MONTHYEARIR 05000255/20244022024-09-0606 September 2024 Public: Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2024402 IR 05000255/20240022024-08-0909 August 2024 NRC Inspection Report No. 05000255/2024002 IR 05000255/20240112024-07-15015 July 2024 Nuclear Plant - Restart Inspection Report 05000255/2024011 IR 05000255/20240012024-05-10010 May 2024 NRC Inspection Report No. 05000255/2024001 IR 05000255/20244012024-04-0909 April 2024 – Decommissioning Security Inspection Report 05000255/2024401 IR 05000255/20240102024-03-20020 March 2024 Plant Reference Simulator Inspection Report 05000255/2024010 IR 05000255/20230042024-02-20020 February 2024 NRC Inspection Report 05000255/2023004(DRSS) Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20230032023-10-0404 October 2023 NRC Inspection Report No. 05000255/2023003(DRSS)-Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20230022023-07-19019 July 2023 NRC Inspection Report 05000255/2023002 DRSS-Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20220032022-12-28028 December 2022 NRC Inspection Report No. 05000255/2022003(DRSS); 07200007/2022001 (Drss) – Holtec Decommissioning International, LLC, Palisades Nuclear Plant IR 05000255/20224012022-11-0909 November 2022 Decommissioning Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2022401 IR 05000255/20220022022-08-0303 August 2022 Integrated Inspection Report 05000255/2022002 IR 05000255/20220012022-05-13013 May 2022 Integrated Inspection Report 05000255/2022001 IR 05000255/20220102022-04-0101 April 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000255/2022010 IR 05000255/20210062022-03-0202 March 2022 Annual Assessment Letter for Palisades Nuclear Plant, Unit 1, (Report 05000255/2021006) IR 05000255/20210102022-02-24024 February 2022 Triennial Fire Protection Inspection Report 05000255/2021010 IR 05000255/20210042022-02-0808 February 2022 Integrated Inspection Report 05000255/2021004 and Exercise of Enforcement Discretion IR 05000255/20214042021-11-15015 November 2021 NRC Independent Spent Fuel Storage Installation Security Inspection Report 05000255/2021404 and 07200007/2021401 IR 05000255/20210032021-11-0303 November 2021 Integrated Inspection Report 05000255/2021003 IR 05000255/20214032021-10-21021 October 2021 Material Control and Accounting Program Inspection Report 05000255/2021403 IR 05000255/20214022021-10-0606 October 2021 Security Baseline Inspection Report 05000255/2021402 IR 05000255/20210052021-09-0101 September 2021 Updated Inspection Plan for Palisades Nuclear Plant (Report 05000255/2021005) IR 05000255/20210022021-08-10010 August 2021 Integrated Inspection Report 05000255/2021002 ML21197A0322021-07-21021 July 2021 Review of the Fall 2020 Steam Generator Tube Inspection Report IR 05000255/20210012021-05-12012 May 2021 Integrated Inspection Report 05000255/2021001 IR 05000255/20214012021-04-14014 April 2021 Security Baseline Inspection Report 05000255/2021401 IR 05000255/20200062021-03-0404 March 2021 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2020006) IR 05000255/20200042021-02-11011 February 2021 Integrated Inspection Report 05000255/2020004 IR 05000255/20204012021-01-0606 January 2021 Security Baseline Inspection Report 05000255/2020401 ML20342A1812020-12-10010 December 2020 Security Inspection Report Cover Letter 05000255/2020420 IR 05000255/20204202020-12-10010 December 2020 Security Inspection Report 05000255/2020420 IR 05000255/20204022020-11-30030 November 2020 Cyber Security Inspection Report 05000255/2020402 IR 05000255/20205012020-11-20020 November 2020 Emergency Preparedness Inspection Report 05000255/2020501 IR 05000255/20200032020-11-13013 November 2020 Integrated Inspection Report 05000255/2020003 IR 05000255/20200052020-09-0101 September 2020 Updated Inspection Plan for Palisades Nuclear Plant (Report 05000255/2020005) IR 05000255/20200102020-08-24024 August 2020 Biennial Problem Identification and Resolution Inspection Report 05000255/2020010 IR 05000255/20203012020-08-13013 August 2020 NRC Initial License Examination Report 05000255/2020301 IR 05000255/20200022020-08-11011 August 2020 Integrated Inspection Report 05000255/2020002 and Exercise of Enforcement Discretion IR 05000255/20010082020-05-12012 May 2020 Final ASP Analysis - Palisades (IR 050002552001008) IR 05000255/20200012020-05-12012 May 2020 Integrated Inspection Report 05000255/2020001 IR 05000255/20200112020-04-21021 April 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000255/2020011 IR 05000254/20204012020-03-23023 March 2020 Security Baseline Inspection