IR 05000390/2019011

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Teams) Inspection Report 05000390/2019011 and 05000391/2019011
ML19274C630
Person / Time
Site: Watts Bar  
Issue date: 10/01/2019
From: James Baptist
NRC/RGN-II, Division of Reactor Safety II
To: James Shea
Tennessee Valley Authority
Reeder D
References
IR 2019011
Download: ML19274C630 (23)


Text

October 1, 2019

SUBJECT:

WATTS BAR NUCLEAR PLANT, UNITS 1 AND 2 - DESIGN BASIS ASSURANCE INSPECTION (TEAMS) INSPECTION REPORT 05000390/2019011 AND 05000391/2019011

Dear Mr. Shea:

On August 29, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Watts Bar, Units 1 and 2 and discussed the results of this inspection with Mr. Tom Marshall and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety

Docket Nos. 05000390 and 05000391 License Nos. NPF-90 and NPF-96

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000390 and 05000391

License Numbers:

NPF-90 and NPF-96

Report Numbers:

05000390/2019011 and 05000391/2019011

Enterprise Identifier: I-2019-011-0006

Licensee:

Tennessee Valley Authority

Facility:

Watts Bar, Units 1 and 2

Location:

Spring City, TN

Inspection Dates:

August 12, 2019 to August 29, 2019

Inspectors:

P. Braxton, Reactor Inspector

A. Della Greca, Contractor

N. Morgan, Resident Inspector

R. Patterson, Senior Reactor Inspector

M. Schwieg, Reactor Inspector

W. Sherbin, Contractor

Approved By:

Brian R. Bonser, Chief

Engineering Branch 3

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Watts Bar, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (4 Samples)

(1) Division II 125VDC Power Bus
  • Material condition and configuration (i.e. visual inspection during walkdown)
  • Component modification
  • Component health reports, corrective action history
  • Maximum available fault current
  • DC voltage analysis
  • Breaker coordination
(2) Auxiliary Feedwater Motor-Driven Pump Level Control Valve 2-LCV-3-171 & Auxiliary Feedwater Turbine-Driven Pump Level Control Valve 2-LCV-3-175
  • Material condition and configuration (i.e., visual inspection during walkdown)
  • Maintenance effectiveness
  • Component health reports, corrective maintenance records, and corrective action history
  • Component modifications
  • Surveillance and Inservice testing results
  • Procurement and Design Specifications
(3) Unit 2 6.9 KV Shutdown Board 2A-A [2-BD-211-A-A]
  • Compliance with UFSAR, TS, and TS Bases
  • Conformance with manufacturer instructions for installation, maintenance, and operation
  • Adequacy of corrective action activities
  • Material condition and configuration
  • System Health Reports accurately reflect current system conditions
  • Design requirements (Voltage drop calculations, degraded grid and loss of voltage relays setting, load flow analysis and short circuit calculation, etc.)
  • Setting and coordination of protective relays for selected supply and load breakers
  • Verification that selected relays calibrations meet intended design requirements
  • Design verification of bounding design basis events, including fast bus transfer between offsite power sources and transfer to standby source
  • Verification that TS system surveillance requirements demonstrate performance requirements of system and components
  • Design basis and adequacy of recent modifications
  • Adequacy of instrumentation and operating procedures for system and components performance/operation during normal, abnormal, and accident conditions
(4) Unit 2 Centrifugal Charging Pump CCP-2A
  • Material condition and configuration (e.g., visual inspection during a walkdown)
  • Consistency between station documentation (e.g. procedures) and vendor specifications
  • Operating procedures and Emergency Procedures
  • Training Manual and System Description
  • Maintenance effectiveness
  • Component health reports, corrective maintenance records, and corrective action history
  • Consistency between design bases calculations and test procedure acceptance criteria
  • Surveillance and calibration testing and recent test results
  • Pump room cooler capability versus cooling load
  • Pump horsepower requirements compared to driver motor capability
  • Seismic qualification of pump skid and piping attachments (nozzle loads)

