IR 05000346/2007006
Download: ML071350100
Text
May 14, 2007
Mr. Mark B. BezillaSite Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT: DAVIS-BESSE NUCLEAR POWER STATIONNRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION INSPECTION REPORT 05000346/2007006(DRS)
Dear Mr. Bezilla:
On April 5, 2007, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection atyour Davis-Besse Nuclear Power Station. The enclosed inspection report documents the inspection results, which were discussed on April 5, 2007, with Mr. V. Kaminskas and other members of your staff.As a result of your intent to adopt the National Fire Protection Association Standard (NFPA)805 code, "Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition," as defined by Title 10, Code of Federal Regulations (CFR),
Part 50, Section 48(c), the inspection was conducted in accordance with Inspection Procedure 71111.05TTP, "Fire Protection - NFPA 805 Transition Period (Triennial)," dated May 9, 2006.
The inspection examined activities conducted under your license, as they relate to safety and to compliance with the Commission's rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.Based on the results of this inspection, no findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter andits enclosure will be available electronically for public inspection in the NRC Public DocumentRoom or from the Publicly Available Records System (PARS) component of NRC's Agencywide M. Bezilla-2-Documents Access and Management System (ADAMS), accessible from the NRC Web site athttp://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,/RA/Julio F. Lara, ChiefEngineering Branch 3 Division of Reactor SafetyDocket No. 50-346License No. NFP-3
Enclosure:
Inspection Report 05000346/2007006
w/Attachment:
Supplemental Informationcc w/encl:The Honorable Dennis KucinichJ. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer Richard Anderson, Vice President, Nuclear Support Manager - Site Regulatory Compliance D. Pace, Senior Vice President of of Fleet Engineering J. Rinckel, Vice President, Fleet Oversight D. Jenkins, Attorney, FirstEnergy Director, Fleet Regulatory Affairs Manager - Fleet Licensing Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners
SUMMARY OF FINDINGS
IR 05000346/2007006(DRS); 03/12/07 - 04/05/07; Davis-Besse Nuclear Power Station; RoutineTriennial Fire Protection Baseline Inspection.This report covers an announced triennial fire protection baseline inspection. The inspectionwas conducted by Region III inspectors. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not apply may be "Green" or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 3; dated July 2000.A.Inspector-Identified and Self-Revealed Findings
Cornerstone: Initiating EventsNo findings of significance were identified.Cornerstone:
Mitigating SystemsNo findings of significance were identified.
B.Licensee-Identified Violations
No findings of significance were identified.
Enclosure3
REPORT DETAILS
1.REACTOR SAFETYCornerstones: Initiating Events and Mitigating Systems1R05Fire Protection (71111.05TTP)FirstEnergy Nuclear Operating Company (FENOC), the licensee, in a letter to theU. S. Nuclear Regulatory Commission (NRC) dated February 27, 2007, committed toadopt the National Fire Protection Association Standard (NFPA) 805 code,
"Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition," as defined by 10 CFR 50.48(c) for the Davis-Besse Nuclear Power Station. The NFPA 805 code establishes a comprehensive set of requirements for fire protection programs at nuclear power plants. The code incorporated both deterministic and risk-informed, performance-based concepts. The deterministic aspects of the code are comparable to traditional requirements. However, the transition to a risk-informed, performance-based fire protection program requires an in-depth nuclear safety circuit analysis for equipment identified for nuclear safety functions such as safe shutdown. Because the conversion and licensing process to NFPA 805 was expected to identify and address a variety of issues that were normally the subject of the triennial fire protection baseline inspection, the NRC modified the fire protection inspection program and Enforcement Policy for licensees in transition to NFPA 805. As a result, this inspection was conducted in accordance with IP 71111.05TTP, "Fire Protection - NFPA 805 Transition Period (Triennial)," dated May 9, 2006. Associated with the transition to NFPA 805, when a circuit-related finding not associated with a finding of high safety significance meets the four criteria established by Section A of the NRC's Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR 50.48), the violation would receive enforcement discretion in accordance with the NRC's Enforcement Policy.The purpose of this inspection was to review the Davis-Besse Nuclear Power StationFire Protection Program for selected risk-significant fire areas. Emphasis was placed on determining that the post-fire safe shutdown capability and the fire protection features were maintained free of fire damage to ensure that at least one post-fire safe shutdown success path was available. The inspection was performed in accordance with the NRC's regulatory oversight process using a risk-informed approach for selecting the fire areas and attributes to be inspected. The inspectors used the Davis-Besse Nuclear Power Station Individual Plant Examination for External Events to choose several risk-significant areas for detailed inspection and review. The fire zones chosen for review during this inspection are listed below and constitute five samples:
