IR 05000289/1990009

From kanterella
Jump to navigation Jump to search
Partially Withheld Insp Rept 50-289/90-09 on 900404-06 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected: Unresolved Items Noted in Insp Rept 50-289/89-13 Re Testing & Maint of motor-operated Valves & Concerns Re Fuel Oil
ML20043A354
Person / Time
Site: Crane Constellation icon.png
Issue date: 05/08/1990
From: Anderson C, Woodard C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20043A348 List:
References
50-289-90-09, 50-289-90-9, NUDOCS 9005210239
Download: ML20043A354 (6)


Text

.

>

, --

.

.,

,

t DIUC}I8 $ !RA

""

'

R flhso Q.66Lt d Q[.f ( E im) --

y.:0;?aus);

g

,

M O A h _ _..-

W...ip440-

'

( E **.c.c; '"a; (h2) *

U. S. NUCLEAR REGULATORY COMMISSION i

REGION I'

?

,y Report No,. 50-289/90-09 l

Docket No, 50-289 License No. DPR-50 Licensee: GPU Nuclear Corporation-P.O. Box 480 Middletown, Pennsylvania 17057 Facility Name: Three Mile Island Unit l'

.l

Inspection ~At: Middletown Pennsylvania

'

Inspection Conducted: ' April 4-6, 1990 Inspectors:

//

Afr/90-

!

C. H. Woodard,_ Reactor Engineer, PSS/EB

'

date

!

. Approved by:

Reis (1 LW 4&/10 C. J. Anderson, Chief, Plant Systems date--

Section, EB, DRS i

Inspection Summary:

Inspection on April 4-6, 1990 (Inspection Report No. 50-289/90-09)--

'

Areas Inspected:

Routine announced inspection to address the licensee's I

t-actions taken to address unresolved items identified during ' previous NRC

!

Inspection 89-13.

These items ~ involved questions of operability,. testing and maintenance of motor operated valves and concerns for maintainingithe quality of the emergency diesel generators fuel oil.

j Results: Of the areas inspected, no violations were identified.

<9005210239 900509

!

PDR ADOCK 05000289

,,

.,

O PDC

!

t

i

'

L

.

^

<

,

,

-

.

.

DETAILS-I 1.0, Persons Contacted

'

<

~

1.1 General-- Public Utilities Nuclear (GPUN) Corporation E. Fuhrer, Manager Plant Chemistry i

',

  • D. Hassler, Licensing Engineer

-*H. Knight,' Licensing-Engineer

'

C. Kaylor,: Manager Planning

  • L. Lucas,' Chemist
  • R. Maag, Manager Plant Material

'*M.. Moore, Materials Engineer

  • J. Stacy, Manager Plant Security
  • R. Wells, Licensing Engineer

"

-

"R. Zimmerman, Plant Engineer-

'

1.2 Nuclear Regulatory Commission (NRC)

+

F.-Young

..,

  • D. Johnson

'

  • R. Brady d
  • Denotes those present at the' exit meeting

'

.-

2.0' Licensee's Actions on Previously Identified Items i

,

2.1 (Closed) Unresolved Item 50-289/89-13-01,- Controls For

!

Motor Operated Valve (MOV) Torque Switch Settings During inspection 89-13, the NRC inspectorLfound that=the-licensee _.

-

relies on previous test data to determine the requireditorque switch:

settings.

These results were not. documented'in a controlled document to ensure that the correct setpoints'are maintained. The4setpoints and the corresponding thrust values _were retained in uncontrolled

=}a files located in the maintenance shop. ~As a c'nsequence, this-o situation could lead to the use of obsolete setpoint values'during a

maintenance.

' During this inspection,. the inspector reviewe'dcthe: corrective' actions taken by the licensee to resolve' this-item. - The. inspector reviewed the steps, interfaces and controls used by maintenance in performing z

work on an MOV which could affect setpoints. The inspector also discussed with engineering and planning ~pers'onnel a current Work

~

'

-Request (#756501) which involves the installation _of new Belleville d

spring packs and MOV testing. The inspector found that the licensee.

>

has established control of the MOV setpoints by including the-main-

'

tenance of these MOVs in their GMS-2 computerized maintenance

_

. program. The setpoints were established and. confirmed by cognizant engineering personnel and entered into this program.

By being a part l

,

of the GMS-2 Program, MOV input data including setpoints are-l i-i-

]

u

&

-

'

^T fa

,

=f

m

.

.

,

.

,

+

w e

q

'

.

