IR 05000348/2011011

From kanterella
Jump to navigation Jump to search
NRC Temporary Instruction 2515/183 Inspection Report 05000348/2011011 and 05000364/2011011
ML111330097
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 05/13/2011
From: Scott Shaeffer
NRC/RGN-II/DRP/RPB2
To: Stinson L
Southern Nuclear Operating Co
References
IR-11-011
Download: ML111330097 (20)


Text

UNITED STATES May 13, 2011

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT - NRC TEMPORARY INSTRUCTION 2515/183 INSPECTION REPORT 05000348/2011011 AND 05000364/2011011

Dear Mr. Stinson:

On April 29, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Joseph M. Farley Nuclear Plant, Units 1 and 2, using Temporary Instruction 2515/183, Follow-up to the Fukushima Daiichi Nuclear Station Fuel Damage Event. The enclosed inspection report documents the inspection results which were discussed on May 5, 2011, with you and other members of your staff.

The objective of this inspection was to promptly assess the capabilities of Joseph M. Farley Nuclear Plant, Units 1 and 2, to respond to extraordinary consequences similar to those that have recently occurred at the Japanese Fukushima Daiichi Nuclear Station. The results from this inspection, along with the results from this inspection performed at other operating commercial nuclear plants in the United States will be used to evaluate the U.S. nuclear industrys readiness to safely respond to similar events. These results will also help the NRC to determine if additional regulatory actions are warranted.

All of the potential issues and observations identified by this inspection are contained in this report. The NRCs Reactor Oversight Process will further evaluate any issues to determine if they are regulatory findings or violations. Any resulting findings or violations will be documented by the NRC in a separate report. You are not required to respond to this letter.

SNC 2 In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket No.: 50-348, 50-364 License No.: NPF-2, NPF-8

Enclosure:

Inspection Report 05000348/2011011 and 05000364/20110011 w/Attachment: Supplemental Information

REGION II==

Docket Nos.: 05000348, 05000364 License Nos.: NPF-2, NPF-8 Report No.: 05000348/2011011 and 05000364/2011011 Licensee: Southern Nuclear Operating Company, Inc.

Facility: Joseph M. Farley Nuclear Plant, Units 1 and 2 Location: Columbia, AL Dates: April 4, 2011 through April 29, 2011 Inspectors: E. Crowe, Senior Resident Inspector Approved by: Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects Enclosure

SUMMARY OF FINDINGS

IR 05000348/2011011, 05000364/2011011; 04/04/2011 - 04/29/2011, Joseph M. Farley

Nuclear Plant, Units 1 and 2, Temporary Instruction 2515/183 - Follow-up to the Fukushima Daiichi Nuclear Station Fuel Damage Event.

This report covers an announced Temporary Instruction inspection. The inspection was conducted a senior resident inspector. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

INSPECTION SCOPE

The intent of the TI is to provide a broad overview of the industrys preparedness for events that may exceed the current design basis for a plant. The focus of the TI was on

(1) assessing the licensees capability to mitigate consequences from large fires or explosions on site, (2)assessing the licensees capability to mitigate station blackout (SBO) conditions,
(3) assessing the licensees capability to mitigate internal and external flooding events accounted for by the stations design, and
(4) assessing the thoroughness of the licensees walk downs and inspections of important equipment needed to mitigate fire and flood events to identify the potential that the equipments function could be lost during seismic events possible for the site.

If necessary, a more specific follow-up inspection will be performed at a later date.

INSPECTION RESULTS

All of the potential issues and observations identified by this inspection are contained in this report. The NRCs Reactor Oversight Process will further evaluate any issues to determine if they are regulatory findings or violations. Any resulting findings or violations will be documented by the NRC in a separate report.

INSPECTION RESULTS

The following table documents the NRC inspection at Joseph M. Farley Nuclear Plant, Units 1 and 2, performed in accordance with TI 2515/183. The numbering system in the table corresponds to the inspection items in the TI.

