MONTHYEARML24283A1192024-10-28028 October 2024 Letter to Shawn Hafen, Re Monticello Subsequent License Renewal Schedule Change L-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 ML24199A1752024-10-0101 October 2024 Issuance of Amendment No. 212 Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 ML24128A0042024-05-0909 May 2024 Letter to Minnesota State Historic Preservation Office- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renewal Application ML24127A1472024-05-0909 May 2024 Letter to Mille Lacs Band- Section 106 Consultation Regarding the Monticello Nuclear Generating Plant Subsequent License Renew. Application L-MT-24-016, 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP)2024-05-0808 May 2024 2023 Annual Report of Individual Monitoring for the Monticello Nuclear Generating Plant (MNGP) ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance IR 05000263/20240012024-04-29029 April 2024 Plan - Integrated Inspection Report 05000263/2024001 ML24115A2902024-04-25025 April 2024 Sec106 Tribal, Jackson-Street, Lonna-Spirit Lake Nation ML24115A2872024-04-25025 April 2024 Sec106 Tribal, Dupuis, Kevin-Fond Du Lac Band of Lake Superior Chippewa ML24115A2932024-04-25025 April 2024 Sec106 Tribal, Johnson, Grant-Prairie Island Indian Community ML24115A3062024-04-25025 April 2024 Sec106 Tribal, Wassana, Reggie-Cheyenne and Arapaho Tribes 05000263/LER-2024-001, Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component2024-04-25025 April 2024 Reactor Scram, Containment Isolation, and Cooldown Rate Outside of Limits Following Technician Adjustment of Wrong Component ML24115A3032024-04-25025 April 2024 Sec106 Tribal, Taylor, Louis-Lac Courte Oreilles Band of Lake Superior Chippewa Indians ML24115A3002024-04-25025 April 2024 Sec106 Tribal, Rhodd, Timothy-Iowa Tribe of Kansas and Nebraska ML24115A2972024-04-25025 April 2024 Sec106 Tribal, Miller, Cole-Shakopee Mdewakanton Sioux Community ML24115A2962024-04-25025 April 2024 Sec106 Tribal, Larsen, Robert-Lower Sioux Indian Community ML24115A2952024-04-25025 April 2024 Sec106 Tribal, Kakkak, Gena-Menominee Indian Tribe of Wisconsin ML24115A2982024-04-25025 April 2024 Sec106 Tribal, Reider, Anthony-Flandreau Santee Sioux Tribe ML24115A2912024-04-25025 April 2024 Sec106 Tribal, Jacskon, Sr., Faron-Leech Lake Band of Ojibwe ML24115A3052024-04-25025 April 2024 Sec106 Tribal, Vanzile, Jr., Robert-Sokaogon Chippewa Community ML24115A2992024-04-25025 April 2024 Sec106 Tribal, Renville, J. Garret-Sisseton Wahpeton Oyate of the Lake Travers Reservation ML24115A3022024-04-25025 April 2024 Sec106 Tribal, Stiffarm, Jeffrey-Fort Belknap Indian Community ML24115A3072024-04-25025 April 2024 Sec106 Tribal, Williams, Jr., James-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24115A2892024-04-25025 April 2024 Sec106 Tribal, Fowler, Thomas-St. Croix Chippewa of Wisconsin 2024-09-26
[Table view] |
Text
UNITED STATES tember 2, 2014
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1, TEMPORARY INSTRUCTION 2201/004, IMPLEMENTATION OF INTERIM CYBER SECURITY MILESTONES 1 - 7 INSPECTION REPORT 05000263/2014403
Dear Ms. Fili:
On July 25, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Monticello Nuclear Generating Plant, Unit 1. The inspection covered the interim cyber security Milestones 1 - 7 of the security cornerstone. The enclosed inspection report documents the inspection results, which were discussed on July 25, 2014, with Mr. Harlan Hanson Jr. and other members of your staff.
The inspection examined activities conducted under your license as they relate to cyber security and compliance with the Commissions rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Two NRC-identified findings of very low significance (Green) were identified during this inspection. The findings were determined to involve violations of NRC requirements. Further, one licensee-identified violation which was determined to be of very low significance (Green),
is listed in Section 4OA7 of this report. The NRC is treating these violations as Non-Cited Violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy. However, in accordance with the Security Issues Forum (SIF) Charter, the NRC may exercise enforcement discretion during inspection of the interim cyber security measures for licensees who demonstrate a good-faith interpretation and attempt to implement Milestones 1 - 7. This discretion applies to licensees who have tried to implement the new requirements, but failed to be in full compliance. Before discretion is considered or granted for any issue, licensees must accept the finding, put the finding into their Corrective Action Program (CAP), and take appropriate corrective action once identified These issues were discussed and reviewed during the Security Issues Forum (SIF) Meeting conducted on August 6, 2014. The results of the SIF Panel review concluded that although these issues constituted violations of your facility operating license (FOL) and Title 10, Code of Federal Regulations (CFR), Part 73, Section 54, Protection of Digital Computer and Enclosure contains Sensitive Unclassified Non-Safeguards Information.
When separated from enclosure, this transmittal document is decontrolled. Communication Systems and Networks, the NRC is exercising enforcement discretion. The NRC is not taking enforcement action for these violations because they meet the criteria established in an NRC memorandum from Barry C. Westreich, Director, Cyber Security Directorate, Office of Nuclear Security and Incident Response, to each Regional Office and Director, Division of Reactor Safety, Subject: Enhanced Guidance for Licensee Near-Term Corrective Actions to Address Cyber Security Inspection Findings and Licensee Eligibility for Good-Faith Attempt Discretion dated July 1, 2013, (ADAMS Accession Number ML13178A203). Consistent with the NRC Memorandum, upon completion of all corrective actions, you are requested to provide written notification to the NRCs regional office as to the method and date of closure for the identified issue(s).
In accordance with Title 10, Code of Federal Regulations (CFR), Part 2, Section 390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA/
Robert C. Daley, Chief Engineering Branch 3 Division of Reactor Safety Docket No.: 50-263 License No.: DPR-22 Nonpublic Enclosure:
Inspection Report 05000236/2014403 w/Attachment: Supplemental Information cc w/o encl: Distribution via LISTSERV cc w/encl: K. Nyberg, Monticello Nuclear Generating Plant, Security Manager B. Westreich, NSIR R. Felts, NSIR J. Rogge, RI S. Shaeffer, RII J. Dixon, RIV N. Coleman, OE