August 24, 2017
SUBJECT:
UPDATED INSPECTION PLAN FOR SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2 (REPORT 05000327, 05000328/2017005)
Dear Mr. Shea:
The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for the Sequoyah Nuclear Plant. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (404) 997-4415 with any questions you have regarding this letter.
Sincerely,
/RA/
Alan Blamey, Chief Reactor Projects Branch 6 Division of Reactor Projects
Docket Nos.: 05000327, 05000328 License Nos.: DPR-77, DPR-79
Enclosure:
Sequoyah Inspection/Activity Plan
(09/01/2017- 06/30/2019)
cc Distribution via ListServ SUBJECT:
UPDATED INSPECTION PLAN FOR SEQUOYAH NUCLEAR PLANT UNITS 1 AND 2 (REPORT 05000327, 05000328/2017005) August 24, 2017
DISTRIBUTION:
M. Kowal, RII K. Sloan, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMSequoyah Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)
ADAMS Accession Number: ML OFFICE RII:DRP
NAME ABlamey
DATE 8/24/2017
OFFICIAL AGENCY RECORD
17236A247
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Sequoyah Inspection / Activity Plan 09/01/2017 - 06/30/2019 Page 1 of 2 08/17/2017 10:17:02 EP
- EP PROGRAM INSPECTION
1, 2 IP Alert and Notification System Testing 7111402 09/11/2017 09/15/2017 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 09/11/2017 09/15/2017 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 09/11/2017 09/15/2017 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 09/11/2017 09/15/2017 1, 2 IP Performance Indicator Verification 71151 09/11/2017 09/15/2017 OL EXAM
- INITIAL LICENSE EXAM PREP
1 SEQUOYAH DECEMBER 2017 INITIAL EXAM AT POWER FACILITIES V23503 10/30/2017 11/03/2017 EQI
- DESIGN BASES ASSURANCE INSPECTION (PROGR
1, 2 IP Design Bases Assurance Inspection (Programs)
7111121N 10/30/2017 11/03/2017 1, 2 IP Design Bases Assurance Inspection (Programs)
7111121N 11/13/2017 11/17/2017 1, 2 IP Design Bases Assurance Inspection (Programs)
7111121N 12/04/2017 12/08/2017 OL EXAM
- INITIAL LICENSE EXAM
1 SEQUOYAH DECEMBER 2017 INITIAL EXAM AT POWER FACILITIES V23503 12/04/2017 12/15/2017 ISI
- UNIT 1 IN-SERVICE INSPECTION
1 IP Inservice Inspection Activities - PWR 7111108P 04/16/2018 04/20/2018 LR
- UNIT 1 POST-APPROVAL LR PHASE 1
1 IP Post-Approval Site Inspection for License Renewal 71003 04/16/2018 04/20/2018 MODS
- PLANT MODIFICATIONS INSPECTION
1, 2 IP Evaluations of Changes, Tests, and Experiments 7111117T 06/04/2018 06/08/2018 HS
- TRIENNIAL HEAT SINK PERFORMANCE
1, 2 IP Heat Sink Performance 7111107T 07/16/2018 07/20/2018 EP
- EP EXERCISE
1, 2 IP Exercise Evaluation 7111401 09/17/2018 09/21/2018 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 09/17/2018 09/21/2018 1, 2 IP Drill/Exercise Performance 71151-EP01 09/17/2018 09/21/2018 1, 2 IP ERO Readiness 71151-EP02 09/17/2018 09/21/2018 1, 2 IP Alert & Notification System Reliability 71151-EP03 09/17/2018 09/21/2018 OL RQ
- REQUAL INSPECTION
1, 2 IP Licensed Operator Requalification Program 7111111B 10/08/2018 10/12/2018 ISI
- UNIT 2 IN-SERVICE INSPECTION
2 IP Inservice Inspection Activities - PWR 7111108P 10/29/2018 11/02/2018 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Sequoyah Inspection / Activity Plan 09/01/2017 - 06/30/2019 Page 2 of 2 08/17/2017 10:17:02 LR
- UNIT 2 POST-APPROVAL LR PHASE 1
2 IP Post-Approval Site Inspection for License Renewal 71003 10/29/2018 11/02/2018 RP
- RP OCCUPATIONAL - WEEK 1
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/29/2018 11/02/2018 1, 2 IP Occupational ALARA Planning and Controls 71124.02 10/29/2018 11/02/2018 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/29/2018 11/02/2018 1, 2 IP Occupational Dose Assessment 71124.04 10/29/2018 11/02/2018 1, 2 IP Radiation Monitoring Instrumentation 71124.05 10/29/2018 11/02/2018 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 10/29/2018 11/02/2018 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 10/29/2018 11/02/2018 SGISI
- UNIT 2 SG IN-SERVICE INSPECTION
2 IP Inservice Inspection Activities - PWR 7111108P 10/29/2018 11/02/2018 RP
- RP OCCUPATIONAL - WEEK 2
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/26/2018 11/30/2018 1, 2 IP Occupational ALARA Planning and Controls 71124.02 11/26/2018 11/30/2018 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/26/2018 11/30/2018 1, 2 IP Occupational Dose Assessment 71124.04 11/26/2018 11/30/2018 1, 2 IP Radiation Monitoring Instrumentation 71124.05 11/26/2018 11/30/2018 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 11/26/2018 11/30/2018 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 11/26/2018 11/30/2018 DBAI
- DESIGN BASES ASSURANCE INSPECTION (TEAMS
1, 2 IP Design Bases Assurance Inspection (Teams)
7111121M 01/28/2019 02/01/2019 1, 2 IP Design Bases Assurance Inspection (Teams)
7111121M 02/25/2019 03/01/2019 1, 2 IP Design Bases Assurance Inspection (Teams)
7111121M 03/11/2019 03/15/2019 PI&R
- PROBLEM IDENTIFICATION AND RESOLUTION
1, 2 IP Problem Identification and Resolution 71152B 06/03/2019 06/07/2019 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.