4Fire AreasDescriptionDDCable Spreading Room;FFControl Room;HHControl Room Ventilation;QHigh Voltage Switchgear Room, Division 2; andXLow Voltage Switchgear Room, Division 2.For each of these fire areas, the inspection focused on the fire protection features, thesystems and equipment necessary to achieve and maintain safe shutdown conditions, determination of license commitments, and changes to the Fire Protection Program..1Shutdown from Outside Main Control RoomTitle 10 CFR Part 50, Appendix R, Section III.G.1, required that structures, systems, andcomponents that were necessary to achieve and maintain post-fire safe shutdown from outside the main control room be protected by fire protection features, such that, one train of systems necessary to achieve and maintain hot shutdown conditions was free of fire damage; and systems necessary to achieve and maintain cold shutdown could be repaired within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
a. Inspection Scope
The inspectors reviewed the functional requirements identified by the licensee asnecessary for achieving and maintaining hot shutdown conditions to ensure that at least one post-fire safe shutdown success path was available in the event of fire in each of the selected fire areas and for alternative shutdown in the case of control room evacuation. The inspectors reviewed the plant systems required to achieve and maintain post-fire safe shutdown to determine if the licensee had properly identified the components and systems necessary to achieve and maintain safe shutdown conditions for each fire area selected for review. Specifically, the review was performed to determine the adequacy of the systems selected for reactivity control, reactor coolant inventory makeup, reactor heat removal, process monitoring, and support system functions. The review also included the fire Safe Shutdown Analysis to ensure that all required components in the selected systems were included in the licensee's Safe Shutdown
Analysis.
The inspectors reviewed the Safe Shutdown Analysis, licensee operating procedures,piping and instrumentation drawings, electrical drawings, the Davis-Besse Nuclear Power Station Updated Final Safety Analysis Report (UFSAR) and other supporting documents to verify that hot and cold shutdown could be achieved and maintained from outside the control room for fires that rely on shutdown from outside the control room.
This review included verification that shutdown from outside the control room could be performed both with and without the availability of offsite power.The inspectors also reviewed the operators' ability to perform the necessary manualactions for achieving safe shutdown by reviewing procedures, the accessibility of safe shutdown equipment, and the available time for performing the actions.
5The inspectors reviewed the Davis-Besse Nuclear Power Station UFSAR and thelicensee's engineering and/or licensing justifications (e.g., NRC guidance documents, license amendments, Technical Specifications, Safety Evaluation Reports, exemptions, and deviations) to determine the licensing basis.
b. Findings
No findings of significance were identified..2Protection of Safe Shutdown CapabilitiesTitle 10 CFR Part 50, Appendix R, Section III.G.1, required the licensee to provide fireprotection features that were capable of limiting fire damage to systems, structures, and components important to safe shutdown. The systems, structures, and components that were necessary to achieve and maintain post-fire safe shutdown were required to be protected by fire protection features that were capable of limiting fire damage to the systems, structures, and components so that:*one train of systems necessary to achieve and maintain hot shutdown conditionsfrom either the control room or emergency control station(s) was free of fire damage; and*systems necessary to achieve and maintain cold shutdown from either thecontrol room or emergency control station(s) could be repaired within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.Specific design features for ensuring this capability were specified by 10 CFR Part 50,Appendix R,Section III.G.2.
