IR 05000254/1980003
| ML19309D275 | |
| Person / Time | |
|---|---|
| Site: | Quad Cities |
| Issue date: | 02/25/1980 |
| From: | Danielson D, Ward K NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | |
| Shared Package | |
| ML19309D267 | List: |
| References | |
| 50-254-80-03, 50-254-80-3, 50-265-80-05, 50-265-80-5, NUDOCS 8004100207 | |
| Download: ML19309D275 (9) | |
Text
im
,w U.S. NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCMENT
REGION III
Report Nos. 50-254/80-03; 50-265/80-05 Docket No. 50-254; 50-265 License No. DPR-29; DPR-30 Licensee:
Commonwealth Edison Company P. O. Box 767 Chicago, IL 60690 Facility Name: Quad-Cities Station, Units 1 and 2 Inspection At: Quad-Cities Site, Cordova, IL Inspection Conducted: January 15-16 and February 11, 1980 M. A M Inspector:
K. D. Ward
_
//- 70
/Wdala/ fn~-
Approved By:
D.11. Danielson, Chief dh' f d'o Engineering Support Section 2 Inspection Summary Inspection on January 15-16 and February 11, 1980 (Report Nos. 50-254/80-03; 50-265/80-05)
Areas Inspected: Torus support modification QA/QC program, implementing procedures, work activities, and review and evaluation of welding and nondestructive examination (NDE) data and reports; interpret radiographs of welds in feedwater system. This inspection involved a total of 19 onsite inspection-hours by one NRC inspector.
Results:
No items of noncompliance or deviation were identified.
8004100 1n2d ?
.m ww
-
.
.
DETAILS
Persons Contacted Commonwealth Edison Company (CECO)
- N. Kalivianakis, Station Superintendent
- W. Burkamper, QC Supervisor
- L. Geruer, Technical Staf f Supervisor K. Graesser, Assistant Supervisor, Administration
- D. Thayer, Sr. QA Inspector Graver Energy Service Incorporated (CES1)
W. Dumke, QA Engineer General Electric (GE)
G. Brevig, Project QC Supervisor Morrison Construction Company (M)
R. Bullock, QC Supervisor The inspector also contacted and interviewed o'ther licensee and con-tractor employees.
- Denotes those present at the final exit interview February 11, 1980.
Functional or Program Areas Inspected 1.
General a.
Reference RIII Report No. 50-254/79-19; 50-265/79-16 (Torus support modification)
b.
To date CECO has not received a written approval for the torus modification.
CECO submitted a current schedule for implementa-tion of the modification May 11, 1979, to the Director, Division of Operating Reactors, US NRC, Washington D.C. Graver Energy Service Inc. started the Unit 1 external modification in June 1979, and Morrison Construction Company started the Unit 2 internal modification December 1979.
c.
Morrison was hired to perform the internal modification for both units, d.
The next outage for Unit I will be approximately September 1980, and Unit 2 approximately September 1981.
-2-
.*
'2.
New or Revised Procedure Review
'
The inspector reviewed the following new and revised procedures:
a.
GESI, SMAW Procedure for Welding Carbon Steel QC-SMI-IN, Revisic n 7, September 21, 1979 b.
GESI, Repair Procedure for Base and Weld Metal Defects, QC-RP-6, Revision 3, July 2, 1979 c.
M, Qualification and Certification of Nondestructive Examination Personnel, NDE/PQC-1, Revision 4, October 1979
d.
M, Visual Inspection of Welds to AWS D1.1 Structural Welding Code, NDE-VE-3, Revision 3, November 1979 c.
M, Process Controls, QSPC-18, Revision 3, November 1979
!
f.
M, Bolt-Up Procedure, QSPC-33, Revision 3, December 1979 g.
M, Process Control; Groove Fillet or Socket Welds, QSPC-37, Revision 4, November 1979 h.
M, Torus Coating, QSPC-38, Revision 1, November 1979 i.
M, Procedure Specification for Shield Arc Welding (SMAW) of Carbon Steel (ASME P-1, Group 2) Material According to ASME Section IX, CS-16, Revision 2, November 1979 j.
M, Procedure Specification for Shield Arc Welding (SMAW) of Carbon Steel (ASME P-1) Materials According to ASME Section IX, CS-17, Revision 2, November 1979 k.
M, Material Control - Receiving of Materials, QSMC-1, Revision 1, November 1979 1.
M, Welding Material Control, QSPC-2, Revision 2, November 1979
,
m.
M, Qualification of Welders, QSPC-4, Revision 1, November 1979 n.
M, ASME Welder Performance Test, QSPC-4A, Revision 1, November 1979
o.
M, Material Handling, Scaffolding and Rigging, QSPC-9, Revision 1, November 1979 p.
M, Use of Weld Data Report for Piping Subassemblies for Sizes 2-1/2" 0.D. and Larger, QSPC-17, Revision 0, September 1979 l
!
l l
-3-
i i
..
q.
