NEXTeraM Duane Arno ld Energy Center 3277 DAEC Road ENERGY~

Palo, Iowa 52324 DUANE ARNOLD August 27, 2020 NG-20-0074 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington , DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 Certification of Permanent Cessation of Power Operations

Reference:

1) Letter from NextEra Energy Duane Arnold, LLC to USN RC, "Certification of Permanent Cessation of Power Operations", dated January 18, 2019 (ML19023A196)
2) Letter from NextEra Energy Duane Arnold, LLC to USNRC, "Certification of Permanent Cessation of Power Operations", dated March 2, 2020 (ML20062E489)
3) Letter from NextEra Energy Duane Arnold, LLC to USN RC, "Post Shutdown Decommissioning Activities Report", dated April 2, 2020 (ML20094F603)

In Reference 1, NextEra Energy Duane Arnold (NEDA) provided formal notification of the intention to permanently cease power operations at the Duane Arnold Energy Center (DAEC) in the fourth quarter of 2020. In Reference 2, NEDA supplemented that letter pursuant to 10 CFR 50.82(a)(1)(i) and 10 CFR 50.4(b)(8), providing the date of October 30, 2020 on which NEDA planned to permanently cease power operation of DAEC.

On August 10, 2020 the DAEC was shut down in response to a derecho storm that struck the DAEC and surrounding area. Upon review, NEDA has determined that DAEC will remain shut down and begin the decommissioning process. Therefore, NEDA is revising the date provided in Reference 2 and certifies to the NRC that DAEC permanently ceased power operations on August 10, 2020.

In Reference 3, NEDA submitted the DAEC Post Shutdown Decommissioning Activities Report (PS DAR) pursuant to 10 CFR 50.82(a)(4). Based on current assessments, the revised date of shutdown will not change the method of decommissioning or significantly change the decommissioning schedule described in the PSDAR. NEDA continues to evaluate the decommissioning schedule and will provide an updated PSDAR if significant changes are identified.

If you have questions regarding this submittal, please contact J. Michael Davis, Licensing Manager at 319-851-7032.

NG-20-0074 Page 2 of 2 I declare under penalty of perjury that the foregoing is true and correct. Executed on August 27, 2020.

Dean Curtland Site Director, Duane Arnold Energy Center NextEra Energy Duane Arnold , LLC cc: NRC Region lllAdministrator NRC Resident Inspector NRC Project Manager A Leek, State of Iowa