July 15, 2015
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT NRC INITIAL LICENSE EXAMINATION REPORT 05000263/2015301
Dear Mr. Gardner:
On June 19, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your Monticello Nuclear Generating Plant (MNGP). The enclosed report documents the results of those examinations. Preliminary observations noted during the examination process were discussed on June 10, 2015, with you and other members of your staff. An exit meeting was conducted by telephone on June 23, 2015, between Mr. T. Shortell, MNGP Training Manager, of your staff and Mr. D. McNeil, Senior Operator Licensing Examiner, to review the proposed final grading of the written examination for the license applicants. During the telephone conversation, the NRC verified with Mr. Shortell that the station had no post examination comments, as originally received by the NRC on June 19, 2015.
The NRC examiners administered an initial license examination operating test during the weeks of June 1 and June 8, 2015. The written examination was administered by MNGP training department personnel on June 11, 2015. Seven Senior Reactor Operator and six Reactor Operator applicants were administered license examinations. The results of the examinations were finalized on June 30, 2015. All applicants passed all sections of the examination and were issued applicable operator licenses.
The written examination and the proposed written examination will be withheld from public disclosure for 24 months per Mr. Shortells verbal request.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosures, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety
Docket No. 50-263 License No. DPR-22
Enclosures:
1. Operator Licensing Examination Report 05000263/2015301 2. Simulation Facility Fidelity Report
REGION III==
Docket No:
50-263 License No:
DPR-22 Report No:
05000263/2015301 Licensee:
Northern States Power Company, Minnesota Facility:
Monticello Nuclear Generating Plant Location:
Monticello, MN Dates:
June 2 through June 19, 2015 Examiners:
D. McNeil, Chief Examiner, RIII
M. Bielby, Examiner, RIII
L. Vick, Examiner, IOLB
J. Seymour, Examiner, RIII
Approved by:
H. Peterson, Chief Operations Branch Division of Reactor Safety, RIII
SUMMARY
ER 05000263/2015301; 06/02/2015 - 06/19/2015; Northern States Power Company, Minnesota,
Monticello Nuclear Generating Plant; Initial License Examination Report.
The announced initial operator licensing examination was conducted by regional U.S. Nuclear Regulatory Commission (NRC) examiners in accordance with the guidance of NUREG-1021,
Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1.
Examination Summary Thirteen of thirteen applicants passed all sections of their respective examinations.
Seven applicants were issued senior operator licenses and six applicants were issued operator licenses. No applicants failed any section of the examination. (Section 4OA5.1)
REPORT DETAILS
4OA5 Other Activities
.1 Initial Licensing Examinations
a. Examination Scope
The U.S. Nuclear Regulatory Commission (NRC) examiners and members of the facility licensees staff used the guidance prescribed in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9-Supplement 1, to develop, validate, administer, and grade the written examination and operating test.
Members of the facility licensees staff prepared the outline and developed the written examination and operating test. The NRC examiners validated the proposed examination during the week of March 30, 2015, with the assistance of members of the facility licensees staff. During the on-site validation week, the examiners audited all of the license applications for accuracy. The NRC examiners, with the assistance of members of the facility licensees staff, administered the operating test, consisting of job performance measures (JPMs) and dynamic simulator scenarios, during the period of June 2, 2015, through June 9, 2015. The facility licensee administered the written examination on June 11, 2015.
b. Findings
- (1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.
Less than 20 percent of the proposed examination questions were determined to be unsatisfactory and required modification or replacement.
All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors, and documented on Form ES-401-9, Written Examination Review Worksheet, which is available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agencywide Documents Access and Management System (ADAMS). (ADAMS Accession Number ML15175A057)
On June 19, 2015, the licensee submitted post-examination documentation noting that there were no post-examination comments for consideration by the NRC examiners when grading the written examination. The proposed written examination (ADAMS Accession Number ML15167A522), as well as the final as-administered written examination and answer key (ADAMS Accession Number ML15174A018), will be available in 24 months electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS.
The NRC examiners graded the written examination on June 25, 2015, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.
- (2) Operating Test The NRC examiners determined that the operating test, as originally proposed by the licensee, was within the range of acceptability expected for a proposed examination.