-

3;

<

?

j controlled. : Any changes require ~ approval by designated personnel l

- with GMS-2 access capability. _ Output in the form lof read-out and i

print-out are availablecto' maintenance,: planning and'others who haves

!

the GMS-2-terminals. Therefore, when,a MOV work request package isL

'

generated, the GMS-2-system provides;the. current MOV data' including.
i setpoints.

.The inspector considered the licensee's corrective actions adequate. This'

item is closed.-

'

"

'

.

-

..

2.2 (0 pen)-Unresolved. Item No '50-289/89-13-02-Demonstration of MOV Operability

!

Ouringinspe'ction89-13,theNRCinspectordetermthedthatftestinglof:

i the MOVs under conditions of_. maximum-differential pressure or certain d

other testing means with appropriate justification is, required to -

demonstrate MOV operability. -In addition, MOV operability anust be:

.

,

assured during conditions of. degraded. grid voltage.

The inspector determined that,the licensee was not' ready,to~ address;

-[

-close out of MOV operability under conditions of maximum differential #

t pressure.L Regarding operability-under conditions of' degraded grid!

voltage, the-licensee had completed calculations to, demonstrate'

-

operability with an. assumed minimum MOV termina1xvoltage of 75% off nominal.< This calculation was considered by the license'e to be.

conservative and was considered _ adequate to, demonstrate' operability.

However, a later calculation of the effects of degraded grid voltage; which reflected actual MOV terminal-. voltage.had not been-factored into the-MOV operability report. The above: items remain _'open pending the licensee's completion' of their-evaluation of these issues'

a

>

q 2.3 (Closed) Unresolved Item No. 50-289/89-13-03 Retesting Guidelines for Motor Operated Valves (MOV)

During inspection 89-13, the inspectors observedL that.-licensee pro- ~

I cedures do not identify the circumstances'which prompt the: retesting; of MOVs. Certain corrective'and preventive maintenance' activities-

'

can influence the as-left conditions of the MOV settings.-

..=

..

a Previously, the cognizant' engineers' determined the retestingLshould a

!

be based on the MOV. maintenance performed without' documented guide-L

" lines.

The inspector determined that the licensee has now established "MOV Retest Criteria" by Memorandum 3330-89-0047 'LAI-89-9134' dated July

!'

25, 1989. The following activities are included in the criteria which require retest:

,

e4

.

b

- '

. -

s,

.

.

--

-

-

3:

lS

,I..

,

,

-

,

,

%

r.,

..

s

,

s,_

.

,

,

L4

-

,

,

,

,

,

Repacking of the-valve l

Replacement of-the torque switch-

  • -
  • '

Any major. work on.the" valve itself Replacement of the worm gear-a Replacement or readjustmentfof the spring pack or: spring'

cartridge cap.

The inspector found.that the followinglMOV maintenance ~ procedures-have been revised.t'o. incorporate theLretest. criteria.-.

t 1420-LTQ-1, ReyL13_- Troubleshooting Limitorque Valve Operatbrs

  • .

and. Control = Circuits,; Removal. and Replacement' of LLimitorquel.

Valve Operators _

'

>

.;

1420-LTQ-2, Rev 11 - Limitorque Operator, Limit Switch ancic

'f

Torque Switch Adjustments-1420-LTQ-8, Rev 2 - Limitorque Valve Operator' Disassembly and-

  • Reassembly

'

E13, Rev. 19 - Limitorque Valves

~

,

The. inspector considered the licensee's' corrective' actions adequate.

This item is~ closed.,

j r

2.4 (Closed) Unresolved' Item No. 50-289/89-13-05,' Emergency Diesel'

Generator Fuel Oil Concerns l

The inspector questioned replenishing.EDG fuel oil by thel use of the local truck fill connection for; fuel storage tank 0F-T-1.

The-

concern was that the licensee's_ analysis of'new fuel takes approxi-mately two weeks. Fuel deficiencies could-lead _to' the common mode failure of the EDG units.

l The licensee addressed this item'in; Diesel Generator Operating Pro-cedure 1107-3, Revision 50.

It clarifies that.new fuel is not-L normally delivered into EDG storage tank DF_-T-1, but, into the 50,000-

i

gallon buffer storage tank'F0-T-1.

Fuel:in this tank is=~ routinely'

L analyzed-each week and analysis is made 'for all; new fuel'within two

,

E weeks. By serving as a buffer storage tank, tank'FO-T-1 provides~

reasonable assurance of proper make up fuel to EDG' storage' tank DF-T-1.

Procedure 1107-3 provides an alternate method for filling the-tank using a local fill connection. Also, a precaution: statement is added,

l-in the procedure which requires analysis of the fuel oil prior-to filling the tank.

.

.

.

-

-

i

'

.

w

(,

>

..

...

-

.

,

,

'

.

a Z

Since fuel: oil degrades'with time-and'_. is subject'to contamination -

i from_ various sources, it is important to establish;a program which ensures the continuing quality of-stored EDG fuel oil, The-inspectorf

_

questioned the fact that the fuel oil Stored in the EDG fuel storage-tart DF-T-1 and in the EDG day' tanks is not periodically' sampled to'

ensure quality.: The licensee has addressed this-issue'by performingi~

initial sampling?and' analysis of fuel in these tanks, by taking

'

appropriate actions to : remove contaminants, and byLimplementing

-

Operations Procedure OPS-S393 to periodically sample and analyze fuel

in EDG storage tank DF-T-1.

Also, periodic;samp1_ing and ana' lysis of-

'

' the day = tanks are done in accordance with Procedure 1301-8.2~.

The-

,

L inspector confirmed that the? licensee-has evaluated the need to-use-

l antioxidant' and biocide fuel, additives in the. diesel fuel. and the.

' need for the periodic. recirculation / filtration of the stored EDG fuel

l'

to remove particulates. DRecirculation/ filtration was-performed-in

December 1989.

Fuel additives will:not:be used at-this; time.~ The inspector;had.no further questions in these areas.

l

'

This item is closed.

.

3.0 Emergency Diesel Generator Control Voltage Concern.

>

,

.The, inspector noted that there may be detrimental effects from the loss ~of i

125 Vdc~ control voltage upon EDG. operation orpossible equipment damage.

  • under.certain modes-of operation of the EDG. units. The licensee has completed an evaluation of. the' effects of loss of the 125 Vde' control voltage and concludes.that there are no detrimental effects from-this loss ~ and there is little probability of equipment damage. = As a consequence, no changes are -contemplated.at the present time. The-

,

inspector had no further ' questions in this area.

.

l 4.0 Emergency Diesel Generators On-site Fuel Oil Supply Adeq'uacy

,

NRC Information Notice (IN) 89-50 alerted licensees! to the potential.

existence of an inadequate Emergency Diesel Generator (EDG) fuel supply to.

_

meet the FSAR and Technical Specification (TS) requirements. The IN.also

>

noted that in several plants, there. were discrepancies between the FSAR

,

and TS basis for the amount of fuel oil required to be available for specific operational requirements for the EDG units.

-

The inspector reviewed the licensee's evaluation which-was made to address the concerns of.IN 89-50. This evaluation is included in the licensee's internal Memorandum LAI-89-9123, dated Se'ptember 26, 1989' entitled

" Inadequate EDG Fuel Supply." - The inspector determined-from the

,

licensee's evaluation that there is no discrepancy ~between the'FSAR and Technical Specification requirements.

The TMI-1 FSAR states that,

" sufficient fuel is stored to-allow one unit to supply post-accident power

-

requirements for seven days" and the TMI-I TS requires that the

" engineer' d safeguards diesel generators are operable and at least 25,000 e

gallons of fuel oil are available in the storage tank."

For these two

9

=

-

a,

I'

~;

'

-

,

'

. -f(

,

!..

.6

' '

,

r documents to be consistent, at least 25,000 gallonsiof fuel oil are

,

- required to allow one EDG unit to supply post-accident power-requirements.

for seven days,

'

The' licensee's evaluation includes the worst case seven day diesel

.-

generator loading, analysis.. It also assumes the, highest EDG fuel.

consumption rate. The evaluation shows a seven day fuel consumption of:

22,651 gallons which is approximately ten percent less.than the 25,000-gallon minimum fuel oil requirements for'the DF-T_-1-30,000 gallon fuel'

. storage tank.

The inspector had no further questions regarding this issue.

J T,$-NfATJil CEIN E

'

GKilEl LD D UT IGR ILE g!stic3W,11 is liiEil!01BilY LEFT ELAM.

i i

J[f;!-N "

l' 1 C ii. 33 f#E E U M

-

l gy: g,, a !i 12i [0!! ILLIC q

0!$Q0E!., ii iS lii!3iTF$!1tY-l s

LEFT 01Al"!.

6.0 Exit Meeting q

Licensee-management was-informed of the' purpose'and scope of the inspection at the entrance interview.

The' findings of the inspectio.n'

a

..

'

were periodically discussed and were summarized'at the exit meeting on

- '

. April 6, 1990.

'

Attendees at the exit meeting are listed in Section 1.0 of-this report.

l

'

At no time during the inspection was written material provided -to the~

. s licensee by the inspector. The licensee did not indicate that the inspection involved any proprietary information.

,

l

!

.

'