Report 05000254/2020401 and 05000265/2020401 IR 05000255/20190062020-03-0303 March 2020 Annual Assessment Letter Palisades Nuclear Plant (Report 05000255/2019006) IR 05000255/20190042020-01-28028 January 2020 Integrated Inspection Report 05000255/2019004 and 07200007/2019001 ML19357A2752019-12-23023 December 2019 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000255/2020011 IR 05000255/20190112019-11-27027 November 2019 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000255/2019011 IR 05000255/20194112019-11-25025 November 2019 Security Baseline Inspection Report 05000255/2019411 and Independent Spent Fuel Storage Security Inspection Report 07200007/2019401 (Cover Letter Only) (DRS-M.Ziolkowski) IR 05000255/20190032019-11-14014 November 2019 Integrated Inspection Report 05000255/2019003 IR 05000255/20190102019-10-29029 October 2019 Reissue - Palisades Nuclear Plant - Design Basis Assurance Inspection (Programs) Inspection Report 05000255/2019010 ML19294A2872019-10-21021 October 2019 Design Basis Assurance Inspection (Programs) Inspection Report 05000255/2019010 2024-09-06
[Table view] Category:Letter
MONTHYEARML24312A2262024-11-0606 November 2024 Letter from C. Nelson, Michigan SHPO Regarding Palisades Nuclear Plant Architectural Survey ML24292A1572024-11-0505 November 2024 Ape Notification to Burt Lake Band Palisades ML24310A0142024-11-0505 November 2024 Ape Notification to Mackinac Bands of Chippewa Palisades ML24310A0132024-11-0505 November 2024 Ape Notification to Grand River Bands of Ottawa Indians Palisades ML24309A2032024-11-0404 November 2024 Ape Notification to Ottawa Tribe of Oklahoma Palisades ML24309A1972024-11-0404 November 2024 Ape Notification to Little Traverse Bay Bands of Odawa Indians Palisades ML24309A1982024-11-0404 November 2024 Ape Notification to Match E Be Nash She Wish Band of Pottawatomi Indians Palisades ML24309A1872024-11-0404 November 2024 Ape Notification to Grand Portage Band of Lake Superior Chippewa Palisades ML24309A2072024-11-0404 November 2024 Ape Notification to Quechan Tribe of the Fort Yuma Indian Reservation Palisades ML24309A1832024-11-0404 November 2024 Ape Notification to Bois Forte Band of the Minnesota Chippewa Tribe Palisades ML24309A2122024-11-0404 November 2024 Ape Notification to Sault Ste. Marie Tribe of Chippewa Indians Palisades ML24309A2042024-11-0404 November 2024 Ape Notification to Pokagon Band of Potawatomi Indians Palisades ML24292A0492024-11-0404 November 2024 Ape Notification to Bad River Band of the Lake Superior Tribe of Chippewa Indians Palisades ML24309A1932024-11-0404 November 2024 Ape Notification to Leech Lake Band of Ojibwe Palisades ML24309A2012024-11-0404 November 2024 Ape Notification to Mille Lacs Band of Ojibwe Palisades ML24309A1922024-11-0404 November 2024 Ape Notification to Lac Vieux Desert Band of Lk Superior Chippewa Indians Palisades ML24309A1892024-11-0404 November 2024 Ape Notification to Hannahville Indian Community Palisades ML24309A2002024-11-0404 November 2024 Ape Notification to Miami Tribe of Oklahoma Palisades ML24309A1952024-11-0404 November 2024 Ape Notification to Little River Band of Ottawa Indians Palisades ML24309A2112024-11-0404 November 2024 Ape Notification to Saint Croix Chippewa Indians of Wisconsin Palisades ML24309A1902024-11-0404 November 2024 Ape Notification to Lac Courte Oreilles Band of Lake Superior Chippewa Palisades ML24309A2022024-11-0404 November 2024 Ape Notification to Nottawaseppi Huron Band of the Potawatomi Palisades ML24309A1852024-11-0404 November 2024 Ape Notification to Citizen Potawatomi Nation Palisades ML24309A2142024-11-0404 November 2024 Ape Notification to White Earth Band of Minnesota Chippewa Tribe Palisades ML24309A2092024-11-0404 November 2024 Ape Notification to Red Lake Band of Chippewa Indians Palisades ML24309A1862024-11-0404 November 2024 Ape Notification to Forest County Potawatomi Community Palisades ML24309A1822024-11-0404 November 2024 Ape Notification to Bay Mills Indian Community Palisades ML24309A2052024-11-0404 November 2024 Ape Notification to Prairie Band Potawatomi Nation Palisades ML24309A2102024-11-0404 November 2024 Ape Notification to Saginaw Chippewa Indian Tribe of Michigan Palisades ML24309A2082024-11-0404 November 2024 Ape Notification to Red Cliff Band of Lake Superior Chippewa Indians Palisades ML24309A1992024-11-0404 November 2024 Ape Notification to Menominee Indian Tribe of Wisconsin Palisades ML24292A0072024-11-0404 November 2024 Ape Notification to Achp Palisades ML24309A1882024-11-0404 November 2024 Ape