Changes made to the operating test, documented in a document titled, Operating Test Comments, as well as the final as-administered dynamic simulator scenarios and JPMs, are available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS. (ADAMS Accession Number ML15176A538)
The NRC examiners completed operating test grading on June 29, 2015.
- (3) Examination Results Seven applicants at the Senior Reactor Operator level and six applicants at the Reactor Operator level were administered written examinations and operating tests. All thirteen applicants passed all portions of their examinations and were issued their respective operating licenses.
.2 Examination Security
a. Scope
The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title10 of the Code of Federal Regulations, Section 55.49, Integrity of Examinations and Tests. The examiners used the guidelines provided in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors, to determine acceptability of the licensees examination security activities.
b. Findings
No findings were identified.
4OA6 Management Meetings
.1 Debrief
The chief examiner presented the examination team's preliminary observations and findings on June 10, 2015, to Mr. P. Gardner, and other members of the Monticello Nuclear Generating Plant Operations and Training Department staff.
.2 Exit Meeting
The chief examiner conducted an exit meeting on June 23, 2015, with Mr. T Shortell, Monticello Nuclear Generating Plant Training Manager, by telephone. The NRC confirmed there were no post-examination comments. The chief examiner asked Mr. Shortell whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
- P. Gardner, Site Vice President
- G. Allex, General Superintendent, Operations Training
- R. Becker, Ops Instructor
- H. Hansen Jr., Plant Manager
- B. Koenig, Shift Manager
- A. Kouba, Reg. Affairs
- C. Peterson, ILT Supervisor
- K. Scott, Director Site Operations
- T. Shortell, Training Manager
- S. Spillum, Supervisor, Operations Training
- A. Ward, Manager, Reg. Affairs
- T. Witschen, Operations Manager
U.S. Nuclear Regulatory Commission
- P. Zurawski, Senior Resident Inspector
- P. Voss, Resident Inspector
- D. McNeil, Chief Examiner
- M. Bielby, Examiner
- L. Vick, Examiner
- J. Seymour, Examiner
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened, Closed, and Discussed
None
LIST OF ACRONYMS USED
Agencywide Documents Access and Management System
CFR
Code of Federal Regulations
Monticello Nuclear Generating Plant
NRC
U.S. Nuclear Regulatory Commission
Publicly Available Records System
SIMULATION FACILITY FIDELITY REPORT
Facility Licensee:
Monticello Nuclear Generating Plant
Facility Docket No:
50-263
Operating Tests Administered:
June 2 - 9, 2015
The following documents observations made by the NRC examination team during the initial
operator license examination. These observations do not constitute audit or inspection findings
and are not, without further verification and review, indicative of non-compliance with
CFR 55.45(b). These observations do not affect NRC certification or approval of the
simulation facility other than to provide information which may be used in future evaluations.
No licensee action is required in response to these observations.
During the conduct of the simulator portion of the operating tests, the following items were
observed:
ITEM
DESCRIPTION
Voltmeter
During administration of a JPM to sync the main generator to the grid,
a voltmeter used to sync the generator did not read as expected.
Simulator
The simulator halted during a reset between JPMs. (AR01482777)
Feed Pumps
Feed pumps were started multiple times without reference to start
requirements - may trip on high temperature in the plant.
P. Gardner
-2-
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections,
Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its
enclosures, and your response (if any) will be available electronically for public inspection in the NRCs
Public Document Room or from the Publicly Available Records (PARS) component of the NRC's
Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the
NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief
Operations Branch
Division of Reactor Safety
Docket No. 50-263
License No. DPR-22
Enclosures:
1. Operator Licensing Examination
Report 05000263/2015301
2. Simulation Facility Fidelity Report
cc w/encls: Distribution via ListServ
DISTRIBUTION w/encls:
Kimyata MorganButler
RidsNrrDorlLpl3-1 Resource
RidsNrrPMMonticello
RidsNrrDirsIrib Resource
Cynthia Pederson
DRPIII
DRSIII
Scott Sloan
ADAMS Accession Number ML15196A369
Publicly Available
Non-Publicly Available
Sensitive
Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE
RIII
N RIII
RIII
RIII
NAME
DMcNeil:jw
HPeterson
DATE
07/10/15
07/15/15
OFFICIAL RECORD COPY