IR 05000285/2010402

From kanterella
Jump to navigation Jump to search
IR 05000285-10-402, on 06/11/2010, for Fort Calhoun Station - NRC Security
ML101820563
Person / Time
Site: Fort Calhoun 
Issue date: 06/30/2010
From: Shannon M
Region 4 Engineering Branch 1
To: Bannister D
Omaha Public Power District
References
IR-10-402
Download: ML101820563 (3)


Text

June 30, 2010

SUBJECT:

FORT CALHOUN STATION - NRC SECURITY INSPECTION REPORT 05000285/2010402

Dear Mr. Bannister:

On June 11, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Fort Calhoun Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on June 11, 2009, with Mr. J. Reinhart, Site Vice President, and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, no findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, ADAMS.

ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

UNITED STATES NUCLEAR REGULATORY COMMISSION R E GI ON I V 612 EAST LAMAR BLVD, SUITE 400 ARLINGTON, TEXAS 76011-4125 Omaha Public Power District

- 2 - In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information-Withhold Under 10 CFR 2.390. and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,

/RA/ James R. Larsen for

Michael P. Shannon, Chief

Plant Support Branch-1

Division of Reactor Safety

Docket No.: 50-285 License No.: DPR-40

Nonpublic Enclosure:

NRC Inspection Report 05000285/2010402 w/Attachment: Supplemental Information

cc w/enclosure:

Jeffrey A. Reinhart Site Vice President Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550 Fort Calhoun, NE 68023-0550

Mr. Thomas C. Matthews Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550 Fort Calhoun, NE 68023-0550 Omaha Public Power District

- 3 - Distribution w/enclosure:

Ronald Albert (Ronald.Albert@nrc.gov), Chief, Reactor Security Oversight Branch Shyrl Coker, (Shyrl.Coker@nrc.gov) NSIR/DSO/DDSO, TWFN Mail Stop: T-3A5M Clay Johnson, (Clay.Johnson@nrc.gov), NSIR/DSO/DDSO/SPEB, TWFN 3D43 Branch Chief, RI DRS (James.Trapp@nrc.gov)

Branch Chief, RII DRS/PSB2 (Michael.Ernstes@nrc.gov)

Branch Chief, RIII DRS/PSB (Eric.Duncan@nrc.gov)

Senior Resident Inspector (John.Kirkland@nrc.gov)

Electronic distribution by RIV w/o enclosure:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Chuck.Casto@nrc.gov)

DRP Director (Dwight.Chamberlain@nrc.gov)

DRP Deputy Director (Anton.Vegel@nrc.gov)

DRS Director (Roy.Caniano@nrc.gov)

DRS Deputy Director (Troy.Pruett@nrc.gov)

Resident Inspector (Jacob.Wingebach@nrc.gov)

Branch Chief, DRP/E (Jeff.Clark@nrc.gov)

Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)

Project Engineer (William.Schaup@nrc.gov)

FCS Administrative Assistant (Berni.Madison@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

Project Manager (Lynnea.Wilkins@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource ROPreports DRS/TSB STA (Dale.Powers@nrc.gov)

OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)

Security Related Complete Report - OUO:

SUNSI Review Completed:

PRF ADAMS: Yes Initials: PRF

Non-Publicly Available : Sensitive-Security-Related-Periodic Review Required

Letter Only:

SUNSI Review Completed: PRF

ADAMS: : Yes Initials: PRF

Publicly Available : Non-Sensitive

PSI:PSB1 PSI:PSB1 PSI:PSB1 C:PSB1 C:DRP/PBE C:PSB1 P. Frechette M. Brooks J. Buchanan MPShannon JClark MPShannon

/RA/

/RA/

/RA/

/RA/JRL for

/RA/

/RA/JRL for 6/30/10 6/30/10 6/29/10 6/30/10 6/29/10 6/30/10 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax