IR 05000327/2024010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000327/2024010 and 05000328/2024010
ML24352A161
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 12/19/2024
From: Masters A
NRC/RGN-II/DORS
To: Erb D
Tennessee Valley Authority
References
IR 2024010
Download: ML24352A161 (1)


Text

SUBJECT:

SEQUOYAH UNITS 1 AND 2 - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000327/2024010 AND 05000328/2024010

Dear Delson Erb:

On November 20, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Units 1 and 2 and discussed the results of this inspection with Tom Marshall, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Anthony D. Masters, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000327 and 05000328

License Numbers:

DPR-77 and DPR-79

Report Numbers:

05000327/2024010 and 05000328/2024010

Enterprise Identifier:

I-2024-010-0048

Licensee:

Tennessee Valley Authority

Facility:

Sequoyah Units 1 and 2

Location:

Soddy-Daisy, TN

Inspection Dates:

November 04, 2024 to November 20, 2024

Inspectors:

P. Braxton, Reactor Inspector

J. Copeland, Reactor Inspector

A. Ruh, Senior Resident Inspector

Approved By:

Anthony D. Masters, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Sequoyah Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21N.03 - Commercial Grade Dedication The inspectors reviewed the implementation of the licensees processes for dedicating commercial-grade items/services as basic components and/or for procuring safety-related structures, systems, and components for the following samples:

Commercial Grade Dedication===

(1) Thermal overload relay, safety injection pump flow control valve (CAA979N) (QA2),

WO 124431338

(2) Drive belt, control room air handling unit (CAM866B) (QA2), WO 123172639
(3) Flexible coupling, essential raw cooling water strainer (DAY447A, DAY446C, DAX918D) (QA2), WO 122596737
(4) Terminal board, main steam header isolation (CBD133T) (QA2), WO 121952165
(5) Thermostatic expansion valve, electric board room chiller (DAC624B) (QA2), WO 120284596
(6) Capacitor, Eagle 21 process protection system power supply (CHP955N) (QA2), WO 122408274
(7) Fast acting fuse, Spare 120V AC Vital Inverter 0-II (BVM483R) (QA2), WO 122503134
(8) Pneumatic damper actuator, electric board room air handling unit (DAL895D) (QA2),

WO 121543475

(9) Lubricating oil (CAT418D) (QA2), WO 117812721
(10) Circuit breaker, 120V AC vital instrument power board 1-IV (CNF467E) (QA1), WO 122167444
(11) Fuse block holder, reactor vessel head vent throttle valve (DAL875K) (QA1), WO 120662966
(12) Solenoid valve, main steam header isolation (CBC720V) (QA1), WO 120831726
(13) Temperature transmitter, auxiliary building high energy line break detection (CYX872B) (QA1), WO 119350135
(14) Cap screw, auxiliary feedwater flow control valve diaphragm screw (DBG631K)

(QA1), WO

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On November 20, 2024, the inspectors presented the design basis assurance inspection (programs) inspection results to Tom Marshall, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

