Similar Documents at Hatch |
---|
Category:Letter
MONTHYEARIR 05000321/20230042024-01-31031 January 2024 Integrated Inspection Report 05000321/2023004 and 05000366/2023004 NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. ML24012A0652024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) IR 05000321/20233012024-01-17017 January 2024 NRC Operator License Examination Report 05000321/2023301 and 05000366/2023301 ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems IR 05000321/20234022023-11-29029 November 2023 Security Baseline Inspection Report 05000321/2023402, 05000366/2023402, and 07200036/2023401 NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal IR 05000321/20230112023-11-17017 November 2023 Biennial Problem Identification and Resolution Inspection Report 050003212023011 and 050003662023011 ML23324A4472023-11-14014 November 2023 302 Exam Approval Letter IR 05000321/20230032023-11-0202 November 2023 Integrated Inspection Report 05000321/2023003, and 05000366/2023003 IR 05000321/20234032023-10-26026 October 2023 Cyber Security Inspection Report 05000321/2023403 and 05000366/2023403 IR 05000321/20234012023-10-17017 October 2023 Security Baseline Inspection Report 05000321 2023401 and 05000366 2023401 ML23250A0472023-09-20020 September 2023 Request for Additional Information Regarding License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts in Technical Specifications Table 1.1-1, Modes ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report IR 05000321/20230052023-08-27027 August 2023 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 & 2 - Report 05000321/2023005 and 05000366/2023005 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 IR 05000321/20230022023-08-0808 August 2023 Integrated Inspection Report 07200036/2023001, 05000321/2023002, and 05000366/2023002 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23201A0292023-07-20020 July 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement ML23178A0012023-06-27027 June 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000321 2023403 and 05000366 2023403 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use IR 05000321/20230102023-06-0909 June 2023 Focused Engineering Inspection Report 05000321 2023010 and 05000366 2023010 NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. ML23136B2942023-05-19019 May 2023 Summary of May 02, 2023, Observation Public Meeting Held with Southern Nuclear Operating Company, Inc., Regarding a LAR for the Reactor Pressure Vessel Head Closure Bolts for Edwin I. Hatch Nuclear Plant, Units 1 and 2 NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 ML23123A2222023-05-0101 May 2023 Notification of Licensed Operator Initial Examination 05000321/2023301, and 05000366/2023301 IR 05000321/20230012023-04-26026 April 2023 Integrated Inspection Report 05000321/2023001 and 05000366/2023001 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update NL-23-0228, Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21)2023-03-20020 March 2023 Nuclear Property Insurance Coverage as of April 1, 2023 and Licensee Guarantees of Payment of Deferred Premiums (10 CFR 140.21) NL-23-0179, National Pollutant Discharge Elimination System (NPDES) Permit Renewal2023-03-13013 March 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal ML23065A1092023-03-0808 March 2023 Correction of Relief Request HNP-ISI-RR-05-02 Allowing to Continue Operation with a Flaw Indication on One Reactor Pressure Vessel Closure Bolt Until December 31, 2025 ML23053A2182023-03-0303 March 2023 Correction of Amendment Nos. 321 and 266 Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program IR 05000321/20220062023-03-0101 March 2023 Annual Assessment Letter Edwin I. Hatch Nuclear Plant, Units 1 and 2 - NRC Inspection Report 05000321/2022006 and 05000366/2022006 NL-23-0101, Cycle 28 Core Operating Limits Report Version 12023-02-23023 February 2023 Cycle 28 Core Operating Limits Report Version 1 ML23034A2462023-02-21021 February 2023 Audit Summary for License Amendment Request to Relax Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs ML22363A3932023-02-15015 February 2023 Issuance of Amendments Nos. 321 and 266, Regarding License Amendment Request to Revise the (National Fire Protection Association) NFPA-805 Fire Protection Program ML22346A1482023-02-0909 February 2023 Issuance of Amendments 320 and 265, Regarding LAR to Revise Technical Specifications to Adopt TSTF-208 and Administrative Correction for Duplicate Technical Specifications 3.4.10 2024-01-31
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 9, 2017 Mr. Stephen Fleet Security Director Southern Nuclear Operating Co., Inc.
Edwin I. Hatch Nuclear Plant 40 Inverness Center Parkway (Bin B042)
Birmingham, AL 35242 SUBJECT: EDWIN I. HATCH NUCLEAR PLANT - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT 05000321/2016405 AND 05000366/2016405
Dear Mr. McGavin:
On December 7, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Hatch Nuclear Plant. The NRC inspectors discussed the results of this inspection with you and other members of your staff. The inspectors documented the results of this inspection in the enclosed inspection report (IR).
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
No findings were identified during this inspection.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public inspections, exemptions, requests for withholding, of the NRC's "Agency Rules of Practice and Procedure," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS); accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
However, the material enclosed herein contains Security-Related Information in accordance with 10 CFR 2.390(d)(1), and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the Enclosure will not be made available electronically for public inspection in the NRC Public Document Room, or from the PARS component of NRCs ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390, in accordance with 10 CFR 2.390(d)(1), and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Binoy B. Desai, Chief Plant Support Branch 2 Division of Reactor Safety Docket No. 50-321, 50-366 License No. DPR-57, NPF-5 Enclosure:
IR 05000321/2016405 and 05000366/2016405 w/Attachment: Supplemental Information (OUO)
cc: (See page 3) for public inspection in the NRC Public Document Room, or from the PARS component of NRCs ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390, in accordance with 10 CFR 2.390(d)(1), and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Binoy B. Desai, Chief Plant Support Branch 2 Division of Reactor Safety Docket Nos. 50-321 and 50-366 License Nos. DPR-57 and NPF-5 Enclosure:
IR 05000321/2016405 and 05000366/2016405 w/Attachment: Supplemental Information (OUO)
cc: (See page 3)
DISTRIBUTION:
E. Wharton, NSIR D. Jackson, RII, PE N. Simonian, NSIR M. Catts, RII, SRI C. Johnson, NSIR M. Schwieg, RII, RI D. Garner, NSIR S. Price, RII, ORA/RC D. Ditto, NMSS L. Gibson, RII, EICS PSB BCs for RI, RIII, and RIV RIDSNRRDIRS J. Dodson, RII, SR PE PUBLIC (OUO removed)
PUBLICLY AVAILABLE (OUO removed) NON-PUBLICLY AVAILABLE SENSITIVE NON-SENSITIVE (OUO removed)
ADAMS: Yes ACCESSION NUMBER: SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS/PSB2 RII:DRS/PSB1 RII:DRP/BR4 RII:DRS/PSB2 SIGNATURE JPT WTL SRS5 BBD NAME J. Tornow W. Pursley S. Sandal B. Desai DATE 1/ 4 /2017 1/9/2017 1/9/2017 1/9/2017 E-MAIL COPY YES NO YES NO YES NO YES NO Official Record Copy G:\DRSII\PSBII\REACTORS\HATCH\Reports\2016\Part 37 TI Inspection\Hatch Part 37 NONpublic Insp Report 2016-405.doc cc:
Mr. Jonathan M. Merritt Site Security Manager (Nuclear)
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513 Michael P. Long Fleet Cyber Security Manager Southern Nuclear Operating Co., Inc.
40 Inverness Center Parkway (Bin B042)
Birmingham, AL 35242 Mr. Steven M. Shipman Fleet Security Project Manager Southern Nuclear Operating Co., Inc.
40 Inverness Center Parkway (Bin B042)
Birmingham, AL 35242