, Notification of Readiness for Supplemental Inspection2024-07-31031 July 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20240022024-07-30030 July 2024 Integrated Inspection Report 05000458/2024002 and Notice of Violation ML24164A0862024-06-12012 June 2024 Notification of Commercial Grade Dedication Inspection (05000458/2024010) and Request for Information 05000458/LER-2023-005-01, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-06-0404 June 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 ML24081A0072024-05-16016 May 2024 Issuance of Amendment No. 213 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b ML24093A0892024-05-16016 May 2024 Issuance of Amendment No. 214 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors IR 05000458/20240012024-05-14014 May 2024 Integrated Inspection Report 05000458/2024001 ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions ML24102A2842024-05-0707 May 2024 Summary of Regulatory Audit in Support of LARs to Revise Technical Specifications to Adopt Risk-Informed Completion Times and Implement the Provisions of 10 CFR 50.69 RBG-48276, 2023 Annual Radioactive Effluent Release Report2024-04-23023 April 2024 2023 Annual Radioactive Effluent Release Report RBG-48288, Louisiana Pollutant Discharge Elimination System Permit Renewal2024-04-15015 April 2024 Louisiana Pollutant Discharge Elimination System Permit Renewal IR 05000458/20244022024-04-15015 April 2024 Security Baseline Inspection Report 05000458/2024402 (Full Report) ML24106A0432024-04-11011 April 2024 June 2024 Emergency Preparedness Exercise Inspection Request for Information ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair RBG-48277, 2023 Annual Radiological Environmental Operating Report2024-04-10010 April 2024 2023 Annual Radiological Environmental Operating Report IR 05000458/20243012024-04-0202 April 2024 Notification of NRC Initial Operator Licensing Examination 05000458/2024301 ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) IR 05000458/20240402024-03-15015 March 2024 – 95001 Supplemental Inspection Report 05000458/2024040 and Follow-Up Assessment ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24066A1802024-03-0707 March 2024 Notification of NRC Follow-Up Inspection for Any Severity Level I or II Traditional Enforcement Violation IR 05000458/20230062024-02-28028 February 2024 Annual Assessment Letter for River Bend Station - Report 05000458/2023006 RBG-48278, 2023 Spent Fuel Storage Radioactive Effluent Release Report2024-02-27027 February 2024 2023 Spent Fuel Storage Radioactive Effluent Release Report RBG-48286, Revision to Owners Activity Report Form (OAR) for Cycle 222024-02-27027 February 2024 Revision to Owners Activity Report Form (OAR) for Cycle 22 ML24031A0042024-02-21021 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0052 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) 05000458/LER-2023-006, Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard2024-02-0808 February 2024 Automatic Reactor Scram Due to a Turbine Trip Following a Disconnect Failure at Switchyard RBG-48274, Notification of Readiness for Supplemental Inspection2024-02-0505 February 2024 Notification of Readiness for Supplemental Inspection IR 05000458/20230042024-01-30030 January 2024 Integrated Inspection Report 05000458/2023004 IR 05000458/20230402024-01-18018 January 2024 – 95001 Supplemental Inspection Supplemental Report 05000458/2023040 and Follow-Up Assessment Letter 05000458/LER-2023-005, Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String2024-01-16016 January 2024 Manual Reactor Scram Due to Lowering Feedwater Temperature Following an Automatic Isolation of Feedwater Heater String RBG-48271, Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk2024-01-12012 January 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 – Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML24011A1742024-01-11011 January 2024 Security Baseline Inspection Report (Cover Letter) 05000458/LER-2023-004, Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure2023-12-28028 December 2023 Drywall Post Accident Radiation Monitor Inoperable Due to Unrecognized Surveillance Failure ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment 2024-09-24
[Table view] |
Text
ber 6, 2018
SUBJECT:
RIVER BEND STATION - NRC SECURITY BASELINE INSPECTION REPORT 05000458/2018404
Dear Mr. Maguire:
On July 26, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your River Bend Station. The NRC inspectors discussed the results of this inspection with Mr. S. Vercelli, General Manager, Plant Operations, and other members of your staff. The inspector documented the results of this inspection in the enclosed inspection report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of ADAMS. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If you choose to provide a response to this report that contains Security-Related Information, please mark your entire response Security-Related Information - Withhold from Public Disclosure Under 10 CFR 2.390 (d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA by DAHolman Acting For Jeremy R. Groom, Chief Plant Support Branch 1 Division Reactor Safety Docket No. 50-458 License No. NPF-47 Enclosure:
Inspection Report 05000458/2018404
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
Docket Number: 05000458 License Number: NPF-47 Report Number: 05000458/2018404 Enterprise Identifier: I-2018-404-0002 Licensee: Entergy Operations, Inc.
Facility: River Bend Station Location: Saint Francisville, Louisiana Dates: July 23 to July 26, 2018 Inspectors: J. Buchanan, Physical Security Inspector A. Meyen, Physical Security Inspector Approved By: Jeremy R. Groom Chief, Plant Support Branch 1 Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Baseline Security Inspection at River Bend Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC identified and self-revealed findings, violations, and additional items are summarized in the table below.
List of Findings and Violations No findings were identified.