03.01 Assess the licensees capability to mitigate conditions that result from beyond design basis events, typically bounded by security threats, committed to as part of NRC Security Order Section B.5.b issued February 25, 2002, and severe accident management guidelines and as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.54(hh). Use Inspection Procedure (IP) 71111.05T, Fire Protection (Triennial), Section 02.03 and 03.03 as a guideline. If IP 71111.05T was recently performed at the facility the inspector should review the inspection results and findings to identify any other potential areas of inspection. Particular emphasis should be placed on strategies related to the spent fuel pool. The inspection should include, but not be limited to, an assessment of any licensee actions to:

Licensee Action Describe what the licensee did to test or inspect equipment.

Licensee personnel completed testing and inspections of equipment associated with Severe a. Verify through test or inspection Accident Management Guidelines (SAMGs), Emergency Planning procedures, and that equipment is available and Abnormal Operating procedures related to the scope of this report item to confirm readiness functional. Active equipment to execute the procedures. Three active pieces of equipment exist for these strategies.

shall be tested and passive One piece is permanently installed and tested per the licensees planned maintenance equipment shall be walked down program. The other two active pieces of equipment were operated to verify readiness. The and inspected. It is not licensee performed an inventory of all passive equipment utilized in these strategies. The expected that permanently licensee completed a review and walk down of SAMGs, Emergency Planning procedures installed equipment that is and Abnormal Operating procedures related to the scope of this report item to confirm tested under an existing readiness to execute the procedures.

regulatory testing program be Describe inspector actions taken to confirm equipment readiness (e.g., observed a test, retested.

reviewed test results, discussed actions, reviewed records, etc.).

The inspectors reviewed the licensees report documenting the completion of the above This review should be done for a activities. The inspectors also scanned the above procedures to gain understanding of the reasonable sample of mitigating strategies and to identify potential equipment for sampling its readiness. The inspectors strategies/equipment.

interviewed station personnel involved in the walk downs and testing of equipment. The inspectors also visually inspected passive equipment to evaluate its condition and readiness for use. The inspectors reviewed all condition reports written by the licensee related to this verification. The inspectors reviewed planned licensee actions.

Discuss general results including corrective actions by licensee.

The licensee discovered a small number of discrepancies which were entered into the licensees corrective action program (i.e air line tubing leak on the emergency air compressor; clamp on style of flow meter non-functional, equipment labeling issues). The licensee recognized some enhancements which would make equipment and procedures more functional. These items were also captured in the licensee corrective action program.

Describe the licensees actions to verify that procedures are in place and can be executed Licensee Action (e.g. walkdowns, demonstrations, tests, etc.)

Senior operations personnel reviewed station procedures utilized in these strategies and b. Verify through walkdowns or performed walk downs to confirm the readiness to execute the procedures. Operations demonstration that procedures personnel walked down procedures to verify equipment connections could be properly made to implement the strategies with equipment provided.

associated with B.5.b and 10 CFR 50.54(hh) are in place and Describe inspector actions and the sample strategies reviewed. Assess whether are executable. Licensees may procedures were in place and could be used as intended.

choose not to connect or The inspectors reviewed each of the station procedures identified by the above senior operate permanently installed operations personnel. The review included an evaluation of the planned strategies and how equipment during this well the strategy encompassed potential events. The review also included an evaluation of verification.

the thoroughness of each procedure and potential for actions of one procedure to preclude implementation of another procedure. Additionally, the inspectors reviewed licensee This review should be done for a procedures/strategies for addressing spent fuel pool emergencies. The inspectors reviewed reasonable sample of mitigating all condition reports written by the licensee related to this verification. The inspectors strategies/equipment.

reviewed planned licensee actions.

Discuss general results including corrective actions by licensee.

