IR 05000254/2019003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000254/2019003 and 05000265/2019003
ML19304B518
Person / Time
Site: Quad Cities  
Issue date: 10/31/2019
From: Kenneth Riemer
NRC/RGN-III
To: Bryan Hanson
Exelon Generation Co
References
IR 2019003
Download: ML19304B518 (16)


Text

October 31, 2019

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000254/2019003 AND 05000265/2019003

Dear Mr. Hanson:

On September 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Quad Cities Nuclear Power Station, Units 1 and 2. On October 1, 2019, the NRC inspectors discussed the results of this inspection with Mr. P. Boyle, Acting Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Kenneth R. Riemer, Chief Branch 1 Division of Reactor Projects

Docket Nos. 05000254 and 05000265 License Nos. DPR-29 and DPR-30

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000254 and 05000265

License Numbers:

DPR-29 and DPR-30

Report Numbers:

05000254/2019003 and 05000265/2019003

Enterprise Identifier: I-2019-003-0061

Licensee:

Exelon Generation Company, LLC

Facility:

Quad Cities Nuclear Power Station, Units 1 and 2

Location:

Cordova, IL

Inspection Dates:

July 01, 2019 to September 30, 2019

Inspectors:

J. Cassidy, Senior Health Physicist

M. Garza, Emergency Preparedness Inspector

C. Mathews, Illinois Emergency Management Agency

R. Murray, Senior Resident Inspector

C. Norton, Senior Resident Inspector

D. Tesar, Resident Inspector

Approved By:

Kenneth R. Riemer, Chief

Branch 1

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Quad Cities Nuclear Power Station,

Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

A licensee-identified non-cited violation is documented in report section: 71124.0

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 The unit began the inspection period at full rated thermal power, where it remained until August 25, 2019, with the exception of short term power reductions as requested by the transmission system operator. On August 25, 2019, the unit experienced an automatic SCRAM following the actuation of the Unit 1 main generator ground fault detection relay. The licensee entered Mode 2 on August 29, 2019, and commenced startup. The unit entered Mode 1 on August 30, 2019.

Following replacement of several insulators on the 'A' phase of the isophase bus duct leading to the unit auxiliary transformer, the licensee synchronized to the grid and achieved full power on September 1, 2019. The unit remained at or near full power for the remainder of the inspection period.

Unit 2 The unit began the inspection period at full rated thermal power, where it remained for the entire inspection period, with the exception of short term power reductions as requested by the transmission system operator.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated readiness for impending adverse weather conditions for extreme hot temperatures expected for the week of July 15, 2019.

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2 emergency diesel generator during 1/2 emergency diesel generator surveillance test on July 22, 2019
(2) Unit 1/2 and Unit 2 emergency diesel generator during extended maintenance on Unit 1 emergency diesel generator on September 9, 2019
(3) Unit 2A, 'B', and 'D' residual heat removal service water loops during planned maintenance on Unit 2C residual heat removal service water loop on September 17, 2019

71111.04S - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (2 Samples)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1/2 emergency diesel generator and Unit 2 emergency diesel generator during residual heat removal outage on June 16, 2019.
(2) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 standby liquid control system following air sparge for chemistry sample on August 1, 2019.

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Fire Zone 8.2.6.E; Unit 2 turbine building, elevation 595'-0", hallway on June 25, 2019
(2) Fire Zones 8.2.7.A, 6.1.A, 6.1.B, and 7.1; Unit 2 turbine building, elevation 615' and 628', battery charger rooms, hydrogen seal oil areas, and battery room on September 17, 2019
(3) Fire Zones 8.2.7.E, 6.2.A, 6.2.B, and 7.2; Unit 1 turbine building, elevation 615' and 628', battery charger rooms, hydrogen seal oil areas, and battery room on September 18, 2019
(4) Fire Zone 11.2.1; Unit 1 reactor building, elevation 554'-0", southwest corner room, 1B core spray on September 19, 2019
(5) Fire Zone 11.2.3; Unit 1 reactor building, elevation 554'-0", northwest corner room, 1A core spray on September 19, 2019