M, Special Process Procedure Manual, Controlled copy 1102,
Revision 0, November 26, 1979 r.
M, General Procedure for Welding of Carbon Steel Piping, Pressure Vessels and Structural Materials, PC-901, Revision 1, October 1979 s.
M, Procedure Specification for Shielded Metal Arc Welding of Carbon Steel Materials According to ASME Section IX, CS-1, Revision 4, November 1979 t.
M, Procedure Specification for Gas Tungsten Arc Welding (GTAW)
of Carbon Steel (ASME P-1) Materials According to ASME Section IX, CS-4, Revision 3, December 1979
'
M, Procedure Specification for Shield Arc Welding (SMAW) of u.
Carbon Steel (ASME P-1) Material According to ASME Section IX, CS-11, Revision 3, October 1979 v.
M, Qualification and Certification of Nondestructive Examination Personnel NDE/PQC-2, Revision 4, October 1979 (1975 Edition)
w.
M, Visual Inspection of Welds to AWS D1.1 Structual Welding Code, NDE-VE-3, Revision 3, November 1979 x.
M, Magnetic Particle Examination, ASME Section V, NDE/MT-2, Revision 4, November 1979 No items of noncompliance or deviations were identified.
3.
Personnel Certifications The inspector reviewed the following personnel certifications:
,
Graver new welders:
Name Stamp No.
D. Green
D. Juncker
C. Tracy
M. Fulwood
A. Fulwood
B. Masterson
L. Tracey
G. Southerland
J. Sofia
F. Maxuiers
D. Chandler
E. Delaboussaye
i
.
-4-
'
l
... -...
_. -
..
_
.. _.
..
.-.
.
.
- o *
'
Morrison new welders:
J Name Stamp No.
D. Besler B-165 G. Foland F-52 t
P. Hasty 11-107 F. Kirby K-17 N. Magnuson M-154 J. McKee M-155
'
T. Naughton N-41 C. Neubaum N-42
M. Ode 0-19 r
R. Ottis 0-2 K. Quick Q-9
.
,
L. Slater S-212
,
T. Boone B-164
'
V. Cambell C-136 E. Cook C-135 M. llolmes H-105 S. Naaden N-40 J. Palsgrove P-84 K. Presley P-83 G. Ralston R-89 l
T. Ryan R-3 i
W. Unger U-4
,
R. Ruiz R-92 C. Witzman W-105
'
Morrison new NDE personnel:
,
Name VT PT MT UT RT R. Bullock II II II II, II
!
R. Pollitz II II II I
II 5-
,
No items of noncompliance or deviations were identified.
4.
Review of Surveillance and Data Reports
,
c The following reports were reviewed:
a.
CECO, QA Surveillance Reports of Morrison Welding Unit 2 Torus
'
Support Modification Internals
i
l b.
CECO, QA Surveillance Reports of Graver Welding Unit 1 Torus
,
Support Modification Externals c.
Graver, Surveillance Reports of Graver Welding Unit 1 Torus
Externals i
r i
5-l.
_
-
..
.
_
.
.-
..
._
e No items of noncompliance or deviations were identified.
'
5.
Observations of Work The inspector observed Graver welders welding on the torus support a
modification externals on Unit I and Morrison welders welding on the torus support modification internals on Unit 2.
No items of noncompliance or deviations were identified.
6.
Material and Equipment Certifications The following material and equipment certfications were reviewed:
I a.
Electrodes:
E7018, 3/32" HT # 422H8211 E7018, 1/8" HT # 421H5281 E7018, 5/32" HT # 659H075 E7018, 3/16" HT # 02T903T i
b.
Tong Tester # AX 40168 e
c.
Pyrometer # 2185 l
t No items of noncompliance or deviations were identified.
,
l 7.
Independent Inspection a.
Ultrasonic Examination Lambert MacGill and Thomas, Inc. performed ultrasonic and l
visual examinations on riser safe end to thermal sleeve welds on all 10 risers in accordance with ASME Section XI, 1974 Edition, Summer 1975 Addenda. No unacceptable indications were identified. The LMT Ultrasonic Examination of Nuclear
,
Coolant System Piping Fittings Forgings Procedure, UT-24, Revision 1, January 25, 1979, was used. The VT and UT data reports, certifications of instruments, transducers and Ultrasonic Couplant, LMT Gel Batch #111778, were reviewed.
.
The following personnel certifications were reviewed and found to be in accordance with SNT-TC-1A, 1975 Edition:
K. King II II I
R. Kellerhall II II II R. Pechacek II II E. Thomas III I
III III W. Tighe I
i-6-
.,
.
- -. -
- --
. - - -
-
,.
>
.e
,
'
b.
Radiography of Feedwater Welds Based on the cracking recently occurring at the feedwater nozzles in PWR plants, there is a question as to whether or not BWR plants might have the same type of preblem. Discus-
_
sions between CECO and the RIII on this subject resulted in a commitment to radiograph the safe end to nozzle and safe i
end to pipe welds on all four feedwater nozzles during the
'
current refueling outage on Unit 2.