Notification to Grand Traverse Band of Ottawa and Chippewa Indians Palisades ML24309A1842024-11-0404 November 2024 Ape Notification to Chippewa Cree Indians of the Rocky Boys Reservation of Montana Palisades ML24309A1912024-11-0404 November 2024 Ape Notification to Lac Du Flambeau Band of Lake Superior Chippewa Indians Palisades ML24309A2132024-11-0404 November 2024 Ape Notification to Turtle Mountain Band of Chippewa Indians Palisades ML24309A2062024-11-0404 November 2024 Ape Notification to Prairie Island Indian Community Palisades PNP 2024-014, Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances2024-10-0909 October 2024 Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances PNP 2024-037, Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-0202024-10-0404 October 2024 Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-020 ML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24263A1712024-09-20020 September 2024 Environmental Request for Additional Information ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24219A4202024-09-12012 September 2024 Change in Estimated Hours and Review Schedule for Licensing Actions Submitted to Support Resumption of Power Operations (Epids L-2023-LLE-0025, L-2023-LLM-0005, L-2023-LLA-0174, L-2024-LLA-0013, L-2024-LLA-0060, L-2024-LLA-0071) IR 05000255/20244022024-09-0606 September 2024 Public: Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2024402 PNP 2024-029, Notice of Payroll Transition at Palisades Nuclear Plant2024-08-15015 August 2024 Notice of Payroll Transition at Palisades Nuclear Plant IR 05000255/20240022024-08-0909 August 2024 NRC Inspection Report No. 05000255/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-032, Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-07-31031 July 2024 Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations ML24206A0572024-07-25025 July 2024 PRM-50-125 - Letter to Alan Blind; Docketing of Petition for Rulemaking and Sufficiency Review Status (10 CFR Part 50) PNP 2024-033, Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-07-24024 July 2024 Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations 2024-09-06
[Table view] |
Text
ber 8, 2008
SUBJECT:
PALISADES NUCLEAR PLANT BASELINE EMERGENCY PREPAREDNESS BIENNIAL EXERCISE INSPECTION 05000255/2008502
Dear Mr. Schwarz:
On September 19, 2008, the U. S. Nuclear Regulatory Commission (NRC) completed a Baseline Emergency Preparedness Biennial Exercise inspection at your Palisades Nuclear Plant. The enclosed report documents the inspection findings, which were discussed on September 19, 2008, with members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no NRC-identified and no self-revealed findings of safety significance were identified.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-255 License No. DPR-20 Enclosure: Inspection Report 05000255/2008502 w/Attachment: Supplemental Information cc w/encl: Senior Vice President Vice President Oversight Senior Manager, Nuclear Safety & Licensing Senior Vice President and COO Assistant General Counsel Manager, Licensing W. DiProfio W. Russell G. Randolph Supervisor, Covert Township Office of the Governor T. Strong, State Liaison Officer Michigan Department of Environmental Quality Michigan Office of the Attorney General
SUMMARY OF FINDINGS
IR 05000255/2008502; 09/15/2008 - 09/19/2008; Palisades Nuclear Plant; Baseline Emergency
Preparedness Biennial Exercise Inspection.
This report covers a 1 week period of baseline inspection by two regional inspectors and a resident inspector. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.
NRC-Identified
and Self-Revealed Findings
Cornerstone: Emergency Preparedness
No findings of significance were identified.
Licensee-Identified Violations
No violations of significance were identified.
REPORT DETAILS
REACTOR SAFETY
Cornerstone: Emergency Preparedness
1EP1 Exercise Evaluation
Main article: IP 71114.01
.1 Exercise Evaluation
a. Inspection Scope
The inspectors reviewed the September 16, 2008, biennial emergency preparedness exercises objectives and scenario to ensure that the exercise would acceptably test major elements of the licensees emergency plan and to verify that the exercises simulated problems provided an acceptable framework to support demonstration of the licensees capability to implement its plan. The inspectors also reviewed records of other drills and exercises conducted in 2006, 2007, and 2008, to verify that those drills scenarios were sufficiently different from the scenario used in the September 16, 2008, exercise.