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

(1) Unit 2 Hydrogen Igniters
  • Verification of equipment necessary to provide backup power to the hydrogen igniters is available
  • Rating of the power supply is adequate to continuously power to the hydrogen igniters and operating time is consistent with commitments
  • Verify procedures are established to govern the provision of backup power to the igniters
  • Maintenance and testing schedules for the backup power supply is consistent with the vendor recommendation.
  • Procedure address the decision to provide backup power to the igniters and the steps required to provide the backup power to the hydrogen igniters
(2) Unit 2 6.9 KV to 480 V Transformer 2A1-A Including Supply and Load Breakers
  • Compliance with UFSAR, TS, and TS Bases
  • Conformance with manufacturer instructions for installation, maintenance, and operation
  • Adequacy of corrective action activities
  • Material condition and configuration
  • Verification that System Health Reports accurately reflect current system conditions
  • Design requirements (Rating, normal and accident loading, tap setting, etc.)
  • Adequacy of supply and load cables
  • Seismic qualification of transformer and supply and load shutdown boards
  • Setting of upstream protective relays and coordination with downstream breaker
  • Verification that protective relays calibrations and breakers maintenance and testing meet intended design requirements

Modification Review - Permanent Mods (IP Section 02.03) (6 Samples)

(1) DCN 58314, Replace Unit 1 Turbine Driven Auxiliary Feed-water (TDAFW) Governor Valve Controller with Digital Controller
(2) DCN 59007, Replace 1-PCV-003-0122 & -0132 with a Cavitating Venturi
(3) DCN 60696, Replace Pressurizer Power Operated Relief Valves (PORVs) Due to Current Valves Being Obsolete
(4) DCN 66471, Modify Solid-state Protection System (SSPS) Turbine Trip on Low Fluid Oil Pressure
(5) DCN 66592, Raise TDAFW DC Exhaust Fan Set-points
(6) DCN 553785, Swapping Power Sources to Eliminate Loss of Power to Two Pumps When One EDG is Not Available

Review of Operating Experience Issues (IP Section 02.06) (3 Samples)

(1) GL 90-06, Resolution of Generic Issues 70, "PORV and Block Valve Reliability," and 94, "Additional LTOP Protection for PWRs"
(2) IN 2010-10, Implementation of a Digital Control System Under 10 CFR 50.59
(3) NRC IN 86-14, PORV and Block Valve Reliability

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 29, 2019, the inspectors presented the design basis assurance inspection (teams) inspection results to Mr. Tom Marshall and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

CEBCAS228

Nozzle Load Qualification for the CCPs

Rev. 3

E31920409300

Shutdown Boards Degraded Voltage Relay Settings

Rev. 1

EDQ00099920070002

AC Auxiliary Power System Analysis

Rev. 067

EDQ00099920080014

Diesel Generator Loading Analysis

Rev. 35

EDQ00299920080016

6.9 KV Protection and Coordination Calculation

Rev. 12

EPMDLB061193

Adequacy of ERCW Flow to Centrifugal Charging

Pumps 1A-A and 2A-A Oil Coolers

Rev. 5

EPMHV0701889

Maximum Brake Horsepower for Centrifugal

Charging Pumps

Rev. 5

EPMPKB012191

HVAC Cooling Load and Room Temperature Calc:

TDAFW Pump Room

Rev. 11

EPMSHC102789

Main Steam Over Pressure Protection Design

Rev. 0

EPMSNM043092

Failure Modes and Effects Analysis for the SI

System

Rev. 0

EPMTEC081689

Cooling Load for CCP Room Aux Building Elevation

2-A9 and A10 Under LOCA Conditions

Rev. 5

N36232A

Summary of Piping Analysis

Rev. 9

R03521E31920108300

Shutdown Board 1A-A Feeders to 6900/480V

Transformers 1A1-A, 1A2-A, and 1A-A

Rev.0

TDRSYS.211-DS1

Demonstrated Accuracy Calculation

Rev. 6

WBNEEBEDQ1999010001 AC Auxiliary Power System Analysis

Rev. 96

WBNEEBMST1060029

Degraded Voltage Analysis

Rev.38

WBNEEBMST1080008

480V 1E Coordination/Protection

Rev. 174

WBNOSG4071

RWST and Containment Sump Safety Limits

Rev. 27

WBPE2119202001

6.9KV Shutdown & Logic Boards Undervoltage

Relays Requirement/ Demonstrated Accuracy

Calculation

Rev. 12

Calibration

Certificate of Calibration for NWS-T-139 & NWS-R-

04/13/19

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Records

Corrective Action

Documents

1158981

1177342

1177660

1181488

1197406

1198767

201099

201726

206585

209629

212101

284810

296987

1359596

1370572

1380308

1381120

1398457

1414582

1419624

26714

1436407

1447534

1447766

1456434

1464817

1472485

1483042

1498200

22586

22957

25931

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

480993

934675

940480

Corrective Action

Documents

Resulting from

Inspection

1540525

2A CCP Oil Leak

1540541

Calculation References Not Updated

1540660

Multiple Fluorescent Lights in Need Repair

1540819

Missed 50.59 Evaluation on Scaffold Installed

Greater Than 90 Days

1542830

2019 Revised Heat loads Missing From Calculation

1542844

0-TI-79.000 Requires Update for frequency

1544436

Revise Calculation WBNEEBMST1060029

Drawings

0-15E500-1

Key Diagram, Aux. Power Station

Rev. 8

0-15E500-2

Key Diagram, Aux. Power Station

Rev. 0

0-15E500-2

Key Diagram Station Aux Power System

Rev. 0

0-15E500-3

Transformer Taps & Voltage Limits, Aux Power

System

Rev. 3

0-45W760211-4

Wiring Diagram, 6900V Shutdown Power Schematic

Diagram,

Rev.0

0-47W866-8

Heating Cooling and Ventilating Air Flow Flow

Diagram

Rev. 1

1-45W600-47-1

Wiring Diagram Turbo-Generator Auxiliaries

Schematic Diagrams

Rev. 13

1-47W610-47-1

Electrical Control Diagram Turbo Generator Cont

Sys

Rev. 40

1-47W611-99-6

Electrical Logic Diagram Reactor Protection System

Rev. 4

2-45W724-3

Wiring Diagrams, 6900V Shutdown Board 2A-A

Single Line

Rev. 18

2-45W724-4

Wiring Diagrams, 6900V Shutdown Board 2B-B

Single Line

Rev. 19

2-45W749-1

Wiring Diagrams, 480V Shutdown Board 2A1-A

Single Line

Rev. 17

2-45W749-2

Wiring Diagrams, 480V Shutdown Board 2A2-A

Single Line

Rev. 14

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-45W749-3

Wiring Diagrams, 480V Shutdown Board 2B1-B

Single Line

Rev. 15

2-45W749-4

Wiring Diagrams, 480V Shutdown Board 2B2-B

Single Line

Rev. 24

2-45W760-211-1

, Wiring Diagram, 6900V Shutdown Power

Schematic Diagram

Rev. 3

2-45W760-211-12

Wiring Diagram, 6900 V Shutdown Power 2A-A

Schematic Diagrams

Rev. 2

2-45W760-211-13

Wiring Diagram, 6900 V Shutdown Power 2A-A

Schematic Diagrams

Rev. 3

2-45W760-211-16

Wiring Diagram, 6900 V Shutdown Power Diesel

Loading Logic

Rev. 1

2-45W760-211-17

Wiring Diagram, 6900 V Shutdown Power -Train A

And B Schematic Diagram,

Rev. 3

2-45W760-211-18

