Security Baseline Inspection Report 05000327/2020410 and 05000328/2020410
ML20050D082
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 02/18/2020
From: James Shehee
Division of Reactor Safety II
To: Jim Barstow
Tennessee Valley Authority
James Shehee, RII/DRS - 404-997-4563
References
IR 2020410
Download: ML20050D082 (8)


Text

February 18, 2020

SUBJECT:

SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 - SECURITY BASELINE INSPECTION REPORT 05000327/2020410 AND 05000328/2020410

Dear Mr. Barstow:

On January 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Nuclear Plant, Units 1 and 2 and discussed the results of this inspection with Mr. Matthew Rasmussen and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James C. Shehee, Chief Plant Support Branch Division of Reactor Safety

Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000327 and 05000328

License Numbers:

DPR-77 and DPR-79

Report Numbers:

05000327/2020410 and 05000328/2020410

Enterprise Identifier: I-2020-410-0013

Licensee:

Tennessee Valley Authority

Facility:

Sequoyah Nuclear Plant, Units 1 and 2

Location:

Soddy Daisy, TN

Inspection Dates:

January 27, 2020 to January 30, 2020 (On-Site)

January 6, 2020 to January 10, 2020 (Corporate Office)

Inspectors:

J. Justice, Physical Security Inspector

R. Patterson, Physical Security Inspector

J. Wallo, Senior Physical Security Inspector

Approved By:

James C. Shehee, Chief

Plant Support Branch

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Sequoyah Nuclear Plant, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Unless otherwise noted, baseline security inspections were conducted in accordance with the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Publicly available IPs are located at:

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

SAFEGUARDS

71130.01 - Access Authorization

The inspectors evaluated the access authorization program. The following elements were

===evaluated:

Access Authorization===

(1)

  • Tier I: All requirements.
  • Tier II: All requirements.
  • Tier III: All requirements.

71130.02 - Access Control

The inspectors evaluated the access control program through completion of the following

===inspection elements:

Access Control===

(1)

  • Tier I: All requirements.
  • Tier II: 02.06 (a-d), 02.07(a), 02.08 (a), (e), (I)
  • Tier III: 02.10(a)

71130.08 - Fitness For Duty Program

The inspectors evaluated the fitness for duty program by completing the following inspection

===elements:

Fitness For Duty Program===

(1)

  • Tier I: All requirements.
  • Tier II: All requirements.
  • Tier III: All requirements.

71130.09 - Security Plan Changes

The inspectors evaluated the security plan changes through completion of the following procedure elements:

Review Security Plan Changes (IP Section 02.01) (1 Sample)

(1) Security Plan Revisions 17 and 18 were implemented based on your determination, in accordance with 10 CFR 50.54(p)(2), that the changes resulted in no decrease in safeguards effectiveness of the security plan, and that the revised security plan continues to meet the requirements of 10 CFR 73.55(b). The inspectors conducted a review of the security plan changes to evaluate for potential decreases in safeguards effectiveness of the security plan. However, this review does not constitute formal NRC approval of the changes. Therefore, these changes remain subject to future NRC inspection in their entirety.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17)

=

(1) The inspectors verified licensee performance indicators submittals for the period from January 2019, through January,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 30, 2020, the inspectors presented the security baseline inspection results to Mr. Matthew Rasmussen and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71130.01

Corrective Action

Documents

1459590

Procedures

NPG-SPP-14.5

Access Authorization

NSDP-23

Plant Access/Badging Process

NSDP-24

Access Authorization Program

NSDP-38

Access Authorization - Reviewing Official

NSDP-43

Adjudication Guidelines

NSDP-51

TVA Nuclear Power Group Access Services Psychological

Screening Manual

Self-Assessments

Various Access Authorization Audits and Self-Assessments

71130.02

Corrective Action

Documents

1446580

1504550

29635

1563098

15656207

1565679

1565684

1565693

1565699

1565702

Procedures

EPIP-8

Personnel Accountability and Evacuation

NPG-SPP-14.3

Security Information Control Program

NSDP-8

Keys and Locks

SQN-SSI-7.10

Gate 56 Vehicle Access

SQN-SSI-7.6

Personnel Access Control

SQN-SSI-7.7

Vehicle Access Control

Self-Assessments

Various Access Control Audits and Self-Assessments

71130.08

Corrective Action

Documents

1394327

1461196

1482431

22336

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1548417

1548502

1548603

1548607

1549529

1565687

Procedures

NPG-SPP-14.1

Fitness-for-Duty and Fatigue Management

NPG-SPP-14.10

Fitness-for-Duty - Drug and Alcohol Testing Requirements

NPG-SPP-14.11

Fitness-For-Duty - Medical Review Officer Procedure

NPG-SPP-14.12

Fitness-for-Duty - Intoxylizers Requirements

NPG-SPP-14.14

Fitness-for-Duty - Training and Field Support for the Fitness-

for-Duty Program

NPG-SPP-14.3

Fitness-for-Duty - Administrative Duties

Self-Assessments

Various Fitness-for-Duty Program Audits and Self-

Assessments

71130.09

Corrective Action

Documents

1517043

Procedures

Sequoyah Nuclear Plant Physical Security Plan and

Description of Changes

Sequoyah Nuclear Plant Physical Security Plan and

Description of Changes

SQN-SSI-16.9

Compensatory Measures

71151

Procedures

NSDP-29

Tracking and Trending and NRC Performance Indicators