1817497,

1818804,

1836301,

1876471,

1494054,

1592594,

1818920,

1631916,

1661993

1970989

SQN CGDI 2024010: Selection of M&TE with Appropriate

Ranges

1972101

WO 119350135 administrative issues

1973677

NRC Observation on Appropriate CCs for Setscrews

Provided with Other Components

Corrective Action

Documents

Resulting from

Inspection

1973778

NRC SQN CGDI 2024010: PD V-Belt Critical

Characteristic Tolerances

011507-225

Control Valve 4" Model 37-20721 ANSI Class 900 Flanged

Ends #24 Direct Actuator

C

1,2-014D17734

KVA Inverter, 100-140VDC, 120VAC, 60 Hz, 1Ø

1,2-21245H-3

Cylinder Mounted Panel Board for 32' Mian Steam Bore

Isolation Valve

1,2-45N601-5

Wiring Diagrams-Main Steam System, Sheet 5

1,2-45N601-6

Wiring Diagram Main Steam, Sheet 6

1,2-45N706-4

Wiring Diagram 120V AC Vital Instrument Power Boards 1-

IV & 2-IV Connection Diagram Sheet-Sheet 4

1,2-45N751-5

Wiring Diagram-480V Reactor MOV BD 1B1-B, Single

Line, Sheet 1

1,2-47W865-7

Flow Diagram Air Conditioning Refrigerant Flow

1-45B793-60

Non-1E Loads Powered from Class 1 E Ac/DC Power

Systems

71111.21N.03

Drawings

1-45N1630-59

Wiring Diagram Miscellaneous Valves Connection

Diagram, Sheet 59

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Changes

SQN-23-054

Allow Installation of Larger Actuator Stem Nut Washer for

the 4" Motor Driven Auxiliary Feedwater - Steam

Generator Level Control Valves

07052400M3

Safety Related Molded Case circuit Breakers

16904M0

Moore Industries RTD transmitters for MCR Panel 2-M-23,

with seismic, mild environment, and EMI/RFI qualification

requirements, third party qualification

19801-SQNM0

Valve, expansion, QA 2

29690M0

Bussman Time delay fuse and fuse block

29715-SQNM0

ACTUATOR, PISTON TYPE, PNEUMATIC,

CONDITIONALLY DEDICATED

CAP-EAGLE-21

Capacitor

2/07/2019

CPEGM-2-00048

Fuse Cartridge 1E

CPEGM-2-00071

Relay, (All Types)- General Purpose

CPEGM-2-

VBELT

V-belts from Carlisle / Timken-By Method-1 dedication

G5305-1-1263

Fasteners to various material specifications (AISI)

excluding ASME and ASTM specifications

G5940-2-046EQ

Terminal Blocks & Strips

G5945-1-641

MSIV Pilot Control Solenoid

G6105-2-1338A

Components for flexible coupling

G9150-2-065

GENERIC TE FOR INDUSTRIAL OILS/LUBRICANTS

(NON 10CFR50.49)

Engineering

Evaluations

SCRs 101841,

104440, 124791,

24807, 124844,

24855, 127053,

27069, 124974,

110777, 97954,

103662, 104230,

106041, 125179,

101879, 100170

Miscellaneous

4405934

Purchase Order: TRANSMITTER,TEMPERATURE, QA 1,

RTD, 117 V/ 50/60 HZ, 3 WIRE

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5669998

Purchase Order: LUBRICANT,OIL, QA 2, SYNTHESIZED

GAS TURBINE, DRUM, ISO VG-32

26479

Purchase Order: ACTUATOR,PNEUMATIC, QA 2,

PISTON, ALUMINUM, DAMPER

6814210

Board, Terminal

7031586

Material Inspection Form: Capacitor

2/14/2022

7031586

TVA Purchase Order: CAPACITOR,ELECTRICAL

DEVICE, QA 2, ELECTROLYTIC, 33 MFD, (2) RADIAL

LEADS

10/17/2021

7362469,

7500762,

7384145,

7362469,

7598927,

5492515,

26479,

7031586,

5669998,

4405934

Material Inspection Form

7401043

Relay, Thermal, Overload

7475763

Fuse, One-Time, QA 2, Cartridge, Fast Acting, 250, 400,

10.6 K, 1-1/2 IN, 3-27/32 IN

5/22/2023

LIT-2681054P

Product Bulletin: D-3153 Pneumatic Actuator

03/12/2015

SQN-VTD-G080-

1150

General Electric Terminal Boards

SQN-VTD-M120-

1610

Masoneilan International Spring-Diaphragm Actuator

Instructions

SQN-VTD-S250-

0040

Parts Lists and Drawings for Solidstate Controls, Inc.

Inverters 0-I, 0-III, and 0-IV

NDE Reports

240425-082017,

230615-150900,

200424-131915

Lab Test Reports

Procedures

0-TI-PMT-000-

000.0

Pre-Post Maintenance Testing Matrices

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NEDP-8.0

Evaluations for Procurement of Materials, Items, and

Services

NPG-SPP-06.3

Pre-/Post-Maintenance Testing

P.S.4.M.1.5

CLASSIFICATION, PROCUREMENT, RECEIPT AND

USE OF LUBRICANTS

SQN-DC-V-

11.4.1

Normal and Emergency AC Auxiliary Power Systems

SQN-DC-V-27.3

Safety Injection System

SQN-DC-V-4.1.1

Main Steam System

SQN-DC-V-40.0

Seismic/Structural Qualification of Seismic Category I,

Electrical and Mechanical Equipment

SQN-DC-V.11.6

20 -V AC Vital Instrument Power System

1912037

Self-Assessment for the NRC CGD Inspection at SQN

03/28/2024

2018N-46

TVA Audit/Survey: Nuclear safety-related commercial-

grade dedication, product qualification, manufacturing and

supporting engineering services.

08/16/2018

Self-

Assessments

Audit Report

SSA2403

Materials Management and Procurement Engineering

Sequoyah Nuclear Plant (SQN)

06/11/2024

117812721

Replace Motor with refurbished spare to support Long

Range Outage Plan

09/23/2021

Work Orders

21543475

SQN-0-FCO-311-0028 will not open on fan start

05/19/2021