IR 05000313/1984036
| ML20137X769 | |
| Person / Time | |
|---|---|
| Site: | Arkansas Nuclear |
| Issue date: | 11/18/1985 |
| From: | Ireland R, Tapia J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML20137X748 | List: |
| References | |
| 50-313-84-36, NUDOCS 8512100625 | |
| Download: ML20137X769 (4) | |
Text
-
-
.
.
APPENDIX B U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
'NRC Inspection Report:
50-313/84-36 License:
DPR-51 Docket:
50-313
'
Licensee:
Arkansas Power and Light Company P. O. Box 551 Little Rock, Arkansas 72203 Facility Name: Arkansas Nuclear One, Unit 1 Inspection At: ANO No. 1 Site, Russellville, Arkansas and U. S. NRC Region IV Offices Inspection Conducted:
December 13-15, 1984 and March 28-30, 1985 Inspector *
$$ YAs/
// ////V5 h
J. I. Tapia, Reactor Inspsetor, Engineering Dath
'
and Operations-Section
////[//3'
Approved:
-
R. E.cIreland, Chief, Engineering and Date
'
Operations Sections
-
Inspection' Summary Inspection Conducted December 13-15, 1984 and March 28-30, 1985
'(Report 50-313/84-36)
Areas Inspected:
Special, announced inspection of the containment integrated leakage rate test. The. inspection involved 26 inspector-hours onsite and 25
_
.in-office inspector-hours by one NRC inspector.
Results: Within the areas inspected, one violation (failure to follow procedures) and no deviations.were identified.
f$f DY Y
G w
-
-
-
.
.
w
,
r
.-
.
.
.
DETAILS-
"
r
.
,
"
' l1',
' Persons Contacted
~
.
l1 Arkansas Power and Light Company (AP&L)
,
L
.c
~D.IN. Bennett, ILRT Director
,
'
,
~C. N..Shively, Plant Engineer
'
'
,
4 -
_L.;J. Dugger, Instrumentation and Control Superintendent l.
-
J. McWilliams, Outage Manager
'-
.,
,
_T..H. Cogburn, Special Projects Manager
.
,
- .
.
- -
>
'
. P.L Campbell, Licensing Engineer
~
,>
c
-
l]f J. M. Levine, General Manager:
r 7t- ~.,
10. B. Lomax, Licensing Supervisor
.
'
iBechtelEngineeringCorporation
,
-
'
' '
,
M. Burgess,.ILRT' Engineer r
.
,
~
2.
' Integrated Leak Rate Test (ILRT)
s-The, third _ periodic containment ILRT conducted using the Absolute Method'as described in' ANSI _N45.4-1972, " Leakage Rate Testing of Containment
Structures-for Nuclear Power Plants,".and ANSI /ANS-56.8-1981, " Containment System Leakage Testing Requirements," was addressed during this
' inspection.' The inspection involved procedure and records review, test
-
s witnessing ;and independent' calculations by the' NRC inspettor. LThis
~ inspection effort was performed in, order to ascertain whether the testing was-conducted in accordance with approved p'rocedures"and satisfied-the
- specified acceptance criteria contained in 10 CFR Part_50,' Appendix J,
" Primary Reactor Containment Leakage-Testing 1.. Water Cooled Power
,
Reactors," and in the Plant Technical Specifications.
Engineering Test Procedure No. 1309.09, " Integrated Leak Rate Test;"
' incorporates the referenced requirements and criteria.
This procedure was reviewed by_the NRC. inspector and no discrepancies from the specified requirements and criteria were noted. The review provided verification that.the following test attributes were correctly addressed:
~
a.
Containment interior and exterior inspection requirements specified.
L b.
Instrument locations justified by area surveys.
c.
' Instrument calibiation requirements specified.
d.
_ Instrument : loss / test abort criteria delineated.
,
-
!-
,
.
.,;
,
.
.,..m
-
..- _--,_..
._._,
._.___,,__z-,,
- _..
- -
.
Qs
,
,
,,
~
,
.
.
-
,
...
'
~
~
'
'
,
,
,
,
,
.
f e.
~ Instrument error analysis : performed.
~
' Type B and-C test. result's correction to' Type A test results f.-
-
specified,
,
g.
' Venting of internal isolated volumes required.
h.
Isdlation valve closing mode specified to be the normal mode.
~
1.