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the Unit 1 startup from Forced Outage Q1F67 on August 29, 2019.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated cycle 5 training on September 23, 2019.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1)work week risk and impending extreme hot temperatures for week of July 15, 2019 (2)emergent work and operational risk activity for the failure of the Unit 2 250 Vdc battery charger on July 30, 2019 (3)emergent work and work week risk following Unit 1 SCRAM and ground on Unit 1 main generator on August 26, 2019 (4)work week risk during week of September 9, 2019 (Unit 1 emergency diesel generator work risk)

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (3 Samples 2 Partials)

The inspectors evaluated the following operability determinations and functionality assessments:

(1)

(Partial)

Issue Report 4254547, Unit 1 HPCI [high pressure coolant injection] Did Not Trip Locally During QCOS 2300-13 on June 5, 2019

(2) Issue Report 4263259, Unit 2 DWEDS [drywell equipment drain sump pump] Level Switch Issues Prevent Accurate Trending on July 9, 2019
(3) Issue Report 4267234, Failure of [Unit]1B 24/48 Volt Battery Charger on July 11, 2019
(4) Issue Report 4267593, Received 902-10 A10, [Unit 2] 250V Battery Charger 2 Trip, on July 29, 2019 (5)

(Partial)

Issue Report 4278317, [Unit] 2A RHRSW [residual heat removal service water] Vault Door Found Not Dogged Closed with Unit 1 EDG [emergency diesel generator] OOS

[out-of-service] for Maintenance on September 12, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post maintenance tests:

(1) QCOS 1000-4, Unit 1 Residual Heat Removal Service Water Pump Operability Test on July 25, 2019
(2) Work Order 4945512, Unit 2 250 Vdc Battery Charger #2 Trip Alarm 902-8 A10 (2-8350) on July 30, 2019 (3)testing and synchronization to the grid following repairs to the Unit 1A phase of the isophase bus on August 31, 2019
(4) Unit 2C residual heat removal service water post-maintenance testing following discharge elbow replacement on September 16, 2019

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Forced Outage Q1F67 from Unit 1 reactor SCRAM due to generator ground fault on August 28, 2019.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) QCOS 6620-01, [Unit 1] SBO [station blackout] DG [diesel generator] Quarterly Load Test on July 29, 2019
(2) QCOS 1100-07, [Unit 1A] SBLC [standby liquid control] Pump Flow Rate Test on July 22, 2019

Inservice Testing (IP Section 03.01) (2 Samples)

(1) QCOS 1000-31, [Unit 1A] RHR [residual heat removal] Logic Test on May 22, 2019
(2) QCOS 2300-06, [Unit 2] HPCI System Air Operated Valve Test on July 30, 2019

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes:
  • Evaluation 18-45, Exelon Nuclear Standardized Radiological Emergency Plan, Revision 30

This evaluation does not constitute NRC approval.

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walk Downs and Observations (IP Section 02.01) (1 Sample)

The inspectors evaluated radiation monitoring instrumentation during plant walkdowns.

(1) The inspectors reviewed the following:

Portable Survey Instruments

  • RO20 - 0014095
  • RO20 - 0020433
  • RO20 - 0018385
  • RO20 - 0014093
  • RO20 - 0012237
  • RAMGAM - 0010619
  • Model 3 - 0020028
  • Model 3 - 0021709
  • Telepole - 00141189

Source Check Demonstration

  • RO20 - 0014095
  • RO20 - 0020433
  • Model 3 - 0021709
  • Telepole - 00141189