The licensee identified procedural enhancements which mainly encompassed procedure quality. The majority of the enhancements emphasized increased detail to provide the user with high quality information. The more notable issues included proper alignment of the portable pump suction sources (i.e. pressurized versus non-pressurized and the possible use of a suction regulator); the desire to make available nitrogen bottles as a backup to the emergency air system for operation of the atmospheric relief valves; and the inability of the abnormal operating procedure for control room inaccessibility to address loss of all AC power concurrent with loss of the control room. The license captured these enhancements in their corrective action program.

Describe the licensees actions and conclusions regarding training and qualifications of Licensee Action operators and support staff.

The licensee reviewed their database to identify the number of qualified individuals for c. Verify the training and required positions such as system operators, reactor operators, shift technical advisors, qualifications of operators and maintenance, health physics, chemistry, fire protection, security and emergency response the support staff needed to personnel. These numbers were verified to meet minimum required staffing numbers.

implement the procedures and Personnel qualifications were then verified to be current in the licensees training database work instructions are current for (plateau).

activities related to Security Describe inspector actions and the sample strategies reviewed to assess training and Order Section B.5.b and severe qualifications of operators and support staff accident management guidelines as required by 10 The inspectors reviewed training material related to the implementation of SAMGs, CFR 50.54 (hh).

Emergency Planning procedures, and B.5.b strategies. The inspectors also reviewed the table created in the licensees review above to ensure that reasonable numbers of appropriate staff were provided. The inspectors interviewed station management related to the content of training for each site discipline and the periodicity of the training.

Discuss general results including corrective actions by licensee.

All require personnel were found to be qualified and no gaps were noted.

Describe the licensees actions and conclusions regarding applicable agreements and Licensee Action contracts are in place.

The licensee reviewed all memorandums of understanding (MOU) related to the scope of d. Verify that any applicable this item. The licensee compared these MOUs to station strategies and/or procedural agreements and contracts are in requirements to identify any gaps or potential enhancements.

place and are capable of For a sample of mitigating strategies involving contracts or agreements with offsite entities, meeting the conditions needed describe inspector actions to confirm agreements and contracts are in place and current to mitigate the consequences of (e.g., confirm that offsite fire assistance agreement is in place and current).

these events.

The inspectors obtained copies of each of the licensees MOUs and compared This review should be done for a services/equipment requested to those outlined in station procedures/strategies.

reasonable sample of mitigating Discuss general results including corrective actions by licensee.

strategies/equipment.

The licensee identified all MOUs were adequate to meet site needs to implement strategies.

The licensee did identify an enhancement that would improve one strategy related to radiological release.

Document the corrective action report number and briefly summarize problems noted by the Licensee Action licensee that have significant potential to prevent the success of any existing mitigating strategy.

The inspectors reviewed the licensees condition reports written associated with equipment e. Review any open corrective testing, strategy walk downs, personnel qualifications and memorandums of understanding action documents to assess (MOUs). All were deemed by the licensee to be enhancements to existing strategies. The problems with mitigating inspectors determined than no significant potential to prevent the success of any existing strategy implementation mitigating strategy was identified. The inspectors reviewed planned corrective actions identified by the licensee.

associated with these enhancements and determined the planned corrective actions were Assess the impact of the adequate.

problem on the mitigating capability and the remaining capability that is not impacted.

03.02 Assess the licensees capability to mitigate station blackout (SBO) conditions, as required by 10 CFR 50.63, Loss of All Alternating Current Power, and station design, is functional and valid. Refer to TI 2515/120, Inspection of Implementation of Station Blackout Rule Multi-Plant Action Item A-22, as a guideline. It is not intended that TI 2515/120 be completely reinspected. The inspection should include, but not be limited to, an assessment of any licensee actions to:

Describe the licensees actions to verify the adequacy of equipment needed to mitigate an Licensee Action SBO event.