a. Inspection Scope
The inspectors reviewed the fire hazards analysis, safe shutdown analysis andsupporting drawings and documentation to verify that safe shutdown capabilities were properly protected. Under the NFPA 805 transition period inspection period, the inspectors were to validate 1 to 3 non-conformances identified in the licensee's transitional assessment of their fire areas. At the time of this inspection, no fire areas had been assessed by the licensee.The inspectors reviewed the licensee procedures and programs for the control ofignition sources and transient combustibles to assess their effectiveness in preventing fires and in controlling combustible loading within limits established in the fire hazards analysis. The inspectors performed plant walkdowns to verify that protective features were being properly maintained and administrative controls were being implemented.The inspectors also reviewed the licensee's design control procedures to ensure that theprocess included appropriate reviews and controls to assess plant changes for any potential adverse impact on the fire protection program and/or post-fire safe shutdown analysis and procedures.
b. Findings
No findings of significance were identified..3Passive Fire ProtectionBranch Technical Position APCSB 9.5-1,Section IV.B.1, "General Guidelines for PlantProtection Building Design,"Section IV.B.3, "Cable Construction, Cable Trays and Penetrations," and Section IV.D.2, "Control Room," identified the requirements for the licensee's fire protection passive features.
a. Inspection Scope
For the selected fire areas, the inspectors evaluated the adequacy of fire area barriers,penetration seals, fire doors, electrical raceway fire barriers, and fire rated electrical cables. The inspectors observed the material condition and configuration of the installed barriers, seals, doors, and cables. The inspectors compared the as-installed configurations to the approved construction details and supporting fire tests. In addition, the inspectors reviewed license documentation, such as NRC Safety Evaluation Reports, and deviations from NRC regulations and the NFPA codes to verify that fire protection features met license commitments.The inspectors walked down accessible portions of the selected fire areas to observematerial condition and the adequacy of design of fire area boundaries (including walls, fire doors, and fire dampers) to ensure they were appropriate for the fire hazards in the area.The inspectors reviewed the installation, repair, and qualification records for a sample ofpenetration seals to ensure the fill material was of the appropriate fire rating and that the installation met the engineering design.
b. Findings
No findings of significance were identified..4Active Fire ProtectionBranch Technical Position APCSB 9.5-1,Section IV.C.1, "Fire Detection,"Section IV.C.3, "Water Sprinkler and Hose Standpipe Systems,"Section IV.C.5,
"Carbon Dioxide Suppression Systems," and Section IV.D.2, "Control Room," identified the requirements for the licensee's fire protection active features.
a. Inspection Scope
For the selected fire areas, the inspectors evaluated the adequacy of fire suppressionand detection systems. The inspectors observed the material condition and configuration of the installed fire detection and suppression systems. The inspectors reviewed design documents and supporting calculations. In addition, the inspectors reviewed license basis documentation, such as NRC Safety Evaluation Reports, and 8deviations from NRC regulations and the NFPA codes to verify that fire suppression anddetection systems met license commitments.
b. Findings
No findings of significance were identified..5Protection from Damage from Fire Suppression ActivitiesTitle 10 CFR Part 50, Appendix A, Criterion 3, "Fire Protection," required that firefightingsystems shall be designed to minimize the adverse effects of fires on systems, structures, and components important to safety and to assure that their rupture or inadvertent operation does not significantly impair the safety capability of these systems, structures, and components.
a. Inspection Scope
For the selected fire areas, the inspectors verified that redundant trains of systemsrequired for hot shutdown would not be subject to damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems including the effects of flooding. The inspectors conducted walkdowns of each of the selected fire areas to assess conditions, such as the adequacy and condition of floor drains, equipment elevations and spray protection.