Area Radiation Monitors and Continuous Air Monitors

  • Area Radiation Monitor, Low Range, Unit 1 Refuel Floor, 690'
  • Area Radiation Monitor, High Range, Unit 1 Refuel Floor, 690'
  • Area Radiation Monitor, Low Range, Unit 2 Refuel Floor, 690'
  • Area Radiation Monitor, High Range, Unit 2 Refuel Floor, 690'
  • Area Radiation Monitor, Low Range, Unit 1 Spent Fuel Pool, 690'
  • Area Radiation Monitor, High Range, Unit 1 Spent Fuel Pool, 690'
  • Area Radiation Monitor, Low Range, Unit 2 Spent Fuel Pool, 690'
  • Area Radiation Monitor, High Range, Unit 2 Spent Fuel Pool, 690'
  • Area Radiation Monitor, Outside Unit TIP Room, 595'
  • Continuous Air Monitor, Unit 1 Refuel Floor, 690
  • Continuous Air Monitor, Unit 1 13-Line, 595'

Personnel Contamination Monitors, Portal Monitors and Small Article Monitors

  • IPM 9, Instrument Number I350
  • SAM 12, Instrument Number 12205
  • PM 12, Instrument Number 12047
  • SAM 11, Instrument Number LAM1

Calibration and Testing Program (IP Section 02.02) (1 Sample)

The inspectors evaluated the calibration and testing program implementation.

(1) The inspectors reviewed the following:

Alarm Setpoint and Calibration Method Check of Personnel Contamination Monitors, Portal Monitors and Small Article Monitors

  • PM 9, Instrument Number I350
  • SAM 12, Instrument Number 12205
  • PM 12, Instrument Number 12047

Failure to Meet Calibration or Source Check Acceptance Criteria

  • RO20 - 0018385
  • RO20 - 0014093
  • RO20 -

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (07/01/2018 - 06/30/2019)
(2) Unit 2 (07/01/2018 - 06/30/2019)

MS06: Emergency AC Power Systems (IP Section 02.05) (2 Samples)

(1) Unit 1 (07/01/2018 - 06/30/2019)
(2) Unit 2 (07/01/2018 - 06/30/2019)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Issue Report (IR) 4238831, [Unit] 1C RHRSW High Pressure Outboard Seal Leak During Run

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Follow-up (IP Section 03.01)

(1) Unit 1 reactor SCRAM event follow-up activities on August 25,

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71124.05 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Technical Specification 5.5.1 states, in part, that the Offsite Dose Calculation Manual shall be established, implemented, and maintained.

Section 12.2.1, Radioactive Liquid Effluent Monitoring Instrumentation, of the Offsite Dose Calculation Manual (Revision 13) includes Radiological Effluent Surveillance Requirement 12.2.1.3, which requires channel functional tests of the Unit 1 and Unit 2 service water effluent gross activity monitors to be performed on a 92 day frequency.

Contrary to the above, between December 19, 2018 and August 6, 2019, the licensee failed to implement radiological effluent surveillance requirements contained within the Offsite Dose Calculation Manual. Specifically, the licensee did not perform channel functional tests on Unit 1 or Unit 2 service water effluent gross activity monitors.

Significance/Severity: Green. The finding was determined to be of very low safety significance (Green) because the issue involved a radioactive effluent release, but did not: (1)represent a substantial failure to implement the radioactive effluent release program; or (2)result in public exposure that exceeded the dose values in Appendix I to 10 CFR Part 50 and/or 10 CFR 20.1301(e) limits.

Corrective Action References: Issue Report 4268906

Observation: 1C Residual Heat Removal Service Water Outboard Seal Leak 71152 The inspectors reviewed Issue Report 4238831, 1C RHRSW High Pressure Outboard Seal Leak During Run, dated April 12, 2019. The condition report documented a large amount of water leaking and spraying from the outboard seal of the 1C residual heat removal service water pump shortly after pump start in support of a surveillance test. Once the report was received in the control room, operators secured the pump. The licensee declared the pump inoperable and entered the appropriate Technical Specification. After the pump was secured, operators reported that the seal was continuing to leak approximately 3 gallons per minute.

