Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-344/93-06
ML20046B088
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 07/20/1993
From: Vandenburgh C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Cross J
PORTLAND GENERAL ELECTRIC CO.
References
NUDOCS 9308030080
Download: ML20046B088 (2)


Text

_,/

  • b UNITED STATES yi NUCLEAR REGULATORY COMMISSION n

REGION V

g

.,i 3%,,,,*/

1450 MARIA LANE WALNUT CREEK, CALIFORNIA 94596-5368 JUL 2 0 is93 Docket No. 50-344 Portland General Electric Co.

121 S. W. Salmon St.

'

Portland, OR 97204

Attention:

Mr. James E. Cross

~

l Vice President and Chief Nuclear Officer Thank you for your letter of June 14, 1993, in response to our Notice of Violation and Inspection Report No. 50-344/93-06, dated May 20, 1993, informing us of the steps you have taken to correct the items which we brought to your attention.

Your corrective actions will be verified during a future inspection.

,

Your cooperation with us is appreciated.

Sincerely, C.A.VanDenburgII,d[ef

^

Reactor Projects Branch cc:

i Mr. Michael J. Sykes, Chairman, Board of County Commissioners, Columbia County Mr. David Stewart-Smith, Oregon Department of Energy

,

Mr. Tom Walt, General Manager, Technical Functions Mr. Lloyd K. Marbet l

Mr. Jerry Wilson, Do It Yourself Committee i

Mr. Eugene Rosolie, Northwest Environmental Advocates

!

r 9300030000 930720 j

PDR ADOCK 05000344:

O PDR

\\

'

'

S EDl -

.

- -

.

.I

!

!

.

Docket No. 50-344 JUL 2 01993 Portland General Electric Co.

121 S. W. Salmon St.

Portland, OR 97204 Attention:

Mr. James E. Cross Vice President and Chief Nuclear Officer

/

GentJ

'n:

y Thank you for your letter of June 14, 1993, in response to our Notice of Violation and Inspection Report No. 50-344/93-06, dated May 20, 1993, I

informing us of the steps you have taken to correct the items which we brought to your attention.

Your corrective actions will be verified during a future inspection.

Your cooperation with us is appreciated.

Sincerely, C. A. VanDenburgh, Chief Reactor Projects Branch j

cc.

Mr. Michael J. Sykes, Chairman, Board of County Commissioners, Columbia County Mr. David Stewart-Smith, Oregon Department of Energy Mr. Tom Walt, General Manager, Technical Functions Mr. Lloyd K. Marbet Mr. Jerry Wilson, Do It Yourself Committee Mr. Eugene Rosolie, Northwest Environmental Advocates f

A'

Regio, V/ ann KJo ston JMel PS fi on RHue CVar1

> gh 1/ j/f),,

g Q q}

1/t /U 7/13A3 7 /l /'/3

/

~UESTTDTVT- '

'ST COPY]

RMIJEST V]

REQUEST COPY]

{STCOPVJ i

YE

/ N0 1 ES / N0 1 YES // N0 il YES) / NO 1 (ES / / NO 1 UU l

wou ro,og ES / N0 1 YES / N0 1 j

i i

.

..

.

._.

j

,.

. -.

A

'

--

..

.

_

!

Portland General BechicCompany

-

m James E. Cross c31 i,. ' '.'; 12 l

.

Vice President and Chief Nuclear Officer

.;

i

!

,

i June 14, 1993 Trojan Nuclear Plant Docket 50-344 i

License NPF-1

!

U.S. Nuclear Regulatory Commission

'

Attn: Document Control Desk Washington DC 20555

Dear Sir:

'

Reolv to a Notice of Violation l

Your letter of May 20, 1993 transmitted a Notice of Violation associated

.

!

with the Nuclear Regulatory Commission Inspection Report No. 50-344/93-06.

Attachment A to this letter contains Portland General Electric Company's

,

response to the violation.

,

,

Sincerely, a

  1. g Attachment c:/r.BobbyH.Faulkenberry M

i Regional Adminirtrator, Region V i

U.S. Nuclear Regulatory Commission Mr. David Stewart-Smith i

State of Oregon i

Department of Energy i

Mr. J. F. Melfi NRC Resident Inspector i

Trojan Nuclear Plant i

,

I

.. =,

-

121 Sw Sa on Street. Por::and. Oregon 97204 (503)464-8897 l

-

.

- _ _ _ -. - _ _ _ _ -

.

June 14, 1993 Trojan Nuclear Plant Document Ccntrol Desk

'

-

Docket 50-344

.

License NPF-1 Attachment A Page 1 of 2 EEPLY TO NOTICE OF VIOLATION Violation 93-06-01 Title 10, Code of Federal Regulations, Part 50 (10 CFR 50), Appendix B, Criterion V states in part:

" Activities af fecting quality shall be prescribed by documented instructions, procedures, or drawings of a type appropriate to the circumstances, and shall be accomplished in accordanca with these instructions, procedures, and drawings."

Trojan Plant Procedure (TPP) 13-5, Revision 0, dated May 29, 1991,

" Control of In-Plant Unsecured Equipment / Material", requires that all unattended equipment / material which has sufficient mass and mobility to damage safety-related equipment during a seismic event and is located in an area within the scope of the procedure, includi_g the area surrounding the Spent fuel Pool, shall be properly secured. Step 4.2.8 states,

" Portable laddera shall be tied down or laid down when left unattended... "

Contrary to the above:

On Apri*. ?7. 1993, three portable ladders had been left unattended in the area rurrovtding the Spent Fuel Pool.

This.8c a Severity Level IV violation (Supplement I).

Response Portland General Electr.

'

ny (PGE) acknowledges the violation.

,

a 1.

Reason for the Violation The reason for the violation was personnel error, failure to follow the procedure as written. Trojan Plant Procedure (TPP) 13-5 required ladders to be tied down or laid down when left unattended.

2.

Corrective Steps That Have Peen Taken and the Riaults Achieved

!

The scaffold ladders were laid on the floor to comply with the a.

requirements of TPP 13-5.

b.

At a later date, the scaffolding and scaffold ladders were removed to a proper storage location outside the area of the Spent Fuel Pool.

c.

Radwaste Handlers wero sited on this violation and compliance

-

L with the requirements atw med in TPP 13-5.

-

r

--

'--

-

-

. _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

<

..

.

-

,

.

June 14, 1993 i

l Document Control Desk Trgjan Nuclear Plant

!

'

' Docket 50-344 f

Attachment A License NPF-1 Page 2 of 2 d.

PGE inspected the Spent Fuel Fool area to determine if the equipment / material in the area complied with the requirements of

TPP 13-5.

One other item was identified and was corrected to meet the requirements of TPP 13-5.

3.

Corrective Steps That Will Be Taken to Avoid Further Violations i

TPP 13-5 will be revised to better define storage locations and

'

This is equipment requirements, including ladders, within the Plant.

l scheduled to be completed by August 15, 1093.

'

i

.

4.

Date When Full Compliance Will Be Achieved

_

<

Full compliance was achieved when the inspection of the Spent Fuel

[

Pool area was completed and the equipment / material in the area was

stored to comply with the requiremants of TPP 13-5.