Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station, Units 1 and 2 Report 05000254/2025005 05000265/2025005
ML25237A226
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 08/25/2025
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
DPR-029, DPR-030 IR 2025005
Download: ML25237A226 (1)


Text

SUBJECT:

UPDATED INSPECTION PLAN AND ASSESSMENT FOLLOW-UP LETTER FOR QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 (REPORT 05000254/2025005; 05000265/2025005)

Dear David Rhodes:

The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for Quad Cities Nuclear Power Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025 (ML25042A278), the NRC determined that a broad, comprehensive review of the ROP is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented.

In its annual assessment letter dated March 11, 2025, (ML25069A600), the NRC opened a cross-cutting issue (CCI) with the aspect of conservative bias (H14). This assessment follow-up letter serves as the second consecutive letter documenting a CCI with the same cross-cutting aspect. To address the CCI, your staff is performing an evaluation to identify the causes of the behaviors and develop a plan to address the safety culture behavior underlying the cause(s) of the CCI. As discussed in full detail in the annual assessment letter, this CCI will remain open until the NRC has performed its 71152 inspection of your evaluation and you have satisfied the closure criteria.

August 25, 2025

D. Rhoades

This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at 630-829-9732 with any questions you have regarding this letter.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000254, 05000265, and 07200053 License Nos. DPR-29 and DPR-30 Enclosure:

Inspection Plan cc: Distribution via LISTSERV Signed by Ruiz, Robert on 08/25/25

ML25237A226

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE RIII RIII NAME NShah:gmp RRuiz DATE 08/25/2025 08/25/2025

Site Inspection Activity Plan Quad Cities 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Cyber Security Inspection - QUAD

1,2 8/25/2025 8/29/2025 IP 71130.10 000741 Cybersecurity Security Baseline Inspection - QUAD

1,2 9/8/2025 9/12/2025 IP 71130.02 000734 Access Control 1,2 9/8/2025 9/12/2025 IP 71130.09 001656 Security Plan Changes 1,2 9/8/2025 9/12/2025 IP 71151 001338 Performance Indicator Verification 1,2 9/8/2025 9/12/2025 IP 81311 000831 Physical Security Requirements for Independent Spent Fuel Storage Installations 1,2 10/13/2025 10/17/2025 IP 71130.07 000739 Security Training Emergency Preparedness Program Inspection / Performance Indicator Review - QUAD

1,2 9/29/2025 10/3/2025 IP 71114.02 000717 Alert and Notification System Testing 1,2 9/29/2025 10/3/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 9/29/2025 10/3/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 9/29/2025 10/3/2025 IP 71151 001397 Performance Indicator Verification Quad Cities 2025 Biennial Licensed Operator Requalification Inspection

1 10/5/2025 10/11/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Quad Cities December 2025 Initial License Examination

1,2 10/26/2025 11/1/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 12/7/2025 12/13/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Eplan and EAL Changes Review - QUAD

1,2 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Functional Engineering Inspection - Fire Protection - QUAD

1,2 11/3/2025 11/21/2025 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Corporate Security Baseline Inspection - QUAD

1,2 1/19/2026 1/23/2026 IP 71130.01 000733 Access Authorization 1,2 1/19/2026 1/23/2026 IP 71130.08 000740 Fitness-For-Duty Program Emergency Preparedness Exercise Inspection / Performance Indicator Verification - QUAD

1,2 2/23/2026 2/27/2026 IP 71114.01 000716 Exercise Evaluation 1,2 2/23/2026 2/27/2026 IP 71114.08 000723 Exercise Evaluation - Scenario Review 1,2 2/23/2026 2/27/2026 IP 71151 001397 Performance Indicator Verification Security Baseline Inspection - QUAD

1,2 3/16/2026 3/20/2026 IP 71130.01 000733 Access Authorization 1,2 3/16/2026 3/20/2026 IP 71130.02 000734 Access Control Prepared on 8/20/2025 7:28:23 AM 1 of 4

Site Inspection Activity Plan 1,2 3/16/2026 3/20/2026 IP 71130.08 000740 Fitness-For-Duty Program Inservice Inspection - Unit 2 - QUAD

2 3/23/2026 4/3/2026 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Radiation Protection Baseline Inspection - QUAD

1,2 3/30/2026 4/3/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 3/30/2026 4/3/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 3/30/2026 4/3/2026 IP 71124.04 000728 Occupational Dose Assessment 1,2 3/30/2026 4/3/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation Baseline Security Inspection - QUAD

1,2 4/20/2026 4/24/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2 4/20/2026 4/24/2026 IP 71130.09 001656 Security Plan Changes 1,2 4/20/2026 4/24/2026 IP 71151 001338 Performance Indicator Verification PENDING Radiation Protection Baseline Inspection - QUAD

1,2 5/11/2026 5/15/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation Functional Engineering Inspection - Commercial Grade Dedication - QUAD

1,2 5/18/2026 6/5/2026 IP 71111.21N.03 001808 Commercial Grade Dedication Security Baseline Inspection - QUAD

1,2 8/17/2026 8/21/2026 IP 71130.14 000743 Review of Power Reactor Target Sets Quad Cities 2026 Biennial Problem Identification and Resolution Inspection

1,2 9/14/2026 10/2/2026 IP 71152B 000747 Problem Identification and Resolution EAL & EPlan Changes Review - QUAD

1,2 11/1/2026 12/31/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Security Baseline Inspection - QUAD

1,2 1/25/2027 1/29/2027 IP 71130.02 000734 Access Control 1,2 1/25/2027 1/29/2027 IP 71130.09 001656 Security Plan Changes Quad Cities Unit 1 Inservice Inspection

1 3/15/2027 4/9/2027 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Radiation Protection Baseline Inspection - QUAD

1,2 3/15/2027 3/19/2027 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 3/15/2027 3/19/2027 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 3/15/2027 3/19/2027 IP 71124.04 000728 Occupational Dose Assessment Quad Cities June 2027 Initial License Examination

1,2 5/23/2027 5/29/2027 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 6/20/2027 7/3/2027 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Force-on-Force Planning and Exercise Weeks - QUAD

1,2 5/24/2027 5/28/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Prepared on 8/20/2025 7:28:23 AM 2 of 4

Site Inspection Activity Plan 1,2 6/21/2027 6/25/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Radiation Protection Baseline Inspection - QUAD

1,2 6/7/2027 6/11/2027 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment Emergency Preparedness Program Inspection / Performance Indicator Review - QUAD

1,2 6/21/2027 6/25/2027 IP 71114.02 000717 Alert and Notification System Testing 1,2 6/21/2027 6/25/2027 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 6/21/2027 6/25/2027 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 6/21/2027 6/25/2027 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 6/21/2027 6/25/2027 IP 71151 001397 Performance Indicator Verification Prepared on 8/20/2025 7:28:23 AM 3 of 4

Site Inspection Activity Plan Quad Cities 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count ISFSI Security Inspection

9/8/2025 9/12/2025 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations Security Baseline Inspection

1/25/2027 1/29/2027 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations Prepared on 8/20/2025 7:28:23 AM 4 of 4