The licensee had been tracking the leaking seal on this pump since it was first reported on March 18, 2019, which was documented in Issue Report 4230672, 1C RHRSW HP [high pressure] O/B [outboard] Seal Leaking. Following the seal leak identified in Issue Report 4230672, the licensee determined that seal replacement would be required, and planned the repair for a future residual heat removal work window. The licensee completed all necessary repairs on April 15, 2019, and the pump was restored to an operable status. The inspectors determined that the licensee's corrective action for this issue was appropriate and in accordance with the significance of the issue. The licensee identified that the cause of the seal failure was inadequate pump seal cooling water flow due to a small pebble getting stuck in a flow-restricting orifice, which blocked flow in the seal cooling line. The inspectors reviewed the licensees responses to Issue Reports 4230672 and 4238831, the design of the RHRSW system, prior RHRSW bay inspections, and internal operating experience. The inspectors determined that the cause of the pump failure and seal leak was not within the licensee's ability to foresee and correct, and no performance deficiency was identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 1, 2019, the inspectors presented the integrated inspection results to Mr. P. Boyle, Acting Plant Manager, and other members of the licensee staff.
  • On September 20, 2019, the inspectors presented the radiation protection inspection results inspection results to Mr. K. Ohr, Site Vice President, and other members of the licensee staff.
  • On October 3, 2019, the inspectors presented the Exit Meeting for EP Inspection per IP 71114, Attachment inspection results to Mr. L. Baker, EP Fleet Programs Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04Q Procedures