b. Findings
No findings of significance were identified..6Alternative Shutdown CapabilityTitle 10 CFR Part 50, Appendix R, Section III.G.1, required that systems, structures, andcomponents important to safe shutdown be provided with fire protection features capable of limiting fire damage to ensure that one train of systems necessary to achieve and maintain hot shutdown conditions was free of fire damage. Options for providing this level of fire protection were delineated in 10 CFR Part 50, Appendix R, Section III.G.2. Where the protection of systems whose function was required for hot shutdown did not satisfy 10 CFR Part 50, Appendix R, Section III.G.2, an alternative ordedicated shutdown capability independent of the area under consideration was required to be provided. Additionally, alternative or dedicated shutdown capability must be able to achieve and maintain hot standby conditions and achieve cold shutdown conditions within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and maintain cold shutdown conditions thereafter. During the post-fire safe shutdown, the reactor coolant process variables must remain within those predicted for a loss of normal ac power, and the fission product boundary integrity must not be affected (i.e., no fuel clad damage, rupture of any primary coolant boundary, or rupture of the containment boundary).
9
a. Inspection Scope
The inspectors reviewed the licensee's systems required to achieve alternative safeshutdown to determine if the licensee had properly identified the components and systems necessary to achieve and maintain safe shutdown conditions. The inspectors also focused on the adequacy of the systems to perform reactor pressure control, reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and support system functions.The inspectors performed a walkdown of a sample of the actions defined in ProcedureDB-OP-02519, "Serious Control Room Fire." The team conducted the walkdown to determine if operators could reasonably be expected to perform the procedure actions and that equipment labeling was consistent with the procedure. The review also looked at operator training as well as consistency between the operations shutdown procedures and any associated administrative controls. The inspectors' review of the adequacy of emergency lighting associated with these procedures are documented in Section
1R05
.9 of this report.
b. Findings
No findings of significance were identified..7Circuit Analyses
a. Inspection Scope
In accordance with Inspection Procedure 71111.05TTP, "Fire Protection - NFPA 805Transition Period (Triennial)," dated May 9, 2006, this section of the IP was suspended for facilities in NFPA 805 transition.
b. Findings
No findings of significance were identified..8CommunicationsBranch Technical Position APCSB 9.5-1, required that emergency communicationequipment be provided. For a fire in an alternative shutdown fire area, control room evacuation may be required and a shutdown is performed from outside the control room.
Radio communications are relied upon to coordinate the shutdown of both units and for fire fighting.
a. Inspection Scope
The inspectors reviewed, on a sample bases, the adequacy of the communicationsystem to support plant personnel in the performance of alternative safe shutdown functions and fire brigade duties.
10
b. Findings
No findings of significance were identified..9Emergency LightingTitle 10 CFR Part 50, Appendix R, Section III.J., required that emergency lighting unitswith at least an eight-hour battery power supply be provided in all areas needed for operation of safe shutdown equipment and in access and egress routes thereto.
a. Inspection Scope
The inspectors performed a plant walkdown of areas in which a sample of the actionswould be performed as described in procedure DB-OP-02519, "Serious Control Room Fire." As part of the walkdowns, the inspectors focused on the existence of sufficient emergency lighting for access and egress to areas and for performing necessary equipment operations.
b. Findings
No findings of significance were identified..10Cold Shutdown RepairsTitle 10 CFR Part 50, Appendix R, Section III.G.1.b, required that equipment andsystems comprising the means to achieve and maintain cold shutdown conditions should not be damaged by fire; or the fire damage to such equipment and systems should be limited so that the systems can be made operable and cold shutdown achieved within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Materials for such repairs shall be readily available onsite and procedures shall be in effect to implement such repairs.
a. Inspection Scope
The inspectors reviewed the licensee's procedures to determine whether repairs wererequired to achieve cold shutdown and to verify that dedicated repair procedures, equipment, and material to accomplish those repairs were available on-site. The inspectors also evaluated whether cold shutdown could be achieved within the required time using the licensee's procedures and repair methods.
