IR 05000346/2019005

From kanterella
Jump to navigation Jump to search
Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2019005)
ML19240A882
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 08/28/2019
From: Billy Dickson
Division Reactor Projects III
To: Bezilla M
FirstEnergy Nuclear Operating Co
References
IR 2019005
Download: ML19240A882 (7)


Text

ust 28, 2019

SUBJECT:

UPDATED INSPECTION PLAN FOR DAVIS-BESSE NUCLEAR POWER STATION (REPORT 05000346/2019005)

Dear Mr. Bezilla:

The enclosed inspection plan lists the inspections scheduled through June 30, 2021, for the Davis-Besse Nuclear Power Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

As shown in the attached schedule, the NRC now plans on conducting a team inspection during the weeks of September 23 and October 7 through 18, 2019, using Inspection Procedure (IP) 60854.1, ISFSI Preoperational and Initial Loading Inspection. Also during the period of October 13 through November 9, 2019, the NRC will do a Design Bases Assurance Inspection (Programs) using IP 71111.21N and, during the period of March 23 through March 27, 2020, will do an evaluation of changes, tests, and experiments using IP 71111.17T This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at 630-829-9827 with any questions you have regarding this letter.

Sincerely,

/RA/

Billy Dickson, Chief Branch 2 Division of Reactor Projects Docket No. 50-346 License No. NPF-3 Enclosure:

Inspection Plan cc: Distribution via LISTSERV