Annual Assessment Letter for the Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2018006 and 05000410/2018006)
ML19064B344
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 03/04/2019
From: Erin Carfang
Reactor Projects Branch 1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2018006
Download: ML19064B344 (7)


Text

rch 4, 2019

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR THE NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 (REPORTS 05000220/2018006 AND 05000410/2018006)

Dear Mr. Hanson,

The NRC has completed its end-of-cycle performance assessment of your Nine Mile Point Nuclear Station (Nine Mile Point), Units 1 and 2, reviewing performance indicators (PIs),

inspection results, and enforcement actions from January 1, 2018, through December 31, 2018.

This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined the performance at Nine Mile Point during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at Nine Mile Point.

The enclosed inspection plan lists the inspections scheduled through December 31, 2020. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections). Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. Furthermore, all the inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In addition to normal baseline inspections, the NRC will be performing Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal, and IP 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants, at your facility. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 610-337-5120 with any questions you have regarding this letter.

Sincerely,

/RA/

Erin Carfang, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-220 and 50-410 License Nos.: DPR-63 and NPF-69 Enclosure:

Nine Mile Point Inspection Plan

ML19064B344 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME ARosebrook per email ECarfang DATE 2/22/19 2/26/19

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count INSERVICE INSPECTION - UNIT 1 1 1 03/24/2019 03/30/2019 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

RAD SAFETY OUT 1 1, 2 04/01/2019 04/05/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/01/2019 04/05/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 04/01/2019 04/05/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/01/2019 04/05/2019 IP 71124.04 000728 Occupational Dose Assessment 50.59 PROCESS 3 1, 2 04/21/2019 04/27/2019 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments RAD SAFETY 01,02,03,04 1 1, 2 05/20/2019 05/24/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 05/20/2019 05/24/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 05/20/2019 05/24/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 05/20/2019 05/24/2019 IP 71124.04 000728 Occupational Dose Assessment ACCESS CONTROL, PROTECTIVE STRATEGY, TSR 4 1, 2 05/20/2019 05/24/2019 IP 71130.02 000734 Access Control 1, 2 05/20/2019 05/24/2019 IP 71130.05 000737 Protective Strategy Evaluation 1, 2 05/20/2019 05/24/2019 IP 71130.14 000743 Review of Power Reactor Target Sets 1, 2 05/20/2019 05/24/2019 IP 71151 001338 Performance Indicator Verification CYBER FULL IMP 2 1, 2 06/03/2019 06/07/2019 IP 71130.10P 000741 Cyber Security 1, 2 06/17/2019 06/21/2019 IP 71130.10P 000741 Cyber Security ISFSI OPERATIONAL INSPECTION 2 1, 2 06/09/2019 06/15/2019 IP 60855 001001 Operation Of An ISFSI 1, 2 06/09/2019 06/15/2019 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Heat Sink 1 1, 2 08/04/2019 08/10/2019 IP 71111.07T 000700 Heat Sink Performance -Triennial This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.

1/30/2019 10:49:29 AM

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count PI&R BIENNIAL 4 1, 2 08/12/2019 08/16/2019 IP 71152B 000747 Problem Identification and Resolution 1, 2 08/26/2019 08/30/2019 IP 71152B 000747 Problem Identification and Resolution RAD SAFETY 01,02,03,04 1 1, 2 08/19/2019 08/23/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 08/19/2019 08/23/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 08/19/2019 08/23/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 08/19/2019 08/23/2019 IP 71124.04 000728 Occupational Dose Assessment 1, 2 08/19/2019 08/23/2019 IP 71151 000746 Performance Indicator Verification RAD SAFETY REMP 1 1, 2 09/09/2019 09/13/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 09/09/2019 09/13/2019 IP 71151 000746 Performance Indicator Verification NMP EP EXERCISE INSPECTION 5 1, 2 10/07/2019 10/11/2019 IP 71114.01 000716 Exercise Evaluation 1, 2 10/07/2019 10/11/2019 IP 71151 001397 Performance Indicator Verification NMP2 REQUAL INSP W/ P/F RESULTS 2 1, 2 10/21/2019 10/25/2019 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)

1, 2 10/21/2019 10/25/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)

EQ PROGRAM 3 1, 2 10/21/2019 10/25/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

1, 2 11/04/2019 11/08/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

NMP2 INITIAL OL EXAM 4 2 11/11/2019 12/06/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

2 12/09/2019 12/20/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

NMP UNIT 1 - LICENSE RENEWAL PHASE 4 3 1 12/08/2019 12/14/2019 IP 71003 000687 Post-Approval Site Inspection for License Renewal This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.

1/30/2019 10:49:29 AM

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count Rad Safety Refuel 1 1, 2 03/02/2020 03/06/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/02/2020 03/06/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 03/02/2020 03/06/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/02/2020 03/06/2020 IP 71124.04 000728 Occupational Dose Assessment ISI - UNIT 2 1 2 03/09/2020 03/13/2020 IP 71111.08G 000701 Inservice Inspection Activities (BWR)

Rad Safety RETS 1 1, 2 05/18/2020 05/22/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 05/18/2020 05/22/2020 IP 71151 000746 Performance Indicator Verification Access Control, Equipment Testing and Maintenance, Training 3 1, 2 06/01/2020 06/05/2020 IP 71130.02 000734 Access Control 1, 2 06/01/2020 06/05/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 06/01/2020 06/05/2020 IP 71130.07 000739 Security Training 1, 2 06/01/2020 06/05/2020 IP 71151 001338 Performance Indicator Verification Rad Safety Inspection 1 1, 2 06/08/2020 06/12/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 06/08/2020 06/12/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 06/08/2020 06/12/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 06/08/2020 06/12/2020 IP 71124.04 000728 Occupational Dose Assessment NMP EP PROGRAM INSPECTION 1 1, 2 07/13/2020 07/17/2020 IP 71114.02 000717 Alert and Notification System Testing 1, 2 07/13/2020 07/17/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 07/13/2020 07/17/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 07/13/2020 07/17/2020 IP 71151 001397 Performance Indicator Verification Radwaste 1 1, 2 07/27/2020 07/31/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.

1/30/2019 10:49:29 AM

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2019 - 12/31/2020 Unit Start End Activity CAC Title Staff Count Rad Safety Instruments 1 1, 2 08/02/2020 08/07/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation Rad Safety Inspection 1 1, 2 10/05/2020 10/09/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/05/2020 10/09/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/05/2020 10/09/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/05/2020 10/09/2020 IP 71124.04 000728 Occupational Dose Assessment 1, 2 10/05/2020 10/09/2020 IP 71151 000746 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS 7 1, 2 10/05/2020 10/09/2020 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1, 2 10/26/2020 10/30/2020 IP 71130.03 000735 Contingency Response - Force-On-Force Testing DESIGN BASIS ASSURANCE INSPECTION - TEAMS 7 1, 2 10/19/2020 10/23/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

1, 2 11/02/2020 11/06/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)

NMP1 Requal Inspecton with P/F Results 2 1 11/02/2020 11/06/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance (Biennial)

1 11/16/2020 11/20/2020 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance (Annual)

NMP1 INITIAL OL EXAM 4 1 11/02/2020 11/06/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 11/30/2020 12/11/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.