Proper postaccident system alignment.to prevent creation of
.
artificial leakage barriers specified.
,
j.
Quality control hold points specified.
.-
l k.
Test log entries required for repairs needed to complete test.
'1.
' Acceptance criteria specified.
_
.m.
Data acquisition. requirements specified.
'
'n.
. Data analysis technique specified.
Met' hod of depressurization specified.
o.
The-inspector observed portions of the test preparations including
. alignment of valves, instrumentation distribution and the general inspection of the containment' interior.
Based on observations of instrumentation locations-during the containment tour, the N,RC inspector
,
requested the calculational basis for the volumetric distribution of the-Tresistaace temperature detectors located above the refueling floor.
The method for volume fraction redistribution in the event of a detector
~ failure was'also requested.. Justification for -locating all detectors
.above the refueling floor within 180 degrees of. arc was s'ubsequently
~
- provided.. Temperature area surveys prior to pressurization and ta yn at each end 'and;at midpoint of the polar crane as well as at each detector
,
%
location along the 180 degree arc indicated a homogeneous atmosphere.
'
'
-Reevaluation of volume. fraction values'resulting from a potential detector
<
failure was. found to be based on-information from the volume fraction
~
'
calculation, the. temperature survey and air' communication paths associated l
with the failed' detector and surrounding areas.
'
,
-
The-instrument calibration ~ certification traceable to the U. S. Bureau of Standards for the resistance temperature detectors, humidity measuring
~
.,
~
devices, pressure gauges,'and the flowmeter used in the verification. test i
.were reviewed.
The guideline's of ANSI /ANS-56.8-1981,' were used'to select
,
-
- the instruments for the ILRT.
The formula from'th'e Instrumentation
' Selection Guide (ISG) was used during the ILRT to ensure that the data-
,
acquisition system accuracy was sufficient to provide reliable test
'
-
.-s
+
,,
.\\
y w
%
I y
~
.
.
<
w
.
.
<
.
w
.-
-
...
'
,
,
f W
.
results.. This formula utilizes'the systematic error of each sensor to
-
determine'an'overall value for the data acquisition system.
The
instrumentation system for the ILRT was based on a computer controlled data acquisition system capable of reading all sensors _ rapidly, storing.
..
the'information and then outputting to the. computer for conversions and-
~
'
calculation of the data.
An add'itional component of test methodology inspected involved the.
verification.of valve' positions.
During the pressurization phase, three
valves (Nos; IA-15, SA-45, and N -1021) were-found tagged and. positioned
in opposition ~ to the signed. procedural valve lineup control room test log.
., -
-The valve lineup discrepancies rcsulted from a failure to modify the test-
-
log sign off after.requ' ired valve realignments resulting from prerequisite.
,
' local leak rate retests.
The difficulty in. establishing a controlled priority for tagging represents a. failure to -follow-the test procedure and therefore constitutes a violation of 10 CFR Part 50, Appendix B,.
,
'.
Cri terion ~ V - (50-313/8436-01).
Due to the' valve lineup discrepancies identified during the first hour.of pressurization, all test activities.
~ were halted and a reverification of valve positions was initiated.
No
additional l discrepancies were identified. AP&L revised the ILRT procedure
'
by adding a. hold card temporary lift form to ensure that any valve.
position and accompanying valve position tag' changes are documented in the'
~
control room log sheets.
.
<
- After correct valve lineups were achieved, the ILRT pressurization was
?
-restarted.
The NRC re'sident inspector monitored subsequent ILRT
'
4 \\-
~
Jactivities.
y
,n Subsequent.to the performance of: the test, the NRC inspector obt'ained the
-
.
1 ~ *
raw'. data and computed the leakage rate'in accordance with the Mass Point
.
'
Data! Analysis technique. The computations performed were compared with p-c
.
Lthe license'e's 'results for the purpose of verifying the calculational:
'
?. "
procedure-and confirming the.results.
This analytical technique confirmed
,
>f '
_
.providing the.as-found and as-left values.for the type B and C tests were-the' acceptability of the results obtained by the licensee.
The data
-
"
also reviewed.
~
'
,
Exit Interview
'
TheNRC[inspectormetwithlicenseerepresentativesattheconclusionof
-
the inspection. :The NRC inspector summarized the. scope and findings of*
--
l the inspection.
.
E s
(
..
.
.