b. Findings
No findings of significance were identified..11Compensatory Measures
a. Inspection Scope
The inspectors conducted a review to verify that compensatory measures were in placefor out-of-service, degraded or inoperable fire protection and post-fire safe shutdown 11equipment, systems, or features (e.g., detection and suppression systems andequipment, passive fire barriers, pumps, valves or electrical devices providing safe shutdown functions or capabilities). The inspectors also conducted a review on the adequacy of short term compensatory measures to compensate for a degraded function or feature until appropriate corrective actions were taken.
b. Findings
No findings of significance were identified.4.OTHER ACTIVITIES4OA2Identification and Resolution of Problems
a. Inspection Scope
The inspectors reviewed the corrective action program procedures and samples ofcorrective action documents to verify that the licensee was identifying issues related to the fire protection program at an appropriate threshold and entering them in the corrective action program. The inspectors reviewed selected samples of condition reports, work orders, design packages, and fire protection system non-conformance documents.
b. Findings
No findings of significance were identified.4OA6Meetings.1Exit MeetingOn April 5, 2007, at the conclusion of the on-site inspection activities, the inspectorspresented preliminary inspection results to Mr. V. Kaminskas and other members of licensee management. The inspectors asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
- V. Kaminskas, Director, Site Operations
- J. Grabner, Director, Station Engineering
- R. Hruby, Jr., Manager, Fleet Oversight
- A. Miller, System Engineer, Fire Protection
- D. Moul, Manager, Plant Operations
- M. Murtha, Fire Protection Engineer, Design Engineering
- V. Patton, Fire Marshal
- C. Price, Director, Performance Improvement
- D. Wuokko, Manager, Regulatory Compliance
- G. Wolf, Engineer, Regulatoy ComplianceNRC
- J. Lara, Chief, Engineering Branch 3, Region III
- R. Smith, Resident Inspector, Davis-Besse Nuclear Power Station
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened, Closed, and DiscussedNone
AttachmentA-2
LIST OF DOCUMENTS REVIEWED
The following is a list of documents reviewed during the inspection.
- Inclusion on this list doesnot imply that the NRC team reviewed the documents in their entirety, but rather, that selected sections of portions of the documents were evaluated as part of the overall inspection effort.
- Inclusion of a document on this list does not imply NRC acceptance of the document or any part of it, unless this is stated in the body of the inspection report.Calculations15.49; Automatic Suppression System Flow Rates for Drainage; Revision 0
- 15.50; Evaluation of Fire Suppression System Impact on Auxiliary Bldg. and Intake Structure;Revision 1C-EE-013.10-001; 480 V Breaker Coordination to Meet Common Power Source Criteria forAppendix R; Revision 3C-FP-013.10-006; Appendix 12, Combustible Loading Calculation; Revision 4
- Condition Reports03-03152; Fire Detection Coverage Concerns for Rooms 429Aa and 429B; dated April 24, 2003
- 04-05703; During NRC Inspection Activity in the Component Cooling Water Pump Room aSprinkler Head was Observed to Have Evidence of past Leakage; dated September 16, 200404-05725; There is an Abnormal Noise Coming from
- FP 1055; dated September 19, 2004
