IR 05000352/2024006
| ML25070A009 | |
| Person / Time | |
|---|---|
| Site: | Limerick |
| Issue date: | 03/11/2025 |
| From: | Sarah Elkhiamy Division of Operating Reactors |
| To: | Rhoades D Constellation Energy Generation, Constellation Nuclear |
| References | |
| IR 2024006 | |
| Download: ML25070A009 (1) | |
Text
March 11, 2025
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR LIMERICK GENERATING STATION,
UNITS 1 AND 2 (REPORTS 05000352/2024006 AND 05000353/2024006)
Dear David Rhoades:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Limerick Generating Station (Limerick), Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2024, through December 31, 2024. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at Limerick, Units 1 and 2, during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2026.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In addition to baseline inspections, the NRC plans to conduct Inspection Procedure 37060, 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Inspection, at your facility. The NRC will also be performinganinspection ofyour modification of instrumentation and control systems to digitalin accordance with Inspection Procedure 52003, Digital Instrumentation and Control Modification Inspection.Thespecific schedule to be used for thisinspection is being developed by NRC staffto coincide with specific milestonesand activitiesin your project plan. NRC staff willcommunicate the specific schedulewithyouas it is identified.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 610-337-6916 with any questions you have regarding this letter.
Sincerely, Sarah H. Elkhiamy, Chief Projects Branch 4 Division of Operating Reactor Safety
Docket Nos. 05000352 and 05000353 License Nos. NPF-39 and NPF-85
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
SARAH ELKHIAMY Digitally signed by SARAH ELKHIAMY Date: 2025.03.11 11:07:24 -04'00'
SUNSI Review
X Non-Sensitive Sensitive
X Publicly Available Non-Publicly Available
OFFICE RI/DORS RI/DORS
NAME SHaney SElkhiamy
DATE 3/10/2025 3/10/2025
Site Inspection Activity Plan Limerick 01/01/2025 - 12/31/2026 Unit Start End Activity CAC Title Staff Count Comprehensive Engineering Team Inspection - Limerick
1,2 1/13/2025 1/17/2025 IP 71111.21M 000713 Comprehensive Engineering Team Inspection 1,2 1/27/2025 1/31/2025 IP 71111.21M 000713 Comprehensive Engineering Team Inspection 10 CFR 50.69 - Risk Informed SSC Implementation - Limerick
1,2 3/24/2025 3/28/2025 IP 37060 000521 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems, and Components Inspection Q2 2025 Integrated Inspection - LIM
1,2 4/1/2025 6/30/2025 IP 71151 000746 Performance Indicator Verification Inservice Inspection - Limerick Unit 2
2 5/5/2025 5/9/2025 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
RP-71124.01 Rad Hazards
2 5/12/2025 5/16/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls RP - 71124.05 Rad. Instrumentation
1,2 8/18/2025 8/22/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation RP - 71124.07 REMP
1,2 9/22/2025 9/26/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program Access Control, Protective Strategy, TSR, SPR, PIs - LIM
1,2 10/14/2025 10/17/2025 IP 71130.02 000734 Access Control 1,2 10/14/2025 10/17/2025 IP 71130.05 000737 Protective Strategy Evaluation 1,2 10/14/2025 10/17/2025 IP 71130.09 001656 Security Plan Changes 1,2 10/14/2025 10/17/2025 IP 71130.14 000743 Review of Power Reactor Target Sets 1,2 10/14/2025 10/17/2025 IP 71151 001338 Performance Indicator Verification Material Control and Accounting - Limerick
1,2 10/27/2025 10/31/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)
Limerick Requal Inspection with P/F Results
1,2 11/3/2025 11/7/2025 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 1,2 11/3/2025 11/7/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP-71151 PIV
1,2 11/10/2025 11/14/2025 IP 71151 001397 Performance Indicator Verification EP Exercise Inspection - Limerick
1,2 11/17/2025 11/21/2025 IP 71114.01 000716 Exercise Evaluation 1,2 11/17/2025 11/21/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Prepared on 2/4/2025 5:23:23 PM 1 of 3
Site Inspection Activity Plan 1,2 11/17/2025 11/21/2025 IP 71151 001397 Performance Indicator Verification Cyber Security - Limerick
1,2 12/8/2025 12/12/2025 IP 71130.10 000741 Cybersecurity Sec - AA, FFD - Lim
1,2 1/12/2026 1/16/2026 IP 71130.01 000733 Access Authorization 1,2 1/12/2026 1/16/2026 IP 71130.08 000740 Fitness-For-Duty Program 1,2 2/23/2026 2/27/2026 IP 71130.01 000733 Access Authorization 1,2 2/23/2026 2/27/2026 IP 71130.08 000740 Fitness-For-Duty Program 2026 Limerick Initial License Operator Exam
1,2 2/2/2026 2/6/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
1,2 3/2/2026 3/6/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
EP Program Inspection - Limerick
1,2 3/9/2026 3/13/2026 IP 71114.02 000717 Alert and Notification System Testing 1,2 3/9/2026 3/13/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 3/9/2026 3/13/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 3/9/2026 3/13/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 3/9/2026 3/13/2026 IP 71151 001397 Performance Indicator Verification Inservice Inspection - Limerick Unit 1
1 4/27/2026 5/1/2026 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
1 5/4/2026 5/8/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls RP - 71124.03 Resp. Protection and 71124.04 Occupational Dose
1,2 6/1/2026 6/5/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 6/1/2026 6/5/2026 IP 71124.04 000728 Occupational Dose Assessment Fire Protection - Limerick
1,2 9/21/2026 9/25/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
1,2 10/5/2026 10/9/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
1,2 10/5/2026 10/9/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Sec - Access Control, Protective Strategy, TSR, SPR, PIs - Lim
1,2 10/19/2026 10/23/2026 IP 71130.02 000734 Access Control 1,2 10/19/2026 10/23/2026 IP 71130.05 000737 Protective Strategy Evaluation 1,2 10/19/2026 10/23/2026 IP 71130.09 001656 Security Plan Changes 1,2 10/19/2026 10/23/2026 IP 71130.14 000743 Review of Power Reactor Target Sets 1,2 10/19/2026 10/23/2026 IP 71151 001338 Performance Indicator Verification PI&R Biennial Team Inspection - Limerick
Prepared on 2/4/2025 5:23:23 PM 2 of 3
Site Inspection Activity Plan 1,2 11/2/2026 11/6/2026 IP 71152B 000747 Problem Identification and Resolution 1,2 11/16/2026 11/20/2026 IP 71152B 000747 Problem Identification and Resolution RP - 71151 PIV
1,2 11/16/2026 11/18/2026 IP 71151 000746 Performance Indicator Verification Prepared on 2/4/2025 5:23:23 PM 3 of 3