Additional Tracking Items No Additional Items.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, "Security Inspection Program for Commercial Nuclear Power Reactors." The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.04 - Equipment Performance, Testing, and Maintenance
Main article: IP 71130.04
The inspectors evaluated the security equipment performance, testing and maintenance program. The following elements were evaluated:
Tier I: all requirements Tier II: all requirements Tier III: all requirements
71130.07 - Security Training
Main article: IP 71130.07
The inspectors evaluated the security training program. The following elements were evaluated:
Tier I: all requirements Tier II: all requirements Tier III: all requirements
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
On July 26, 2018, the inspectors presented the Baseline Security Inspection results to Mr. S. Vercelli, General Manager, Plant Operations, and other members of the licensee staff.
The inspector verified no proprietary information was retained or documented in this report.
DOCUMENTS REVIEWED
71130.04 - Equipment Performance, Testing, and Maintenance
Condition Reports
CR-RBS-2017-00018 CR-RBS-2017-04897 CR-RBS-2017-05929 CR-RBS-2018-04114
Procedures
Number Title Revision
EN-NS-203 General Security Program 2
EN-NS-212 Weapons Maintenance Accountability Program 5
EN-NS-220 Managing safety/Security Interface 3
EN-NS-221 Security Organization, Standards and 11
Expectations
EN-NS-227 Security Department Challenge Testing 2
EN-NS-230 Security Equipment Accountability 0
SDI-010 Security System Compensation(SGI) 11
SDI-013 Issue, Control, and Maintenance of Security 9
Force Equipment
SDI-016 Protected Area and Vital Area Access Control 11
SDI-017 Security System Test, Inspection, and 6
Maintenance
STI-017-01 Security system Operability Test 24
STI-017-07-02 X-Ray Equipment Image Test-PAP 7
STI-017-07-02-01 X-Ray Equipment Image Test-Warehouse 0
STI-017-07-06 SOCA Active Vehicle Barrier Operational test 9
STI-017-07-07 Portable Explosive Detector Operability Test 3
STI-017-07-08 BRE Equipment Performance Test 7
STI-017-07-09 Explosive Detector Operability Test 10
STI-017-07-10 Metal Detector Operability Test 4
STI-017-07-11 SOCA Early warning System Operability Test 8
STI-017-90-02 Diesel Generator 108 Gates 4,5,6, and DG131- 4
H1 Operability Test
STI-017-90-04 Quarterly Light Survey 6
STI-017-90-06 Biometric hand Reader Quarterly Performance 5
Test
STI-017-90-07 Defense Equipment Performance Test 6
STI-017-180-01 PAIDS Test 2
STI-017-180-02 SOCA Early Warning System Performance 6
Test
Miscellaneous Documents Revision
Number Title or Date
Security Plan Physical Security Plan
Logs Security Event Logs Date 7-1-17 to 6-30-18
711130.07 Security - Training
Condition Reports
CR-RBS-2017-07413 CR-RBS-2018-01401 CR-RBS-2018-01646 CR-RBS-2018-02050
CR-RBS-2018-02354 CR-RBS-2018-02362 CR-RBS-2018-02363 CR-RBS-2018-03039
CR-RBS-2018-04099 CR-RBS-2018-04100
Procedures
Number Title Revision
EN NS-215 Conduct of Security Force Exercises and Drills 18
EN-NS-216 Controller Responsibilities Guidelines 11
EN-NS-221 Security Organization, Standards & 11
Expectations
EN-NS-232 Visitor Escort Responsibilities 1
EN-NS-234 Force on Force Mock Adversary Program 0
EN-NS-300 Security Training Program 8
EN-NS-301 Security Systematic Approach to Training 4
(SAT) Process
EN-NS-303 Security Training Oversight Program 6
EN-NS-304 Security On-the-Job Training, Task 7
Performance Evaluation and Training
Exemptions
EN-LI-102 Corrective Action Program 33
SPI-35 Bearcat Officers 2
Miscellaneous Documents Revision
Number Title or Date
Critical Group List July 23,
2018
Daily Shift Report July 25,
2018
Form No. NSF-304-09, On the Job Training 1
Checklist
Job Performance Measure RJPM-SEC-20.0, 2
Respond to Contingency Events and Execute the
Defensive Strategy
Job Performance Measure RJPM-SEC-23.0, 3
React to Bomb, Hostage and Civil Disturbance
Situations
Lesson Plan FLP-SECI-DRILLEX, Entergy 0
Security Fleet Force-on-Force Controller Training
Lesson Plan RLP-SEC-RTL, Response Team 0
Leader
Sample of Security Personnel Training Records 0
River Bend Station Critical Target Sets 7
River Bend Station Physical Security, 12
Safeguards Contingency and Training and
Qualification Plan
RTL Checklist Days April 20,
2018
RTL Checklist Nights April 20,
2018
Short Term Disabilities (STD/FMLA) July 23,
2019
Tactical Response Drill Reports 2018
Training Calendar 2016-2018
ML18250A200
Entire Report: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review By: ADM Yes No Publicly Available Sensitive ______ NRC-002
OFFICE PSI:PSB1 PSI:PSB1 C:PSB1 C:PBC C:PSB1
NAME JBuchanan AMeyen JGroom JKozal JGroom
SIGNATURE /RA/ /RA/ /RA/ Jwk /RA by
DAHolman
Acting For/
DATE 8/29/18 8/29/18 8/29/18 9/3/2018 09/6/18