- 04-05886; Door 406 (Door to SFP Corridor from East Hallway in the RRA) was Found to beApproximately 8 Inches Open at 0810, 1420, and 1545 on September 25, 2004; dated September 25, 200404-05970; Fire Area HH Appendix R, Exemption Request; dated September 28, 2004
- 05-01999; Fire Valve FP123 the North Underground Loop to Turbine Building Loop IsolationWas Found to be Leaking While Performing
- DB-FP-04031 Quarterly Fire Valve Alignment Verification; dated April 2, 200505-03695; EDG Room 2 Pre-Action Valve Pressure Switch; dated July 2, 2005
- 05-04150; the Question has been Asked as to Where a Fire Brigade Member Can Go,Particularly Outside the Protected Area, and Still Meet Any Requirements for Responding to a Fire; dated August 2, 200505-04323; NRC Issued Non-cited Violation of 10 CFR Part 50, Appendix R, Section III. J; datedJune 21, 2005
- AttachmentA-306-00271; Drawings M-341 Sh. 2 of 3, M-362 Sh. 1 of 3, and M-362 Sh. 2o fo 3 Show SprinklerHead Labeled as U03 Being a Pendent Sprinkler; dated February 1, 200606-00531; the NRC Resident Reported that Door 306 Was Found Approximately 2 to 3 InchesOpen; dated March 1, 200606-01027; Notified by the Nuclear Regulatory Commission Resident Inspector that Door 206,AB2 Southeast Stairwell-AUX Bldg, was Found ajar; dated March 17, 200606-01224; Door 406 had a New Closer Installed under Order
- 200194334 and Failed TestDB-FP-04036; dated March 23, 200606-02227; Failure of Flanged Joint on Cable Spread Room SprinklerHeader; dated May 6, 200606-03389; Received Notification from the NRC Resident Inspector Door 308 did not Fully Latchwithout Assistance when He Passed Through the Door; dated September 5, 200606-07330; Found 2 Unidentified Penetrations in Room 240-F (Floor); dated October 5, 2006
- 07-14222; Db-ss-06-38: Hose Station Calcs. Not Signed nor Issued; dated February 8, 2007
Condition Reports
- Initiated as a Result of Inspection07-16265; Door 317 Will Not Close and Latch from 1/4 Open; dated March 15, 2007
- 07-16296; NRC FP Triennial Inspection Procedure Issue
- DB-OP-02519; dated March 15, 2007
- 07-16308; During the NRC Triennial Fire Protection Inspection the Inspectors Noted a Concernwith the Installation of DAAS Units in the Control Room Cabinet Room; dated March 14, 200707-16318; During the NRC Fire Protection Triennial Inspection the Inspectors Expressed aConcern over the Use of Neoprene Insulation in Room 603 Control Room Heaving Ventilation and Air Conditioning; dated March 15, 200707-17553; a Walkdown by the NRC Found a Small Amount of Transient Combustibles Left onthe Top of a Health Physics Department Cabinet in the Center of Corridor 227; datedApril 4, 200707-17589; FHAR Wording Relating to the Radio Repeater; dated April 4, 2007
- 07-17722; During the Exit of the Fire Protection Triennial Inspection the Inspectors Made anObservation Concerning the "Temporary" Installation in the Control Room of the ICS DAAS;
dated April 5, 200707-18037; During the Exit Meeting for the NRC Fire Protection Triennial Inspection(April 5, 2007), the Lead Inspector Provided an Observation on the Control of Combustibles Program; dated April 5, 2007
- AttachmentA-4CorrespondenceSerial Number 3003; Request for Exemption from 10 CFR Part 50, Appendix R, Section
- III.G.3for Fire Area HH; dated January 20, 2004Serial Number 3076; Supplemental Information Regarding the Request for Exemption from10 CFR Part 50, Appendix R, Section
- III.G.3 for Fire Area HH (TAC No. MC1833); datedSeptember 3, 2004Serial Number 3106; Supplemental Information Regarding the Request for Exemption from10 CFR Part 50, Appendix R, Section