The licensee reviewed and walked down all procedures related to the mitigation of a station a. Verify through walkdowns and blackout. The station blackout diesel and related equipment necessary to support the SBO inspection that all required procedures were also walked down. Additionally, the licensee evaluated the material materials are adequate and condition of the station emergency diesel generators during these walk downs.

properly staged, tested, and maintained.

Describe inspector actions to verify equipment is available and useable.

The inspectors obtained copies of station procedures that implement the various strategies for loss of 4160 volt electrical buses and off site electrical power. The inspectors reviewed these procedures to evaluate thoroughness of licensee strategies. The inspectors reviewed the licensees SBO coping study to identify the planned strategy and equipment necessary for its implementation including the required duration of time needed. The inspectors identified that all required equipment is permanently installed in the plant. The inspectors also inspected the emergency diesel generators and attendant equipment to evaluate equipment readiness. The inspectors also inspected the emergency air compressors to evaluate the equipment readiness and ability to supply backup air to the turbine driven auxiliary feedwater (TDAFW) steam supply valves.

Discuss general results including corrective actions by licensee.

The licensee identified no gaps or deficiencies.

Licensee Action Describe the licensees actions to verify the capability to mitigate an SBO event.

The licensee reviewed and walked down all procedures related to the mitigation of a station b. Demonstrate through blackout. The station blackout diesel and related equipment necessary to support the SBO walkdowns that procedures for procedures were also walked down.

response to an SBO are executable.

Describe inspector actions to assess whether procedures were in place and could be used as intended.

The inspectors obtained copies of station procedures that implement the various strategies for loss of 4160 volt electrical buses and off site electrical power. The inspectors reviewed these procedures to evaluate thoroughness of licensee strategies. The inspectors reviewed the licensees SBO coping study to identify the planned strategy and equipment necessary for its implementation including the required duration of time needed.

Discuss general results including corrective actions by licensee.

The licensee identified no gaps or deficiencies.

03.03 Assess the licensees capability to mitigate internal and external flooding events required by station design. Refer to IP 71111.01, Adverse Weather Protection, Section 02.04, Evaluate Readiness to Cope with External Flooding, as a guideline. The inspection should include, but not be limited to, an assessment of any licensee actions to verify through walkdowns and inspections that all required materials and equipment are adequate and properly staged. These walkdowns and inspections shall include verification that accessible doors, barriers, and penetration seals are functional.

Describe the licensees actions to verify the capability to mitigate existing design basis Licensee Action flooding events.

The licensee utilized teams to conduct walk downs. The scope of the walk downs and a. Verify through walkdowns and associated acceptance criteria were defined by the licensee request for engineering review inspection that all required (RER) CR 110603501. Accessible areas of Units 1 and 2 Auxiliary Buildings, Emergency materials are adequate and Diesel Generator Building, Service Water Intake Structure, River Water Intake Structure and properly staged, tested, and site grounds were investigated. Condition reports were written and entered into the CAP for maintained.

deficiencies identified. No items were identified that failed to meet the current flood analysis.

Describe inspector actions to verify equipment is available and useable. Assess whether procedures were in place and could be used as intended.

The inspectors reviewed the licensee internal flooding analysis to determine strategies and required equipment for the strategies. The inspectors noted the only equipment involved in the strategy included water tight doors for emergency safeguards features. The inspectors inspect these doors during plant tours to ensure the operability of the doors and their adequacy to meet the internal flooding analysis. The inspectors inspected a sample of the floor drains and reviewed condition reports written by the licensee related to potential debris blockage of floor drains. The inspectors also reviewed the licensees Final Safety Analysis Report (FSAR) Section 2.4, Hydrologic Engineering, with emphasis upon site topography, proximity to the Chattahoochee River and it dams, flood history, and probable maximum precipitation. The inspectors evaluated the elevation of site buildings and structures related to the above information. The inspectors also walked down the protected area storm drains to ensure grating was free of debris and would provide proper drainage. Additionally, the inspectors reviewed station procedures which involved strategies to combat internal flooding to ensure their adequacy to maintain necessary and appropriate equipment operable. The inspectors reviewed planned corrective actions associated with these minor deficiencies and determined the planned corrective actions were adequate.

