|
---|
Category:Inspection Plan
MONTHYEARIR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) ML23090A0192023-03-31031 March 2023 Information Request for the Cyber Security Baseline Inspection; Notification to Perform Inspection 05000334/2023401 and 05000412/2023401 IR 05000334/20220062023-03-0101 March 2023 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2022006 and 05000412/2022006) IR 05000334/20220052022-08-31031 August 2022 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2022005 and 05000412/2022005) IR 05000334/20210062022-03-0202 March 2022 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2021006 and 05000412/2021006) IR 05000334/20210052021-09-0101 September 2021 Updated Inspection Plan for the Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2021005 and 05000412/2021005) ML21124A1322021-05-0404 May 2021 Notification of Conduct of a Fire Protection Team Inspection IR 05000334/20200062021-03-0303 March 2021 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2020006 and 05000412/2020006) IR 05000334/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000334/2020005 and 05000412/2020005) IR 05000334/20190062020-03-0303 March 2020 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2019006 and 05000412/2019006) IR 05000334/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000334/2019005 and 05000412/2019005 IR 05000334/20180062019-03-0404 March 2019 Annual Assessment Letter for Beaver Valley Power Station, Unit Nos. 1 and 2 (Reports 05000334/2018006 and 05000412/2018006) IR 05000334/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000334/2018005 and 05000412/2018005 IR 05000334/20170062018-02-28028 February 2018 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2(Reports 05000334/2017006 and 0500412/2017006; 05000334/2017402 and 05000412/2017402 and 05000334-2017501 and 05000412/2017501) ML17271A0662017-09-28028 September 2017 Information Request for the Cyber Security Baseline Inspection Notification to Perform Inspection 05000334/2018403 and 05000412/2018403 IR 05000334/20160062017-03-0101 March 2017 Annual Assessment Letter for Beaver Valley Power Station, Unit Nos. 1 and 2 (Report 05000334/2016006 and 05000412/2016006) with Report 22 IR 05000334/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2016005 and 05000412/2016005) IR 05000334/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Beaver Valley Power Station, Units 1 & 2 (Report 05000334/2015006 and 05000412/2015006) IR 05000334/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Beaver Valley Power Station (Report 05000334/2015005 and 05000412/2015005) IR 05000334/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2, (Report 05000334/2014001 and 05000412/2014001) IR 05000334/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000334/2014006 and 05000412/2014006 IR 05000334/20130012014-03-0404 March 2014 ROP-14 2013 Beaver Valley Power Station Units 1 and 2, Annual Assessment Letter, Report 05000334/2013001 and 05000412/2013001, and Inspection Plan IR 05000334/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000334/2013006 and 05000412/2013006 IR 05000334/20120012013-03-0404 March 2013 Annual Assessment Letter for Beaver Valley Units 1 and 2 (Report 05000334/2012001 and 05000412/2012001) IR 05000334/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Beaver Valley Power Station (Report 05000334/2012006 and 05000412/2012006) IR 05000334/20110012012-03-0505 March 2012 Annual Assessment Letter for Beaver Valley Power Station Units 1 and 2 (Report 05000334-11-001 and 05000412-11-001) ML1124206842011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Beaver Valley Units 1 and 2 IR 05000334/20100012011-03-0404 March 2011 Annual Assessment Letter for Beaver Valley Units 1 and 2, EOC 11 (Report 05000334/2010001 and 05000412/2010001) ML1024406392010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Beaver Valley Units 1 and 2 IR 05000334/20010012010-03-0303 March 2010 Annual Performance Review and Inspection Plan - Beaver Valley Power Station (Beaver Valley) Units 1 and 2 (05000334-01-001 and 05000412-01-001) ML0924401272009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Beaver Valley Units 1 and 2 IR 05000334/20090012009-03-0404 March 2009 Annual Assessment Letter - Beaver Valley Power Station Units 1 and 2 (05000334/2009001 and 05000412/2009001) ML0824704722008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Beaver Valley IR 05000334/20080012008-03-0303 March 2008 (05000334-08-001, 05000412-08-001), Annual Assessment Letter ML0734706972007-12-13013 December 2007 ROP 8 - Beaver Valley - Change to Inspection Plan, 12/13/07 ML0724309412007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan ML0706104772007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Beaver Valley Station ML0624305972006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Beaver Valley Power Station Units 1 and 2 ML0606201582006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Beaver Valley Power Station Units 1 and 2 (Reports 05-334-2006001 and 05-412-2006001) ML0524207222005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Beaver Valley ML0406301322004-03-0202 March 2004 2003-04 Annual Assessment Letter - Beaver Valley ML0323906412003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Beaver Valley Power Station ML0306205872003-03-0303 March 2003 2003 Annual Assessment Letter - Beaver Valley Power Station, Units 1 & 2 IR 05000334/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Beaver Valley Power Station Units 1 & 2 (Report 50-334/02-01, 50-412/02-01) 2023-08-31
[Table view] Category:Letter
