March 11, 2025
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR MILLSTONE POWER STATION, UNITS 2 AND 3 (REPORTS 05000336/2024006 AND 05000423/2024006)
Dear Eric Carr:
The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Millstone Power Station, Units 2 and 3, reviewing performance indicators (PIs),
inspection results, and enforcement actions from January 1, 2024, through December 31, 2024.
This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at Millstone Power Station, Units 2 and 3, during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. Note that Millstone Power Station, Units 2 and 3, transitioned into the Regulatory Response Column (Column 2) at the beginning of the second quarter of 2024, as a result of one or more greater-than-Green findings in the Security cornerstone as documented in NRC Inspection Reports 05000336/2024442 and 05000423/2024442 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML24170A784), but returned to the Licensee Response Column (Column 1) on July 11, 2024, following a supplemental inspection documented in NRC Inspection Reports 05000336/2024441 and 05000423/2024441 (ML24219A016).
The enclosed inspection plan lists the inspections scheduled through December 31, 2026.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. As noted in the attached inspection plan, in addition to baseline inspections, the NRC plans to conduct License Renewal Phase 1 and Phase 2 inspections at Millstone Power Station, Unit 3, using Inspection Procedure 71003, Post-Approval Site Inspection for License Renewal, at your facility.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Matt Young at (610) 337-5205 with any questions you have regarding this letter.
Sincerely, Blake D. Welling, Director Division of Operating Reactor Safety
Docket Nos. 05000336 and 05000423 License Nos. DPR-65 and NPF-49
Enclosure:
As stated
cc w/ encl: Distribution via LISTSERV
BLAKE WELLING Digitally signed by BLAKE WELLING Date: 2025.03.11 09:17:48 -04'00'
SUNSI Review
X Non-Sensitive Sensitive
X Publicly Available Non-Publicly Available
OFFICE RI/DORS RI/DORS RI/DORS
NAME NMentzer MYoung BWelling
DATE 3/6/2025 3/7/2025 3/10/2025
Site Inspection Activity Plan Millstone 01/01/2025 - 12/31/2026 Unit Start End Activity CAC Title Staff Count ISFSI - IP 60859 License Renewal, Millstone
2,3 1/6/2025 1/8/2025 IP 60859 Independent Spent Fuel Storage Installation (ISFSI) License Renewal Inspection RP - 71124.03 & 71124.04 - Airborne & Dose - Millstone
2,3 1/1/2025 2/15/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation 2,3 1/27/2025 2/4/2025 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2,3 1/27/2025 2/4/2025 IP 71124.04 000728 Occupational Dose Assessment License Renewal Phase 1 - Millstone Unit 3
3 4/14/2025 4/25/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal Inservice Inspection - Millstone Unit 3
3 4/14/2025 4/25/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP - 71124.01 - Rad Hazard & Controls - Millstone
2,3 4/28/2025 5/2/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls EP Program Inspection - Millstone
2,3 5/19/2025 5/23/2025 IP 71114.02 000717 Alert and Notification System Testing 2,3 5/19/2025 5/23/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2,3 5/19/2025 5/23/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2,3 5/19/2025 5/23/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness 2,3 5/19/2025 5/23/2025 IP 71151 001397 Performance Indicator Verification RP - 71124.07 - REMP - Millstone
2,3 5/19/2025 5/23/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program Access Control, Protective Strategy, TSR, SPR, PIs - MS
2,3 6/23/2025 6/27/2025 IP 71130.02 000734 Access Control 2,3 6/23/2025 6/27/2025 IP 71130.05 000737 Protective Strategy Evaluation 2,3 6/23/2025 6/27/2025 IP 71130.09 001656 Security Plan Changes 2,3 6/23/2025 6/27/2025 IP 71130.14 000743 Review of Power Reactor Target Sets 2,3 6/23/2025 6/27/2025 IP 71151 001338 Performance Indicator Verification License Renewal Phase 2 - Millstone Unit 3
3 7/7/2025 7/11/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal
7/21/2025 7/25/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal RP - 71124.05 - Instrumentation - Millstone
2,3 7/14/2025 7/18/2025 IP 71124.05 000729 Radiation Monitoring Instrumentation 2025 MS3 Initial Operator Licensing Exam
Prepared on 2/18/2025 8:01:38 PM 1 of 3