The inspectors evaluated the licensees exercise performance, focusing on the risk significant activities of emergency classification, notification, and protective action decision making, implementation of accident mitigation strategies, and correction of past exercise weaknesses in the following emergency response facilities:
- Control Room Simulator (CRS);
- Emergency Operations Facility (EOF).
The inspectors also assessed the licensees recognition of abnormal plant conditions, transfer of responsibilities between facilities, internal communications, interfaces with offsite officials, readiness of emergency facilities and related equipment, and overall implementation of the licensees emergency plan.
The inspectors attended post-exercise critiques in the CRS, TSC, and EOF to evaluate the licensees initial self-assessment of its exercise performance. The inspectors later met with the licensees lead exercise evaluators and managers to obtain the licensees findings and assessments of its exercise participants performances. These self-assessments were then compared with the inspectors independent observations and assessments to assess the licensees ability to adequately critique its exercise performance. Documents reviewed are listed in the Attachment to this report.
This exercise evaluation inspection constituted one sample as defined in Inspection Procedure (IP) 71114.01-05.
b. Findings
No findings of significance were identified.
OTHER ACTIVITIES
4OA1 Performance Indicator Verification
.1 Drill/Exercise Performance
a. Inspection Scope
The inspectors sampled licensee submittals for the Drill/Exercise Performance performance indicator (PI) for the period from the 3rd quarter 2007 through the 2nd quarter 2008. To determine the accuracy of the PI data reported during those periods, PI definitions and guidance contained in the Nuclear Energy Institute (NEI)
Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5, were used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the NEI guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the PI; assessments of PI opportunities during predesignated control room simulator training sessions, performance during the 2007 off-year exercise, and performance during other drills. Documents reviewed are listed in the Attachment to this report.
This inspection constituted one drill/exercise performance sample as defined in IP 71151-05.
b. Findings
No findings of significance were identified.
.2 Emergency Response Organization Drill Participation
a. Inspection Scope
The inspectors sampled licensee submittals for the Emergency Response Organization (ERO) Drill Participation performance indicator for the period from the 3rd quarter 2007 through the 2nd quarter 2008. To determine the accuracy of the PI data reported during those periods, PI definitions and guidance contained in the NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5, were used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the NEI guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the PI; performance during the 2007 offyear exercise and other drills; and revisions of the roster of personnel assigned to key emergency response organization positions.
Documents reviewed are listed in the Attachment to this report.
This inspection constituted one ERO drill participation sample as defined in IP 71151-05.
b. Findings
No findings of significance were identified.
.3 Alert and Notification System
a. Inspection Scope
The inspectors sampled licensee submittals for the Alert and Notification System (ANS)performance indicator for the period from the 3rd quarter 2007 through the 2nd quarter 2008. To determine the accuracy of the PI data reported during those periods, PI definitions and guidance contained in the NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 5, were used. The inspectors reviewed the licensees records associated with the performance indicator to verify that the licensee accurately reported the indicator in accordance with relevant procedures and the NEI guidance. Specifically, the inspectors reviewed licensee records and processes including procedural guidance on assessing opportunities for the PI and results of periodic ANS operability tests. Documents reviewed are listed in the Attachment to this report.
This inspection constituted one alert and notification system sample as defined in IP 71151-05.
b. Findings
No findings of significance were identified.
4OA6 Management Meetings
.1 Exit Meeting Summary
- On September 19, 2008, the inspectors presented the inspection results to you and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors confirmed that none of the potential report input discussed was considered proprietary.
.2 Public and Media Briefing
- On September 19, 2008, the inspector summarized the NRC's preliminary exercise inspection conclusions at a public and media briefing hosted by Department of Homeland Security/Federal Emergency Management Agency Region V Field Office staff in Paw Paw, Michigan.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee
- C. Schwarz, Site Vice President
- C. Arnone, Nuclear Safety Assurance Director
- J. Bergeron, Maintenance Superintendant
- N. Brott, Emergency Preparedness Coordinator
- B. Dotson, Licensing Specialist IV
- M. Fields, Emergency Preparedness Specialist
- J. Fontaine, Emergency Preparedness Coordinator
- A. Jones, Quality Assurance
- T. Kirwin, Plant General Manger
- L. Lahti, Licensing Manager
- D. Malone, Emergency Preparedness Manager
- W. Nelson, Emergency Preparedness Training
- M. Sweet, Emergency Preparedness Coordinator
Nuclear Regulatory Commission
- J. Giessner, Resident Inspector
LIST OF ITEMS
OPENED, CLOSED AND DISCUSSED
Opened, Closed and
Discussed
None Attachment
LIST OF DOCUMENTS REVIEWED