uly 26, 2011

SUBJECT:

FERMI POWER PLANT, UNIT 2 NRC SECURITY BASELINE INSPECTION REPORT 05000341/2011404(DRS)

Dear Mr. Davis:

On June 17, 2010, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection of your Fermi Power Plant, Unit 2. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process.

The enclosed inspection report documents the inspection results, which were discussed on June 17, 2010, with Mr. T. Conner and other members of your staff.

The inspection examined activities conducted under your licenses as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your licenses. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, no findings were identified.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosures, and in accordance with 10 CFR 2.390, a copy of this letters enclosures will not be available for public inspection.

Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA by D. Funk for/

Richard A. Skokowski, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-341 License No. NPF-43 Nonpublic Enclosure: Inspection Report 05000341/2011404(DRS)