Discuss general results including corrective actions by licensee.

The licensee noted minor discrepancies related to house keeping with potential debris that may clog floor drains. The licensee noted some storm drains were partially blocked by metal plates (for security purposes). The licensee identified four blocked floor drains in the service water intake structure and one in the Auxiliary Building of Unit 2. The licensee identified minor procedure deficiencies in FNP-0-AOP-21.0, Severe Weather. The licensee entered all discrepancies in their corrective action program.

03.04 Assess the thoroughness of the licensees walkdowns and inspections of important equipment needed to mitigate fire and flood events to identify the potential that the equipments function could be lost during seismic events possible for the site. Assess the licensees development of any new mitigating strategies for identified vulnerabilities (e.g., entered it in to the corrective action program and any immediate actions taken). As a minimum, the licensee should have performed walkdowns and inspections of important equipment (permanent and temporary) such as storage tanks, plant water intake structures, and fire and flood response equipment; and developed mitigating strategies to cope with the loss of that important function. Use IP 71111.21, Component Design Basis Inspection, Appendix 3, Component Walkdown Considerations, as a guideline to assess the thoroughness of the licensees walkdowns and inspections.

Describe the licensees actions to assess the potential impact of seismic events on the Licensee Action availability of equipment used in fire and flooding mitigation strategies.

The licensee staff reviewed the Fire and Flood design basis with support from Southern a. Verify through walkdowns that Nuclear Engineering. Teams were assembled to walk down and inspect all accessible all required materials are structures, systems, and components. The walk down focused on degraded material adequate and properly staged, conditions that could impact the ability of fire or flood mitigation equipment to function in the tested, and maintained.

event of a seismic event. All accessible areas/rooms in the Auxiliary Building, Turbine Building, Service Water Intake Structure, River Water Intake Structure, Fire Pump House, Condensate Storage Tanks, Reactor Makeup Water Storage Tanks, Refueling Water Storage Tanks, Fire Protection, and B.5.b storage were walked down by the licensees staff.

Permanent and portable equipment were inspected by the staff.

Describe inspector actions to verify equipment is available and useable. Assess whether procedures were in place and could be used as intended.

The inspectors reviewed the licensees Final Safety Analysis Report (FSAR) Section 3.2, Classification of Structures, Components and System, with emphasis on the related seismic classification. The inspectors reviewed the licensees report documenting the completion of the above activities. The inspectors also reviewed SAMGs, Emergency Planning procedures, and Abnormal Operating procedures to evaluated licensee strategies and equipment utilized with these associated procedures. The inspectors determined that licensee activities were thorough.

Discuss general results including corrective actions by licensee. Briefly summarize any new mitigating strategies identified by the licensee as a result of their reviews.

The licensee inspections and reviews reveal that Plant Farley has the equipment, procedures, and agreements to respond to a design basis fire or flood event following a seismic event (no gaps identified). The licensee was planning additional reviews with the protected area yards non-seismic fire protection piping. Enhancement opportunities exist in responding to multi-unit events beyond design basis, procedure clarification, equipment staging for seismic event, and housekeeping. Licensee staff also recognized training opportunities for additional SMAGs and accidents beyond design basis.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

C. Barefield, Operations Superintendent
E. Berry, Engineering Support Supervisor
D. Hobson, Operations Superintendent
J. Hutto, Operations Manager
R. Martin, Rapid Response Manager
S. Odom, Emergency Preparedness Supervisor
W. Oldfield, Fleet Oversight Supervisor

NRC personnel

Scott

M. Shaeffer, Chief, Branch 2, Division of Reactor Projects

LIST OF DOCUMENTS REVIEWED