One weld was radiographed, safe end to pipe (weld N4D) with the original thermal sleeve in place. The purpose of this was to determine that radiography is feasible in the event radiography of the same welds on other units are required.
The remainder of the welds were radiographed with the thermal
sleeves removed, but still prior to removal of the internal cladding in the area of nozzle.
After removing the cladding and with the new thermal sleeve
installed, a nozzle to safe end weld was radiographed (N4C).
'
This determi;.ed that such a technique was not feasible by radiography for future inspections with the new type thermal sleeve installed. Different speeds of film were used to try and accomplish an acceptable radiograph with approximately 100 curies of IR192.
The leakage land grooves of the new thermal sleeve are approx-imately 1-1/4" apart, 1/4" wide, with one end of the weld in the area of interest. The grooves have abrupt changes and make clongated indications.
Penetrameter essential holes and the outline of the penetrameters were not visible. Definition, latitude, and sensitivity were very poor. All the above are unacceptable to ASME Section III, 1977 Edition, Summer 1979
,
Addenda and CECO procedure, Radiographic Examination, NDT-A, Revision 7, December 6, 1978.
CONAM inspection performed the radiography.
The radiography was also performed in accordance with IE Bulletin No. 79-13 titled " Cracking in Feedwater System Piping", except for the width of the coverage on the adjacent pipewelds. The material thickness is approximately one inch thick and the radiographic films were 4-1/2" wide. The Bul-j letin stated that there would be a distance equal to at least two wall thicknesses on each side of the weld. The radio-graphic films used on the safe end to nozzle welds were 7" wide.
The inspector reviewed the radiographs of the following welds:
,
-7-
-
_
.
._.
. __
_
..
..
Safe End to Sparger in
Weld No.
Nozzle or Pipe or out
,
N4A Nozzle Out r
N4A Pipe Out L
i N4B Nozzle Out N4B Pipe Out N4C Nozzle Out N4C Nozzle (New Sparger)
In N4C Pipe Out
N4D Nozzle Out
'
N4D Pipe (Old Sparger)
In N4D Pipe Out c.
Clad Revmoval Unit 2 The clad removal was being performed by GE.
Nonconformity reports and travelers of GE by GE were reviewed; also the
following procedures and NDE personnel certifications:
(1) GE ASBD (Apparatus Service Business Division) - NDT Per-sonnel Training, Qualification and Certification
,
Procedure 1101, Revision 3, January 31, 1979 (SNT-TC-1A 1975 Edition)
(2)
GE, Installation of Platform, QCCR-1002, Revision 0, December 5, 1979 (3)
GE, Sparger Removal and Inspectian, QCCR-1003, Revision 1, September 26, 1979
,
(4)
GE, CRM Preoperational Test of Cladding Removal Machine, QCCR-1004, Revision 0, October 22, 1979 (5) Riggin of CRM, QCCR-1005, Revision 0, October 4, 1979 (6)
GE, Dimensional Measurements, Feedwater Nozzle, QCCR-1006, Revision 0, September 26, 1979 (7)
GE, Rough Alignment, QCCR-1007, Revision 0, October 3, 1979 (8)
GE, Fine Alignment, QCCR-1008, Revision 0, December 5,1979 (9)
GE, Nozzle Machining,QCR-1009, Revision 1, November 29, 1979 (10) GE, Sparger Fit-Up and Installation, QCCR-1010, Revision 0, October 19, 1979
.
(11) GE, UT Thickness Measurements, QCCR-1012, Revision 1, l
December 14, 1979
,
l-8-
.,_
_.. _..
_ _. _
-
_
_.
_
_
_
_
_....
.. _
t
,
i '
(12) GE, Liquid PT Procedure, QCCR-1013, Revision 1, November 26, 1979
,
l (13) GE, Wall Bracket Visual Examination, QCCR-1014, Revision 0, l
October 4, 1979
,,
(14) GE, Tool Control QCCR-1015, Revision 0, December 5,1979
'
?
(15) GE, Materials and Processes, QCCR-1016, Revision 0,
'
October 3, 1979 I
(16) Cleanliness, QCCR-1017, Revision 0, October 2, 1979 (17) The following personnel certifications were reviewed:
,
'
t i
i D. Holthaus III III
M. Chubarov I
J. Evans I
T. Moscella II II B. Warchuch, Jr.
II II l
G. Lockyer III III D. King III III
L. Tanton I
,
The inspector observed the cladding removal machine (CRM) in
_,
the 240' nozzle. The machine made the last cut in the nozzle.
,
No items of noncompliance or deviations were identified.
l
.
Exit Interview The inspector met with site representatives at the conclusion of the
!
inspections and summarized the scope and-findings of the inspections.
-
.
i f
L
'
r I
i-9-
.
. -.. -,
._
- -. - ~.. -,
,,
,.
-
, - -
..,,
. --
m-~
w
-. v
-
,y
-