QCOP 1000-04

RHR Service Water System Operation

QCOP 6600-04

Diesel Generator 1/2 Preparation for Standby Operation

QCOP 6600-24

Unit 2 Diesel Generator Preparation for Standby Operation

71111.04S

Corrective Action

Documents

IR 4025834

Replace Unit 1 SBLC Heat Trace and Insulation

06/26/2017

Procedures

M-40

Diagram of Standby Liquid Control Piping

QOM 1-1100-01

Unit 1 Standby Liquid Control Valve Checklist

Work Orders

WO 4657736

EM Replace/Upgrade 1-1101 U1 SBLC Heat Trace &

Insulation

09/06/2018

71111.05Q Fire Plans

FZ 11.2.1

Unit 1 RB 554'-0 Elev. SW Corner Room - 1B Core Spray

July 2009

FZ 11.2.3

Unit 1 RB 554'-0 Elev. NW Corner Room - 1A Core Spray

November

2011

FZ 6.1.A

Unit 1 TB 615'-6 Elev. 'A' Battery Charger Room U-1

October

2013

FZ 6.1.B

Unit 1 TB 615'-6 Elev. 'B' Battery Charger Room U-1

October

2013

FZ 6.2.A

Unit 2 TB 615'-6 Elev. 'A' Battery Charger Room U-2

July 2009

FZ 6.2.B

Unit 2 TB 615'-6 Elev. 'B' Battery Charger Room U-2

October

2013

FZ 7.1

Unit 1 TB 628'-6 Elev. 250V Battery Room

October

2013

FZ 7.2

Unit 2 TB 628'-6 Elev. 250V Battery Room

July 2009

FZ 8.2.6.E

Unit 2 TB 595'-0 Elev. Hallway

November

2018

FZ 8.2.7.A

Unit 1 TB 615'-6 Elev. Hydrogen Seal Oil Area and MCC's

October

2015

FZ 8.2.7.E

Unit 2 TB 615'-6 Elev. North Mezzanine Floor

November

2018

71111.12

Miscellaneous

Unavailability

Report

July 2018 -

June 2019

71111.13

Corrective Action

Documents

IR 4267593

Received 902-10 A10, 250V Battery Charger 2 Trip

07/28/2019

IR 4268103

250 Vdc Drawing Enhancement

07/30/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

IR 4268124

250 Vdc Charger Require Updates

07/30/2019

71111.15

Corrective Action

Documents

IR 4262214

7/6/19 DWEDS Pumping had Step Change in Total Gallons

Pumped

07/06/2019

IR 4262426

U2 DWED Sump Level Switch Fails to Stop 2A Pump at Low

Level

07/07/2019

IR 4263259

U2 DWEDS Level Switch Issues Prevent Accurate Trending

07/11/2019

IR 4263286

EO ID: Water Leak from 0-2007-22 AOV FDF Backwash

Inlet

07/11/2019

IR 4264763

NRC ID: U2 DWFDS Leakage Increase Above NRC

Threshold

07/17/2019

IR 4267593

Received 902-10 A10, 250V Battery Charger 2 Trip

07/28/2019

Drawings

Drawing 4E-1319

Key Diagram and Elevations 48-24 Vdc Distribution Centers

N

Miscellaneous

Alarm 902-8 A10

250V Battery Charger 2 Trip

OP-AA-108-111

Adverse Condition Monitoring and Contingency Plan

(ACMP) U2 Drywell Equipment Drain Sump (DWEDS) Pump

Degraded Flow (Rev. 1)

07/18/2019

Procedures

QOM 1-6300-T01

48/24 Vdc Distribution Panel + 1A Bus 4E-1319

QOM 1-6300-T02

48/24 Vdc Distribution Panel + 1B Bus 4E-1319

UFSAR Table

11.1-4

Drywell Equipment Drain Sump Sources for Radioactive

Material

71111.19

Procedures

QCOS 1000-04

RHR Service Water Pump Operability Test

Work Orders

WO 4916933

QCOS 1000-4 'A' RHR Serv Wtr Pump Flow Group 'A' Test

(IST)

07/23/2019

WO 4916934

QCOS 1000-6 'A' RHR Pump Flow Rate Group 'A' Test (IST) 07/23/2019

WO 4916935

QCOS 1000-6 'B' RHR Pump Flow Rate Group 'A' Test (IST) 07/23/2019

WO 4916936

QCOS 1000-4 'B' RHR Serv Wtr Pump Flow Group 'A' Test

(IST)

07/23/2019

WO 4916937

QCOS 1000-06 'A' Loop LPCI Mode RHR Flow Rate

07/23/2019

WO 4945512

250 Vdc Battery Charger 2 Trip Alarm 902-8 A10 (2-8350)

07/30/2019

71111.20

Corrective Action

Documents

IR 4274286

U-1 Reactor Scram Gen Trip from Ground Relay (GIX 104)

08/25/2019

71111.22

Procedures

ER-AA-310

Maintenance Rule

OP-AA-108-115

Operability Determinations

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

QCOS 1100-07

SBLC Pump Flow Rate Test

QCOS 2300-06

HPCI System Air Operated Valve Test

QCOS 6620-01

SBO DG 1(2) Quarterly Load Test

WC-AA-101

On-line Work Control Process

WC-AA-101-1006

On-line Risk Management and Assessment

Work Orders

WO 4916523-01

HPCI Valve Timing Test (IST)