Wiring Diagram, 6900 V Shutdown Power Schematic

Diagram

Rev. 4

2-45W760-211-2

Wiring Diagram, 6900V Shutdown Power Schematic

Diagram

Rev. 1

2-45W760-211-3

Wiring Diagram, 6900V Shutdown Power Schematic

Diagram

Rev. 2

2-45W760-211-5

Wiring Diagram, 6900 V Shutdown Power Schematic

Diagram

Rev. 1

2-45W760-211-6

Wiring Diagram, 6900V Shutdown Power Train A

Schematic Diagram

Rev. 1

2-45W760-212-1

Wiring Diagram, 480V Shutdown Power Schematic

Diagrams

Rev. 1

2-45W760-212-2

Wiring Diagram, 480V Shutdown Power Schematic

Diagrams

Rev. 1

2-45W760-268-1

Unit 2 Wiring Diagram Permanent Hydrogen

Mitigation System Schematic Diagrams

Rev. 4

2-45W760-63-1

Wiring Diagram, Safety Injection System Schematic

Diagram

Rev. 9

2-47W809-1

Flow Diagram CVCS

Rev. 46

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-47W810-1

Flow Diagram, RHR System

Rev. 26

2-47W811-1

Flow Diagram, Safety Injection System

Rev. 54

45N1612-2

Turbine Instrumentation & Auxiliaries Connection

Diagrams Wiring Diagram -Sheet 2

Rev. 8

8002577-1-1

Unit 1 Schematic Diagram Turbine Driven AFW

Governor

Rev. 0

2UU-001-12BB

Rev. J

CNL-15-088

TVA Letter to NRC, Watts Bar Nuclear Plant Unit 1 -

Application to Revise Technical Specification for

Component Cooling Water and Essential Raw

Cooling Water to Support Dual Unit Operation (TS-

WBN-15-13)

06/17/15

WBN 1190E37

Safety Injection System Process Flow Diagram

Rev. 6

Engineering

Changes

53785

Swap Power and Control Cables for ERCW Pumps

B-A and C-A (Train A) and F-B & G-B (Train

B), Rev. A

2/25/16

64063

Install Open Phase Protection Relays

Rev.A

66471

Modify SSPS Turbine Trip on Low Fluid Oil Pressure

Function To a Trip on Lox Electrohydraulic Control

(EHC ) Oil Pressure

Rev. 1

M-08672-A

Polychlorinated Byphenyls Risk Reduction for

Transformers

03/37/92

Engineering

Evaluations

1-Sl-3-923-S

Auxiliary Feedwater Pump 1A-S Comprehensive

Pump Test

Rev. 18

EDQ00023620070003

26V DC VITAL BATTERY SYSTEM ANALYSIS

Rev. 42

EDQ0010462016000789

Demonstrated Accuracy for TDAFW Time Delay

Relays

Rev. 2

EL-20916

EGSCS MARSH Qualification Report

Rev. A

EPMJAF112091

Failure Modes and Effects Analysis for the Auxiliary

Feedwater System

Rev. 12

Miscellaneous

LTOP White Paper Response

08/29/19

Watts Bar Letter that Revises A Commitment in

10/26/95

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

TVA's response to GL 90-06

Watts Bar Generic Letter 90-06 Clarification of

Commitment Letter for Testing Pressurizer Power

Operated Relief Valves

2/22/98

Watts Bar Changes to Power Operated Relief Valve

Surveillance Testing Commitment

03/01/99

480V Quarterly System Walkdown Results, 1/15/15-

06/27/19

01/15/15

CCP-2A Oil Sample Trending Analysis, 09/20/2011

to 04/22/2019

Letter from

R. Gridley, TVA to USNRC, Subject:

TVAs Response to NRC Bulletin 88-04, Potential

Safety Related Pump Loss

2/27/1989

Westinghouse Letter number LTR-SEE-IV-10-25,

ECCS Analysis Report

04/28/2016

CVCS System Health Report, April 2019

Site Engineering Setpoint And Scaling Document

Loop Number1-T-1-17A, AFW Turbine Pump Room

Temperature Detector

Rev. 2

Minimum Flows for Safety Related Pumps in Nuclear

Service

09/23/88

Watts Bar Response Letter to GL 90-06

2/21/90

0-TI-100.011

In-service Testing Program

Rev. 1

0-TI-79.000

Program for Implementing NRC Generic Letter 89-13 Rev. 5

2010

Magnetic Pickups (MPUs)