MONTHYEARML24025A0922024-01-25025 January 2024 Requalification Program Inspection L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 IR 05000334/20230112023-12-0404 December 2023 Age-Related Degradation Inspection Report 05000334/2023011 and 05000412/2023011 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports IR 05000334/20233012023-11-27027 November 2023 Initial Operator Licensing Examination Report 05000334/2023301 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20230032023-11-0606 November 2023 Integrated Inspection Report 05000334/2023003 and 05000412/2023003 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23198A3592023-10-0202 October 2023 Issuance of Amendment Nos. 322 and 212 Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident (EPID L-2022-LLA-0129) - Nonproprietary IR 05000334/20234022023-09-29029 September 2023 Security Baseline Inspection Report 05000334/2023402 and 05000412/2023402 (Cover Letter Only) ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure IR 05000334/20234012023-09-21021 September 2023 Cybersecurity Inspection Report 05000334/2023401 and 05000412/2023401 (Cover Letter Only) ML23263A0192023-09-20020 September 2023 Operator Licensing Examination Approval ML23243A9272023-09-19019 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23249A1842023-09-18018 September 2023 Authorization and Safety Evaluation for Alternative Request No. 2-TYP-4-RV-06 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000334/20230022023-08-0909 August 2023 Integrated Inspection Report 05000334/2023002 and 05000412/2023002 ML23219A0592023-08-0707 August 2023 Steam Generator Inspection Reports - Spring 2023 Spring Refueling Outrage L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 ML23188A0982023-07-17017 July 2023 Correction to the Safety Evaluation Issued Related to Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time ML23188A0672023-07-10010 July 2023 Project Manager Assignment L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report ML23157A1072023-06-0707 June 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000334/2023011 and 05000412/2023011 ML23143A0272023-05-23023 May 2023 Licensed Operator Positive Fitness-For-Duty Test L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 ML23102A1472023-05-22022 May 2023 Issuance of Amendment Nos. 321 and 211 Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report ML23124A3882023-05-16016 May 2023 Summary of Regulatory Audit in Support of License Amendment Request to Revise Technical Specification 5.6.3, Core Operating Limits Reports (COLR) and TS 4.2.1 Fuel Assemblies ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000334/20230012023-05-0808 May 2023 Integrated Inspection Report 05000334/2023001 and 05000412/2023001 L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations ML23118A3812023-04-28028 April 2023 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML23107A2502023-04-18018 April 2023 Requalification Program Inspection 2024-01-25
[Table view] |
Text
March 3, 2008
SUBJECT:
ANNUAL ASSESSMENT LETTER - BEAVER VALLEY POWER STATION UNITS 1 AND 2 (REPORT 05000334/2008001 AND 05000412/2008001)
Dear Mr. Sena:
On February 12, 2008, the NRC staff completed its performance review of Beaver Valley Power Station, Units 1 and 2. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period January 1 through December 31, 2007. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as Official Use Only-Security Information" will include the security cornerstone review and resultant inspection plan.
Beaver Valley Unit 1 and Unit 2 plant performance for the last two quarters of 2007 was within the Licensee Response column of the NRC Action Matrix based on all inspection findings being classified as very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). No substantive cross cutting issues were identified in any of the three cross cutting areas.
Plant performance for the first two quarters of 2007 was within the Regulatory Response column of the NRC Action Matrix, based on one inspection finding being classified as having low to moderate safety significance (White) in the Emergency Preparedness (EP) Cornerstone due to a dose assessment procedure inadequacy that could have resulted in untimely protective action recommendations. The NRC completed a supplemental inspection in accordance with Inspection Procedure 95001 in June 2007 to review actions taken to address the White EP finding and concluded that FENOC appropriately identified root causes and adequately implemented corrective actions for this issue. As a result, plant performance was restored to the Licensee Response column of the NRC Action Matrix.
Based on current plant performance, we plan to conduct reactor oversight process (ROP)
baseline inspections at Beaver Valley. In addition, we will also conduct inspections related to the completion of the Extended Power Uprate for Unit 2, and inspections related to the Beaver Valley license renewal review. The enclosed inspection plan details the inspections, less those related to physical protection scheduled through June 30, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
In accordance with 10 CFR 2.390 of the NRCs Rules and Practices, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).
The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Dr. Ronald Bellamy at 610-337-5200 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
David C. Lew, Director Division of Reactor Projects Docket Nos. 50-334, 50-412 License Nos. DPR-66, NPF-73 Enclosure: Beaver Valley Power Station, Units 1 and 2 Inspection/ Activity Plan cc w/encl:
J. Hagan, President and Chief Nuclear Officer J. Lash, Senior Vice President of Operations D. Pace, Senior Vice President, Fleet Engineering J. Rinckel, Vice President, Fleet Oversight R. Anderson, Vice President, Nuclear Support, FirstEnergy Nuclear Operating Company D. Jenkins, Attorney, FirstEnergy Corporation G. Halnon, Director, Fleet Regulatory Affairs, FirstEnergy Nuclear Operating Company Manager, Fleet Licensing, FirstEnergy Nuclear Operating Company K. Ostrowski, Director, Site Operations E. Hubley, Director, Maintenance M. Manoleras, Director, Engineering L. Freeland, Director, Site Performance Improvement C. Keller, Manager, Regulatory Compliance M. Clancy, Mayor, Shippingport, PA