Site Inspection Activity Plan
8/10/2025 8/15/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
9/14/2025 9/20/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
Age Related Degradation Inspection - Millstone
2,3 9/22/2025 9/26/2025 IP 71111.21N.04 001832 Age-Related Degradation 2,3 10/6/2025 10/10/2025 IP 71111.21N.04 001832 Age-Related Degradation RP - 71124.08 - Rad Waste & Transportation - Millstone
2,3 10/6/2025 10/10/2025 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation RP - 71151 - PIV - Millstone
2,3 11/17/2025 11/21/2025 IP 71151 000746 Performance Indicator Verification MS3 Requal Inspection with P/F Results
3 12/1/2025 12/5/2025 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance
12/1/2025 12/5/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Cyber Security - Millstone
2,3 2/2/2026 2/6/2026 IP 71130.10 000741 Cybersecurity PI&R Biennial Team Inspection - Millstone
2,3 2/23/2026 2/27/2026 IP 71152B 000747 Problem Identification and Resolution 2,3 3/9/2026 3/13/2026 IP 71152B 000747 Problem Identification and Resolution Inservice Inspection - Millstone Unit 2
2 4/13/2026 4/24/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP-71124.01 - Rad Hazards - Millstone
2,3 4/27/2026 5/1/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Sec - Access Control, Equipment Testing and Maintenance, Training, SPR, PI Verification - MS
2,3 5/18/2026 5/22/2026 IP 71130.02 000734 Access Control 2,3 5/18/2026 5/22/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 2,3 5/18/2026 5/22/2026 IP 71130.07 000739 Security Training 2,3 5/18/2026 5/22/2026 IP 71130.09 001656 Security Plan Changes 2,3 5/18/2026 5/22/2026 IP 71151 001338 Performance Indicator Verification EP Exercise Inspection - Millstone
2,3 6/22/2026 6/26/2026 IP 71114.01 000716 Exercise Evaluation 2,3 6/22/2026 6/26/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 2,3 6/22/2026 6/26/2026 IP 71151 001397 Performance Indicator Verification Fire Protection - Millstone
2,3 7/20/2026 7/24/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
2,3 8/3/2026 8/7/2026 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
Prepared on 2/18/2025 8:01:38 PM 2 of 3
Site Inspection Activity Plan 2026 MS2 Initial Operator Licensing Exam
2 8/3/2026 8/7/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
9/14/2026 9/18/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - MS
2,3 8/10/2026 8/14/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 2,3 8/31/2026 9/4/2026 IP 71130.03 000735 Contingency Response - Force-On-Force Testing RP - SAFSTOR - Millstone U1
1 8/17/2026 8/21/2026 IP 37801 000009 Safety Reviews, Design Changes, And Modifications At Permanently Shutdown Reactors
8/17/2026 8/21/2026 IP 40801 000010 Self-Assessment, Auditing, And Corrective Action At Permanently Shutdown Reactors
8/17/2026 8/21/2026 IP 60801 000011 Spent Fuel Pool Safety At Permanently Shutdown Reactors
8/17/2026 8/21/2026 IP 64704 000018 Fire Protection Program at Permanently Shutdown Reactors
8/17/2026 8/21/2026 IP 71801 000023 Decommissioning Performance And Status Review At Permanently Suhutdown Reactors
8/17/2026 8/21/2026 IP 83750 000035 Occupational Radiation Exposure at Permanently Shutdown Reactors
8/17/2026 8/21/2026 IP 84750 000040 Radioactive Waste Treatment and Effluent And Environmental Monitoring
8/17/2026 8/21/2026 IP 86750 000045 Solid Radioactive Waste Management And Transportation Of Radioactive Materials RP - 71124.06 - RETS - Millstone
2,3 8/17/2026 8/21/2026 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Material Control and Accounting - Millstone
2,3 8/24/2026 8/28/2026 IP 71130.11 000742 Material Control and Accounting (MC&A)
RP - 71124.03 & 71124.04 - Airborne & Dose - Millstone
2,3 9/14/2026 9/18/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2,3 9/14/2026 9/18/2026 IP 71124.04 000728 Occupational Dose Assessment Inservice Inspection - Millstone Unit 3
3 10/12/2026 10/23/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP - 71124.01 - Rad Hazzard & Controls - Millstone
2,3 10/12/2026 10/16/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls MS2 Biennial Requal Inspection
2 11/16/2026 11/20/2026 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP - 71151 - PIV - Millstone
2,3 11/16/2026 11/20/2026 IP 71151 000746 Performance Indicator Verification Prepared on 2/18/2025 8:01:38 PM 3 of 3