Rev. C

1-47A630-46-1

TDAFW Governor Configuration

Rev. 1

2-SI-211-1-A

Month 6.9 KV Shutdown Board 2A-A Automatic

and Manual Transfer Tests

04/21/19

2-SI-211-3-A

Month System Functional Rest on 6900V SD BD

2A-A Degraded Voltage and Undervoltage Relays

06/24/17

2-SI-211-3-A

Month System Functional Rest on 6900V SD BD

2A-A Degraded Voltage and

Undervoltage Relays

04/21/19

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-SI-211-4-A

Day Trip Actuating Device Operational Test of UV

Relays for 2A-A 6,9 KV Shutdown Board

03/20/19

2-SI-211-4-A

Day Trip Actuating Device Operational Test of UV

Relays for 2A-A 6,9 KV

Shutdown Board

06/18/19

2-SI-211-4-A

Day Trip Actuating Device Operational Test of UV

Relays for 2A-A 6,9 KV Shutdown Board

06/18/19

2-SI-211-5-A

Channel Calibration Test on Degraded Voltage

Relays for 6.9KV Shutdown Board 2A-A

09/07/18

2-SI-211-5-A

Channel Calibration Test on Degraded Voltage

Relays for 6.9KV Shutdown Board 2A-A

03/20/19

2-SI-211-6-A

Channel Calibration Test on Loss of Voltage Relays

for 6.9KV Shutdown Board 2A-A

03/19/18

2-SI-211-6-A

Channel Calibration Test on Loss of Voltage Relays

for 6.9KV Shutdown Board 2A-A

09/07/19

2-SI-211-7-A

Channel Calibration Test on Load Shed and Diesel

Start Undervoltage Relays for

6.9KV Shutdown Board 2A-A

09/07/18

2-SI-211-7-A

Channel Calibration Test on Load Shed and Diesel

Start Undervoltage Relays for 6.9KV Shutdown

Board 2A-A

03/20/19

2-SI-211-8-A

Channel Calibration Test on Degraded Voltage and

Loss of Voltage Timing

Relays for 6.9KV Shutdown Board 2A-A

06/24/17

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-SI-211-8-A

Channel Calibration Test on Degraded Voltage and

Loss of Voltage Timing Relays for 6.9KV Shutdown

Board 2A-A

04/21/19

2-SI-262-1A

Unit 2 Train A Auto Start Lockout Test

11/18/17

2-SI-262-1A

Unit 2 Train A Auto Start Lockout Test

04/24/19

280-RLCU00079-01

Bechtel Power Corporation Test Report, 2.5 RLIJ 11

Stages Pump Serial No. 48592

2/18/11

8002577-01

Qualification Report For Electronic Governor Speed

Control System (EGSCS)

Rev. 0

8002577-PTR-1

Panel Temperature Rise Test Procedure

Rev. 3

8002577-TR-1

Test Report For Turbine Control System

Rev. 0

CNL-15-147

TVA Letter to NRC, Responses to NRC Acceptance

Review Questions for Watts Bar Nuclear Plant Unit 1

Essential Raw Cooling Water and Component

Cooling System License Amendment Request (TAC

No. MF 6376)

07/14/15

CNL-15-153

TVA Letter to NRC, Watts Bar Nuclear Plant Unit 1 -

Response to Request for Additional Information

Relate to Application to Revise Technical

Specifications for Component Cooling Water and

Essential Raw Cooling Water to Support Dual Unit

Operation (TAC No. MF6376)

08/03/15

CNL-15-170

TVA Letter to NRC, Watts Bar Nuclear Plant Unit 1 -

Responses to NRC Questions for Watts Bae Nuclear

Plant Unit 1Request for Essential Raw Cooling

Water and Component Cooling Water System

License Amendment Request

08/28/15

CNL-15-181

TVA Letter to NRC, Revisions to Watts Bar Nuclear

09/03/15

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Plant Unit 1 Essential Raw Cooling Water and