WO 4918552-01

SBO Load Test

71114.04

Miscellaneous

Evaluation 18-45

Exelon Nuclear Standardized Radiological Emergency Plan,

Revision 30

2/14/2019

71124.05

Calibration

Records

Certificate

  1. 0011135270

Certificate of Calibration RO20AA

2/14/2019

Certificate

  1. 0011138654

Certificate of Calibration Model 3

11/29/2018

Certificate

  1. 0011150060

Certificate of Calibration Model 3

2/01/2019

Certificate

  1. 0011173293

Certificate of Calibration RAM GAM 1

05/28/2019

Certificate

  1. 0011173354

Certificate of Calibration BAK-2270

08/19/2019

Certificate

  1. 001153485

Certificate of Calibration RO-20AA

2/26/2019

RP-AA-232-1001

ACCUSCAN II Calibration Acceptance Criteria

07/25/2018

RP-AA-232-1001

Calibration Acceptance Criteria FASTSCAN

07/24/2018

RP-AA-700-1210

IPM Calibration Data Sheet #I350

10/24/2018

RP-AA-700-1235

PM-12 Calibration Data Sheet #12047

08/30/2019

RP-AA-700-1239

SAM-12 Calibration Data Sheet #12205

2/18/2018

Corrective Action

Documents

AR 04157428

Out of Tolerance Instrumentation During Calibration

07/20/2018

AR 04207695

Out of Tolerance Instrumentation During Calibration

01/03/2019

AR 04264231

Instruments Not Marked Information Only As Required

07/15/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 04268906

Request Re-establish SWRM Channel Functional Test

Frequency to 92 Days

08/01/2019

Corrective Action

Documents

Resulting from

Inspection

AR 04280816

Portable Instrument Source Check Acceptance Criteria

Exceeds Range of Scale

09/19/2019

AR 04280821

Portable Instrument Source Check Acceptance Criteria

Significant Figure Issue

09/19/2019

Miscellaneous

C&C Irradiator Service LLC; Dose vs. Distance Curves

07/17/2019

Ref No S125722

Radcal Corporation Service Report

04/15/2019

Procedures

CY-AA-130-201

Radiochemistry Quality Control

RP-AA-232-1001

Calibration Verification of Whole Body Counting Systems

Using APEX In-Vivo

RP-AA-700-1208

Irradiator Reference Data Sheet

07/17/2019

RP-AA-700-1210

Operation and Calibration of IPM Whole Body Frisking

Monitor

RP-AA-700-1235

Operation and Calibration of the PM-12 Gamma Portal

Monitor

RP-AA-700-1239

Operation and Calibration of the Model SAM-12 Small

Articles Monitor

Self-Assessments AR 4207564

NRC: Rad Protection - Rad Monitoring Instrumentation

Inspection

07/16/2019

Work Orders

01949080-01

QCIS 2400-05 Division II Rad Monitor Calibration/Functional

Test

04/19/2018

71152

Corrective Action

Documents

ACE

1C Residual Heat Removal Service Water (RHRSW) High

Pressure Pump Outboard (OB) Seal Failure

IR 4161140

1C RHRSW HP Pump O/B Seal Has Increased

08/02/2018

IR 4230672

EO ID: 1C RHRSW HP O/B Seal Leaking

03/18/2019

IR 4232246

EO ID: 1C RHRSW HP O/B Seal Leaking (Leak Template

IR)

03/18/2019

IR 4234945

EOID: 1C RHRSW High Pressure Pump Outboard Seal

Leak Increase

03/31/2019

IR 4238831

1C RHRSW High Pressure Pump OB Seal Leak During Run

04/12/2019

IR 4254019

Pump Failed to Start During QCOS 1000-04

06/03/2019

IR 4272141

Eold - 1C RHRSW High Pressure Pump Inboard Seal Leak

08/15/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

IR 4272309

1C RHRSW HP Pump 1B Seal Leak Follow-up to IR

272141

08/15/2019

IR 490375

PSU Q1M19 1C RHRSW Pump Seal Leak

05/16/2006

IR 580419

Gap Below RHRSW Separation Screen

01/18/2007

Drawings

Drawing B-35

Crib House Plan El. 595'-0 South Area

P

Drawing B-36

Crib House Plan El. 595'-0 North Area

N

Drawing B-37

Crib House Plan El. 559'-8

F

Drawing M-11

General Arrangement Crib House

E

Drawing M-79,

Sheet 1

Diagram of RHR Service Water Piping

BJ

Miscellaneous

UCC Job #02-14-

233.296 Letter

RHR Service Water Bay Inspection Report

2/07/2018

UCC Job #02-14-

233.327 Letter

RHR Service Water Bay Inspection Report

08/07/2018

UCC Job #02-14-

233.367

RHR Service Water Bay Inspection Report

2/07/2019

71153

Corrective Action

Documents

IR 4274286

U-1 Reactor Scram Gen Trip from Ground Relay (GIX 104)

08/25/2019