- III.G.3 for Fire Area HH (TAC No. MC1833); datedFebruary 25, 2005DrawingsE-6 Sh 1; 480 VAC MCC (Essential) One Line Diagram; Revision 81
- E-45b Sh-11A; Elementary Wiring Diagram Afpt and Mfpt Control and Auxiliaries Afpt Control;Revision 14E-45b Sh-11B; Elementary Wiring Diagram Afpt and Mfpt Control and Auxiliaries Afpt Control;Revision 16E-45b Sh-11C; Elementary Wiring Diagram Afpt and Mfpt Control and Auxiliaries Afpt Control;Revision 5E-52b Sh 12; Elementary Wiring Diagrams Reactor Cooling System RC Przr Pwr Rlf ShutoffVlv; Revision 13E-892, Sh 3; Raceway-Fire Alarm System Auxiliary Building Plan Elev. 613' - 6"; Revision 4
- M-360, Sh 3; Fire Protection Piping Sprinkler System Rm. 422A Auxiliary Building Elev. 613'-6";Revision 1Fire Protection Program DocumentsFire Hazards Analysis; Revision 21
- NG-DB-00302; DBNPS Fire Protection Program; dated August 24, 2005
- Licensee AssessmentsDB-C-06-02; Davis-Besse Fleet Oversight Quarterly Assessment Report; dated July 28, 2006
- DB-SS-06-038; Fire Protection Triennial Inspection Readiness; dated March 12, 2007
- AttachmentA-5ProceduresDB-FP-00007; Control of Transient Combustibles; Revision 8DB-OP-02519; Serious Control Room Fire; Revision 11
- DB-OP-02501; Serious Station Fire, Attachment 20: Fire in Area Hh; Revision 12
- PFP-AB-422A; Protected Area Pre-Fire Plan:
- Cable Spreading Room 422A Fire Area DD;Revision 3PFP-AB-323; Protected Area Pre-Fire Plan:
- High Voltage Switchgear Room B Room 323 FireArea Q; Revision 4PFP-AB-428; Protected Area Pre-Fire Plan:
- Low Voltage Switchgear Room F-bus Room 428Fire Area X; Revision 3PFP-AB-505; Protected Area Pre-Fire Plan:
- Control Room and Adjacent Support Rooms;Revision 6PFP-AB-603; Protected Area Pre-Fire Plan:
- Ac Equipment Room and Records and StorageArea; Revision 3Surveillances and TestsDB-FP-04014; Periodic Test Procedure Fire Hose Station Inspections; dated March 07, 2007
- DB-FP-04015; Periodic Test Procedure Fire Hose Hydrostatic Tests, Rerack, and VisualInspections; Dated November 17, 2006DB-FP-04016; Fire Extinguisher Quarterly Inspection; Preformed February 26, 2007
- DB-FP-04028; Appendix a Fire Door 18 Month Inspection; Dated August 3, 2005
- DB-MI-04813-001; Supervisory and Functional Test for Node 3 C3520; dated January 26, 2006
- DB-MI-04813-001; Supervisory and Functional Test for Node 3 C3520; datedFebruary 23, 2005DB-MI-04814-001; Supervisory and Functional Test for Node 4 C4520; datedDecember 12, 2005DB-MI-04818-001; Supervisory and Functional Test of Detectors for Node 8 C6713; datedOctober 21, 2005DB-MI-04819; Supervisory and Functional Test of Accessible Detectors for Node 9 C5796A;Dated September 22, 2006Davis-Besse, Appendix R, Radio Communications Study; Revision 2
- AttachmentA-6Appendix R Emergency Lighting Checklist; Room No. 237, AUX Feed Pump Room; datedMay 3, 1989Appendix R Emergency Lighting Checklist; Room No. 428, Low Voltage Switchgear Room FBus; dated May 3, 1989Temporary Modifications04-0005; Cabinets for ICS, NNI, EHC, and CRDT; dated October 27, 2004
- AttachmentA-7List of Acronyms UsedADAMSAgencywide Documents Access and Management SystemAPCSBAuxiliary and Power Conversion Systems Branch
- CFRCode of Federal Regulations
- DRSDivision of Reactor Safety
- FENOCFirstEnergy Nuclear Operating Company
- IMCInspection Manual Chapter
- IPInspection Procedure
- NFPANational Fire Protection Association
- NRCU.S. Nuclear Regulatory Commission
- PARSPublicly Available Records
- SDPSignificance Determination Process
- UFSARUpdated Final Safety Analysis Report