Component Cooling System License Amendment

Request, Including Proposed Changes to Auxiliary

Feedwater Pump Suction Transfer Instrumentation

and Reactor Coolant System Loops - Mode 4

EL-21049

Commercial Grade Dedication Report For The

INTROL Positioner PIN 890265-010

Rev. 0

LTR-SCS-15-31

Watts Bar Unit 1 PORV Replacement - Cold

Overpressure Mitigation System (COMS) Setpoint

Analysis

01/04/17

PER 265331

Testing Program for Small Oil Filled Transformers

2010

Report No. 9390

PORV Flow Data Analysis Model 82UU-001-12BB

Rev. A

SDD-N3-30AB-4001

Auxiliary Building Heating, Ventilation, Air

Conditioning System (30, 31, 44) Unit 1/Unit 2 QA

Record

Rev. 45

SDD-N3-32-4002

Compressed Air System

Rev. 15

SDD-N3-3B-4002

AUXILIARY FEEDWATER SYSTEM

Rev. 28

SDD-N3-62-4001

Chemical and Volume Control System System

Description

Rev. 39

SDD-N3-68-4001

Reactor Coolant System

Rev. 41

SECL-94-066

Main Steam Safety Valve and Pressurizer Safety

Valve Setpoint Tolerance Increase form +/- 1% to +/-

3% Safety Evaluation

2/27/94

System Health Report

Summary

6.9 KV Medium Voltage Switchgear

10/11/18

System Health Report

Summary

6.9 KV Medium Voltage Switchgear

05/29/19

System Health Report

Summary

480V Load Centers

10/20/17

System Health Report

Summary

480V Load Centers

09/18/18

System Health Report

480V Load Centers

04/01/19

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Summary

TAC No.MF6376

NRC Letter to TVA, Watts Bar Nuclear Plant Unit 1 -

Issuance of Amendment Regarding Application to

Revise Technical Specifications for Component

Cooling Water and Essential Raw Cooling Water to

Support Dual Unit Operation

10/20/15

WB-DC-30-28

Low and Medium Voltage Power Systems, Unit

1/Unit 2

Rev. 22

WBN EEB-MS-T109-0041

Appendix D, Summary of Heat Generated in Each

Room

2/25/10

WBN PM 1-PIPE-067-C

Flushing of ERCW Emergency Makeup Supply To

CCP 1A Oil Coolers

Rev. 8

WBN-VTD-GE27-0010

Vendor Manual GE Digital Energy Multilin 735 / 737

Feeder Protection Relay Instruction Manual

WBN-VTD-MT02-0040

Vendor Manual: MTU Onsite Energy Model # 3250-

XC6DT2

SERIAL NUMBERS: 350800-1-1-0113 & 350800-1-

2-0113

WBN-VTD-P025-0040

Pacific Pumps IJ Operating and Maintenance

Instructions

Rev. 7

WBN-VTD-T020-0550

Target Rock Technical Manual for PORV Model

2UU-001-12BB

Rev. D

WBN-VTD-W120-2352

Instructions for Westinghouse Rectangular Core and

Coil Assembly Type SL Transformers

Rev.0

WBN-VTD-W120-2358

Instructions for Westinghouse Self-Cooled

Transformers

Rev.0

WBN-VTD-W120-2624

Technical Bulletin for Pacific Centrifugal

Charging/Safety Injection Pumps

Rev.0

WBNEE8SWW0011

Turbine Driven Auxiliary Feedwater Dedication,

Qualification, and Software Verification & Validation

Rev. 1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documentation

WBNP-DS-1830-5402-

R005

Certification Design Specification for 1,2-PCV-068-

0334-B & -0340A-A

09/16/14

WBT-D-5655

Westinghouse, Watts Bar Nuclear Plant, Unit 2,

Updated ECCS Analysis Report for Flow Test Data

Rev. 4

WCG-ACQ-0419

Seismic Qualification of 6.9 KV SD BD

Rev. 2

WCG-ACQ-0421

Seismic Qualification of 6900 V Shutdown Boards for

Added Components and Attached Conduits

Rev. 8

WCG-ACQ-0424

Seismic Qualification of 6900 V Shutdown Boards

Logic Panels

Rev. 6

WCG-ACQ-0460

Equipment Seismic Evaluation of 480V Shutdown

Board Transformers

Rev. 0

Operability

Evaluations

CR1372641

Prompt determination of operability documentation

Rev. 0

Procedures

0-FSI-5.01

Initial Assessment and FLEX Equipment Staging

Rev. 8

0-FSI-5.02

6900V FLEX DG Startup and Alignment

Rev. 2

0-FSI-5.03

6.9kV & 480V Shutdown Board Initial FLEX

Alignment

Rev.0

0-FSI-5.04

6900V FLEX DG Plant Equipment Loading

Rev. 05

0-FSI-7

Loss of Vital Instrumentation or Control Power

Rev. 3

0-MI-57.027

Initial Testing of Molded Case Circuit Breakers

Rev.0

0-MI-57.200

480 Volt Switchgear Inspection

Rev. 2

0-SI-82-3

Month Loss of Offsite Power With Safety Injection

- DG 1A-A

Rev. 68

0-SI-82-5

Month Loss of Offsite Power With Safety Injection

- DG 2A-A

Rev.43

0-SI-82-5

Month Loss of Offsite Power With Safety Injection

- DG 2A-A

Rev.47

0-SOI-211.03

System Operating Instructions, 6.9KV Shutdown

Board 2A-A,

Rev.5

0-SOI-212.05

System Operating Instructions, 480V Shutdown

Rev. 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Board 2A1-A

1-AOI-16

Loss of Normal Feedwater

Rev. 8

1-AOI-25.03

Loss of 120V AC Vital Instrument Power Boards 1-III

or 2-III

Rev. 5

1-ARI-57-63

Feedwater & Main Steam

Rev. 3

1-SI--68-904-A

Reactor Coolant System Valve Position Indication

Verification

10/10/18

2-ARI-8-14

Unit 2 Annunciator Response Instructions, Aux

Power

Rev. 1

2-E-0

Reactor Trip Or Safety Injection

Rev. 8

2-ECA-0.0

Loss of Shutdown Power

Rev. 02

2-ES-1.3

Transfer To Containment Sump

Rev. 4

2-SI-211-1-A

Month 6.9 KV Shutdown Board 2A-A Automatic

and Manual Transfer Tests

Rev. 2

2-SI-3-19

Month Channel Calibration of Steam Generator 4

Turbine Driven AFW Level Control Loop 2-LPL-3-

175

Rev. 8

2-SI-3-63

Month Channel Calibration of Steam Generator 4

Auxiliary Feedwater Level Control Loop 2-LPL-3-171

Rev. 9

2-SI-3-903-B

Valve Full Stroke Exercising During Plant Operation

Auxiliary Feedwater (Train B)

Rev. 9

2-SI-3-908

Valve Full Stroke Exercising During Plant Operation

Turbine Driven Auxiliary Feedwater

Rev. 5

2-SI-3-920

Valve Position Indication Verification Auxiliary

Feedwater System Turbine Driven AFW Train

Rev. 8

2-SI-62-901-A

Pump CCP 2A-A, Quarterly Performance Test

Rev. 1

2-SI-62-916-A

Pump CCP2A-A Pre-service Test During Refueling

Outages

Rev. 4

2-SOI-268.01

Permanent Hydrogen Mitigation System

Rev.1

2-SOI-62.01

CVCS Charging and Letdown

Rev. 20

600112315

Preventive Maintenance Work Instructions, 480V

Shutdown Board 2A1-A Relay Calibration Tests

Rev.3

600114255-A

Preventive Maintenance Preplanned Text, Protective

Rev.3A

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Relay Operability

BTI-EEB-TI-28

Setpoint Calculations

Rev.11

NPG-SPP-09.3

Plant Modification and Engineering Chane Control

Rev.30

NPG-SPP-12.8

Nuclear Cyber Security Program

Rev. 4

NWS-T-139

NWS Technologies Test Procedure for TVA - Watts

Bar Nuclear Plant, Target Rock Power Operated

Relief Valves (PORV)

Rev. 1

Self-

Assessments

2019 DBAI Self-Assessment Report

Rev.1

Work Orders

113197994

114522319

114522416

114559272

115972327

115972382

117199468

117351335

117761841

117761842

117823686

1178236913693

117828086645

118086653

118134438

118152988

118191476

118439102

118526808

118681437

118801173

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

118801174

118968515

119001477

119001486

119064791

119065107

119065109

119065476

119080284

119174352

119205642

119281674

119297603

119297605

119301437

119307555

119347104

119347106

119381172

119381222

119430432

119440457

119440469

119518459

119526793

119526805

119526810

119527434

119570164

119570240

119582577

119719602

119837841

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

119837862

119837865

119837866

119896530

119897039

119897107

119903710

119903859

20055311

20355623

19347105